1
9
9
9
b
y
C
R
C
P
r
e
s
s
L
L
C
FIGURE20.4: Lewiston-Queenston arch bridge, near Niagara Falls, New York, 1962. Theworlds
longest xed-arch span, at 1000 ft (305 m); riseis159 ft (48 m). Box arch-rib sectionsaretypically
about 3 13-1/2 ft (0.9 4.1 m) in cross-section and about 44-1/2 ft (13.6 m) long. Job was
estimatedusingerection tiebacks(sameasshown in Figure20.3), but subsequent studiesshowedthe
long, slopingfalsework bentsto bemoreeconomical (even if lesssecurelooking). Much permanent
steelwork was used in the falsework bents. Derricks on approaches load steelwork onto material
carsthat travel up arch ribs. The115-ton-capacity travelersareshown erecting thelast full-length
arch-rib sections, leavingonly theshort, closingcrown sectionsto beerected. Canadaisat left, the
U.S. at right. (Courtesy of BethlehemSteel Corporation.)
and erection of steel bridgesof all types. Thistheoremholdsthat thecontractorsbest procedurefor
achieving, in thecompleted structure, thedeadload geometry and stressingstipulated on thedesign
plans, isgenerally asfollows:
1. Determine deadload stress data for the structure, at its geometric outline and under
normal temperature, based on accurately calculated weightsfor all components.
2. Determinethecambered (i.e., no-load ) dimensionsof each component. Thisinvolves
determining the change of shape of each component from the deadload geometry, as
its deadload stressing is removed and its temperature is changed from normal to the
shop-tape temperature.
3. Fabricate, withall dueprecision, eachstructural component toitsproper no-loaddimen-
sions except for certain exiblecomponentssuch aswireropeand strand members,
which may requirespecial treatment.
4. Accomplish shop assembly of membersand reaming assembled of holesin joints, as
needed.
5. Carry out comprehensive engineering studies of the structure under erection at each
key erection stage, determiningcorrespondingstressand geometric data, and preparea
step-by-step erection procedureplan, incorporating any check measurementsthat may
benecessary or desirable.
6. Duringtheerection program, bringall membersand jointsto thedesignated alignment
prior to boltingor welding.
c 1999by CRCPressLLC
FIGURE20.5: Lewiston-Queenston arch bridge, near NiagaraFalls, NewYork. Crawler craneserect steelwork for spans1and 6and erect material
derricks thereon. These derricks erect traveler derricks, which move forward and erect supporting falsework and spans 2, 5, and 4. Traveler
derrickserect arch-rib sections1and 2and supportingfalsework at each skewback, then set up creeper derricks, which erect archesto midspan.
c
1
9
9
9
b
y
C
R
C
P
r
e
s
s
L
L
C
7. Enter and connect thenal or closingstructural components, followingtheclosingpro-
cedureplan, without attemptingany eld measurementsthereof or adjustmentsthereto.
In summary, thekey to construction successisto accomplish theeld surveysof critical baselines
and support elevations with all due precision, perform construction engineering studies compre-
hensivelyand shop fabrication accurately, and then carrytheerection evolutionsthrough in theeld
without any second guessingand ill-advised attemptsat measurement and adjustment.
It maybenotedthat nospecial treatment isaccordedtostaticallyindeterminatemembers; theyare
fabricated and erected under thesamegoverningconsiderationsapplicableto statically determinate
members, as set forth above. It may be noted further that this general steel bridge construction
philosophydoesnot ruleout check measurementsaltogether, aserection goesforward; under certain
special conditions, measurements of stressing and/or geometry at critical erection stages may be
necessary or desirablein order to conrm structural integrity. However, beforetheerector callsfor
any such measurementsheshould makecertain that they will proveto bepractical and meaningful.
20.14 Exampleof SuspensionBridgeCableConstruction
In order to illustratetheshop control construction philosophy further, itsapplication to themain
cablesof therst Wm. Preston Lane, Jr., Memorial Bridge, crossingtheChesapeakeBayin Maryland,
completed in 1952 (Figure20.6), will bedescribed. Suspension bridgecablesconstituteoneof the
most difcult bridgeerection challenges. Up until rst Chesapeake thecablesof major suspension
bridges had been adjusted to the correct position in each span by means of a sag survey of the
rst-erected cablewiresor strands, usingsurveyinginstrumentsand target rods. However, on rst
Chesapeake, with its 1600-ft (488-m) main span, 661-ft (201-m) side spans, and 450-ft (l37-m)
back spans, thesteelwork contractor recommended abandoning thestandard cable-sag survey and
adopting the setting-to-mark procedure for positioning the guide strands a signicant new
concept in suspension bridgecableconstruction.
FIGURE20.6: Suspension spansof rst ChesapeakeBay Bridge, Maryland, 1952. Deck steelwork is
under erectionandisabout 50%complete. Atypical four-panel through-trussdecksection, weighing
about 100 tons, isbeingpicked in west sidespan, and also in east sidespan in distance. Main span
is1600ft (488m) and sidespansare661ft (201m); towersare324ft (99m) high. Cablesare14in.
(356mm) in diameter and aremadeup of 61helical bridgestrandseach (seeFigure20.8).
Thesteelworkcontractorsrationalefor settingtomarks wasspelledout inaletter tothedesigning
engineer (see Figure 20.7). (The complete letter is reproduced because it spells out signicant
c 1999by CRCPressLLC
construction philosophies.) Thisinnovation wasaccepted by thedesigning engineer. It should be
noted that thecontractorsmajor argument wasthat settingto markswould lead to amoreaccurate
cableplacement than would thesagsurvey. Theminor arguments, alluded to in theletter, werethe
resultingsavingsin preparatoryofceengineeringwork andin theeldengineeringeffort, andmost
likely in construction timeaswell.
Each cable consisted of 61 standard helical-type bridge strands, as shown in Figure 20.8. To
implement the setting-to-mark procedure each of three lower-layer guide strands of each cable
(i.e., strands1, 2, and 3) wasaccurately measured in themanufacturing shop under thesimulated
full-deadload tension, and circumferential markswereplaced at thefour center-of-saddlepositions
of each strand. Then, in theeld, theguidestrands(each about 3955ft [ 1205m] long) wereerected
and positioned accordingto thefollowingprocedure:
1. Placethethreeguidestrandsfor each cableon themark at each of thefour saddlesand
set normal shimsat each of thetwo anchorages.
2. Under conditions of uniform temperature and no wind, measure the sag differences
amongthethreeguidestrandsof each cable, at thecenter of each of thevespans.
3. Calculatethecenter-of-gravity position for each guide-strand group in each span.
4. Adjust thesag of each strand to bring it to thecenter-of-gravity position in each span.
Thisposition wasconsideredtorepresent thecorrect theoretical guide-strandsagin each
span.
Themaximumspread fromthehighest tothelowest strandat thespancenter, prior toadjustment,
wasfound to be1-3/4in. (44mm) in themain span, 3-1/2in. (89mm) in thesidespans, and 3-3/4
in. (95mm) in theback spans. Further, themaximumchangeof perpendicular sagneeded to bring
theguidestrandsto thecenter-of-gravity position in each span wasfound to be15/16 in. (24 mm)
for the main span, 2-1/16 in. (52 mm) for the side spans, and 2-1/16 in. (52 mm) for the back
spans. Thesesmall adjustments testify to theaccuracy of strand fabrication and to thevalidity of
thesetting-to-mark strand adjustment procedure, which wasdeclared to beasuccessby all parties
concerned. It seemsdoubtful that such accuracyin cablepositioningcouldhavebeen achievedusing
thestandard sag-survey procedure.
