Blue Nose II ABSID YY227007- Canadian Flag


Action Plan
Rev. 1
23/Jul/14
Ser. Remaining Items Action by
Expected closing
date
1
O2E technical comment as per attached list need to be sorted out.
See attached
2
Excessive Water leakage across Aft Transverse bulkhead to be dealt
with,alternatively risk assessement to be conducted and submitted for review
UPDATE
No action done. Lengkeek stated that same will be sent on 28 July 2014. Owner
concent will be required to accept Risk assessement
Leenkek
18 July 2014
28 July 2014
3
O2E surveyors comment #P 20 need to be verified
Yard Closed 15 July 2014
4
Shell isolating valves (Port & STB) of for the shaft seal sea water line, need to be
replaced with positive closing arrangement as it found ball valve.. O2E technical
comment found raised in this regards since 2012
closed ABS
5



this under owner
control
6
Anchor/ mooring winch. Handle of hand brake need to be re located as the anchor
chain hit the handle when in use also the liferaft in way of the chain to be
protected as same will be damage due to chain whipping during lowering the
anchor.
UPDATE
No action taken. Stated by Lengkeek that same may be completed on 30 July
2014
MHPM and
lengkeek
18 July 2014
30 July 2014
7
Main Engine protection device . Over speed trip to be provided.
UPDATE
Not Done . MHPM will issue request to yard to install it. Expect within 5 weeks
MHPM and Yard
8
Approved damage and stability calculation to be verified onboard. This is currently
under review by ABS
UPDATE
Still under review. ABS Technical office to advise
ABS 27-Aug-14
S.17(1)(d)(e)
2 of 2
Blue Nose II ABSID YY227007- Canadian Flag
Action Plan
Rev. 1
23/Jul/14
Ser. Remaining Items Action by
Expected closing
date
9
Hight of four (4) tanks vents located on main deck found less than required by
ILL convention. Designer has been advised to rectify same or MTRB to be
submitted
UPDATE
Fwd Pipes will be corrected by 30 July 2014. Aft Pipe Pending due to new
steering. Owner action is required
Leenkek and
Yrad
30-Jul-14
10
Safety Equipment are to be provided based on the trading area and nos. of
passenger. Trading area and nos. of passengers need to be confirmed by the
client.
UPDATE
None
Owner
11
Certificate of the oily water separator along with 5 PPM alarm are to be provided
also the system to be tested. Oil record book to be verified.
(submitted by yard on 15 J uly 2014- To be verified against the actual installation
and to be tested)
UPDATE
Certificate submitted. OWS satisfactory tested. Operation instruction need to be
posted in the vicinity of OWS. To be verified 30 July 2014
ABS
Partilly Closed 15
July 2014-
12
Main Engine Certificates re IAPP and their technical file to be provided re IAPP
certification.
UPDATE
Received from the Yard and found approved by EPA. ABS will check with TC if
EPA is accepted or not
ABS to consult
with TC
30-Jul-14
13
Navigation lights not yet provided also no records that navigation drawing has
