0 penilaian0% menganggap dokumen ini bermanfaat (0 suara)
2K tayangan2 halaman
The document defines formulas used in critical path method analysis including:
1) The PERT formula which calculates the estimated time for an activity using optimistic, pessimistic and most likely estimates.
2) Formulas for standard deviation and variance of an activity which use the same time estimates in different calculations.
3) Other formulas calculate cost and schedule variance, performance indexes, estimates at completion, and variance at completion.
Deskripsi Asli:
These are various analytical formula in Project Management
The document defines formulas used in critical path method analysis including:
1) The PERT formula which calculates the estimated time for an activity using optimistic, pessimistic and most likely estimates.
2) Formulas for standard deviation and variance of an activity which use the same time estimates in different calculations.
3) Other formulas calculate cost and schedule variance, performance indexes, estimates at completion, and variance at completion.
Hak Cipta:
Attribution Non-Commercial (BY-NC)
Format Tersedia
Unduh sebagai DOC, PDF, TXT atau baca online dari Scribd
The document defines formulas used in critical path method analysis including:
1) The PERT formula which calculates the estimated time for an activity using optimistic, pessimistic and most likely estimates.
2) Formulas for standard deviation and variance of an activity which use the same time estimates in different calculations.
3) Other formulas calculate cost and schedule variance, performance indexes, estimates at completion, and variance at completion.
Hak Cipta:
Attribution Non-Commercial (BY-NC)
Format Tersedia
Unduh sebagai DOC, PDF, TXT atau baca online dari Scribd
PERT Program PERT = P + 4M + O / 6 Evaluation and P = Pessimistic Estimate Review M = Most Likely Estimate Technique O = Optimistic Estimate Standard Deviation of P–O/6 Activity Variance of an Activity [P-O/6]² Total Float LS – ES or LF – EF Communications [N(N-1)] / 2 Channels CV Cost CV = EV – AC Variance SV Schedule SV = EV – PV Variance CPI Cost CPI = EV / AC Performance Index SPI Schedule SPI = EV / PV Performance Index EAC Estimate EAC = BAC / CPI at Completion EAC = AC + ETC
EAC = AC + (BAC – EV)
ETC Estimate ETC = EAC – AC to Complete
VAC Variance VAC = BAC – EAC
at Completion CPIc Cumulative CPIc = Σ EV / Σ AC Cost Performance Index
GimKonsult | NPI Quarters, Gaduwa, Abuja, Nigeria
PERT Formula
PERT – Program Evaluation and Review Technique.
If you’re going to take the PMP exam, you MUST remember this formula. I’ve used it countless times in the real world and it works with surprising accuracy. Formula: (P+4M+O)/6 Optimistic time (O): the minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected. Pessimistic time (P): the maximum possible time required to accomplish a task, assuming everything goes wrong (excluding major catastrophes). Most likely time (M): the best estimate of the time required to accomplish a task, assuming everything proceeds as normal. How does it work? Obtain three time estimates (optimistic, pessimistic, and most likely) for every activity along the critical path. Plug your numbers into the formula and then sum the totals. Though people will challenge you, you WILL have a more accurate critical path estimate. I will speak to “Standard Deviation of an Activity” and “Variance of an Activity” at a later time. They both leverage the same values but in different formulas.