Predecessors Duration Work Resource Names May June July August Septemb October Novembe Decembe January February March April May June July August Septemb October Novembe
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E
1 Solution Phase Mon 5/14/07 Tue 6/26/07 32 days 154 days Dev1,Architect2
21 Construction Phase Wed 7/4/07 Wed 6/11/08 245.19 days? 1,363 days
24 Data Access Layer Wed 7/4/07 Tue 7/31/07 20 days? 20 days Dev6 Dev6
25 Validation layer Tue 7/17/07 Wed 7/25/07 23 7 days 14 days Dev1,Dev2 Dev1,Dev2
26 Access Controls Tue 7/17/07 Wed 7/25/07 23 7 days 14 days Dev4,Dev3 Dev4,Dev3
27 Main Menu Tue 7/17/07 Wed 7/25/07 23 7 days 14 days Dev5,Dev7 Dev5,Dev7
28 Query Builder Thu 7/26/07 Wed 8/1/07 27 5 days 15 days Dev2,Dev1,Dev3 Dev2,Dev1,Dev3
30 Control Gate Thu 8/2/07 Fri 8/3/07 29 2 days 2 days SourceEdge SourceEdge
32 Analysis & Review Mon 8/6/07 Wed 8/8/07 3 days 3 days SourceEdge SourceEdge
34 Manage Properties Mon 8/6/07 Fri 9/7/07 25 days? 50 days Dev3,Dev2 Dev3,Dev2
35 Manage Resource Mon 8/6/07 Fri 9/7/07 25 days? 50 days Dev5,Dev4 Dev5,Dev4
36 Manage Unit Systems Mon 8/20/07 Wed 9/19/07 33 23 days 23 days Dev1 Dev1
37 Manage Schema Mon 9/10/07 Fri 9/21/07 34 10 days? 40 days Dev2,Dev3,Dev4,Dev5 Dev2,Dev3,Dev4,Dev5
38 Control Gate Mon 9/24/07 Tue 9/25/07 37 2 days 2 days SourceEdge 9/25
40 Analysis & Review Wed 9/5/07 Fri 9/7/07 3 days 3 days SourceEdge SourceEdge
42 Calculation WorkFlow Wed 9/5/07 Thu 10/4/07 22 days 132 days Dev3,Dev2,Dev4,Dev5,Dev6,Dev1 Dev3,Dev2,Dev4,Dev5,Dev6,Dev1
43 Manage Form for Schema Fri 10/5/07 Thu 10/25/07 42 15 days 45 days Dev2,Dev3,Dev1 Dev2,Dev3,Dev1
44 Manage Form for Resource Fri 10/5/07 Thu 10/25/07 42 15 days 45 days Dev4,Dev6,Dev5 Dev4,Dev6,Dev5
45 Manage Forecasting/Budget/Limit/Target Fri 10/26/07 Thu 11/8/07 44 10 days 40 days Dev1,Dev4,Dev2,Dev3 Dev1,Dev4,Dev2,Dev3
46 Manage Data Entry Fri 10/26/07 Fri 11/16/07 44 16 days 32 days Dev5,Dev6 Dev5,Dev6
47 Manage Navigation Fri 10/26/07 Thu 11/8/07 44 10 days 20 days Dev8,Dev7 Dev8,Dev7
48 Control Gate Mon 11/19/07 Tue 11/20/07 46 2 days 2 days SourceEdge 11/20
50 Analysis & Review Fri 12/21/07 Wed 12/26/07 4 days 4 days SourceEdge SourceEdge
52 Data Access Layer Fri 12/21/07 Tue 1/1/08 7.5 days? 15 days Dev1,Dev2 Dev1,Dev2
53 Business Entities , Business Logic and UI Fri 12/21/07 Mon 12/31/07 7 days? 7 days Dev3 Dev3
54 Manage Credit Data Entry Fri 12/21/07 Thu 1/3/08 10 days 10 days Dev4 Dev4
55 Manage Export & Import Fri 12/21/07 Thu 1/24/08 25 days 75 days Dev5,Dev6,Dev7 Dev5,Dev6,Dev7
56 Manage Report Fri 1/4/08 Thu 1/17/08 54 10 days 40 days Dev3,Dev2,Dev1,Dev4 Dev3,Dev2,Dev1,Dev4
57 Manage User Tasks Fri 1/18/08 Mon 2/4/08 56 12 days 24 days Dev3,Dev1 Dev3,Dev1