been sent for review.(Desgner submitted approved drawing. Installation to be
verified against the approved drawings
UPDATE
Verified 23 July 2014- Alarm need to be sound at control station (manned area).
Yard will provid same by 30 July 2014
Yard 30-Jul-14
AMERICAN BUREAU OF SHIPPING
INFORMATION MANAGEMENT SYSTEM
ENGINEER COMMENTS REPORT
22-JUL-14 14:27:31
Page 1 of 2
2443826 Project No :
LENGKEEK VESSEL ENGINEERING Submitter :
P-009
P-020
S-122
S-123
S-124
Please advse location of main and emergency lighting panels and switchboards in accordance with 4-
6-3/3.7, 4-6-3/3.11.4, and 4-6-3/3.9 of the Under 90M Rules.
4-6-3/3.7 above is a typo and should read 4-6-3/13.7. To be demonstrated to the satisfaction of the
attending Surveyor.
Please provide flexible hose details in accordance with 4-4-1/9.19.3 of the Under 90M Rules.
We note the drawing say Approved wire reinforced, please provide approval certificates to the
attending Surveyor.
Surveyor to verify permanent mean of weather tight closure is attached. See (Transport Canada, TP
13313 E, 5.6 Ventilators).
Surveyor to verify Deck House Penetration and Removable Access Plate are weather tight.
Surveyor to verify that fan plenum and riser pipe is securely attached to deckhosue structure.
J09056-M01
J09056-M04
J09056-M05
J09056-M16
J09056-M16
J09056-M16
Machinery Arrangement
Sea Water Cooling Diagram
Fuel Transfer and Service System
GALLEY VENTILATION
ARRANGEMENT
GALLEY VENTILATION
ARRANGEMENT
GALLEY VENTILATION
ARRANGEMENT
638911
T1213687
774918
774918
T1213687
T1213687
T1213687
YY227007 Facility No :
Technical
Surveyor
Technical
Surveyor
Surveyor
Surveyor
Surveyor
Open
Open
Open
Open
Open
Open
Open
Houston SED Structures - Navy & Yachts Engineering Office :
02-Mar-2011
18-Jul-2014
02-Mar-2011
05-Aug-2011
18-Jul-2014
18-Jul-2014
18-Jul-2014
WCN : 918542
Observation :
Observation :
Observation :
Observation :
Observation :
Observation :
Observation :
Comment
Number
Drawing
Number
Drawing
Title
Task No Reviewer Comment
Action Type
Status Opened In Closed In
Closed In Report :
Closed In Report :
Closed In Report :
Closed In Report :
Closed In Report :
Closed In Report :
Closed In Report :
S.20(1)
S.20(1)
S.20(1)
S.20(1)
S.20(1)
S.20(1)
S.20(1)
AMERICAN BUREAU OF SHIPPING
INFORMATION MANAGEMENT SYSTEM
ENGINEER COMMENTS REPORT
22-JUL-14 14:27:31
Page 2 of 2
3308981
2443826
Project No :
Project No :
LUNENBURG SHIPYARD ALLIANCE (LSA)
MHPM PROJECT MANAGERS INC.
Submitter :
Submitter :
E-076
E-077
L-011
The new motor controllers disconnect if located more than 50 feet from the motor or if not within sight
of both motor and its controller, means for locking in the open position is to be provided in accordance
with 4-6-3/3.13.2(b) of the SV Rules <90M. This item is to be verified to the satisfaction of the
attending Surveyor.
The steering gear is to be tried out on the trial trip in order to demonstrate to the Surveyors
satisfaction that the requirements of the Rules have been met in accordance with 4-3-3/15.3 of the
SV Rules <90M.