With therst-layer strandsin proper position in each cable, thestrandsin thesecond and subse-
quent layerswerepositionedtohangcorrectlyin relation totherst layer, asiscustomaryandproper
for suspension bridgecableconstruction.
This example provides good illustration that the construction engineering philosophy referred
to astheshop-control procedurecan beapplied advantageously not only to typical rigid-typesteel
structures, such ascontinuoustrussesand arches, but also to exible-typestructures, such assus-
pension bridges. Thereis, however, an important caveat: thesteelwork contractor must bearmof
suitablecaliber and experience.
20.15 Exampleof Cable-StayedBridgeConstruction
Inthecasecable-stayedbridges, therst of whichwerebuilt inthe1950s, it appearsthat thegoverning
construction engineering philosophy callsfor eld measurement and adjustment asthemeansfor
control of stay-cableand deck-structuregeometry and stressing. For example, wehaveseen speci-
cationscallingfor thecompleted bridgeto meet thefollowinggeometricand stressrequirements:
1. Thedeck elevation at midspan shall bewithin 12in. (305mm) of theoretical.
2. Thedeckproleat eachcableattachment point shall bewithin2in. (50mm) of aparabola
passingthrough theactual (i.e., eld-measured) midspan point.
c 1999by CRCPressLLC
FIGURE20.7: Settingcableguidestrandsto marks.
c 1999by CRCPressLLC
FIGURE20.7: (Continued) Settingcableguidestrandsto marks.
c 1999by CRCPressLLC
FIGURE20.8: Main cableof rst ChesapeakeBay suspension bridge, Maryland. Each cableconsists
of 61 helical-typebridgestrands, 55 of 1-11/16 in. (43 mm) and 6 of 29/32 in. (23 mm) diameter.
Strands1, 2, and3weredesignatedguidestrands andwereset tomark at eachsaddleandtonormal
shimsat anchorages.
3. Cable-stay tensionsshall bewithin 5%of thecorrected theoretical values.
Such specication requirementsintroduceanumber of problemsof interpretation, eldmeasure-
ment, calculation, and eld correction procedure, such asthefollowing:
1. Interpretation:
Thespecicationsaresilent withrespect totransverseelevationdifferentials. There-
fore, two deck-prolecontrol parabolasarepresumably needed, onefor each side
of thebridge.
2. Field measurement of actual deck prole:
The temperature will be neither constant nor uniform throughout the structure
duringthesurvey work.
Thesurvey procedureitself will introducesomeinherent error.
3. Field measurement of cable-stay tensions:
Hydraulic jacks, if used, arenot likely to beaccuratewithin 2%, perhapseven 5%;
further, theexact point of lift off will beuncertain.
Other proceduresfor measuring cabletension, such asvibration or strain gaging,
do not appear to denetensionswithin about 5%.
All cabletensionscannot bemeasured simultaneously; an extended period will be
needed, duringwhich conditionswill vary and introduceadditional errors.
c 1999by CRCPressLLC
4. Calculation of actual bridgeproleand cabletensions:
Field-measured data must be transformed by calculation into corrected actual
bridge proles and cable tensions, at normal temperature and without erection
loads.
Actual deadweightsof structural componentscandiffer byperhaps2%fromnomi-
nal weights, whiletemporaryerectionloadsprobablycannot beknownwithinabout
5%.
Theactual temperatureof structural componentswill beuncertainandnot uniform.
Themathematical model itself will introduceadditional error.
5. Target condition of bridge:
Thetarget condition to beachieved by eld adjustment will differ from thegeo-
metriccondition, becauseof theabsenceof thedeck wearingsurfaceandother such
components; it must thereforebecalculated, introducingadditional error.
6. Determiningeldcorrectionstobecarriedout byerector, totransformcorrectedactual
bridgeinto target condition bridge:
Thebridgestructureishighly redundant, and changingany onecabletension will
send geometric and cable-tension changes throughout the structure. Thus, an
iterativecorrection procedurewill beneeded.
It seemslikely that thetotal effect of all thesepractical factorscould easily besufcient to render
ineffectivethecontractorsattemptstonetunethegeometryandstressingof theas-erectedstructure
in order to bring it into agreement with thecalculated bridgetarget condition. Further, therecan
be no assurance that the specications requirements for the deck-prole geometry and cable-stay
tensionsareeven compatible; it seemslikely that either thedeck geometry or thecabletensionsmay
beachieved, but not both.
Specications clauses of the type cited seem clearly to constitute unwarranted and unnecessary
eld-adjustment requirements. Such clauses are typically set forth by bridge designers who have
great condence in computer-generated calculations, but do not have a sufcient background in
and understandingof thepractical factorsassociated with steel bridgeconstruction. Experiencehas
shown that eld proceduresfor major bridgesdeveloped unilaterally by design engineersshould be
reviewed carefully to determinewhether they arepractical and desirableand will in fact achievethe
desired objectives.
In viewof all theseconsiderations, thequestion comesforwardastowhat design andconstruction
principlesshouldbefollowedtoensurethat thedeadloadgeometryandstressingof steel cable-stayed
bridgeswill fall within acceptablelimits. Consistent with thegeneral construction-engineeringpro-
ceduresrecommendedfor other typesof bridges, weshouldabandon relianceon eldmeasurements
followed by adjustmentsof geometry and stressing, and instead placeprimerelianceon proper geo-
metriccontrol of bridgecomponentsduringfabrication, followed by accurateerection evolutionsas
thework goesforward in theeld.
Accordingly, theproper construction procedurefor cable-stayed steel bridgescan besummarized
asfollows:
1. Determinetheactual bridgebaselinelengthsand pier-top elevationsto ahigh degreeof
accuracy.
2. Fabricatethebridgetowers, cables, and girdersto ahigh degreeof geometricprecision.
3. Determine, in thefabricatingshop, thenal residual errorsin critical fabricated dimen-
sions, includingcable-staylengthsafter socketing, andpositionsof socket bearingsurfaces
or pinholes.
c 1999by CRCPressLLC
4. Determinecorrected theoretical shimsfor each individual cablestay.
5. Duringerection, bringall tower and girder structural jointsinto shop-fabricated align-
ment, with fair holes, etc.
6. At theappropriateerectionstages, install correctedtheoretical shimsfor eachcablestay.
7. With the structure in the all-steel-erected condition (or other appropriate designated
condition), check it over carefully to determine whether any signicant geometric or
other discrepanciesarein evidence. If therearenone, declareconditionsacceptableand
continuewith erection.
This construction engineering philosophy can be summarized by stating that if the steelwork
fabrication and erection areproperly engineered and carried out, thegeometry and stressingof the
completed structure will fall within acceptable limits; whereas, if the fabrication and erection are
not properly done, correctivemeasurementsand adjustmentsattempted in theeld arenot likely to
improvethestructure, or even to provesatisfactory. Accordingly, in constructingsteel cable-stayed
bridgesweshould placefull relianceon accurateshop fabrication and on controlled eld erection,
just as is doneon other types of steel bridges, rather than attempting to makemeasurements and
adjustmentsin theeld to compensatefor inadequatefabrication and erection.
