Anda di halaman 1dari 11

m.

Reinforcement:
a. Reinforcement of footings up to roofing average 9~0
man hours/lOO kilos.
FormWork: .: ", ' '
a. Footing. grade, column ....2.5 man hours/sq. m.
b. Beams, bond beams"floor slab - 2.8 man hf$./sq .. m,
c. Roof beams and bond beams - 3.01 manhrs.Zsq, m.
d. Roof slabs - 3~34man hours /sq. m.
e. Retaining walls - 2.4man houra/sq.m,
f. Stairs and landing> 2.48 man hours/sq. m.
g. Formonapplication - 6.0 man hours/lO sq. m.
EarthWork:
a. Excavation-182to 2.89 man hours/cu. m.:
b. Back Fill- 134manhours/cu. m.
I .
CONSTRUCTION WQRltCAPACI1'IJ !:S IN f d A l \ I . HO~
2 E >.
22.
2 1.
20.
19.
Installation of OJ . Pipe1/2 0 x 20"
2men install 20lights/day
Installation of Doors and WindowJ amp:
1man InstallSpes,2"x5"x16'"or 40 bel: ft./day
Installation of Door (Completeof Hinges and Knob);
1man Install 2,pes.door/day, '
Fabrication of Doors (ExcludingPlanning of Frames):
1Ill<lIl makes 3pes./day,, '
Planning RoughLumber (IncludingAlligDIn~nt):
1man Planes 4pcs. 2' x4' xIS' or 48bd. ft../day
Planntttg Rougb Lumber (NoAlignment)
I,IllaD.Planes,.10pes. 2"x 4":x:1.8"or 120bet ft../day.
Installation of PlyW<J Od, ~d:
2men install 1$sheets 4"x S"/day
'Installation of WoodenPost:
.,2men install6 pes.4"x 4"x 12 or 96bd, It./day
In~tallat1onof\VoodJ alousies Windows:
lOmanmstaU2 pes, 30"x.45" or 18.15 sq. ft/day
18.
85
24.
, 25.
23.
1. Concretlng of Plain Flooring:
2men pour 1.2cuv m. concrete/day
2. Concreting of Reinf. Flooring:
2men pour 0.84 cu. em.cQnc./day
3. Concreting of Column and Beam:
2.menpour O.flOcu. In. conc./daY
4. Finishing of Flooring (rough)
2mert finishcs12.sqi m./day
5. Ftmshtng of CHBJ oints:
2menflntshes 4?0 pcs.! d~y
6. Plastering of CHB: -. ' I ~~,' j
2men plasters 8 sq. m/ day' {j
7. Layingof CHB:
" 2merday 100pes/day"
8. Breakingold,R-C FlOOring:
2.men,bteak~.30 cu. m./day
9. LayingofgIazed tile'4" x 4"
2men lay 100pcs./daY
10. Layingofgiazed tile6"x 6,"
'2menlay 72 pcs./day
11. Installation of Water Closet:
2men mstall J -set wC/2 days
12. Installation of Lavatory:
/ 2men illstalll-setLav./1 1/2 day
13. InstallationofG.I. Sheets, 32"x8" onSteel Frames
2men installs 11sheets/day
14. Installatiion of G.L Sheets 32..x 8"onWooden Frames
, 2men install 20sheets/day
15. Installation of G.I. Sheets 32"x 12"onSteel Frames
2men tnstall Io sheets/day
16. Installation of o.r, Sheets 32"x 12"onWooden Frames
2men install 15sheets/day
17. Fabricating and Installation of Gutter Downspout. Rider
Roll:
2ment,')ricated install 5sheets: 32"x8"O.I. sheets/
day
LABOR E STIMATE
84
N01E: Cmph = = cum/hour: cmpt = cu.m/truck
5cmpt
3.5cmpt
9. 5-Tdump truck a. haulmg.common
.borrow
b. hauling selected
borrow base course
a. vibratory rolling
(6passes - 20emlift) 240cmph
a. static rolling
(6passes - 20em. lift) 24cmph
8. tandem roller
7. tractor - drawn
roller (1- d)
6. no. 3Wroad roller a. static rolling 24cmph
(6passes - 20em. lift)
a. static. rolltng
12pases - 15em, lift)
b.: vlbnltory rolling
(4passes - 15emliftj 135 em,/hr.