4
4
4. Electrical Schematic Drawing 14-
094-ES 01 01 3
4. Electrical Schematic Drawing 14-
094-ES 01 01 3
T1222075
T1222075
653963
YY227007
YY227007
Facility No :
Facility No :
Surveyor
Surveyor
Surveyor
Open
Open
Open
Houston SED Machinery - Equipment
Houston SED Structures - Navy & Yachts
Engineering Office :
Engineering Office :
22-Jul-2014
22-Jul-2014
02-Mar-2011
WCN :
WCN :
404983
330994
Observation :
Observation :
Observation :
Comment
Number
Comment
Number
Drawing
Number
Drawing
Number
Drawing
Title
Drawing
Title
Task No
Task No
Reviewer
Reviewer
Comment
Action Type
Comment
Action Type
Status
Status
Opened In
Opened In
Closed In
Closed In
Closed In Report :
Closed In Report :
Closed In Report :
S.20(1)
S.20(1)
S.20(1) S.17(1)(d)(e) S.17(1)(d)(e)
S.17(1)(d)(e)
Page 1 of 9
Comment No. Drawing No. Drawing Title Opened In Engineering Office Description
S-061 `J09056-S01 Structural Midship
Section
18-Feb-11 Please submit Tonnage Admeasurement.
L-001 `J09056-A03 Lifesaving Plan 02-Mar-11 The symbols are to be white on a green background per IMO Resolution A.760(18).
L-004 `J09056-A03 Lifesaving Plan 02-Mar-11 A battery-powered loud hailer shall be located at each embark station per 70.d.i of C.R.C. 1436.
P-002 `J09056-A04 Fire Control Plan 02-Mar-11 Please update symbols in accordance with IMO Resolution A.952(23).
P-024 `J09056-M03 Bilge and Fire Fighting
System
02-Mar-11 We assume a vent and sounding diagram will be provided showing compliance with 4-4-4/9,4-4-
3/11, 4-4-3/13, and 4-4-4/1.9. Also see 13 of Schedule XII Part I and Schedule XV Part I Division II
Sections 78 through 111 of the Marine Machinery Regulations.
P-024 `J09056-M06 Potable Water System 02-Mar-11 We assume a vent and sounding diagram will be provided showing compliance with 4-4-4/9,4-4-
3/11, 4-4-3/13, and 4-4-4/1.9. Also see 13 of Schedule XII Part I and Schedule XV Part I Division II
Sections 78 through 111 of the Marine Machinery Regulations.
P-024 `J09056-M09 L.O. Transfer Diagram 02-Mar-11 We assume a vent and sounding diagram will be provided showing compliance with 4-4-4/9,4-4-
3/11, 4-4-3/13, and 4-4-4/1.9. Also see 13 of Schedule XII Part I and Schedule XV Part I Division II
Sections 78 through 111 of the Marine Machinery Regulations.
P-020 `J09056-M04 Sea Water Cooling
Diagram
02-Mar-11 Please provide flexible hose details in accordance with 4-4-1/9.19.3 of the Under 90M Rules.
P 020 `J09056 M04 Sea Water Cooling
Diagram
05 Aug 11 We note the drawing say Approved wire reinforced, please provide approval certificates to the
attending Surveyor.
P 020 `J09056 M05 Fuel Transfer and Service
System
05 Aug 11 We note the drawing say Approved wire reinforced, please provide approval certificates to the
attending Surveyor.
P-024 `J09056-M06 Potable Water System 08-Jun-11 We note your response and await updated drawing showing sounding arrangement. Vent pipe shall
have a minimum area of 125% of the fill lines in accordance with 4-4-3/9.5 of the Under 90M Rules.
Please advise.
S-069 `J09056-S01 Structural Midship
Section
15-May-12 Details of fore and main mast shrouds submitted on 18 April 2012 and approved in association with
task 888109. Please submit details of deck attachments for remaining stays and runners.
P-039 `N/A Fire Suppression
Specification
02-May-12 We note it is your intent to provide components as listed in the manual, please provide us with a
specific bill of materials for DRB120124001 Sheets 1 and 2 so we can confirm compliance.
S-107 `J09056-A18 Deck Vent Arrangement 25-Jul-12 Provide details of "water excluding caps," closures on ventilation goosenecks and mushroom vents.
S-107 `J09056-A18 Deck Vent Arrangement 29-Nov-12 Details of mushroom vents and closures on ventilators have been provided. Provide details of
"water excluding caps" on tank vents, as referenced in General Note 6.
P-024 `J09056-A07 Tank Capactiy Plan 24-May-13 Common fuel vent pipe in salon has increased to 3.5" piping to ensure 125% of fill pipe sizing has
been met. Changes will be reflected on "As-Fitted" drawings.
Page 2 of 9
Comment No. Drawing No. Drawing Title Opened In Engineering Office Description
P-024 `J09056-M03 Bilge and Fire Fighting
System
24-May-13 Common fuel vent pipe in salon has increased to 3.5" piping to ensure 125% of fill pipe sizing has