20.16 FieldCheckingat Critical ErectionStages
Ashasbeen stated previously, thebest governingprocedurefor steel bridgeconstruction isgenerally
the shop control procedure, wherein full reliance is placed on accurate fabrication of the bridge
componentsasthebasisfor theintegrity of thecompleted structure. However, thisphilosophy does
not ruleout thedesirability of certain checksin theeld aserection goesforward, with theobjective
of providingassurancethat thework ison target and no signicant errorshavebeen introduced.
It would beimpossibleto catalogthosecasesduringsteel bridgeconstruction whereaeld check
might be desirable; such cases will generally suggest themselves as the construction engineering
studiesprogress. Wewill only comment that theseeld-check cases, and theproceduresto beused,
should belooked at carefully, and even skeptically, to makecertain that themeasurementswill be
both desirableand practical, producing meaningful information that can beused to augment job
integrity.
20.17 Determinationof ErectionStrengthAdequacy
Quitecommonly, bridgemember forcesduringtheerection stageswill bealtogether different from
thosethat will prevail in thecompleted structure. At each critical erection stagethebridgemembers
must bereviewed for strength and stability, to ensurestructural integrity asthework goesforward.
Such aconstruction engineering review istypically theresponsibility of thesteelwork erector, who
carries out thorough erection studies of the structure and calls for strengthening or stabilizing of
membersasneeded. Theerector submitsthestudiesandrecommendationstothedesigningengineer
for reviewandcomment, but normallythefull responsibilityfor steelwork structural integrityduring
erection restswith theerector.
In the U.S., bridgework design specications commonly require that stresses in steel structures
under erection shall not exceed certain multiplesof design allowablestresses. Although thistypeof
erection stresslimitation isprobably safefor most steel structuresunder ordinary conditions, it is
not necessarily adequatefor thecontrol of theerection stressingof largemonumental-typebridges.
The key point to be understood here is that fundamentally, there is no logical xed relationship
between design allowable stresses, which are based upon somewhat uncertain long-term service
c 1999by CRCPressLLC
FIGURE20.9: Cable-stayedorthotropic-steel-deck bridgeover Mississippi River at Luling, La., 1982;
view looking northeast. Themain span is1222 ft (372 m); theA-frametowersare350 ft (107 m)
high. A barge-mounted ringer derrick erected the main steelwork, using a 340-ft (104-m) boom
with a 120-ft (37-m) jib to erect tower components weighing up to 183 tons, and using a shorter
boomfor deck components. Cablestaysat theendsof projectingcrossgirdersarepermanent; others
aretemporary erection stays. Girder section 16-west of north portion of bridge, erected afewdays
previously, isprojectingat left; companion girder section 16-east ison bargeready for erection (see
Figure20.10).
loadingrequirementsalongwith somedegreeof assumed structural deterioration, and stressesthat
aresafeandeconomical duringthebridgeerectionstages, whereloadsandtheir locationsarenormally
well dened and thestructural material isin new condition. Clearly, thebasic premisesof thetwo
situations are signicantly different, and factored design stresses must therefore be considered
unreliableasabasisfor evaluatingerection safety.
Thereisyet afurther problem with factored design stresses. Largetruss-typebridgesin various
erection stages may undergo deections and distortions that are substantial compared with those
occurring under service conditions, thereby introducing apprehension regarding the effect of the
secondary bendingstressesthat result fromjoint rigidity.
Recognizing these basic considerations, the engineering department of a major U.S. steelwork
contractor went forward in the early 1970s to develop a logical philosophy for erection strength
appraisal of large structural steel frameworks, with particular reference to long-span bridges, and
implemented this philosophy with a stress analysis procedure. The effort was successful and the
resultswerereported in apaper published by theAmerican Society of Civil Engineersin 1977 [ 5] .
This stress analysis procedure, designated the erection rating factor (ERF) procedure, is founded
directlyupon basicstructural principles, rather than on bridge-member design specications, which
areessentially irrelevant to theproblemof erection stressing.
c 1999by CRCPressLLC
FIGURE20.10: Luling Bridgedeck steelwork erection, 1982; view looking northeast (refer to Fig-
ure 20.9) The twin box girders are 14 ft (4.3 m) deep; the deck plate is 7/16 in. (11 mm) thick.
Girder section 16-east is being raised into position (lower right) and will be secured by large-pin
hingebarsprior to fairing-up of joint holesand permanent bolting. Temporary erection staysare
jumped forward asgirder erection progresses.
It may benoted that asignicant inducement toward development of theERFprocedurewasthe
failureof therst Quebeccantilever bridgein1907(seeFigures20.11and20.12). It wasquiteobvious
that evaluation of thestructural safety of theQuebec bridgeat advanced cantilever erection stages,
suchasthat portrayedinFigure20.11, bymeansof thefactoreddesignstressprocedure, wouldinspire
no condenceand would not bejustiable.
Theerection ratingfactor (ERF) procedurecan besummarized asfollows:
1. Assumeeither (a) pin-ended members(no secondary bending), (b) plane-frameaction
(rigid trussjoints, secondary bendingin oneplane), or (c) space-frameaction (bracing-
member joints also rigid, secondary bending in two planes), as engineering judgment
dictates.
2. Determine, for each designated erection stage, the member primary forces (axial) and
secondary forces(bending) attributableto gravity loadsand wind loads.
3. Computethemember stressesinducedbythecombinederectionaxial forcesandbending
moments.
4. ComputetheERFfor eachmember at threeor velocations: at themiddleof themember;
at each joint, insidethegusset plates(usually at therst rowof bolts); and, whereupset
member platesor gusset platesareused, at thestepped-down cross-section outsideeach
joint.
5. Determine the minimum computed ERF for each member and compare it with the
stipulated minimumvalue.
c 1999by CRCPressLLC
FIGURE20.11: First Quebecrailway cantilever bridge, 23August 1907. Cantilever erection of south
main span, 6 daysbeforecollapse. Thetower traveler erected theanchor span (on falsework) and
then thecantilever arm; then erectedthetop-chordtraveler, whichisshown erectingsuspendedspan
at end of cantilever arm. Themain span of 1800ft (549m) wastheworldslongest of any type. The
sidespan bottomchordssecondfrompier (arrow) failedin compression becauselatticingconnecting
chord corner angleswasdecient under secondary bendingconditions.
6. WherethecomputedminimumERFequalsor exceedsthestipulatedminimumvalue, the
member isconsidered satisfactory. Whereit isless, themember may beinadequate; the
critical part of it isreevaluatedin greater detail andtheERFrecalculatedfor further com-
parison with thestipulated minimum. (Initially calculated valuescan often beincreased
signicantly.)
7. When the computed minimum ERF remains less than the stipulated minimum, the
member must bestrengthened asrequired.
Notethat member forcesattributableto wind aretreated thesameasthoseattributableto gravity
loads. The old concept of increased allowable stresses for wind is not considered to be valid
for erection conditions and is not used in theERF procedure. Maximum acceptable/r and b/t
valuesareincluded in thecriteria. ERFsfor memberssubjected to secondary bendingmomentsare
calculated usinginteraction equations.