58 Manage Dashboard Fri 1/25/08 Mon 2/4/08 55 6.5 days 26 days Dev6,Dev5,Dev7,Dev4 Dev6,Dev5,Dev7,Dev4
59 Array Calculations Tue 2/5/08 Tue 3/4/08 58FS+1 day 20 days 40 days Dev5,Dev6 Dev5,Dev6
60 Control Gate Wed 3/5/08 Tue 3/11/08 59FS+1 day 4 days 4 days SourceEdge 3/11
62 Analysis & Review Mon 3/24/08 Thu 3/27/08 3 days 3 days SourceEdge SourceEdge
64 Manage Data Drilling Mon 3/24/08 Thu 4/10/08 13 days 52 days Dev2,Dev3,Dev1,Dev4 Dev2,Dev3,Dev1,Dev4
65 Manage Roles & Access Rights Mon 3/24/08 Thu 4/10/08 13 days 26 days Dev6,Dev5 Dev6,Dev5
66 Manage System Messages Mon 3/24/08 Thu 4/10/08 13 days 26 days Dev7,Dev8 Dev7,Dev8
67 Manage Transfer Fri 4/11/08 Fri 5/23/08 64FS+1 day 30 days 90 days Dev2,Dev1,Dev3 Dev2,Dev1,Dev3
68 Import/Export with respect to XML Fri 4/11/08 Wed 5/28/08 64FS+1 day 33 days 99 days Dev6,Dev5,Dev4 Dev6,Dev5,Dev4
Project: Emis Project with SourceEdge Task Progress Summary External Tasks Deadline
Date: Wed 12/9/09 Split Milestone Project Summary External Milestone
Page 1
ID Task Name Start Finish Predecessors Duration Work Resource Names May June July August Septemb October Novembe Decembe January February March April May June July August Septemb October Novembe
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E
69 Run Report Mon 5/26/08 Wed 6/4/08 67FS+1 day 7 days 14 days Dev2,Dev1 Dev2,Dev1
70 System Documentation Thu 5/29/08 Mon 6/9/08 68FS+1 day 7 days 28 days Dev3,Dev4,Dev5,Dev7 Dev3,Dev4,Dev5,Dev7
71 Manage Options Thu 5/29/08 Mon 6/9/08 68FS+1 day 7 days 14 days Dev6,Dev8 Dev6,Dev8
72 System tester Mon 3/24/08 Fri 5/16/08 39 days 78 days Test1,Test2 Test1,Test2
74 Control Gate Tue 6/10/08 Wed 6/11/08 71FS+1 day 1 day 1 day SourceEdge 6/11
75 Approval & Completion Phase Thu 6/12/08 Thu 7/31/08 74 35 days 29 days
76 Functional test Thu 6/12/08 Mon 6/23/08 74FS+1 day 7 days 7 days SourceEdge SourceEdge
77 Performance tests and other technical tests Tue 6/24/08 Wed 6/25/08 76FS+1 day 1 day 1 day SourceEdge SourceEdge
78 UAT Thu 6/26/08 Wed 7/9/08 77FS+1 day 9 days 9 days EmiSoft EmiSoft
79 Rectification and Optimization Thu 7/10/08 Fri 7/18/08 78FS+1 day 6 days 6 days SourceEdge SourceEdge
80 Preparation of the production environment/test operation Mon 7/21/08 Tue 7/22/08 79FS+1 day 1 day 1 day SourceEdge SourceEdge
81 Final Acceptance Test Wed 7/23/08 Fri 7/25/08 80FS+1 day 2 days 2 days EmiSoft EmiSoft
82 Delivery Mon 7/28/08 Thu 7/31/08 81FS+1 day 3 days 3 days SourceEdge 7/31
83 Maintainance Fri 8/1/08 Fri 10/31/08 75FS+1 day 65 days 65 days Dev1 Dev1
Project: Emis Project with SourceEdge Task Progress Summary External Tasks Deadline
Date: Wed 12/9/09 Split Milestone Project Summary External Milestone