been met. Changes will be reflected on "As-Fitted" drawings.
P-024 `J09056-M05 Fuel Transfer and Service
System
24-May-13 We note your response and await submission of the "As-Fitted" drawing.
P-024 `J09056-M06 Potable Water System 16-Dec-11 Per my email to fuel oil tanks 1 and 2 (also 3 and 4) have a common 2.5 vent while
each tanks is provided with its own 2 fill.
P-024 `J09056-M09 L.O. Transfer Diagram 16-Dec-11 Per my email to fuel oil tanks 1 and 2 (also 3 and 4) have a common 2.5 vent while
each tanks is provided with its own 2 fill.
P-024 `J09056-M09 L.O. Transfer Diagram 24-May-13 We note your response and await submission of the "As-Fitted" drawing.
P-024 `J09056-M10 Tank Filling, Discharge
and Vent Piping
Arrangement (FWD)
24-May-13 Common fuel vent pipe in salon has increased to 3.5" piping to ensure 125% of fill pipe sizing has
been met. Changes will be reflected on "As-Fitted" drawings.
P-024 `J09056-M10 Tank Filling, Discharge
and Vent Piping
Arrangement (FWD)
24-May-13 We note your response and await submission of the "As-Fitted" drawing.
L-026 `J09056-M11 Ventilation Diagram 24-May-13 We note your response and await submission of J09056-M11 - Ventilation Diagram.
P-055 `J09056-M03 Bilge and Fire Fighting
System
18-Jul-14 We note that the notes were removed from these drawings, please note that the notes closed or
prevent many comments from being made. We assume they were removed in error, please advise.
P-055 `J09056-M06 Potable Water System 18-Jul-14 We note that the notes were removed from these drawings, please note that the notes closed or
prevent many comments from being made. We assume they were removed in error, please advise.
P-055 `J09056-M13 Oily Water Separator
Diagram
18-Jul-14 We note that the notes were removed from these drawings, please note that the notes closed or
prevent many comments from being made. We assume they were removed in error, please advise.
P-024 `J09056-A07 Tank Capactiy Plan 18-Jul-14 We note the revised fuel drawing provides separate 2.5vents. Please revise the Tank Filling,
Discharge and Vent Piping Arrangement (J09056-M10) to be in agreement. We note that details of
the potable water tanks, Lube Oil tank, OWS tank, remain to be provided.
P-024 `J09056-M05 Fuel Transfer and Service
System
18-Jul-14 We note the revised fuel drawing provides separate 2.5vents. Please revise the Tank Filling,
Discharge and Vent Piping Arrangement (J09056-M10) to be in agreement. We note that details of
the potable water tanks, Lube Oil tank, OWS tank, remain to be provided.
S.20(1)
S.20(1)
Page 3 of 9
Comment No. Drawing No. Drawing Title Opened In Engineering Office Description
P-024 `J09056-M10 Tank Filling, Discharge
and Vent Piping
Arrangement (FWD)
18-Jul-14 We note the revised fuel drawing provides separate 2.5vents. Please revise the Tank Filling,
Discharge and Vent Piping Arrangement (J09056-M10) to be in agreement. We note that details of
the potable water tanks, Lube Oil tank, OWS tank, remain to be provided.
S-124 `J09056-M16 GALLEY VENTILATION
ARRANGEMENT
18-Jul-14 Surveyor to verify that fan plenum and riser pipe is securely attached to deckhosue structure.
P-024 `J09056-M05 Fuel Transfer and Service
System
08-Jun-11 We note your response and await updated drawing showing sounding arrangement. Vent pipe shall
have a minimum area of 125% of the fill lines in accordance with 4-4-3/9.5 of the Under 90M Rules.
Please advise.
S-063 `J06056-SK18 18-Feb-11
L-006 `J09056-A04 Fire Control Plan 02-Mar-11 One 45L foam fire extinguisher is required in addition to the 9L in accordance with 46.1 1.c and 1.d
of C.R.C. 1422.
P-024 `J09056-M10 Tank Filling, Discharge
and Vent Piping
Arrangement (FWD)
08-Jun-11 Vent arrangement has been provided. -F.O. storage and domestic tank levels are indicated through
senders and gauges and note has been added to revised Vent and Filling arrangement (M10). -F.O.
service tanks include gauge glasses with valves as indicated on F.O transfer and service diagram
(M05) -Note has been added to F.O. transfer and Service diagram (M05) to indicate ball valves to be
installed inline with pressure gauges. -
P-024 `J09056-A07 Tank Capactiy Plan 16-Dec-11 Per my email to fuel oil tanks 1 and 2 (also 3 and 4) have a common 2.5 vent while
each tanks is provided with its own 2 fill.
P-024 `J09056-M05 Fuel Transfer and Service