20.18 Philosophyof theErectionRatingFactor
In order that thestructural integrityor reliabilityof asteel framework can bemaintainedthroughout
theerection program, theminimumprobable(or minimumcharacteristic ) strength valueof each
member must necessarily be no less than the maximum probable (or maximum characteristic )
forcevalue, under themost adverseerection condition. In other words, thefollowingrelationship is
c 1999by CRCPressLLC
FIGURE20.12: Wreckageof south anchor span of rst Quebecrailwaycantilever bridge, 1907. View
lookingnorth fromsouth shoreafewdaysafter collapseof 29August 1907, theworst disaster in the
history of bridgeconstruction. About 20,000tonsof steelwork fell into theSt. LawrenceRiver, and
75workmen lost their lives.
required:
S S F +F (20.1)
where
S = computed or nominal strength valuefor themember
S = maximumprobablemember strength underrun fromthecomputed or nominal value
F = computed or nominal forcevaluefor themember
F = maximumprobablemember forceoverrun fromthecomputed or nominal value
Equation 20.1 states that in the event the actual strength of the structural member is less than
thenominal strength, S, by an amount S, whileat sametimetheactual forcein themember is
greater than thenominal force, F, by an amount F, themember strength will still beno lessthan
themember force, and so themember will not fail duringerection. Thisequation providesadirect
appraisal of erection realities, in contrast to theallowable-stressapproach based on factored design
stresses.
Proceedingnowto rearrangethetermsin Equation 20.1, wend that
S
1
S
S
1 +
F
F
;
S
F
1 +
F
F
1
S
S
(20.2)
c 1999by CRCPressLLC
TheERFisnowdened as
ERF
S
F
(20.3)
that is, thenominal strength value, S, of themember divided by itsnominal forcevalue, F. Thus,
for erection structural integrity or reliability to bemaintained, it isnecessary that
ERF
1 +
F
F
1
S
S
(20.4)
20.19 MinimumErectionRatingFactors
In view of possibleerrorsin (1) theassumed weight of permanent structural components, (2) the
assumed weight and positioningof erection equipment, and (3) themathematical modelsassumed
for purposesof erection structural analysis, it isreasonableto assumethat theactual member force
for agiven erection condition may exceed thecomputed forcevalueby asmuch as10%; that is, it is
reasonableto takeF/F asequal to 0.10.
For tension members, uncertainties in (1) the area of the cross-section, (2) the strength of the
material, and (3) themember workmanship, indicatethat theactual member strength may beup
to 15% lessthan thecomputed value; that is, S/S can reasonably betaken asequal to 0.15. The
additional uncertaintiesassociatedwithcompressionmember strengthsuggest that S/S betakenas
0.25for thosemembers. Placingthesevaluesinto Equation 20.4, weobtain thefollowingminimum
ERFs:
Tension members: ERF
t,min
= (1 +0.10)/(1 0.15)
= 1.294, say 1.30
Compression members: ERF
c,min
= (1 +0.10)/(1 0.25)
= 1.467, say 1.45
Theproper interpretationof theseexpressionsisthat if, for agiventension(compression) member,
theERFiscalculatedas1.30(1.45) or more, themember canbedeclaredsafefor theparticular erection
condition. Notethat higher, or lower, valuesof erection ratingfactorsmay beselected if conditions
warrant.
Theminimum ERFsdetermined asindicated arebased on experienceand judgment, guided by
analysisandtest results. Theydonot reect anyspecicprobabilitiesof failureandthusarenot based
on theconcept of an acceptablerisk of failure, which might beconsidered thekeytoatotallyrational
approach to structural safety. This possible shortcoming in the ERF procedure might be at least
partially overcomeby evaluating theparameters F/F and S/S on a statistical basis; however,
thiswould involveaconsiderableeffort, and it might not even producesignicant results.
It isimportant to recognizethat theERFprocedurefor determiningerection strength adequacy is
baseddirectlyon fundamental strengthandstabilitycriteria, rather than beingonlyindirectlyrelated
to such criteriathrough themedium of adesign specication. Thus, theproceduregivesuniform
resultsfor theerection ratingof framed structural membersirrespectiveof thespecication that was
used to design themembers. Obviously, theend useof thecompleted structureisirrelevant to its
strength adequacy duringtheerection congurations, and thereforethedesign specication should
not bebrought into thepictureasthebasisfor erection appraisal.
Experience with application of the ERF procedure to long-span truss bridges has shown that it
placestheerection engineer in much better contact with thephysical signicanceof theanalysisthan
can be obtained by using the factored design stress procedure. Further, the ERF procedure takes
account of secondary stresses, which havegenerally been neglected in erection stressanalysis.
c 1999by CRCPressLLC
AlthoughtheERFprocedurewaspreparedfor applicationtotrussbridgemembers, thesimplegov-
erningstructural principleset forth by Equation 20.1could readily beapplied to bridgecomponents
of any type.
20.20 Decienciesof Typical ConstructionProcedure
DrawingsandInstructions
At thisstageof thereviewit isappropriatetobringforwardakeyproblemin therealmof bridgecon-
struction engineering: thestrongtendency for construction proceduredrawingsto beinsufciently
clear, and for step-by-step instructionsto beeither lackingor lessthan denitive. Asaresult of these
decienciesit isnot uncommon to nd thecontractorsshop and eld evolutionsto begoingalong
under somethinglessthan suitablecontrol.
Shopandeldoperationspersonnel whoareinapositiontospeakfranklytoconstructionengineers
will sometimeslet them know that proceduredrawingsand instructionsoften need to beclaried
and upgraded. Thisisapervasiveproblem, and it resultsfromtwo primecauses: (1) thefabrication
and erection engineersresponsiblefor drawingsand instructionsdo not haveadequateon-the-job
experience, and (2) they are not sufciently skilled in the art of setting forth on the documents,
clearly and concisely, exactly what isto bedoneby theoperationsforcesand, sometimesof equal
importance, what isnot to bedone.
Thismatter of clear and conciseconstruction proceduredrawingsand instructionsmay appear to
beapedestrian matter, but it isdecidedly not. It isakeyissueof utmost importancetothesuccessof
steel bridgeconstruction.
20.21 ShopandFieldLiaisonbyConstructionEngineers
In addition to the need for well-prepared construction procedure drawings and instructions, it
is essential for the staff engineers carrying out construction engineering to set up good working
relationswith theshop and eld production forces, and to visit thework sitesand establish effective
communication with thepersonnel responsiblefor accomplishingwhat isshown on thedocuments
(seeFigure20.13).
Construction engineersshouldrevieweachprojectedoperation in detail withthework forces, and
upgradetheproceduredrawingsand instructionsasnecessary, asthework goesforward. Further,
engineersshould bepresent at thework sitesduring critical stagesof fabrication and erection. As
acomponent of thesesitevisits, theengineersshould organizespecial meetingsof key production
personnel to go over critical operationsin detailcompletewith slidesand blackboard asneeded
thereby providing thework forceswith opportunitiesto ask questionsand discussproceduresand
potential problems, and providingengineerstheopportunity to determinehowwell thework forces
understand theoperationsto becarried out.
This matter of liaison between the ofce and the work siteslike the preceding issue of clear
construction procedure documentsmay appear to be somewhat prosaic; again, however, it isa
matter of paramount importance. Failure to attend to these two key issues constitutes a serious
problem in steel bridge construction, and opens the door to high costs and delays, and even to
erection accidents.
