Presented at the 1985 SME-AIME Annual General Meeting, New York, NY, Preprint #85-100.
THE IMPACT OF SCREEN DESIGN PARAMETERS
ON THE OPERATION EFFICIENCY OF SECONDARY CRUSHING PLANTS
J. A. Meech and R. J. Tucker Queen's University, Department of Mining Engineering
Presented at the SME-AIME Annual Meeting New York, New York February 24-28, 1985 Preprint Number 85-100
Abstract An analysis of screen design options on the operating efficiency of secondary crushing plants has been conducted using a dynamic computer model. The model allows for the simulation of a wide variety of crushing circuits and can be run on either a microcomputer (IBM PC/XT) or a large time-sharing mainframe computer. Size reduction and separation characteristics of crushers and screens are based on standard manufacturer design and performance data. Input/output routines are available in tabular, alarm or strip chart recorder modes to facilitate operation of the program. A number of alternate circuit designs are compared to show the influence of surge capacity, screen size and area, screen deck location, and closed side crusher settings on the operation of a 10,000 ton per day plant. The program is currently in use at Queen's University to teach plant operations and control. It has potential to be a valuable tool for operator training.
Introduction Future trends in the design of secondary crushing plants will emphasize simplicity in order to minimize capital costs and to reduce operating downtime from maintenance functions. Some of the changes likely to be encountered include:
1. No internal surge bin capacity 2. Separate screening of secondary and tertiary products 3. Open circuit crushing 4. Single-stage closed circuit crushing 5. Single-stage open circuit crushing
While these features can reduce overall investment requirements, it must be recognized that they can impact negatively on the operating efficiency of crushing circuits designed with the same equipment sizes and installed power. Future crushing plants will need to be more over-designed than those of the past.
Recently at Queen's University we have been using a simulation model of secondary crushing operations (1) to examine the impact of some of these changes and, in particular, how sensitive are the effects to adjustments in screen design parameters. The model was originally developed as a teaching tool for mineral processing students to learn about the operation and control of secondary crushing facilities. As such, it could also be an effective training technique for new crushing plant operators. Since the model is capable of demonstrating operational problems 2
created at the design stage, we believe it has a potential use to avoid under-designing certain types of circuits. This paper describes such an approach for a secondary crushing plant designed to produce about 10,000 tonnes per day of ore. Four different types of crushing circuits using similar equipment have been studied. The hole size and effective area of the screens used in each circuit have been varied to establish the throughput efficiency of each circuit.
Model Design The program was developed to provide "hands-on" experience in the operation of crushing plants for students and new operating personnel. The program is dynamic as opposed to the steady-state nature of other crushing models (2-5), in order to demonstrate circuit responses to operator actions and ore variations. The model can consider extreme cases of over-loading or under- loading equipment and incorporates a number of circuit upsets and interruptions that occur in a real plant. Input and output are controlled interactively in the form of actual control information available to an operator in a plant control room. Program speed can be varied between a real- time simulation to one in which an 8-hour shift is completed within about 12 minutes.
Calculations are based on the design considerations, performance specifications and suggested operating and control procedures of the major equipment manufacturers (3,7). The model is designed to reflect the general trends and relationships encountered in normal plant operations. Directional accuracy has been emphasized to indicate the correct trends in circuit response to changes in operating strategy and ore variation. It was considered that a rigorously accurate determination of product sizes was not warranted since intermediate products are not routinely sampled in an operating plant. When conducted, these studies produce data that are difficult to assess and require statistical adjustment to remove error (4).