System
16-Dec-11 Per my email to fuel oil tanks 1 and 2 (also 3 and 4) have a common 2.5 vent while
each tanks is provided with its own 2 fill.
S-122 `J09056-M16 GALLEY VENTILATION
ARRANGEMENT
18-Jul-14 Surveyor to verify permanent mean of weather tight closure is attached. See (Transport Canada,
TP 13313 E, 5.6 Ventilators).
S-062 `J06056-SK18 18-Feb-11
P-024 `J09056-M03 Bilge and Fire Fighting
System
08-Jun-11 We note your response and await updated drawing showing sounding arrangement. Vent pipe shall
have a minimum area of 125% of the fill lines in accordance with 4-4-3/9.5 of the Under 90M Rules.
Please advise.
P-024 `J09056-M03 Bilge and Fire Fighting
System
16-Dec-11 Per my email to fuel oil tanks 1 and 2 (also 3 and 4) have a common 2.5 vent while
each tanks is provided with its own 2 fill.
P-024 `J09056-M06 Potable Water System 18-Jul-14 We note the revised fuel drawing provides separate 2.5vents. Please revise the Tank Filling,
Discharge and Vent Piping Arrangement (J09056-M10) to be in agreement. We note that details of
the potable water tanks, Lube Oil tank, OWS tank, remain to be provided.
S.20(1)
S.20(1)
S.20(1)
S.17(1)(d)(e)
S.17(1)(d)(e)
S.17(1)(d)(e)
S.17(1)(d)(e)
Page 4 of 9
Comment No. Drawing No. Drawing Title Opened In Engineering Office Description
L-003 `J09056-A03 Lifesaving Plan 02-Mar-11 11 children's lifejackets are required per 17.5.b.ii of C.R.C. 1436.
P-024 `J09056-M09 L.O. Transfer Diagram 08-Jun-11 Vent arrangement has been provided. -F.O. storage and domestic tank levels are indicated through
senders and gauges and note has been added to revised Vent and Filling arrangement (M10). -F.O.
service tanks include gauge glasses with valves as indicated on F.O transfer and service diagram
(M05) -Note has been added to F.O. transfer and Service diagram (M05) to indicate ball valves to be
installed inline with pressure gauges. -
P-039 `N/A Fire Suppression
Specification
14-Jun-12 A bill of materials has been included on drawing DRB120124001, which has been submitted to ABS.
P-053 `DRB073012001 Galley Fire Protection
System Specification
30-Aug-12 Please revise sheet 2 to include the specific burner arrangement and nozzle distances in accordance
with 3-3 of the Manual.
P-024 `J09056-M09 L.O. Transfer Diagram 24-May-13 Common fuel vent pipe in salon has increased to 3.5" piping to ensure 125% of fill pipe sizing has
been met. Changes will be reflected on "As-Fitted" drawings.
P-055 `J09056-M07 Black and Grey Water
System
18-Jul-14 We note that the notes were removed from these drawings, please note that the notes closed or
prevent many comments from being made. We assume they were removed in error, please advise.
P-009 `J09056-M01 Machinery Arrangement 18-Jul-14 4-6-3/3.7 above is a typo and should read 4-6-3/13.7. To be demonstrated to the satisfaction of
the attending Surveyor.
S-123 `J09056-M16 GALLEY VENTILATION
ARRANGEMENT
18-Jul-14 Surveyor to verify Deck House Penetration and Removable Access Plate are weather tight.
P-024 `J09056-M10 Tank Filling, Discharge
and Vent Piping
Arrangement (FWD)
08-Jun-11 We note your response and await updated drawing showing sounding arrangement. Vent pipe shall
have a minimum area of 125% of the fill lines in accordance with 4-4-3/9.5 of the Under 90M Rules.
Please advise.
L-002 `J09056-A03 Lifesaving Plan 02-Mar-11 110 Lifejackets are required per 17.5.b.i of C.R.C. 1436.
P-009 `J09056-M01 Machinery Arrangement 02-Mar-11 Please advse location of main and emergency lighting panels and switchboards in accordance with 4-
6-3/3.7, 4-6-3/3.11.4, and 4-6-3/3.9 of the Under 90M Rules.
P-024 `J09056-A07 Tank Capactiy Plan 08-Jun-11 Vent arrangement has been provided. -F.O. storage and domestic tank levels are indicated through
senders and gauges and note has been added to revised Vent and Filling arrangement (M10). -F.O.
service tanks include gauge glasses with valves as indicated on F.O transfer and service diagram
(M05) -Note has been added to F.O. transfer and Service diagram (M05) to indicate ball valves to be
installed inline with pressure gauges. -
Page 5 of 9
Comment No. Drawing No. Drawing Title Opened In Engineering Office Description
P-024 `J09056-M06 Potable Water System 08-Jun-11 Vent arrangement has been provided. -F.O. storage and domestic tank levels are indicated through
