Anda di halaman 1dari 2

ID Task Name Start Finish Predecessors Duration Work Resource Names May June July August Septemb October

Predecessors Duration Work Resource Names May June July August Septemb October Novembe Decembe January February March April May June July August Septemb October Novembe
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E
1 Solution Phase Mon 5/14/07 Tue 6/26/07 32 days 154 days Dev1,Architect2

21 Construction Phase Wed 7/4/07 Wed 6/11/08 245.19 days? 1,363 days

22 Iteration 1 Wed 7/4/07 Fri 8/3/07 23 days? 139 days

23 Framework Wed 7/4/07 Mon 7/16/07 9 days 45 days Dev1,Dev2,Dev3,Dev4,Dev5 Dev1,Dev2,Dev3,Dev4,Dev5

24 Data Access Layer Wed 7/4/07 Tue 7/31/07 20 days? 20 days Dev6 Dev6

25 Validation layer Tue 7/17/07 Wed 7/25/07 23 7 days 14 days Dev1,Dev2 Dev1,Dev2

26 Access Controls Tue 7/17/07 Wed 7/25/07 23 7 days 14 days Dev4,Dev3 Dev4,Dev3

27 Main Menu Tue 7/17/07 Wed 7/25/07 23 7 days 14 days Dev5,Dev7 Dev5,Dev7

28 Query Builder Thu 7/26/07 Wed 8/1/07 27 5 days 15 days Dev2,Dev1,Dev3 Dev2,Dev1,Dev3

29 UI Controls Thu 7/26/07 Wed 8/1/07 27 5 days? 15 days Dev4,Dev6,Dev5 Dev4,Dev6,Dev5

30 Control Gate Thu 8/2/07 Fri 8/3/07 29 2 days 2 days SourceEdge SourceEdge

31 Iteration 2 Mon 8/6/07 Tue 9/25/07 22 37 days? 178 days

32 Analysis & Review Mon 8/6/07 Wed 8/8/07 3 days 3 days SourceEdge SourceEdge

33 GUI Mon 8/6/07 Fri 8/17/07 10 days 10 days Dev1 Dev1

34 Manage Properties Mon 8/6/07 Fri 9/7/07 25 days? 50 days Dev3,Dev2 Dev3,Dev2

35 Manage Resource Mon 8/6/07 Fri 9/7/07 25 days? 50 days Dev5,Dev4 Dev5,Dev4

36 Manage Unit Systems Mon 8/20/07 Wed 9/19/07 33 23 days 23 days Dev1 Dev1

37 Manage Schema Mon 9/10/07 Fri 9/21/07 34 10 days? 40 days Dev2,Dev3,Dev4,Dev5 Dev2,Dev3,Dev4,Dev5

38 Control Gate Mon 9/24/07 Tue 9/25/07 37 2 days 2 days SourceEdge 9/25

39 Iteration 3 Wed 9/5/07 Tue 11/20/07 55 days 324 days

40 Analysis & Review Wed 9/5/07 Fri 9/7/07 3 days 3 days SourceEdge SourceEdge

41 GUI Wed 9/5/07 Tue 9/11/07 5 days 5 days GUI GUI

42 Calculation WorkFlow Wed 9/5/07 Thu 10/4/07 22 days 132 days Dev3,Dev2,Dev4,Dev5,Dev6,Dev1 Dev3,Dev2,Dev4,Dev5,Dev6,Dev1

43 Manage Form for Schema Fri 10/5/07 Thu 10/25/07 42 15 days 45 days Dev2,Dev3,Dev1 Dev2,Dev3,Dev1

44 Manage Form for Resource Fri 10/5/07 Thu 10/25/07 42 15 days 45 days Dev4,Dev6,Dev5 Dev4,Dev6,Dev5

45 Manage Forecasting/Budget/Limit/Target Fri 10/26/07 Thu 11/8/07 44 10 days 40 days Dev1,Dev4,Dev2,Dev3 Dev1,Dev4,Dev2,Dev3