The program has been structured in a general and adaptable way to allow the simulation of a wide range of plant capacities, equipment sizes and circuit configurations. Adjustments to individual units within a circuit can be made quickly to reflect site specific factors or to emphasize a particular facet of the operation. The main program flowchart is shown in Figure 1. The main program (PLANT) reads the input data of circuit configuration and equipment details. For the first cycle of a shift all counters and alarms are initialized; material remaining in the circuit from a previous shift is recalled; and provision is made to adjust-crusher closed side settings. Each unit within the model is set-up to process up to 30 blocks of ore. The following parameters define an ore block:
- Tonnage - Grade of Mineral A - Grade of mineral B - Grade of mineral C - Percent moisture - Work index - Specific gravity - 80% passing size - 20% passing size - Bulk density
3
At the start of each cycle a new packet of ore is created. The value of each parameter is selected independently on a random trending basis and the packet is inserted into the first block of the first unit operation in the circuit, usually a coarse ore pile. By calling the appropriate subroutine in sequence (LAG, CRUSH, or SCREEN), ore is moved through bins, crushers and screens where the material is stored, reduced in size, or split into size fractions. From within these subroutines a summation subprogram (SIZE) is called as required to combine ore packets of similar or different size distributions and to blend the above mentioned ore parameters. At the completion of each cycle, the output subroutine (OUT) is called to display the operating parameters and any alarms triggered. The operator has the opportunity to adjust set-points or to start or stop any of the equipment in response to this information.
When operated on a microcomputer, output can be viewed in a variety of modes. A tabular mode showing all unit power draws, feed rates and alarms is the normal configuration. A1ternatively, a graphical strip chart each unit power draw and feed rate can be called to depict output for the entire shift. Alarm signals both visual and audio can be acknowledged through a separate alarm panel. The main program increments the clock timer, advances material through the circuit and creates a new block of ore for the first unit. Cycle time can be altered between 1 and 120 seconds as required. Although 1 second increments increase the precision of the model, the total simulation time increases significantly limiting the number of studies which can be performed. Typically 20 to 120 seconds is the range used most often at Queen's.
Crushing The CRUSH subroutine is capable of considering three commonly used crusher sizes in either secondary or tertiary service (1.3, 1.7 and 2.1 m). The model calculates product tonnage, product size distribution, crusher power draw and tonnage of material held up within the crusher chamber according to the flowchart shown in Figure 2.
The model is designed to demonstrate two main trends in the operation of a crusher: first, the generally accepted concept that product size decreases with higher power draw and secondly, that capacity or throughput .can be limited either volumetrically or by available horsepower. A block of ore assigned to the crusher by the LAG subroutine is adjusted to reflect SG and bulk density changes and is added to material held within the crusher chamber from the previous cycle. Amperage is then calculated in a form similar to that used by Hatch and Mular (4) as follows:
A = B1 + B2T + B3R(T/TMAX) + B4W(T/TMAX)
where Bl, B2, B3 and B4 are coefficients determined by the crusher type and size, T is the tonnage rate, R is the reduction ratio (initially feed size/closed side setting), W is the ore work index and TMAX is a calculated maximum feedrate based on maximum available amperage B5). The values of the coefficients used for tertiary crushing reflect an increase in the relative influence of ore hardness as opposed to feed size since tertiary crushers receive material of more uniform size than do secondary units.
Next, the 80 percent passing size of the product (DD) is calculated as follows:
4
DD = 3.0 CSS/(1.0 + A/B5)
where CSS is the closed size crusher setting. Thus as the crusher power draw approaches full load, the 80 percent passing size of the discharge product approaches 1.50 times the closed size setting in agreement with published product size distributions reported at full load (7). Lower crusher loading results in a coarser product. At idling conditions, the 80 percent passing size becomes approximately twice the close side setting. A new value of R is then calculated based on DD and values for TMAX, A, DD and R are continually recalculated until successive values of R agree within 1 percent.