senders and gauges and note has been added to revised Vent and Filling arrangement (M10). -F.O.
service tanks include gauge glasses with valves as indicated on F.O transfer and service diagram
(M05) -Note has been added to F.O. transfer and Service diagram (M05) to indicate ball valves to be
installed inline with pressure gauges. -
P-024 `J09056-M10 Tank Filling, Discharge
and Vent Piping
Arrangement (FWD)
02-Mar-11 We assume a vent and sounding diagram will be provided showing compliance with 4-4-4/9,4-4-
3/11, 4-4-3/13, and 4-4-4/1.9. Also see 13 of Schedule XII Part I and Schedule XV Part I Division II
Sections 78 through 111 of the Marine Machinery Regulations.
P-020 `J09056-M05 Fuel Transfer and Service
System
02-Mar-11 Please provide flexible hose details in accordance with 4-4-1/9.19.3 of the Under 90M Rules.
P-024 `J09056-A07 Tank Capactiy Plan 08-Jun-11 We note your response and await updated drawing showing sounding arrangement. Vent pipe shall
have a minimum area of 125% of the fill lines in accordance with 4-4-3/9.5 of the Under 90M Rules.
Please advise.
P-024 `J09056-M09 L.O. Transfer Diagram 08-Jun-11 We note your response and await updated drawing showing sounding arrangement. Vent pipe shall
have a minimum area of 125% of the fill lines in accordance with 4-4-3/9.5 of the Under 90M Rules.
Please advise.
P-039 `N/A Fire Suppression
Specification
14-Jun-12 We note that generally components are as listed in the manual, however The discharge nozzle part
number contains xx-xxx rather than the part number, please revise. The 100 ft roll of 1/16 cable is
listed as 06-118316-100 rather than 06-118316-000 as listed in the manual, we assume this is a
typo, please confirm.
P-039 `N/A Fire Suppression
Specification
18-Jul-12 We note your response and clarification to the typo. We also understand from your response that
you will supply the full model number of the discharge nozzle to ABS when it becomes known. This
comment remains open pending the submittal of the model number.
P-024 `J09056-A07 Tank Capactiy Plan 24-May-13 We note your response and await submission of the "As-Fitted" drawing.
P-024 `J09056-M05 Fuel Transfer and Service
System
24-May-13 Common fuel vent pipe in salon has increased to 3.5" piping to ensure 125% of fill pipe sizing has
been met. Changes will be reflected on "As-Fitted" drawings.
P-024 `J09056-M06 Potable Water System 24-May-13 We note your response and await submission of the "As-Fitted" drawing.
P-024 `J09056-M10 Tank Filling, Discharge
and Vent Piping
Arrangement (FWD)
16-Dec-11 Per my email to fuel oil tanks 1 and 2 (also 3 and 4) have a common 2.5 vent while
each tanks is provided with its own 2 fill.
L-026 `J09056-M11 Ventilation Diagram 24-May-13 Change has been reflected on drawing J09056-A18. Changes will be reflected on drawing M11
when submitted as "As Fitted" drawing.
S.20(1)
Page 6 of 9
Comment No. Drawing No. Drawing Title Opened In Engineering Office Description
Z-001 `Correspondence 17 JUNE 2013- J09056 -
Bluenose II - Loadline
calculation
25-Sep-13 A request has been sent to Transport Canada on 24 Sept 2013 for a Marine Technical Review Board
decision regarding the use of the USCG Trim Resistivity Method to reduce the Bow Height
perscribed in ICLL Regulation 39. This comment will be closed following the final desision from the
MTRB.
P-055 `J09056-M09 L.O. Transfer Diagram 18-Jul-14 We note that the notes were removed from these drawings, please note that the notes closed or
prevent many comments from being made. We assume they were removed in error, please advise.
L-006 `J09056-A04 Fire Control Plan 18-Jul-14 We note that 2 additional 2.5 gallon foam extinguishers have been added. While we would have no
objections to the use of smaller fire extinguishers this is a Transport Canada requirement and
requires an MTRB to resolve. Further we note that the 5 gallons added is less than half the 45L
required.
P-002 `J09056-A04 Fire Control Plan 18-Jul-14 We note that several symbols have been revised. The fuel oil pump remote shut-off and the remote
control for fuel oil valves shall be gray not black. The right side of the fire hydrant valve shall be
green. The color for the NOVEC symbols shall be brown. Please advise the location of the
emergency source of power (2.35 IMO Resolution A.852(23)).
