Planning Plant 1001 1101 2001 2002

How
system
determines
permits??
PG-11
Maintenance Plant
1001-
1001
1002-
1001 1101-1101

Permit Agreement required depending on setting before an order may be released or technically completed.

Advisable to group permits into permit categories, like Work permit, Safety Permit, etc.

Purpose Before an order can be executed or technically completed, a planner ensures that:


* All the necessary safety precautions have been taken


* The required financial resources are available.


* The work has been approved at management level.

A Permit category must be assigned to each permit.

Permit class: 049

T-Code: IPMD (Control of Order release & Order Completion in permits)
All Permits needs to be created as master data in system. Based on safety advice from the manufacturer of a technical
object, general legal regulations on safety in the workplace or fixed company rules.
T357G-Table containing all permits

Every user can assign permits to orders or technical objects

But Role & Authorization maintenance needed to authorize specific user to issue & cancel permits
Proposal can be set when assigning this permit to technical object, if a permit should be valid for each order on a
particular technical objects or its sub objects. Deletion of permit assignment is possible any time.
Issued permits can be cancelled in two ways only

* The permits must be issued before the order is released, but the order has not yet been released

* The permits must be issued before the order is technically completed, but the order has not yet been technically completed.


PERMIT IN AN OBJECT HIERARCHY

In Clarification plant C1, there is a pumping station C1-B01, in which a pump C1-B01-1 is installed
Ear protection is normal requirement for work in the pumping station. The permit ear protection was created and
assigned to function location C1-B01
A Welding Permit is required for welding work in the pump. The permit Welding Permit was created and assigned to
functional location C1-B01-1
In an order for the pump, ear protection for pumping station C1-B01 and welding permit for pump C1-B01-1 are
proposed by the system, since functional location C1-B01 is superior to functional location C1-B01-1
If the indicator Proposal was set when the permits Ear protection and Welding permit were assigned to the respective
functional locations, the corresponding permit is automatically copied to the order.

Permits assignment to an Order can be done manually or automatically by the system.