Finally a maximum discharge rate (TC) for the incoming ore and current crusher loading is calculated. If TC is greater than T, the crusher is capable of handling the current feed rats. Should T be greater than TC, the crusher conditions and product size are recalculated with T=TC. Each new value of R modifies TC and iteration continues until T is less than TC. The discharge tonnage is taken as TC and the excess material (F) is stored to be added to the new feed to the next cycle. No size reduction of the excess material occurs. Currently the crusher capacity (TC) is a function of the amperage limiting capacity (TMAX) and is inversely related independently to ore hardness and reduction ratio. Literature references to capacity restrictions are not extensive. Motz (8) states that "capacity can be limited volumetrically in the case of the softer ores, or by the horsepower in the case of the harder ores". Flavel (9) shows that capacity can be severely reduced by increases in feed size. In either case, the limitations are not likely to be related simply to ore and crusher volumes, but also reflect the increased tine required to reduce the size of larger or harder material enough to pass the discharge opening. High level alarms trip out the crusher and feeder, when maximum power draw and/or chamber levels are exceeded. In cases where the crusher shuts down on overload, the tonnage in the machine is retained and must be jogged out by the operator on subsequent start up.
Screening The SCREEN subroutine was designed to accept crusher discharge material and to split it into undersize and oversize fractions. Tonnage and size distributions are calculated for both fractions. The feed characteristics are a result of previous crushing operations and the feed rate is either the set-point tonnage for circuits with feeders or crusher discharge tonnage.
Screen calculations are based on the standard relationships used by manufacturers to determine screen area requirements for a given feed, a selected screen opening and a desired efficiency (3, 10). For the purposes of the subroutine, where screen area and opening are set, the process is reversed so that the efficiency is calculated based on the feed and operating conditions:
EF = _______TPH of undersize in feed_________ A x C x bulk density x modifying factors
where EF is the efficiency factor, C is the basic capacity of the screen (in tonnes per unit screen area), A is the total screen surface area and the modifying factors account for screen open area, shape of opening, percent fines in the feed and number of decks.
5
The efficiency factor is converted to a screening efficiency term and this is used to split the undersize material in the feed into the undersize and oversize products. The efficiency is modified by the moisture content in the feed, to simulate sticky ore which may clog the screen openings, and by the percent loading of the screen. Both under-loading and over-loading produce reduction in screening efficiency (5). Tonnages of both the oversize and undersize are determined by consideration of the efficiency and the fines contained in the feed. The size distribution of the coarse fraction is determined by the top-size of the feed and the carry-over of fines. The size distribution of the undersize is defined by the 80% passing size based on screen efficiency and the fines in the feed.
Screen amperage and overload calculations are based on the greater of either the total screen feed or the oversize tonnage. Total feed load is based on the assumption that a screen area of 14.9 m 2
(8 ft x 20 ft) is capable of handling 1000 tph. Oversize load is based on this same screen handling 700 tph of oversize. Similar to the procedure for the crushers, a trip-out due to overload conditions results in retention of material for treatment on subsequent start up. Products discharged from the various units of equipment during each cycle are summed in an appropriate manner to allow calculation of the amperages on interconnecting conveyors.
Surge Capacity Conveyors or surge bins are represented within the system by subroutine LAG. This model provides a method to control equipment feed rates when feeders are defined as part of the circuit. Output from a preceeding operating is placed in the first block of the unit. This material is advanced one block at the completion of each cycle (first in - first out or plug flow). When used as a bin a certain degree of mixing occurs when the discharge feeder is operating.
The tonnages contained in all blocks are summed and depending on maximum and minimum Limits, a high or low level alarm can be triggered. A low level alarm shuts off the discharge feeder and a high level alarm trips out preceeding equipment. As a conveyor, the time delay between major units in the plant is modified by specifying the block number which must be reached before material is discharged to the next unit operation. Incorporated within the program are the normal plant interlocks that shutdown in-line equipment should the succeeding unit be non-operative or incapable of receiving material sent to it.
Circuits Examined The model was used to evaluate the following four circuit types:
1. Closed circuit with two 450 tonne surge bins 2. Closed circuit with no surge bin 3. Closed circuit with a screen plant surge bin 4. Closed circuit with separate screening of secondary and tertiary crushing products (no surge bin), screens located immediately beneath crushers.