20.22 ConstructionPracticesandSpecicationsTheFuture
Themany existing differencesof opinion and proceduresin respect to proper governanceof steel-
work fabrication and erection for major steel bridges raises the question: How do proper bridge
c 1999by CRCPressLLC
FIGURE20.13: Visitingtheworksite. It isof rst-order importancefor bridgeconstructionengineers
to visit thesiteregularly and confer with thejob superintendent and hisforemen regardingpractical
considerations. Construction engineershavemuch to learn from thework forcesin shop and eld,
and viceversa. (Courtesy of BethlehemSteel Corporation.)
construction guidelinescomeinto existenceand nd their way into practiceand into bridgespeci-
cations?Lookingback over theperiod roughly from 1900to 1975, wend that themajor steelwork
construction companiesin theU.S. developed and maintained competent engineeringdepartments
that planned and engineered largebridges (and smaller ones as well) through thefabrication and
erection processeswith ahigh degreeof prociency. Traditionally, thesteelwork contractorsengi-
neers worked in cooperation with design-ofce engineers to develop the full range of bridgework
technical factors, includingconstruction proceduresand practices.
However, timeshavechangedduringthelast twodecades; since1970smajor steel bridgecontractors
haveall but disappeared in theU.S., and further, very few bridgedesign ofceshaveon their staffs
engineersexperiencedin fabrication anderection engineering. Asaresult, construction-engineering
often receiveslessattention and effort than it needsand deserves, and thisisnot agood omen for the
futureof thedesign and construction of largebridgesin theU.S.
Bridgeconstruction engineeringisnot asubject that isor can betaught in theclassroom; it must
belearned on thejob with major steelwork contractors. Thebest routefor an aspiringyoungcon-
struction engineer is to spend signicant amounts of time in the fabricating shop and at the job
site, interspersed with timedoingconstruction-engineeringtechnical work in theofce. It hasbeen
pointed out previously that although construction engineering and design engineering arerelated,
they constitute different practices and require diverse backgrounds and experience. Design engi-
neeringcanessentiallybelearnedinthedesignofce; constructionengineering, however, cannotit
requiresabackground of experienceat work sites. Such experience, it may benoted, isvaluablealso
for design engineers; however, it isnot asnecessary for themasit isfor construction engineers.
The training of future steelwork construction engineers in the U.S. will be handicapped by the
demiseof the Big Two steelwork contractorsin the1970s. Regrettably, it appearsthat surviving
steelworkcontractorsintheU.S. generallydonot havetheresourcesfor supportingstrongengineering
c 1999by CRCPressLLC
departments, andsothereissomequestionastowherethenext generationof steel bridgeconstruction
engineersin theU.S. will becomingfrom.
20.23 ConcludingComments
In closing this review of steel bridge construction it is appropriate to quote from the work of an
illustriousBritish engineer, teacher, and author, thelateSir Alfred Pugsley [14] :
Afurther crop of [ bridge] accidentsaroselast century fromoverloadingby trafcof
variouskinds, but aswehaveseen, engineerstoday concentratemuch of their effort to
ensurethat amarginof strengthisprovidedagainst thiseventuality. But thereisonetype
of collapsethat occursalmost asfrequently today asit hasover thecenturies: collapseat
alatestageof erection.
Theerection of abridgehasalwayspresented itsspecial perilsand, in spiteof ever-
increasingcareover thecenturies, fewgreat bridgeshavebeen built without lossof life.
Quite apart from the vagaries of human error, with nearly all bridges there comes a
critical time near completion when the success of the bridge hinges on some special
operation. Amongsuch are. . . thettingof alast section . . . in asteel arch, theinsertion
of theclosingcentral [ members] inacantilever bridge, andtheliftingof theroadwaydeck
[ structure] intopositiononasuspensionbridge. Andtherehavebeenmajor accidentsin
manysuch cases. It maybewondered why, if such critical circumstancesarewell known
to arise, adequate care is not taken to prevent an accident. Special care is of course
taken, but there are often reasons why there may still be a slip betwixt cup and lip.
Such operationscommonly involveunusually closecooperation between constructors
and designers, and between every gradeof staff, from thelaborersto thedesignersand
directorsconcerned; andthismayput astrain on thedesign skill, on detailedinspection,
and on practical leadership that isenough to exhaust even aBrunel.
In such circumstances it does well to . . . recall [ the] dictum . . . that it is essential
not to havefaith in human nature. Such faith isarecent heresy and avery disastrous
one. Onemust relyheavilyon thelessonsof past experiencein theprofession. Someof
thisexperienceisembodied in professional papersdescribingerection processes, often
(and particularly to young engineers) supercially uninteresting. Someiscrystallized
in organizational habits, such astheappointment of resident engineersfrom both the
contracting and [ design] sides. And somein precautionsI havemyself endeavored to
list . . . .
It isan easy matter to list such precautionsand warnings, but quiteanother for the
senior engineersresponsiblefor thecompletion of abridgetostand their ground in real
life. This is an area of our subject that depends in a very real sense on the personal
qualitiesof bridgeengineers. . . . At bottom, thesafety of our bridgesdependsheavily
upon theintegrity of our engineers, particularly theleadingones.
c 1999by CRCPressLLC
20.24 FurtherIllustrationsofBridgesUnderConstruction, Show-
ingErectionMethods
FIGURE 20.14: Royal Albert Bridge across River Tamar, Saltash, England, 1857. The two 455-ft
(139-m) main spans, each weighing 1060 tons, wereconstructed on shore, oated out on pairsof
barges, and hoisted about 100 ft (30 m) to their nal position using hydraulic jacks. Pier masonry
wasbuilt up after each 3-ft (1-m) lift.
c 1999by CRCPressLLC
FIGURE20.15: EadsBridgeacrosstheMississippi River, St. Louis, Mo., 1873. Therst important
metal arch bridgein theU.S., supported by four planesof hingelesstrussed archeshavingchrome-
steel tubular chords. Spans are502-520-502 ft (153-158-153 m). During erection, arch ribs were
tied back by cablespassingover temporary towersbuilt on thepiers. Arch ribswerepacked in iceto
effect closure.
c 1999by CRCPressLLC
FIGURE20.16: Glasgow(Missouri) railwaytrussbridge, 1879. Erectiononfull supportingfalsework
was commonplace in the 19th century. The worlds rst all-steel bridge, with ve 315-ft (96-m)
through-trusssimplespans, crossingtheMissouri River.
c 1999by CRCPressLLC
FIGURE20.17: Niagara River railway cantilever truss bridge, near Niagara Falls, New York 1883.
Massivewood erection traveler constructed sidespan on falsework, then cantilevered half of main
span to midspan. Erection of other half of bridgewassimilar. First modern-typecantilever bridge,
with 470-ft (143-m) clear main span havinga120-ft (37-m) center suspended span.
c 1999by CRCPressLLC
FIGURE20.18: Construction of monumental Forth Bridge, Scotland, 1888. Numeroussmall mov-
ableboomswereused, alongwith erection travelersfor cantileveringthetwo 1710-ft (521-m) main
spans. Themain compression membersaretubes12 ft (3.65 m) in diameter; many other members
arealsotubular. Total steelwork weight is51,000tons. Recordsarenot clear regardingsuchessentials
ascamberingand eld ttingof individual membersin thisheavily redundant railway bridge. The
Forth isarguably theworldsgreatest steel structure.