35cu.m./hr
30cu.m./hr
300sq.m./hr.
40cu.m./hr
SOOsq.m./hr.
200sq.m./hr.
r25. ciim~
, 5OCiL nr./hf.
3sq.m/hr.
CapabWty -
a. loading
aloading
a. sub-graving
b. spreading
,. 1
a. clearing
b. strtpping
c. excavation
d. quanying
e. pushing
Type of Work
{roller
5. sheep'sCoot
4. crane shovel
3. pay loader
2. grader
.I. dozen
Item
87
CAPABIL ITIES OF EQ'Q1PMENT
28sq. IU.
1.86sq.ni.
1.86sq.m.
20sq. m,
20sq. D1.
22pes.
2.09cu.m.
2.0cu. m.
4.0cu. m.
0.61eu.m.
0.38cu.m.
1.22cu.m.
0.76CU,m,
3.
1Mason a. L ayingC? f CHBand adobe
&
1 Helper b. .Cement finish
1Carpenter a. Erecting f01111S
&
1 Helper b. Removingforms
2.
man a. Excavating Loamor sand
b. Excavating Clay or Heavy
SoU
c. Excavating Rock
d. Backfilling .
e. Spreading. tamping and
Grading ~.
f. Placingeseombro fill
g. Placingbinders
h. Cleaning undergrowth arid
small blush
I, Cleaning underground and
brush 12"0
1.
TJpeof Work Unit
CAPABIL ITIES OF l\fANl1AL L ABOR PER HOUR
-
b. Oradeslab EWP- 13man hours/lOO sq. m.
c. Floor membrane - 15man hours/IOO sq. m.
.d. Roofbeams and bond beams- 2.88manhours/cu. m.
e. Stairs - 2.6man houra/cu, m.
f. .Roofslab - 2.91 man hoursj'cu. m.
g. Curtng(water) - 2.0man hours/day for 7days
h. Equipment:
. 1. Vibrator - 16min/cu.m.
2. Crane With concrete bucket - 4- cu. m./man hour
86
7.
6.
5 .
3~
4.
2.
Septic tanks arenolonger allowed.in. ~la wherethe
santtarysewerIsnowinoperation.Theymaystill however.
beofgreat serviceinsub-urban communities.
Location;noseptictankshall beInstalled withinorunder
thehouse.
Tanksmustbebulltwater tightofconcrete. Stoneorbrick.
Bothcompartment areprovided withmanholesandtight
coversforcleaningandnecessaryrepairs.
Inletsandoutletsaresubmergedinsuchawaythat neither
scumor sludgebe'undulydisturb.
Inletsandoutletsarearrangedsoastodeliverthesewage
tothemiddlethirdofthetankdepth. ForInstance, ina_tank
1.20 mdeep. the inlet and outlet be submerged'0.40
meters. .
Thevault isventedthru thesanitary feesinthetnletand
outlet. havingtopendsopenand. screenedtomake- tank
mosquito- proof.
1.
IMPORTANT FEATURES OF SEPTIC VAtlLTS
No. of Person 'Depth(M) Width(M) Length(M)
10 1.20 0.90 LaO
15 1.20 0.10 2.20
20 1.20 1.25 2.50
25 1.20 1.40 2.80
30 1.30 1.50 3.00
35 1.30 1.60 3.20
40 1.40 1.6E "3.30
45 1.40 1.80 3.50
50 1.50 1.80 3.50
60 1.50 1.90 .3.90
~~.
,_
4:'00 70 1.60
A OO
80 1.60 .20 4.40
2.20 90 1.80 4.40
100 1.80 2.30 4.60
INSIDE DIMENSIONSOF THE DIGESTION CHAMBER
89
1metrictonofasphalt cone. covers8sq. of pavement0.05m-
thickor0.43cu.rn. ofasphalt concrete.
