LIST DATA YANG DIPERLUKAN

A. DATA TAMBAHAN
1. PETA TOPOGRAFI DAERAH BANKO BARAT
2. PENAMPANG LITOLOGI TAMBANG BANKO BARAT PIT 1
3. PETA GEOLOGI REGIONAL PT BA UPTE
4. PENAMPANG STRATIGRAFI TAMBANG BANKO BARAT PIT 1
5. JENIS BATUAN OVERBURDEN YANG AKAN DIRIPPING DAN KARAKTERISTIKNYA (SIFAT
FISIK DAN MEKANIK BATUAN)
6. DATA CADANGAN BATUBARA YANG ADA DI BANKO BARAT (PIT 1 KHUSUSNYA)
7. DATA KUALITAS BATUBARA DI PIT 1 BANKO BARAT
8. KONSUMEN BATUBARA PT BA
9. HARGA BATUBARA PER TON UNTUK TIAP KONSUMEN
10. DATA CURAH HUJAN JULI 2014

B. DATA PENELITIAN
KAJIAN TEKNIS
1. DATA LOKASI YANG AKAN DILAKUKAN RIPPING
2. DATA LUAS DAERAH YANG AKAN DI-RIPPING DAN VOLUMENYA
3. ALAT YANG DIGUNAKAN UNTUK RIPPING DAN SPESIFIKASINYA
4. ALAT MUAT YANG DIGUNAKAN UNTUK MENGGALI MATERIAL HASIL DARI RIPPING DAN
SPESIFIKASINYA
5. DIGGING RATE DARI ALAT GALI MUAT YANG MENGGALI MATERIAL HASIL DARI RIPPING
(DIHITUNG SENDIRI)
KAJIAN EKONOMIS (SISTEM RENTAL)
1. JAM KERJA DOZER RATA-RATA PER TAHUN
2. JADWAL KERJA DOZER PER SHIFT (UNTUK MENGHITUNG EFISIENSI KERJA)
3. CYCLE TIME ALAT DOZER SAAT MELAKUKAN RIPPING
4. PRODUKTIVITAS ALAT DOZER PER JAM
5. BIAYA SEWA ALAT DOZER PER JAM
KAJIAN EKONOMIS
1. HARGA RIPPER
2. UMUR PAKAI ALAT DOZER
3. JAM KERJA/TAHUN
4. BIAYA ASURANSI
5. BIAYA SOLAR
6. BIAYA PELUMAS
7. BIAYA GREASE
8. BIAYA FILTER
9. BIAYA PEMELIHARAAN
10. UPAH OPERATOR
11. JAM KERJA OPERATOR