FIGURE20.19: PecosRiver railway viaduct, Texas, 1892. Erection by massivesteam-powered wood
traveler havingmany setsof fallsand very longreach. Cantilever-trussmain span has185-ft (56-m)
clear opening.
c 1999by CRCPressLLC
FIGURE20.20: Raising of suspended span, Carquinez Strait Bridge, California, 1927. The433-ft
(132-m) suspended span, weighing 650 tons, was raised into position in 35 min., driven by four
counterweight boxeshavingatotal weight of 740tons.
FIGURE 20.21: First Cooper River cantilever bridge, Charleston, S.C., 1929. Erection travelers
constructed 450-ft (137-m) side spans on falsework, then went on to erect 1050-ft (320-m) main
span (including437.5-ft [ 133-m] suspended span) by cantileveringto midspan.
c 1999by CRCPressLLC
FIGURE20.22: Erectingsouth tower of Golden GateBridge, San Francisco, 1935. Acreeper traveler
with two90-ft (27-m) boomserectsatier of tower cellsfor each leg, then isjumped tothetop of that
tier andproceedstoerect thenext tier. Thetower legsare90ft (27m) center-to-center and690ft (210
m) high. When thetraveler completed thenorth tower (in background) it erected aChicago boom
onthewest tower leg, whichdismantledthecreeper, erectedtower-topbracing, anderectedtwosmall
derricks(oneshown) to servicecableerection. Each tower contains22,200tonsof steelwork.
c 1999by CRCPressLLC
FIGURE20.23: Balanced-cantilever erection, Governor O.K. Allenrailway/highwaycantilever bridge,
Baton Rouge, La., 1939. First useof longbalanced-cantilever erection in theU.S. On each pier 650
ft (198m) of steelwork, about 4000tons, wasbalanced on the40-ft (12-m) baseformed by asloping
falsework bent. The compression load at the top of the falsework bent was measured at frequent
intervals and adjusted by positioning a counterweight car running at bottom-chord level. The
main spansare848-650-848 ft (258-198-258 m); 650 ft span shown. (Courtesy of Bethlehem Steel
Corporation.)
c 1999by CRCPressLLC
FIGURE 20.24: Tower erection, second Tacoma Narrows Bridge, Washington, 1949. This bridge
replaced rst TacomaNarrowsbridge, which blewdown in a40-mph (18-m/sec) wind in 1940. The
tower legsare60ft (18m) on centersand 462ft (141m) high. Thecreeper traveler isshown erecting
thewest tower, in background. On theeast tower, thecreeper erected a Chicago boom at thetop
of thesouth leg; thisboom dismantled thecreeper, then erected thetower-top bracingand astifeg
derrick, which proceeded to dismantletheChicago boom. Thetower manhoist can beseen at the
second-from-topmost landingplatform. Rivetingcagesareapproachingthetop of thetower. Note
tower-base erection kneebraces, required to ensure tower stability in free-standing condition (see
Figure20.27).
c 1999by CRCPressLLC
FIGURE20.25: Aerial spinning of parallel-wire main cables, second Tacoma Narrows suspension
bridge, Washington, 1949. Eachmaincableconsistsof 8702parallel galvanizedhigh-strengthwiresof
0.196-in. (4.98-mm) diameter, laidupas19strandsof mostly460wireseach. Followingcompaction
thecablebecameasolid round massof wireswith adiameter of 20-1/4in. (514mm).
Figure20.25a Tramwaystartsacrossfromeast anchoragecarryingtwowireloops. Three460-wirestrandshavebeen
spun, with two moreunder construction. Tramway spinningwheelspull wireloopsacrossthethreespansfrom east
anchorageto west anchorage. Suspended footbridgesprovideaccessto cables. Spinninggoeson 24hoursper day.
c 1999by CRCPressLLC
Figure20.25b Tramway arrivesat west anchorage. Wireloopsshown in Figure20.25aareremoved from spinning
wheelsand placed around strand shoesat west anchorage. Thistramway then returnsempty to east anchorage, while
tramwayfor other leg of endlesshaulingropebringstwowireloopsacrossfor secondstrandthat isunder construction
for thiscable.
c 1999by CRCPressLLC
Figure20.26a Erection of individual wireloops.
Figure20.26b Adjustment of individual wireloops.
FIGURE 20.26: Cable-spinning procedure for constructing suspension bridge parallel-wire main
cables, showing detailsof aerial spinning method for forming individual 5-mm wiresinto strands
containing400to500wires. EachwireloopiserectedasshowninFigure20.26a(refer toFigure20.25),
then adjusted to thecorrect sag asshown in Figure20.26b. Each completed strand isbanded with
tape, then adjusted to thecorrect sagin each span. With all strandsin place, they arecompacted to
formasolid round homogeneousmassof wires. Theaerial spinningmethod wasdeveloped by John
Roeblingin themid-19th century.
c 1999by CRCPressLLC
FIGURE20.27: Erection of suspendeddeck steelwork, secondTacomaNarrowsBridge, Washington,
1950. TheChicago boom on thetower raisesdeck steelwork componentsto deck level, wherethey
aretransported to deck travelersby material cars. Each trussdoublepanel isconnected at top-chord
level to previously erected trusses, and left open at bottom-chord level to permit temporary upward
deck curvature, which resultsfromthepartial loadingcondition of themain suspension cables. The
main span (at right) is2800ft (853m), and sidespansare1100ft (335m). Thestiffeningtrussesare
33ft (10m) deep and 60ft (18m) on centers. Tower-basekneebraces(seeFigure20.24) showclearly
here.
c 1999by CRCPressLLC
FIGURE20.28: Movingdeck traveler forward, second TacomaNarrowsBridge, Washington, 1950.
Thetraveler pulling-fallsleadlinepassesaroundthesheavebeamsat theforwardendof thestringers,
and isattached to thefront of thematerial car (at left). Thematerial car ispulled back toward the
tower, advancingthetraveler two panelsto itsnewposition at theend of thedeck steelwork. Arrows
show successive positions of material car. (a) Traveler at star of move, (b) traveler advanced one
panel, and (c) traveler at end of move.
c 1999by CRCPressLLC
FIGURE20.29: Erectingclosinggirder sectionsof Passaic River Bridge, NewJersey Turnpike, 1951.
Hugedouble-boomtravelers, eachweighing270tons, erect closingplategirdersof the375-ft (114-m)
main span. Theclosing girdersare14 ft (4.3 m) deep and 115 ft (35 m) long and weigh 146 tons
each. Sidewiseentry wasrequired (asshown) becauseof long projecting splicematerial. Longitu-
dinal motion wasprovided at onepier, wheregirderswerejacked to effect closure. Closinggirders
werelaterally stablewithout oor steel ll-in, such that derrick fallscould bereleased immediately.
(Courtesy of BethlehemSteel Corporation.)
c 1999by CRCPressLLC
FIGURE20.30: Floating-in erection of atrussspan, rst ChesapeakeBay Bridge, Maryland, 1951.
Erected300-ft (91-m) deck-trussspansformerectiondock, providingaworkplatformfor twoderrick
travelers. Apermanent deck-trussspan servesasafalsework trusssupported on bargesand isshown
carrying the470-ft (143-m) anchor arm of thethrough-cantilever truss. Thisspan isoated to its
permanent position, then landed onto its piers by ballasting the barges. (a) Float leaves erection
dock, and (b) oat arrivesat permanent position. (Courtesy of BethlehemSteel Corporation.)