0.23m/br.
0.30m./ht.
0.S8rn./ht.
0.49m./hr:
0.76m./hr.
22cu.m./trip
11cu.m./trip
a. haulingheap
capacity
a. haulingheap
capacity
a. drtllmgshardrock
b.drtllings looserock
c. drillingslimestone
d. drillingstickyclay
e. drillinglooseclay
a. fmishingcone. floor 140s.m.lhr~
21. percussion
20. scraper tour-
mapull45ton
19. scrapertowed
12cycap
is, cone.floor
. finisher
,
. b U c mix 40cu.m./hr.
17. concretevibrator a. vi ra ngcon .
30cu.m./hr.
.9. cm./hr.
300sq.m./hr
1000sq.m./hr.
0.01em./trip
a. crushingmixed
.sandandgravel
a. watering .
a. sprayingasphalt
prime
.a. haulingaggregates
l a. haulingcone. miXer 0.17cml/trip
2.5eu.m./trip
2.0cu.m./trip
a. haulingcommon
borrow
b. haulingsbbc
15. 1(:)-5 cone. mixer
16. rockcrusher
14. asphalt
distributor
13. watertruck
11. buggy
12. wheel borrow
dumptruck
10. 2-1/2 ~T
88
Check site condition and location. check availability of
transportation water supply electricity. etc.' Beforeproceedingto
estimate (consider an additional feefor hauling materials. ad-
justment of'labor cost fornon-avai!abilityofmanpower andother
factors that will affect construction operation due site).
GENERALCHECKLIST FOR ESTIMATE
SITE CHECKING:
3. FieldOffice: rental. telephone. electricity. officesupplies
4. Temporary' Factlttles: light arid power. water. sanitary
facilitles. fuel. gas for welding. roads. stairs. barricades,
runways. fencer. tool shed, warming lights.
5. Permit: building, streets. sidewalk, water sewer for trans-
portingheavyloads overcnystreete, '.Foruseofcitydumps.
6. Quality control: soil-compaetton test and boring, concrete
tests for aggregate. slump and strength, manufacturers
and materials suppliers certifications and, samples.
7. Meetings and submitWs: as-built drawings. progress
photographs. shop schedules,' progress report. J ob meet-
ing. .
8., 'Iransportatton.and freight: railway. trucking. demttrraged.
unloadfng. .
9. ocordmatmg: Cutting and patching. inspectlcing'subcon-
tractor work.
10. Final clean up: Patching -: touch up.. 'janitorial work.
handlingdebns finalinspection.
11. bonds: .suretylabor~and material payment bond. perfonn..,
.ance, bid, completton, supply. .
12. Insurance; general liability. fire. damage etc.
13. Protection: safety requirements, etc.
14. Repairs: sidewalk, streets; and curbs.
15. Miscellaneous: professional fee for engineer. attorney.
general company overhead, realttate taxes. contengenctes.
91
1. Equipment: rental. delivery. landing, erectmg, and des-
mantling
2. Personnel: salaries. fringebenefits. and payroll taxes for
superintendent. foreman. timekeeper. clerk etc.
J obOverhead:
CHECKLIST OF ITEMS TO BE CONSIDERED:
100iX !, ft./cu.m. formlumber
Cement-lO bags/cu. inplaster
Steel relnf. - 100to 130kgs./cu.m. of concrete
Roofframing- 14lxi. ft./sq.m. of roof area
Cellfugframing- '1bd. ft./sq.m. ceiling'
Nalls- 20kgs./IOOa bd. ft.
Studding. 2"x3"- 4bel ftjsq.m.
Sid,ing..;.~0.7bd. ft.,/sq.m.
Flooring- 10.8bd. ft./ sq.m.
FloorJ oists """ 2" x 6" - 15bd. ft.jsq.m.
Cellingjolsts - 2" x 2" - 4lxi. ft:/sq.m.
Purlins - 2" x 4" - 4.4 bd. ft./sq.m.
G.I. sheets - 32" x 8"- 0.7238,pcs./sq.m.