Crushing equipment for all circuits consisted of one secondary crusher and two tertiary crushers, all of size 2.1 m (7 ft.). Installed horsepower was 350 hp (260 kW), Each of circuits 1, 2 and 3 were serviced by two double-deck screens of variable area (17-30 m ) and opening size (19 or 13 mm). Circuit 4A contained one 14.9 m (8x20) double deck screen for the secondary product with 6
two separate screen decks for the tertiary product. Circuit 48 contained a smaller 11.9 m (8x16) double deck screen for the secondary product with the same variation in tertiary screening area. Table 1 shows the screen variations used in all circuits.
Each circuit was evaluated by processing the same ore over a period of 3 shifts. The ore conditions varied considerably over the progress of the three shifts as shown in Table 2. Basically shift 1 received intermediately hard feed of considerable variation; shift 2 ore was softer and more consistent while the ore fed during shift 3 steadily increased in both size and hardness as the shift progressed.
Operating and Control Strategies Each circuit was adjusted to optimize the crusher settings for the particular screens installed, Basically as the screen area was decreased, both the secondary and tertiary crushers were tightened to decrease the amount of oversize to be handled. Similarly when the screen hole size was changed from 19 to 13 mm, the crushers were tightened further to match the change in final product size required.
The feed rates controlled in each circuit were adjusted to attempt to maintain an operating power draw of between 75 to 80 percent of available power. This control strategy was not always possible however due to ore changes that produced circuit upsets or because of unbalanced crusher loads as the closed side settings approached their minimum levels (26 mm for the secondary and 6 mm for the tertiaries).
Selection of Closed Side Settings Each circuit containing the different screening equipment was operated for 3 shifts at a variety of closed side settings to establish the "best average settings for the ore conditions and the installed screening equipment. Figures 3 and 4 present power draw results for Circuits 1 and 2 respectively run under relatively Loose crusher settings for the same operating period. Variations in crusher power draw reflect fluctuations in the size and hardness of feed material and changes in federate due to operator adjustments and random deviations from the feeder setpoint.
The tertiary crusher variations for Circuit 2 as compared to Circuit 1 are more extreme since with no surge capacity or intermediate feed control, fluctuation in plant feed rate and ore conditions are transferred directly to the screens. As a result, screen oversize tonnages and size vary considerably compared with the buffering action of the surge bins in Circuit 1.
As can be seen in Figures 3 and 4, the tertiary power draw in Circuit 1 is both more stable and consistently higher than that achieved in Circuit 2. In fact, the higher tonnage processed by the tertiaries in Circuit 1 results in a 10 minute shut down of the tertiary crusher due to an enpty surge bin. Furthermore, after the first hour of the shift, the surge capacity and feed rate control available in Circuit 1 have allowed an increase in the secondary crusher feedrate.
Approximately four hours into the shift, one of the tertiary crushers in Circuit 2 tripped out on high amperage resulting in the shutdown of the entire plant under full load. Two hours of operating time were required to jog the circuit empty and restart the plant. 7
This lost time and lower power draw combined to reduce the shift throughput to 2505 tonnes for Circuit 2 as compared to 4106 tonnes for Circuit 1.
To improve on the performance of each circuit with varying screen equipment, studies were conducted at several crusher settings. Figures 5 and 6 show typical results of this work for Circuit 2 operating with undersized screens. The importance of balancing the load between the various circuit components is apparent from this data. When either crusher is operated loose, the screens become the limiting production constraint. If a crusher is set too tight for the screen area available, it becomes the bottleneck. Figure 5 shows a peak average shift production of about 2700 tonnes when the tertiaries are set at 12 mm.
Although the circuit appears balanced, further production increases can be achieved by tightening up the secondary crusher from 34 to 30 mm as shown in Figure 6. This surprising result occurs because finer and more consistent feed is delivered to the screens and tertiary crushers, enhancing their performance and allowing higher overall power draw on the secondary and higher overall tonnage through the plant.