FIGURE20.31: Floating-in erection of atrussspan, rst ChesapeakeBay Bridge, Maryland, 1952. A
480-ft (146-m) trussspan, weighing850tons, supportedonfalseworkconsistingof apermanent deck-
trussspan alongwith temporary members, isbeingoated-in for landingonto itspiers. Suspension
bridgecablesareunder construction in background. (Courtesy of BethlehemSteel Corporation.)
c 1999by CRCPressLLC
FIGURE20.32: Erection of atrussspan by hoisting, rst ChesapeakeBay Bridge, Maryland, 1952.
A 360-ft (110-m) truss span is oated into position on barges and picked clear using four sets of
lifting falls. Suspension bridgedeck is under construction at right. (Courtesy of Bethlehem Steel
Corporation.)
c 1999by CRCPressLLC
FIGURE20.33: Erectionof suspensionbridgedeck structure, rst ChesapeakeBayBridge, Maryland,
1952. A typical four-panel through-trussdeck section, weighing99 tons, hasbeen picked from the
barge and is being raised into position using four sets of lifting falls attached to main suspension
cables. Theclosingdeck section ison thebarge, ready to go up next. (Courtesy of Bethlehem Steel
Corporation.)
FIGURE 20.34: Greater New Orleans cantilever bridge, Louisiana, 1957. Tall double-boom deck
travelers started at ends of main bridge and erected anchor spans on falsework, then the 1575-ft
(480-m) main span by cantileveringto midspan. (Courtesy of BethlehemSteel Corporation.)
c 1999by CRCPressLLC
FIGURE20.35: Tower erection, second DelawareMemorial Bridge, Wilmington, Del., 1966. The
tower erection traveler hasreached thetopmost erecting position and swingsinto placethe23-ton
closingtop-strut section. Thetower legswerejacked apart about 2in. (50mm) to provideentering
clearance. Thetraveler jumpingbeamsarein thetopmost workingposition, abovethecablesaddles.
The tower steelwork is about 418 ft (127 m) high. Cable anchorage pier is under construction at
right. First DelawareMemorial Bridge(1951) isat left. Themain span of both bridgesis2150ft (655
m). (Courtesy of BethlehemSteel Corporation.)
c 1999by CRCPressLLC
FIGURE20.36: Erectingorthotropic-platedeckingpanel, Poplar Street Bridge, St. Louis, Mo., 1967.
A ve-span, 2165-ft (660-m) continuousbox-girder bridge, main span 600 ft (183 m). Projecting
box ribsare5-1/217ft (1.75.2m) in cross-section, and deckingsection is2750ft (8.215.2
m). Decking sectionswereeld welded, whileall other connectionswereeld bolted. Box girders
arecantilevered to falsework bentsusingoverhead positioningtravelers (triangular structurejust
visibleabovedeck at left) for intermediatesupport. (Courtesy of BethlehemSteel Corporation.)
c 1999by CRCPressLLC
FIGURE20.37: Erectionof parallel-wire-strand(PWS) cables, theNewport Bridgesuspensionspans,
Narragansett Bay, R.I., 1968. Bridgeengineeringhistorywasmadeat Newport withthedevelopment
and application of shop-fabricated parallel-wiresocketed strandsfor suspension bridgecables. Each
Newport cable was formed of seventy-six 61-wire PWS, about 4512 ft (1375 m) long. Individual
wiresare0.202in. (5.13mm) indiameter andarezinccoated. Parallel-wirecablescanbeconstructed
of PWSfaster and at lower cost than bytraditional air spinningof individual wires(seeFigures20.25
and 20.26). (Courtesy of BethlehemSteel Corporation.)
Figure20.37a Aerial tramway tows PWSfrom west anchorage up side span, then on across other spans to east
anchorage. Strandsareabout 1-3/4in. (44mm) in diameter.
c 1999by CRCPressLLC
Figure20.37b Cableformersmaintain strand alignment in cablesprior tocompaction. Each nished cableisabout
15-1/4in. (387mm) in diameter. (Courtesy of BethlehemSteel Corporation.)
c 1999by CRCPressLLC
FIGURE20.38: Pipe-typeanchoragefor parallel-wire-strand(PWS) cables, theNewport Bridgesus-
pension spans, Narragansett Bay, R.I., 1967. Pipeanchoragesshown will beembedded in anchorage
concrete. Thesocketed end of each PWSispulled down itspipefromtheupper end, then seated and
shim-adjusted against theheavy bearing plateat thelower end. Thepipe-typeanchorageismuch
simpler and lesscostly than thestandard anchor-bar typeused with aerial-spun parallel-wirecables
(seeFigure20.25b). (Courtesy of BethlehemSteel Corporation.)
c 1999by CRCPressLLC
FIGURE 20.39: Manufacturing facility for production of shop-fabricated parallel-wire strands
(PWS). Prior to 1966, parallel-wire suspension bridge cables had to be constructed wire-by-wire
in theeld usingtheaerial spinningproceduredeveloped by John Roeblingin themid-19th century
(refer to Figures20.25 and 20.26). In theearly 1960samajor U.S. steelwork contractor originated
and developed aprocedurefor manufacturing and reeling parallel-wirestrands, asshown in these
patent drawings. APWScan contain up to 127wires(seeFigures20.45and 20.46). (a) Plan viewof
PWSfacility. Turntables11contain left-hand coilsof wireand turntables13contain right-hand
coils, such that wire cast is balanced in the formed strand. Fairleads 23 and 25 guide the wires
into half-layplates 27 and 29, followed by full layplates 31 and 32 whoseguideholes delineatethe
hexagonal shapeof nal strand 41. (b) Elevation viewof PWSfacility. Hexagonal die33containssix
spring-actuated rollersthat formthewiresintoregular-hexagon shape; and similar roller dies47, 49,
50, and 51 maintain thewiresin thisshapeasPWS41 ispulled alongby hexagonal dynamic clamp
53. The PWSis bound manually with plastic tape at about 3-ft (1-m) intervals as it passes along
between roller dies. ThePWSpassesacrossroller table163, then acrosstraversecarriage168, which
isoperated by traversemechanism 161 to direct thePWSproperly onto reel 159. Finally, thereeled
PWSismoved off-linefor socketing. Notethat wiremeasuring wheels(201) can beinstalled and
used for control of strand length.
c 1999by CRCPressLLC
FIGURE20.40: Suspended deck steelwork erection, theNewport Bridgesuspension spans, Narra-
gansett Bay, R.I., 1968. Theclosingmainspan deck section isbeingraised into position by two cable
travelers, each madeup of apair of 36-in. (0.91-m) wide-angerolled beamsthat ridethecableson
wooden wheels. Theclosingsection is40-1/2ft (12m) longat top-chord level, 66ft (20m) wideand
16ft (5m) deep, and weighsabout 140tons. (Courtesy of BethlehemSteel Corporation.)
c 1999by CRCPressLLC
FIGURE20.41: Erection of KansasCity Southern Railway box-girder bridge, near Redland, Okla.,
by launching, 1970. Thisnine-span continuousbox-girder bridgeis2110 ft (643 m) long, with a
main span of 330 ft (101 m). Box cross-section is11 14.9 ft (3.35 4.54 m). Thegirderswere
launched in two trains, onefrom thenorth end and onefrom thesouth end. A launchingnose
wasused to carry theleadingend of each girder train up onto theskidway supportsasthetrain was
pushed out onto successivepiers. Closurewasaccomplished at center of main span. (Courtesy of
BethlehemSteel Corporation.)