P-024 `J09056-M03 Bilge and Fire Fighting
System
18-Jul-14 We note the revised fuel drawing provides separate 2.5vents. Please revise the Tank Filling,
Discharge and Vent Piping Arrangement (J09056-M10) to be in agreement. We note that details of
the potable water tanks, Lube Oil tank, OWS tank, remain to be provided.
P-024 `J09056-M09 L.O. Transfer Diagram 18-Jul-14 We note the revised fuel drawing provides separate 2.5vents. Please revise the Tank Filling,
Discharge and Vent Piping Arrangement (J09056-M10) to be in agreement. We note that details of
the potable water tanks, Lube Oil tank, OWS tank, remain to be provided.
S-053 `J09056-S01 Structural Midship
Section
18-Feb-11 Please submit Vessel Operations Manual.
P-024 `J09056-M03 Bilge and Fire Fighting
System
08-Jun-11 Vent arrangement has been provided. -F.O. storage and domestic tank levels are indicated through
senders and gauges and note has been added to revised Vent and Filling arrangement (M10). -F.O.
service tanks include gauge glasses with valves as indicated on F.O transfer and service diagram
(M05) -Note has been added to F.O. transfer and Service diagram (M05) to indicate ball valves to be
installed inline with pressure gauges. -
P-024 `J09056-A07 Tank Capactiy Plan 02-Mar-11 We assume a vent and sounding diagram will be provided showing compliance with 4-4-4/9,4-4-
3/11, 4-4-3/13, and 4-4-4/1.9. Also see 13 of Schedule XII Part I and Schedule XV Part I Division II
Sections 78 through 111 of the Marine Machinery Regulations.
Page 7 of 9
Comment No. Drawing No. Drawing Title Opened In Engineering Office Description
P-024 `J09056-M05 Fuel Transfer and Service
System
08-Jun-11 Vent arrangement has been provided. -F.O. storage and domestic tank levels are indicated through
senders and gauges and note has been added to revised Vent and Filling arrangement (M10). -F.O.
service tanks include gauge glasses with valves as indicated on F.O transfer and service diagram
(M05) -Note has been added to F.O. transfer and Service diagram (M05) to indicate ball valves to be
installed inline with pressure gauges. -
S-069 `J09056-S01 Structural Midship
Section
18-Feb-11 Please submit details of chain plates and attachment points for all shrouds and stays.
P-039 `N/A Fire Suppression
Specification
18-Jul-12 The type and size of discharge nozzle used is dependant on the the length of piping required for the
system. As such the exact nozzle that will be installed cannot be determined, until the piping for the
system is installed. We will supply the full model number of the discharge nozzel to ABS when it
becomes known. The model number for the 100ft roll of 1/16" cable did indeed contain a typo in
the manual. The model number to be used is 06-118316-100.
P-024 `J09056-M03 Bilge and Fire Fighting
System
24-May-13 We note your response and await submission of the "As-Fitted" drawing.
P-024 `J09056-M05 Fuel Transfer and Service
System
02-Mar-11 We assume a vent and sounding diagram will be provided showing compliance with 4-4-4/9,4-4-
3/11, 4-4-3/13, and 4-4-4/1.9. Also see 13 of Schedule XII Part I and Schedule XV Part I Division II
Sections 78 through 111 of the Marine Machinery Regulations.
P-055 `J09056-M05 Fuel Transfer and Service
System
18-Jul-14 We note that the notes were removed from these drawings, please note that the notes closed or
prevent many comments from being made. We assume they were removed in error, please advise.
P-024 `J09056-M06 Potable Water System 24-May-13 Common fuel vent pipe in salon has increased to 3.5" piping to ensure 125% of fill pipe sizing has
been met. Changes will be reflected on "As-Fitted" drawings.
L-026 `J09056-M11 Ventilation Diagram 16-Aug-12 Ventilators shall have coamings of a height of at least 900 mm above the deck in accordance with
Regulation 19.1 of the International Convention on Load Lines per Part II section 15.2.f of SOR02007-
99, Load Line Regulations. Please revise in accordance with J09056-A18 and comment S-106.
S-098 `SMS-BII-003-101 Deck Hatches,
Companionways and
Main Cabin
08-Feb-12 Please submit details contained in reserved areas on drawing.
S-099 `SMS-BII-003-101 Deck Hatches,
Companionways and
Main Cabin
08-Feb-12 Submit details of laminated glass used for portlights and skylights: manufacturer, layer make-up and
approval certificates.
E-080 `4