Results From the application of the preceding testwork with, each circuit, the "best" crusher settings were selected for each screen type used. Figure 7 shows the average results achieved for each circuit. Note that Circuits 1, 2 and 3 all show similar responses with a moderately decreasing production as available screen area is reduced. Circuit 1 performs at the highest level while Circuit 2 is the poorest of the three, indicative of the influence of individual unit feed control and internal surge capacity on the efficiency of plant operations. With one internal bin and screen feedrate control, Circuit 3 falls between these two extremes.
Circuit 4 shows a higher sensitivity to screen area reductions than do the other circuits since the total reduction affects only the tertiary screens and not all of the remaining screen area is available to the tertiary crusher produ5t. At high total screen area (>29m 2 ), note how the lower secondary screen area (4B) limits throughput significantly while at lower total screen area, both curves (4A and 4B) follow similar slopes, displaced by 2 m 2 , indicative of tertiary screens limiting production.
Figure 8 compares the average total power utilization (= %powerdraw x fractional operating time) for each circuit. The relative trend in power utilization with 19 mm screens is remarkably similar to that of the shift production for all circuits. With Circuits 1, 2 and 3, the drop in power utilization with decreased screen area reflects a loss in operating time rather than power level while in the case of Circuit 4, the power levels on all crushers dropped significantly as screen area decreased. Attempting to maintain higher power draw caused frequent screen tripout and subsequent downtime. With the 13 mm screens, the situation is somewhat different. As the crushers are, tightened to match the smaller available screen areas, power draw levels on the secondary crusher decreased while the tertiary crusher power draw increased. With Circuit 1, this trade-off produces a stable total power utilization curve while Circuit 3 data show a decline similar to that occurring at 19 mm. In Circuit 2 however, since the crusher settings at a11 screen areas have approached their minimum permissible level preventing further tightening, the power utilization actually increases as the screen area decreased reflecting a trend toward less 8
inefficient crushing. As in the case at 19 mm, all power levels in Circuits 4A and 4B decline with decreased screen area.
Discussion Loss in production can result from two sources, the inability to achieve satisfactory power input because of equipment limitations within the circuit and the inefficiency of power utilization from operating crushers at lower power draw and from the circulation of large amounts of undersize material because of inefficient screening.
In analysing the results, it is interesting to compare the ratios of tonnage achieved under different conditions with those predicted by the Bond work index formula together with the actual power utilization. The ratios predicted by Bond show the change in production resulting from changes in power input while the deviation between the actual and predicted ratios reflects the inefficiencies of both crushing and screening.
First we examine the ability of the model to predict the tonnage change that occurs when the product specification of a particular circuit is altered. Table 3 shows the average tonnage ratios for all tests with each circuit when the screen hole size is changed from 19 to 13 mm. Note that in Circuit 1, the deviation from the Bond prediction is within 3 percent while in Circuit 3 there is exact agreement.
Circuit 2 and 4A however show deviations of about 5 percent despite achieving higher relative power draws at 13 mm than at 19 mm. Thus, the efficiency of screening and crushing is reduced in those circuits without direct unit feed rate control.
Next the tonnage ratios as a function of screen area are presented in Table 4. The data for Circuits 1, 2 and 3 are combined together here, since the relative effects of screen area reductions are similar in these circuits. A 20 percent reduction in available screen area produces a 4.6 percent decline in tonnage while a 40 percent change lowers the tonnage by 23 percent. A substantial portion of this significant drop is due to inefficient screening and crushing.
Circuit 4A shows a much higher sensitivity to total screen area over this similar range. A 20 percent reduction in available screen area produces a 14.7 percent drop in tonnage while a 27 percent change reduces the tonnage by over 50 percent. As with the other circuits, most of this decline results from inefficient screening and crushing.
