THICKNESS OF PILECAP (T) = 0.

60 m
CLEAR COVER = 0.075 m
WIDTH OF PILECAP (B) = 0.70 m
LENGTH OF PILECAP (L) = 0.70 m
WIDTH OF COLUMN (b) = 0.30 m
DEPTH OF COLUMN (d) = 0.30 m
f
ck
FOR PILECAP = 25 Mpa
f
y
FOR PILECAP = 415 Mpa
THICKNESS OF SOIL LAYER ABOVE PILECAP = 0.80 m
UNIT WEIGHT OF SOIL ABOVE PILECAP = 18.00 kN/m
3
CLEAR CANTILEVER FROM PILE = 0.15 m
DIAMETER OF PILES = 0.40 m
COLUMN F
y
(kN) F
x
(kN) F
z
(kN) M
x
(kN.m) M
z
(kN.m)
317.87 -2.59 -18.94 0.00 0.00
C
Y
0.6 X
Z
0.7
0.3
0.7 0.3
COLUMN
MOMENT DUE TO SHEAR AT PILECAP BASE (M
X
') -11.36 kN.m
MOMENT DUE TO SHEAR AT PILECAP BASE (M
Z
') 1.55 kN.m
TOTAL BENDING MOMENT (M
X
) -11.36 kN.m
TOTAL BENDING MOMENT (M
Z
) 1.55 kN.m
TOTAL VERTICAL UNFACTORED FORCE 363.68 kN
UNFACTORED REACTIONS AT COLUMN BASE
PILECAP DESIGN FOR 1 PILES WITH A SINGLE COLUMN
1
PILE NO. r
xi
(m) r
xi
2
1 0.000 0.00
X
Z
0.3
0.15
364 kN
MAXIMUM ULTIMATE BENDING MOMENT (M
UZ
) = 82 kN.m
EFFECTIVE DEPTH ALONG-X DIRECTION = 0.519 m
EFFECTIVE DEPTH ALONG-Z DIRECTION = 0.507 m
X-DIRECTION
A
st
REQUIRED = 727 mm
2
MIN. A
st
REQUIRED = 436 mm
2
DIA. OF MAIN BARS = 12 mm
DIA. OF DISTRIBUTION BARS = 12 mm
REQUIRED NUMBER OF MAIN BARS = 6 mm
PROVIDED NUMBER OF MAIN BARS = 6 mm
REQUIRED NUMBER OF DISTRIBUTION BARS = 4 mm
PROVIDED SPACING OF DIST. BARS = 4 mm
Z-DIRECTION
MIN. A
st
REQUIRED = 426 mm
2
DIA. OF DISTRIBUTION BARS = 12 mm
REQUIRED NUMBER OF MAIN BARS = 4 mm
PROVIDED NUMBER OF DIST. BARS = 4 mm
SECTION ALONG X
IN PILE (kN)
364
364 kN
FINAL FORCES
MAXIMUM ULTIMATE SHEAR AT CRITICAL SECTION (V
U
) = 546 kN
ULTIMATE SHEAR STRESS (
u
) = 1.50 N/mm
2
pt OF STEEL PROVIDED (%) = 0.20 %
SHEAR STRESS IN CONCRETE (
C
) = 0.33 N/mm
2
SHEAR STRESS RESISTED BY SECTION (
C'
) = 1.69 N/mm
2
DESIGN FOR SHEAR IS NOT REQUIRED IN X-DIRECTION.
CHECK FOR SHEAR
X-DIRECTION
A
st
REQUIRED = 727 mm
2
15
MIN. A
st
REQUIRED = 436 mm
2
0.15 0.28
DIA. OF MAIN BARS = 12 mm 0.2 0.315
DIA. OF DISTRIBUTION BARS = 12 mm 0.25 0.35
NO OF BARS REQUIRED FOR MAIN STEEL = 6 0.5 0.46
NO OF BARS REQUIRED FOR DIST. STEEL = 4 0.75 0.54
REQUIRED SPACING OF MAIN BARS = 99 mm 1 0.6
REQUIRED SPACING OF DISTRIBUTION BARS = 188 mm 1.25 0.64
Z-DIRECTION 1.5 0.68
A
st
REQUIRED = 426 mm
2
1.75 0.71
MIN. A
st
REQUIRED = 426 mm
2
2 0.71
DIA. OF MAIN BARS = 12 mm 2.25 0.71
2.5 0.71
NO OF BARS REQUIRED FOR MAIN STEEL = 4 2.75 0.71
3 0.71
REQUIRED SPACING OF MAIN BARS = 195 mm
2.5
2.8
3.1
3.5
20 25 30
0.28 0.29 0.29
0.315 0.325 0.33
0.36 0.36 0.37
0.48 0.49 0.5 0.2 0.325
0.56 0.57 0.59 0.2 0.325
0.62 0.64 0.66 0.20 0.325
0.67 0.7 0.71
0.72 0.74 0.76
0.75 0.78 0.8
0.79 0.82 0.84
0.81 0.85 0.88
0.82 0.88 0.91
0.82 0.9 0.94
0.82 0.92 0.96
15 2
20 3 4
25 4
30 5