Figure20.41a Leadingend of north girder train movesacross250-ft (76-m) span 4, approachingpier 5. Main span
isto right of pier 5.
c 1999by CRCPressLLC
Figure20.41b Launchingnoseridesup onto pier 5skidway units, removinggirder-train leading-end sag.
Figure20.41c Leadingend of north girder train isnowsupported on pier 5.
c 1999by CRCPressLLC
Figure20.42a Typical assumederectionloadingof box-girder webpanelsincombinedmoment, shear, andtransverse
compression.
Figure20.42b Launch of north girder train frompier 4to pier 5.
Figure20.42c Negative-moment envelopesoccurringsimultaneouslywith reaction, for launch of north girder train
to pier 5.
FIGURE20.42: Erection strengtheningto withstand launching, KansasCity Southern Railway box-
girder bridge, near Redland, Okla. (seeFigure20.41).
c 1999by CRCPressLLC
FIGURE20.43: Erection of west arch span of twin-arch Hernando deSoto Bridge, Memphis, Tenn.,
1972. Thetwo900-ft (274-m) continuous-trusstied-archspanswereerectedbyahigh-tower derrick
boat incorporatingapair of barges. West-arch steelwork (shown) wascantilevered to midspan over
two pile-supported falsework bents. Projectingeast-arch steelwork (at right) wasthen cantilevered
to midspan (without falsework) and closed with falsework-supported other half-arch. (Courtesy of
BethlehemSteel Corporation.)
c 1999by CRCPressLLC
FIGURE20.44: Closureof east sidespan, CommodoreJohn Barry cantilever trussbridge, Chester,
Pa., 1973. A high-tower derrick boat (in background) started erection of trussesat both main piers,
supported on falsework; then erected top-chord travelers for main and side spans. The sidespan
traveler carried steelwork erection to closure, asshown, and thefalsework bent wasthen removed.
Themainspan traveler then cantileveredthesteelwork (without falsework) tomidspan, concurrently
witherectionbythewest-half mainspantraveler, andthetrusseswereclosedat midspan. Commodore
Barry hasa1644-ft (501-m) main span, thelongest cantilever span in theU.S., and 822-ft (251-m)
sidespans. (Courtesy of BethlehemSteel Corporation.)
c 1999by CRCPressLLC
FIGURE20.45: Reel of parallel-wirestrand (PWS), Akashi Kaikyo suspension bridge, Kobe, Japan,
1994. Each socketed PWSismadeup of 127 0.206-in. (5.23-mm) wires, is13,360ft (4073m) long,
and weighs96 tons. Plastic-tapebindingssecurethestrand wiresat 1-m intervals. Socketscan be
seen on right sideof reel. ThesePWSarethelongest and heaviest ever manufactured. (Courtesy of
Nippon SteelKobeSteel.)
c 1999by CRCPressLLC
FIGURE 20.46: Parallel-wire-strand main cable, Akashi Kaikyo suspension bridge, Kobe, Japan,
1994. The main span is 6529 ft (1990 m), by far the worlds longest. The PWSat right is being
towed acrossthespans, supported on rollers. Thecompleted cableismadeup of 290PWS, making
atotal of 36,830wires, and hasadiameter of 44.2in. (1122mm) followingcompactionthelargest
bridgecablesbuilt to date. Each 127-wirePWSisabout 2-3/8 in. (60 mm) in diameter. (Courtesy
of Nippon SteelKobeSteel.)
c 1999by CRCPressLLC
FIGURE20.47: Artistsrenderingof proposed MessinaStrait suspension bridge, Italy. TheMessina
Strait crossing has been under discussion sinceabout 1850, under investigation sinceabout 1950,
and under active design since about 1980. The enormous bridge shown would connect Sicily to
mainland Italy with asinglespan of 10,827ft (3300m). Towersare1250ft (380m) high. Thebridge
construction problems for such a span will be tremendously challenging. (Courtesy of Stretto di
Messina, S.p.A.)
c 1999by CRCPressLLC
References
[ 1] Conditionsof Contract andFormsof Tender, Agreement andBondfor UseinConnectionwith
Worksof Civil Engineering Construction, 6th ed. (commonly known as ICEConditionsof
Contract ), Inst. Civil Engrs. (U.K.), 1991.
[ 2] Copp, J.I., deVries, K., Jameson, W.H., and Jones, J. 1945. Fabrication and Erection Controls,
RainbowArch BridgeOver NiagaraGorge A Symposium, TransactionsASCE, vol. 110.
[ 3] Durkee, E.L, 1945. Erection of Steel Superstructure, RainbowArch BridgeOver NiagaraGorge
A Symposium, TransactionsASCE, vol. 110.
[ 4] Durkee, J.L. 1972. Railway Box-Girder Bridge Erected by Launching, J. Struct. Div., ASCE,
July.
[ 5] Durkee, J.L. and Thomaides, S.S. 1977. Erection Strength Adequacy of LongTrussCantilevers,
J. Struct. Div., ASCE, January.
[ 6] Durkee, J.L. 1977. Needed: U.S. Standard Conditionsfor Contracting, J. Struct. Div., ASCE,
June.
[ 7] Durkee, J.L. 1982. BridgeStructural Innovation: AFirsthand Report, J. Prof. Act., ASCE, July.
[ 8] Durkee, J.L. 1966. Advancementsin Suspension BridgeCableConstruction, Proceedings, In-
ternational Symposium on Suspension Bridges, Laboratorio Nacional de Engenharia Civil,
Lisbon.
[ 9] Enquiry into theBasisof Design and Methodsof Erection of Steel Box Girder Bridges. Final
Report of Committee, 4vols. (commonlyknownas TheMerrisonReport), HMSO(London),
1973/4.
[ 10] Feidler, L.L., Jr. 1962. Erectionof theLewiston-QueenstonBridge, Civil Engrg., ASCE,Novem-
ber.
[ 11] Freudenthal, A.M., Ed. 1972. TheEngineeringClimatologyof Structural Accidents, Proceedings
oftheInternational ConferenceonStructural SafetyandReliability,PergamonPress, Elmsford,
N.Y.
[ 12] Holgate, H., Kerry, J.G.G., and Galbraith, J. 1908. Royal Commission Quebec BridgeInquiry
Report, Sessional Paper No. 154, vols. I and II, S.E. Dawson, Ottawa, Canada.
[ 13] Petroski, H. 1993. PredictingDisaster, AmericanScientist, vol. 81, March.
[ 14] Pugsley, A. 1968. TheSafety of Bridges, TheStructural Engineer, U.K., July.
[ 15] Ratay, R.T., Ed. 1996. Handbookof TemporaryStructuresinConstruction, 2nd ed., McGraw-
Hill, NewYork.
[ 16] Schneider, C.C. 1905. TheEvolution of thePracticeof American BridgeBuilding, Transactions
ASCE, vol.54.
[ 17] Sibly, P.G. andWalker, A.C. 1977. Structural AccidentsandTheir Causes, Proc.Inst.Civil Engrs.
(U.K.), vol. 62(1), May.
[ 18] Smith, D.W. 1976. BridgeFailures, Proc. Inst. Civil Engrs. (U.K.), vol. 60(1), August.
c 1999by CRCPressLLC