Finally, the four circuits examined are compared to each other in Table 5 for conditions in which adequate screen capacity has been installed. The tonnage ratios are referenced against Circuit 1 since it consistently produced the highest shift production.
With Circuit 2, the need to operate at lower power levels to avoid upset conditions causes a reduction in power input which restricts tonnage by 7.6 percent and 17.3 percent at 19 and 13 mm respectively. Additional production losses of 5.0 and 10.3 percent at 19 and 13 mm respectively are caused by inefficient use of available power. Circuit 3 shows some improvement over Circuit 2 with equivalent power input to 9
that of Circuit 1 being achieved at a 19 mm hole size. However a similar reduction in crushing and screening efficiency to that observed In Circuit 2 produces a 5.7 percent production loss at 19 mm.
Either of these circuits could be made to perform at production levels equivalent to Circuit 1 by increasing the installed horsepower on the crushers. The increases required can be summarized as follows:
Circuit 4A outperforms Circuit 1 with screen areas of 29 m 2 and higher. Improved screening efficiencies of the secondary and tertiary screens produce a reduced power level in the tertiary crushers. By operating at higher power draw levels, this suggests the installed tertiary crushing horsepower could be decreased by about 16 percent without loss in shift production. Care must be taken however to ensure that adequate secondary screen area is available. If this screen is smaller than an 8x20 (14.9 m 2 ), the circuit cannot achieve the required production regardless of total screen area installed. This can be seen in Figures 7 and 8 by the data plotted for Circuit 4B.
Open Circuit Crushing Preliminary testwork with the model have also been conducted to examine an open circuit crushing plant containing one 2.1 m secondary crushes with a 350 hp motor, one 8x20 (14.9 m ) double deck screen and one 2.1 m tertiary crusher with a 450 hp motor. The crushers were set to produce a final product size similar to that achieved in the above closed-circuit flowsheets and operate both units at about 75 percent power draw. At 19 mm product size, the plant produced a tonnage ratio to Circuit 1 of 0.813 compared with 0.732 predicted by the Bond formula. This increased efficiency, likely due to improved feed size to the tertiary crusher, suggests that this type of circuit can perform at the same level as Circuit 1 with 450 hp motors on both crushers.
At 13 mm product size, the performance of this circuit was extremely poor. Product size was over 10 percent coarser than any of the equivalent closed circuit despite the crushers being set at their minimum value. Less than 75 percent production could be achieved because of poor power input and inefficient crushing. It is extremely unlikely that this type of circuit could be successfully applied to produce a 13 mm product specification. Instead, this circuit would be used where a rod mill grinding stage is downstream and product quality constraints are not as severe. Crushing plant product size would probably be coarser and less consistent than with a conventional closed-circuit flowsheet.
Conclusion A computer model has been developed to simulate the operation and control of secondary crushing plants. In addition to being a useful teaching and training aid, the model can demonstrate operational characteristics of various design changes and decisions. A study of the impact of screen design parameters on the operating efficiency of several common crushing 10
plants has been successfully conducted. The study shows the importance of independent unit feed control together with internal surge capacity on the performance of closed circuit flowsheets. Circuits without these features operate at reduced power input and increased instability. In order to compensate, the installed crusher horsepower needs to be higher by 13 percent for a 19 mm product size and 28 percent for a 13 mm product size.
Using separate screening for the secondary and tertiary crusher products can lead to a reduction of about 16 percent in the installed tertiary horsepower because of improved screening efficiency. However incorrectly sized secondary screens can limit production severely, unless the secondary crusher horsepower is increased.
Open circuit crushing can also be studied using this model. Preliminary results suggest that product size specification and tonnage equivalent to that achieved by conventional closed-circuit plants are possible at about 86 percent of total installed horsepower for a 19 mm product specification.
Acknowledgements The authors wish to express their appreciation to the Department of Mining Engineering at Queen's University and to the Natural Sciences and Engineering Research Council of Canada for financial support during the development of this program.