46 Manage Data Entry Fri 10/26/07 Fri 11/16/07 44 16 days 32 days Dev5,Dev6 Dev5,Dev6

47 Manage Navigation Fri 10/26/07 Thu 11/8/07 44 10 days 20 days Dev8,Dev7 Dev8,Dev7

48 Control Gate Mon 11/19/07 Tue 11/20/07 46 2 days 2 days SourceEdge 11/20

49 Iteration 4 Fri 12/21/07 Tue 3/11/08 57.5 days? 249 days

50 Analysis & Review Fri 12/21/07 Wed 12/26/07 4 days 4 days SourceEdge SourceEdge

51 GUI Fri 12/21/07 Wed 12/26/07 4 days 4 days GUI GUI

52 Data Access Layer Fri 12/21/07 Tue 1/1/08 7.5 days? 15 days Dev1,Dev2 Dev1,Dev2

53 Business Entities , Business Logic and UI Fri 12/21/07 Mon 12/31/07 7 days? 7 days Dev3 Dev3

54 Manage Credit Data Entry Fri 12/21/07 Thu 1/3/08 10 days 10 days Dev4 Dev4

55 Manage Export & Import Fri 12/21/07 Thu 1/24/08 25 days 75 days Dev5,Dev6,Dev7 Dev5,Dev6,Dev7

56 Manage Report Fri 1/4/08 Thu 1/17/08 54 10 days 40 days Dev3,Dev2,Dev1,Dev4 Dev3,Dev2,Dev1,Dev4

57 Manage User Tasks Fri 1/18/08 Mon 2/4/08 56 12 days 24 days Dev3,Dev1 Dev3,Dev1

58 Manage Dashboard Fri 1/25/08 Mon 2/4/08 55 6.5 days 26 days Dev6,Dev5,Dev7,Dev4 Dev6,Dev5,Dev7,Dev4

59 Array Calculations Tue 2/5/08 Tue 3/4/08 58FS+1 day 20 days 40 days Dev5,Dev6 Dev5,Dev6

60 Control Gate Wed 3/5/08 Tue 3/11/08 59FS+1 day 4 days 4 days SourceEdge 3/11

61 Iteration 5 Mon 3/24/08 Wed 6/11/08 57 days 473 days

62 Analysis & Review Mon 3/24/08 Thu 3/27/08 3 days 3 days SourceEdge SourceEdge

63 GUI Mon 3/24/08 Thu 3/27/08 3 days 3 days GUI GUI

64 Manage Data Drilling Mon 3/24/08 Thu 4/10/08 13 days 52 days Dev2,Dev3,Dev1,Dev4 Dev2,Dev3,Dev1,Dev4

65 Manage Roles & Access Rights Mon 3/24/08 Thu 4/10/08 13 days 26 days Dev6,Dev5 Dev6,Dev5

66 Manage System Messages Mon 3/24/08 Thu 4/10/08 13 days 26 days Dev7,Dev8 Dev7,Dev8

67 Manage Transfer Fri 4/11/08 Fri 5/23/08 64FS+1 day 30 days 90 days Dev2,Dev1,Dev3 Dev2,Dev1,Dev3

68 Import/Export with respect to XML Fri 4/11/08 Wed 5/28/08 64FS+1 day 33 days 99 days Dev6,Dev5,Dev4 Dev6,Dev5,Dev4

Project: Emis Project with SourceEdge Task Progress Summary External Tasks Deadline
Date: Wed 12/9/09 Split Milestone Project Summary External Milestone

Page 1
ID Task Name Start Finish Predecessors Duration Work Resource Names May June July August Septemb October Novembe Decembe January February March April May June July August Septemb October Novembe
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E
69 Run Report Mon 5/26/08 Wed 6/4/08 67FS+1 day 7 days 14 days Dev2,Dev1 Dev2,Dev1

70 System Documentation Thu 5/29/08 Mon 6/9/08 68FS+1 day 7 days 28 days Dev3,Dev4,Dev5,Dev7 Dev3,Dev4,Dev5,Dev7

71 Manage Options Thu 5/29/08 Mon 6/9/08 68FS+1 day 7 days 14 days Dev6,Dev8 Dev6,Dev8

72 System tester Mon 3/24/08 Fri 5/16/08 39 days 78 days Test1,Test2 Test1,Test2

73 Documentation Mon 3/24/08 Fri 5/16/08 39 days 39 days Documents Documents

74 Control Gate Tue 6/10/08 Wed 6/11/08 71FS+1 day 1 day 1 day SourceEdge 6/11

75 Approval & Completion Phase Thu 6/12/08 Thu 7/31/08 74 35 days 29 days

76 Functional test Thu 6/12/08 Mon 6/23/08 74FS+1 day 7 days 7 days SourceEdge SourceEdge

77 Performance tests and other technical tests Tue 6/24/08 Wed 6/25/08 76FS+1 day 1 day 1 day SourceEdge SourceEdge

78 UAT Thu 6/26/08 Wed 7/9/08 77FS+1 day 9 days 9 days EmiSoft EmiSoft

79 Rectification and Optimization Thu 7/10/08 Fri 7/18/08 78FS+1 day 6 days 6 days SourceEdge SourceEdge

80 Preparation of the production environment/test operation Mon 7/21/08 Tue 7/22/08 79FS+1 day 1 day 1 day SourceEdge SourceEdge

81 Final Acceptance Test Wed 7/23/08 Fri 7/25/08 80FS+1 day 2 days 2 days EmiSoft EmiSoft

82 Delivery Mon 7/28/08 Thu 7/31/08 81FS+1 day 3 days 3 days SourceEdge 7/31

83 Maintainance Fri 8/1/08 Fri 10/31/08 75FS+1 day 65 days 65 days Dev1 Dev1

Project: Emis Project with SourceEdge Task Progress Summary External Tasks Deadline
Date: Wed 12/9/09 Split Milestone Project Summary External Milestone

Page 2

Anda mungkin juga menyukai