Roof nails - 2 1/2" - 0.082 kg./sq.m.
Roof cement - 0.042887 gal/sq.m.
Straps - 3" x 8" :- 0.0452377 sht.Zsq.m.
Rivets- 3/8" x 1/4" - 0.0069kg/sq.m.
G.I.washer..:..l/4- 0.15888 kg/sq.m.
ROUGH ESTIMATES
"8. The bottom of the tank should' 1:10 min. toward the
manhole in the center tofacilitate cleaning.
9. Notless than 0.20m, ofairspace should beleftbetween the
top of the sewageandthe underpart of the rank cover.
90
2.54MH/W
8.54MH/W
0.071MH/Kg.
0.4MH/W
1. GRADE MEMBER
Forwork
Concreting
Rebars Work _
Finishing
CONCRETE FOUNDATION ANDELEVATED CONCRETE
UNIT MAN HOURS .
20.MH/IOOSF
20MH/l00BF
22.5'
22.5
25.
25.'
30.
33~
35.
40.'
50.
75.
66.1MH/lOOIF
.100.2MH/IOOIF .
150.3
200.4
300.6
317.3
367.4
417.5
103
1/2"0
3/,*0
1'"0
1-1/20,
1-1/2"0
2"0
2"-1/2"0
3" '"
3"-1/3"0
4"0
5"0
60
PVC PIPES
2"0
4"0
S..-;0
~"0
100
120
14' 0
160
IS"0
CASTIRONPIPE
20.00MH/IOO BF
20J )() MH/IOO BF
20.50
22.50
25:00
25.00
30.00
33.00
35.00
40.00
1/20
3/40
10
1"-/4"0 .
1-1/20
2"0'
2"-1/2"0
30
3"-1/20
4"0
8. Trencliing byMachine
9. PipingInstallation
ASBESTOSCE~T PIPE
7. Trenching byHand
6. lUi.uUngSJ X >1ls
5. StrUcturalBackflU (Machllle
4. Structural Backfill (Manual)
3. Hook EXcavation(Manual and.Ma,chine
MH
6.0 M3
MH
.5W'
MH
8.0 :M3
5.0'MZ
MH
2.0V
MH
1~0W'
a.o':
0. 2 MIl

2 Common Excavation (Machine)


1. Common Exl:avaUon(Manual)
1J lIIIT MAN HOURS ITEM 01' WORK .
102
112
20
Crew 5 M/daywit
Break,s ....2.5 M
3/day
168
64
0.266
0.111
0.286-
0.171
1.33
1.40
2.86
2.86
2.86
1.6,7
4.00
1~67
105
LIght Stru~turaI'Steel Frame _ _
Heavy Structural Steel <Frame----'-_ _ _
Miscellaneous Iron
(Platforms-walkwaYs)<
StaJ rS. strillgers. baridtatIs __ _ _
Stair, treads. gratings<.... _ _ .,_ --
Painting of str, stl; frame _
Concrete demolition ........,; _
$TRuC1URAI.. StEEL
5. CEILING INCWDING FRAMING
1/4" TblL Plywood
Acoustic 1llewith plyWood
Backi
< <<. . ng. .<. .'.-< .--:....----'--- _ ..
Conceated Acoustic TIle Ceiling with
Alum-T<':'Runnes ....... <....... '----- .....
3/10"Thk.AsbestoTS ,_:----'---:-_,...._....
Plain Cement
ColoredCement
Peble Washout
Granul1th1c
MarblenIe
Vinyl
Unglazed
< Asphalt
4. FLOOR FIN.
0.23MH/Ft2
0.314MH/Ft2
0.314MH/Ft2
0.0236MH/Ft2
0.286MFI/Ft2
0.429MH/Ft2
0.42$MH/I;l:&. <
0.286MH/Ft2
0.715 MH/Ft2
0.71~MH/Ft~
O.2~Mtl/Ft2
6.286~/Ft2
0.86~[Ft2<
0.715 iMH/l"t2 .