References 1. Tucker, R.J. and Meech, J.A.: "A Dynamic Computer Model of Ore Crushing plants for Teaching Purposes and Operating Training", Proc. of 1984 Summer Simulation Conference, Boston, Mass., Vol. 2, July, 1984, p. 1107-1113 2. Magerowski, A.J. & Karra, V.K.: "Computer-aided Crushing Circuit Design", Design and Installation of Comminution Circuits, Mular, A.L. and Jergensen 2nd, G.V., Editors, AIME, NY, 1982, pp. 238-300. 3. Nichols, J.P.: "Selection and Sizing of Screens", Design and Installation of Comminution Circuits, Mular, A.L. and Jergensen 2nd, G.V., Editors, AIME, New York, 1982, pp. 509-522. 4. Hatch, C.C. and Mular, A.L.: "Simulation of the Brenda Mines Ltd. Secondary Crushing Plant', Mining Engineering, Volume 30, No. 9, September 1982, pp. 1543-1562. 5. Karra, V.K.: "A Process Performance Model for Cone Crushers", Proc. of XIV Inter. Min. Proc. Congress, Toronto , Canada, Sect. 111, 1982, p. III-6.1. 6. Tucker, R.J. & Meech, J.A.: "Modelling Secondary Crushing Plants for Teaching Purposes and Operator Training", 17th Can. Min. Proc. Conf., Ottawa, Canada, Jan. 1985, pp. 21. 7. Nordberg Process Machinery: Reference Manual (1976). 8. Hotz, J.C.: "Crushing", Mineral Processing Plant Design, Second Edition , Mular , A.L. and Bhappu, R.B., Editors, Society of Mining Engineers of AIME, New York, 1980, pp. 203-238. 9. Flavel , M.D.: " Selection and Sizing of Crushers", Design and Installation of Comminution Circuits , Mular, A.L. & Jergensen 2nd, G.V., Eds., AIME, New York, 1982, pp. 343-386. 10. Coleman, K.G.: "Selection and Guidelines for Size and Type of Vibrating Screens in Ore Crushing Plants", Mineral Processing Plant Design, Second Edition, Mular, A.L. & Bhappu, R.B., Eds., Society of Mining Engineers of AIME, New York, 1980, pp. 341-361.
11
Table 1: Screen Areas Used in this Study.
Circuits 1, 2, and 3 Size Number Installed hp Area (m2) 8 x 20 2 25 29.7 8 x 16 2 20 23.8 8 x 16 2 15 17.8
Circuit 4 Size Number Installed hp Area (m2) Secondary 8 x 20 (4A) 2 25 14.9 8 x 16 (4B) 2 20 11.9 Tertiary 8 x 16 2 20 23.8 6 x 16 2 15 17.8 6 x 12 2 12 13.4 4 x 12 * 2 8 8.9 4 x 9 * 2 6 6.7 * unconventional sizes
Table 2: Typical Ore Conditions Shift 1 2 3 Work Index (kWh/t) 14.0 12.5 15.0 D80 Feed Size (mm) 191 178 203 Variability High variation Low variation Steady increase in hardness and size throughout the shift
Table 3: Impact of Screen Hole Size on Relative Average Shift Production (referenced against a 19 mm hole size) Circuit 1 2 3 4 Screen Hole Size (mm) 19 13 19 13 19 13 19 13 Actual Tonnage Ratio 1.0 0.764 1.0 0.687 1.0 0.736 1.0 0.793 Predicted Tonnage Ratio 1,9 0.744 1.0 0.723 1.0 0.735 1.0 0.838 Deviation due to less (more) efficient crushing/screening 0 (2.7) 0 5.0 0 0 0 5.4 Average Power Level (%) 80 79 72 77 76 79 69 77 Average CSS (mm) Secondaries Tertiaries 33 10 29 8 30 10 28 7 31 10 29 8 33 10 28 7