22-Jul-14


S.17(1)(d)(e) S.17(1)(d)(e)
Page 8 of 9
Comment No. Drawing No. Drawing Title Opened In Engineering Office Description
E-081 `4

22-Jul-14
E-075 `4

22-Jul-14


E-076 `4

22-Jul-14


E-079 `4

22-Jul-14

E-074 `4

22-Jul-14

E-077 `4

22-Jul-14

E-078 `4

22-Jul-14

.
L-011 ` 02-Mar-11






M-004 02-Mar-11
S.17(1)(d)(e)
S.17(1)(d)(e)
S.17(1)(d)(e)
S.17(1)(d)(e)
S.17(1)(d)(e)
S.17(1)(d)(e)
S.17(1)(d)(e)
S.17(1)(d)(e)
S.17(1)(d)(e)
S.17(1)(d)(e)
S.17(1)(d)(e)
S.17(1)(d)(e)
S.17(1)(d)(e)
S.17(1)(d)(e)
S.17(1)(d)(e)
S.17(1)(d)(e)
S.17(1)(d)(e)
S.17(1)(d)(e) S.17(1)(d)(e)
S.17(1)(d)(e)
Page 9 of 9
Comment No. Drawing No. Drawing Title Opened In Engineering Office Description
M-003 ` 02-Mar-11



S.17(1)(d)(e) S.17(1)(d)(e) S.17(1)(d)(e)


King Post is too high (2) (3),
3. Foremast poorly stepped (2)(4)
4. Mainmast poorly stepped (2)
5. Forward cowl vent interferes with jumbo boom and starboard anchor wire (2)(3)(4)
6. Dory chocks in wrong location (too far forward) (2)(3)
7. Stainless steel plate to go on counter around main sheet lower block (1)(3) Plate missing
8. No latches for lifting most of the deck access hatches (1)(4)
9. Supply 4 chairs for salon table (1)(3)
10. Handrails to be installed in all hatchways (1)(3)(4)
11. Guardrails installed (life lines)(Call ABS)1)(3)(4)
12. Capstan Installed Needs better fastening more fittings(1)(3)(4)
14. Signage below decks (1)(3)(4)
15. Steering gear & box (1)(3)(4)
16. Med ladder ironwork ------unknown, no trial completed as this side lays against the dock.
17. "Emergency" fair leads, needs to be assessed and anchor point provided
18. Boom chain anchor points turned 90 degrees
21. Crutch chocks on cabin house Not installed
23. Engine Room fans, excessive noise level (107db) (2)(4) Needs variable speed
25. Plugs not cut & sanded on thumb cleats P/S rail forward.
26. Stainless protection on mooring bitts
27. Steel protection on rail for anchors
29. A large number of the pins on the rails are in the wrong place. Capt marked correct placement as
requested by LSA & owners last year.
30. Wooden covers on escape hatches are splitting
31. Rail split underneath aft port chalk
32. Several deck planks have the shakes and should be replaced as discussed with Wade Croft.
35. Chart table does not slide easily (or at all)
36. Finishing piece inboard of chart drawers

Aft head
37. Deck head by exhaust fan should be boxed in
38. Tiles

39. Method to secure door open
40. Deck head against tile unfinished in upper forward edge of shower space
Aft alley way
41. Supply fan works, but little air from vents
42. Finish on sole in poor shape
43. No finish on sole access panel in book case
44. Skylight interior unfinished, hooks will not hook

Capt cabin
45. Wire chase cover as noted by Covey Island. This may be an ongoing project

Below Forward
46. Spurling pipe shows signs of water leakage
47. Fwd Starboard head sole caulking is pulling away from between sole and wall (for lack of a better
inclusive term)

Fwd port head
48. Stainless nosing damaging door
49. Sole caulking should be examined
50. Saw breakout around lower cabinet doors, it should be filled, sanded and repainted.

Galley
54. Nosing bent on hatch outside cooks cabin, no hatch trim in hatches in galley
Saloon
55. No method to secure heavy watertight doors in the open position
57. Cushions in main salon too soft, sit on wooden lip.