0.09MH/Ft2
O.lOMH/Ft3
O.1l7~/Ft.2
0.133 Ma/Ft2
3.28MH/M
16.70MHM
O.08MH/KG
O.80MH/MI
PARITI10N (INC. FRAMEWORK)
1/2"1bk. SingleWall Plywood __
.1/4"1bk. Double Wall Plywood __
Wooden Louver
CycloneWire6a#10Partltlon __
3.
Fixed AsbestosLouverj, _
FixedG.l. LOuver
FiXed Glasson steel Frame -'- ____
WINDOWS 2 .
Door Exclud1ngc Fin.1shHardw8reS
He .PlyWoo<lFlush 1Y Pe_ < ---"---
sc J ?lyw~ Flush.1)rpe ......_......_.:.....,- ___
Steel Sliding
Steel Htnge
AlUIll..Roll-up
(Manua1J .Open:tted) ~-----
CycloneWIreSllrllng Door .,...
ARCHrIECTURAL SPECIALTIES
ROOFING AND SIDING
Metal Roofing
NOIl-MequRoofing
Metal Sidings
. NOIl-Metal s14fugs
104
2. SUSPENDED MEMBER
Forwork
Concretlrig
RebaIsWork
FInishing
3pft2/md
15ft2/mtl
17ft2/md
22ft2/md
5sets/md
20ft2J rn9
2Patrs/rnd
80If/md
1.34m2/md
00-300 ft2/md
2m2/md
60If/md
38/md
30-60l:>f/md
4O-80bf/md
75-150ft2/md
40-80ft2/rnd
46bf/md
40bf/md
6Q-90bf/md
50-75bf/md
90-120bf/md
40-60bf/Illd
25-3$.bf/md
18Shts/md
J OShts/md
16LF/md
52LF/md
29m2/md
2.3Shts/md
107
\,
QAB~
FranUri " , , g
~'
Plywood~heat:tng
Cabinet &Doors
TRUSSES
'l'ru$$,Fabrication
Truss ErectiOn
Posts
G.1rts
PlateS
Pcirlins
Facta aoax cts
DOORS a:lVlNJ )Ows
inst, WoodenWindows
Inst SasJ i. GlaSs
Inst'SteelWlnd()w
Inst WoodPanel Doors
Inst LOck Set'
trist WoodFlush,Doors
Inst, FlUsh Bolts
Inst Astragal
Vltrltled theWall Fin.
Painting
Floor Hardener
,Copper 1\0 StopCut &Shape - .......... --
Copper 1\0 Stop, Install
ROOFING AND,R2 PROOFING
Insts. Asbestos Roofing
Insts; A lum. or G.I. Roofing
~nst$.l.I. Gutter #24
Cooper Cladding Roof Deck
Insta1l.Memb~eJ i2 Proofmg' -;._
Fabricate. Q;,I.Qutters
8().() W/mcl
2AM2/md
3.87M3/md
1.00)i3/Illd
7Q.OO8F/tnd
112.008F/md
80f'TJ /md
44BF/md
60BF/md
1128F/m<f
33BF/md
)0$ Bt2J md
5OLF/md
18LF/md
27LF/md
60/mdLF/rnd
1.5rn2/md
45IF/md
10Fl/md
3Steps/rnd
1.35M3/m day
3.8? M3/mday
4.70
2.1.0
10kg'/Ill day
,.91 I113/md
11.aM3/rnd
16.5Kg/Illd
4.4Ul11ts/md
0.5M3/md
OraVeFlll
GooundFl()()rSlab (C()ncrettng).;...... --=-=-____
WoodColumns
Tagflooring
,PlywoodPa,:t1ttons
Cell F:ramfng
Siding FramIng
StoneCut SI~g .
Roof.FraIDtng
0.1. Roofing riA 26
0.1. Gutter (CutandShape)
G.I. Butter'(lnstall)
0.1. D.S. (CutandShape)
0.1.'D.S. (InStall)
VertiftedTIleFloor FIn.