12
Table 4: Impact of Screen Area on Relative Shift Production Circuit 1, 2, and 3 Screen Area (m2) 29.7 23.8 17.8 Actual Tonnage Ratio 1.00 0.954 0.770 Predicted Tonnage Ratio * 1.00 0.986 0.915 % Deviation due to less efficient crushing and/or screening 0 3.1 17.6 Average Power Level (%) 78 78 76 Average CSS (mm) Secondaries Tertiaries 33 11 32 10 30 8
Circuit 4 Screen Area (m2) 32.7 29.7 23.8 21.6 Actual Tonnage Ratio 1.027 1.0 0.853 0.476 Predicted Tonnage Ratio * 1.005 1.0 0.936 0.874 % Deviation due to less efficient crushing and/or screening (2.2) 0 3.1 17.6 Average Power Level (%) 80 76 70 64 Average CSS (mm) Secondaries Tertiaries 40 14 35 10 28 8 26 8 * Predicted by Bond Formula and Actual Power Utilization
Table 5: Relative Average Shift Production for each Circuit Type with Adequate Installed Screen Area 29.8 m 2
(referenced against a 19 mm hole size) Circuit 1 2 3 4 Screen Hole Size (mm) 19 13 19 13 19 13 19 13 Actual Tonnage Ratio 1.0 1.0 0.874 0.724 0.943 0.889 1.000 1.054 Predicted Tonnage Ratio 1.0 1.0 0.924 0.827 1.002 0.950 0.898 0.923 Deviation due to less (more) efficient crushing/screening 0 0 3.4 12.4 5.9 6.4 (11.4) (14.2) Average Power Level (%) 80 79 74 75 80 77 73 80 Average CSS (mm) Secondaries Tertiaries 33 10 30 10 30 10 30 10 33 10 30 10 35 10 28 6
13
Figure 1: Flowchart of PLANT Program.
READ IN CRUSHER AND EQUIPMENT SPECIFICATIONS 1. Initialize Shift 2. 2. Load Circuit 3. Adjust Crushers CREATE NEW ORE BLOCK CALL SUBROUTINES IN SEQUENCE ADJUST TIMER AND ORE CONDITIONS STORE CIRCUIT CONTENTS CREATE AND EDIT SHIFT REPORT LAG Store/Delay Ore Movement CRUSH Crusher Calculations SCREEN Screen Calculations SIZE Sum and Blend Ore Blocks OUT Interactive Input/Output 14
T = T(SET) + F
Figure 2. Flowchart for Crusher Amperage and Product Size Calculations. Calculate R1 T = TC Calculate TMAX Calculate A Calculate DD Calculate R2 IF
|R1-R2| < 0.01 R2 NO YES Calculate TC IF
TC > T F = F + T -TC 15
Figure 3. Secondary and Tertiary Crusher Power Draw Circuit 1 (C.S.S. 36, 14, 14)
Figure 4. Secondary and Tertiary Crusher Power Draw Circuit 1 (C.S.S. 36, 14, 14) 16
Figure 5: The influence of tertiary crusher setting on shift production in Circuit 2. Secondary crusher setting = 34 mm Secondary crushers = 2.1 mm (7 ft) 350 hp Tertiary crushers = 2.1 m (7 ft) 350 hp 19 mm Screens (Extra Heavy Duty) = 2 (6 x 16) 25 hp
Figure 6: The influence of secondary crusher setting on shift production in Circuit 2. Tertiary crusher setting = 12 mm Secondary crushers = 2.1 m (7 ft) 350 hp Tertiary crushers = 2.1 m (7 ft) 350 hp 19 mm Screens (Extra Heavy Duty) = 2 (6 x 16) 25 hp 17
Figure 7: Effect of screen area on average shift production in Circuits 1, 2, 3, and 4 for 19 and 13 mm.
18
Figure 8: Effect of screen area on total crusher power utilization in Circuits 1, 2, 3, and 4 for 19 and 13 mm.