Inst Casing Plates
Inst Steel SUdingDoor
Place Metal Nosing
Excavation
BackFUl
OisP<>saI of spons
ForWorlt
SteelWorK
Conci"etfilg
Flnislrlng
SetAnChorBolts
Sct.A nchor Box es
DemoUtlon (AdobeWall)
~avation Crane ~d ClamSh~ wId
Lab. aJ ld2Operators
CHB z Ocalo Wall
MISCELLANEOUS LABOR OUTPUT
'106
108
109
EXCAVATION
DEMOLITION
Hand Excavation
MANHOURS PER UNIT LISTED
Soil Excavation ManHours/Cu.M.
Dry 2.50/cu.m.
ITEM
MANHOURS
SoftClay
Wet 3.51 Ui11t Laborer AIrtooI Total
Hard Medium Dry 4.90
Operator
Wet 8.50
HardAdobe Dry 13.50
WithPneumatic Breaker
sq.m. 0.16 0.46 0.62
Wet 13.50
By Hand WithSledge sq.m, 3.24 3.24
BACKFILL
ELEVATED SLABS
Unit ManHo1U'S WithPneumatic Breaker
cu.m, 3.28 2.72 6.00
Labor Optr on Total
By Hand WithSledge
cu.m, 16.24
16.24
Hand Placed&Tamped
ByHand cu.m. 2.17 2.77
CONCRETE WALLS
Loader &Tamped
WithPneumatic Breaker
eu.m. 1.03 2.06 3.09
ByVibratory Roller cu.m. 0.40 0~O2 0.42
ByHand WithSledge
14.41 cu.m:
14.41
GRAVEL FILL
REMOVE CONCRETE CURDS
Hand Placed&Tamped
WithPneumatic Breaker
L.m.
0~36 0.36
ByVibratory Roller cu.m, 1.42 0.33 0.02 1.77
ByHand WithSledge
L.m. 1.48
1.48
SELECTED .FILL
CUT CONCRETE OPENINGS
Hand Placed&Tamped Pneumatic Chisels
cu.m,
7.96 7.96
ByRoller cu.m. 3.30 0.33 0.02 .3.65
Hand Chisels 1
cu.m,
18.34
1R34
Loader &TampedBy
0.42 Vibratory Roller cu.m. 0.40 0.02
Preparation of SOF s.m. 1.70 1.70
11
CONCRETING
MANHOURS
Item Laborer Carpenter optr.. Oller Total
Continuous Wall TypeFtgs.
Job MIx 5.10 0.05 0.05 5.20
Chute 0.75 0.05 0.80
Buggies 0.98 Q.98
Spread TypeFootings
JobMix s.io 0~05 0.05 5.20
Chute 0.86 0.07 0.93
Buggies 1.14 1.14
FootingTIeBeam
JobMbc 5.10 0.05 0.05 5.20
Chute 0.90 0.07 0.97
Buggies 1.48 .148
Foundation or Basement Walls
Job Mix 5.10 0.05 0.05 5~20
Chute 0.90 0.07 0.97
Buggies 1.48 1.48
Columns
By Hand &: Pulley 8.51 8.51
Porta-Lift 6:35 0.08 0.08 6.51
Crane, Bucket &: Buggies 2.02 0.16 0.16 2.34
RetainingWall to 10' High
By Hand &: Pulley 12.71 12.71
Porta-Uft 10.60 0.08 0.08 10..7~
TooledJoint Finish 3.67 1.22 4.89
PlaihCement Ftnfsh
(LouverBlocks) 4.00 0.47 4.47
GlazedTIles 6.38 2.13 8.51
Rubbed Concrete 4.27 O.H 4.38
Carpenter Laborer Total
Repair 1stre-use 0.01 0.003
0.().l3
Repair 2nd re-use 0.02 0.004 0.024
Repair 3rdre-use 0.03 0.006 .0.036
~pair subsequent re-use 0.04 0.007 0.047
Oilingafter each use 0.05 0.005 0.005
lto2SecttonLong 1.20 0.35 2.05 1.40 1.00 2.40
3to 5'SecUonLong 0.75 0.50 1.25 0.85 0.60 1.45
6sectionor morelong 0.65 0.35 0.95 0.75 0.40 1.15
I._ ; '
U-USEFACTORS
MANHOURSPERSECTION
1or 2SectionHigh Morethan2Sec. High
Erect Dls- Total Erect Dis- Total
mantle mantle
LENG'Ilt
SCAFFOLDING
ITEMS
MANHOURS
Carpenter Laborer Total
1. Continuous Wall 'I)'pe
0.70 0.40 1.10
(CHB)
2. FoUnda~()nonPtleCaps
1.50 0.65 2.15
3. Gradcf.Beamor FTB
0.75 0.40 1.15,
4. W~ Ground to8' High
1.10 0.72 2.92
5; WaDs S' to 16' High 1.21 0.78 1.99
6. Walls 16to2(),High 1.35 0.90 2.25
7. Columns
1.22 0.80 2.02
8. Beams & : Girders
1.90 1.22 3.12
9. Elevated Slabs (WordShores} 1.15 1.16 2.31
10. Elevated Slabs.(AdjustedShores) 0.70 0.90 1.60
'MANBOURS PER SQU~ METER
110
l'utDbf:d of.n_1
aar L eDllh
20' SO'
l q 22
12 19
10 15
S 12
7 11
6 10
6 9
5 S
5 7
4 6
4 6
4 6
1.33
1.66
2.00
2~33
2.66
3.0Q
3.S3
3.M
4.00
4.33.
4.66
5.00
_ecU.. Length
011'1_ InPeet
S xS"
S"xlO
10 X 10
10 ]C: 12
12 x 12"
12""x . 14
14x14~
I.x16"
16 xIS
16 X IS
IS xIS"
IS x20
.20 x.20
.2Qx.25
~25x. 2S
.25.x~~O
.SOx.SO
.SOx-.35
.35x.35
~35x.40
.40x.40
.40'x.45
.40x.45
.45x .50
Grout Joint
EaCh
0.26
0.29
0.35
0.43
0.65
0.93
1.20
1045
1.79
2.01
2.15
2.$7.
115
Set ..AUgnPipe
Per Meter
0.23
0.26
0.33
0.36
0.49
0.66
0.95
1.05
1.15
1.21
1.2S
1 . 4 4
PlpeS~
Iachea
4-
~.
S
10
12
I5!'
IS
2r"
24 -
').7
30
33
sITE DRAINAGE PIPE
CONCRETE DRAINPIPE
CUpente,r Belper ToW.
7.94 2.65 lO~59
6.35 2.12 ~.47[
4~12 U3& 5.5
1.73 O.f?7 2.3
12.61 4.79 16.8
.0
2.3 1.13 0.57
12.61 4.79. 16.8
9.45 3;15 12.6
6.30 2~10 8.4
4.72 l.58 6. 3
11.63 3.87 i5.S
11.63 3.87
1.5 tl
8.72 2:91 10.91
1 . 56
1.40
6.23
5~61
4.67
4.21
1.37 1.37
Il'aialaOUftl Per Sq.Meter
CarpeJa_ Helper Total
6.(;8 2.22 8.90
1.15 2.38 9.53
5.63 L 87 7.50
Item
S~l AWningWIndow
S~l C8se~t Window
Aluminwn SlidiitgWJndow
.JalQu8ie Windows on.Alu:tn.
Fnune
aollow Me.tal Door Single SWing
FIxec:t 0_ onWood Frame:
;Hollowp.fetal Door Double Swing
SteeJ, $liding.Doors
Aluminum Door Single SWing
AlUminum Sliding DoQrs
Wooden Panel DOor
WoodenFlush Door
WoodenS~dIngDoor
DOORS 8 WINDOWS
Item
Double Wall PartItion
PlywQod Ceilfng
Accoustlc TIlt!Out Runner
Accoustlc TIle on.Plywood Ceding
Wire Mesh Pat. onW~ Ri.urie
Wire Mesh PartItion
114
WAL L S8 CEIL ING:

Anda mungkin juga menyukai