Part 1B - Technical Specification TIDEL PARK COIMBATORE LTD (A JV of TIDCO, ELCOT, TIDEL & STPI) INTERNATIONAL TECHNO COMMERCIAL TENDER PART 1 B TECHNICAL SPECIFICATION
PROVIDING SEWAGE TREATMENT PLANT WORKS IN CONSTRUCTION OF BUILDING COMPLEX OF INFORMATION TECHNOLOGY PARK AT VILLANKURICHI (SEZ AREA), COIMBATORE
DUE DATE FOR SUBMISSION: ON OR BEFORE 19 th June, 2009 at 15.00 Hours TO BE SUBMITTED TO: The Chairman and Managing Director M/s. TIDEL Park Coimbatore Ltd (First Floor TIDEL Park) 4, Rajiv Gandhi Salai, Taramani, Chennai - 600 113. Telephone No.: +91 44 22540500/501 Fax No.: +91 44 22541744. ARCHITECTS & ENGINEERS:
M/s C.R.Narayana Rao Architects & Engineers #5/10, Karpagambal Nagar, Luz, Chennai- 600 004 INDIA Tel No: 044-24991676 (4 lines) Fax No: 044-24991318. OWNERS ENGINEERS: M/s TCE CONSULTING ENGINEERS LTD # 73/1, Sheriff Centre, St. Marks Road, Bangalore 560001. INDIA Tel No: 080-66226000 Fax No: 080-22274873. BID SUBMITTED BY: M/s._________________________
Address_____________________
____________________________
MAY 2009
C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 1 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification TIDEL PARK COIMBATORE LTD (A JV of TIDCO, ELCOT, TIDEL & STPI)
PROVIDING DOMESTIC SEWAGE TREATMENT PLANT FOR MEMBRANE BIO REACTOR TECHNOLOGY IN CONSTRUCTION OF BUILDING COMPLEX OF INFORMATION TECHNOLOGY PARK AT VILLANKURICHI (SEZ AREA), COIMBATORE
TECHNICAL SPECIFICATION FOR DOMESTIC SEWAGE TREATMENT PLANT FOR MEMBRANE BIO REACTOR TECHNOLOGY 400 KLD
1.0 DOMESTIC SEWAGE TREATMENT PLANT
1.1 GENERAL
The main source of effluent is wastewater resulting from Toilets, pantries, and washrooms. The scope of work includes detail design, drawings, getting approvals from statutory bodies, coordinating during construction, erection, commissioning and obtaining best results for completely below ground domestic sewage treatment plant with electrical, mechanical and piping. (Treatment of Kitchen waste is not included in this scope of work)
The treated effluent should be fit to reuse for gardening, HVAC and Flushing Disposal purpose.
The work should be carried out on a turnkey basis covering a performance guarantee of plant as per the standards committed for minimum of Ten years.
TURNKEY TENDER Vendor to submit detail design, hydraulics, plan and section with detail equipment specs along with TENDER justifying each parameters.
Also vendor to submit pay back calculation, operation and maintenance cost sheet.
1.2 BASIC DATA ON RAW WASTE WATER (SEWAGE)
Total Suspended Solids (TSS) : 300 mg/lit BOD 5 days : 300 - 400 mg/lit COD : 500 mg/lt pH : 7.5 8.5 Peak Factor : 2.5 Inflow Time : 18 Hrs
As stipulated by State Pollution Control Board (PCB), the treated effluent quality shall be within the following values for various parameters, for both present and future. pH - 7.0 - 8.0 TSS - NIL BOD 5 days <10 mg/lit COD <20 mg/lt Turbidity <2 mg/lt E coli - absent Color <05 hazen Odor - unobjectionable
1.4 THE TREATMENT PLANT (STP)
Based on the Raw Waste Water characteristics following treatment scheme is suggested:
The Sewage is led into a Bar Screen Chamber provided with MS Bar Screen for removal of floating and large suspended matters.
The screened effluent is collected in an equalisation tank. This sump is provided to dampen the flow fluctuations and, in order to keep the solids in suspension, pre-aeration is provided with coarse bubble tubular diffusers.
From the equilisation tank sewage is allowed to flow through fine screen chamber, which has opening less than 3 mm and cleaning is done automatically.
From fine screen chamber sewage is allowed to Aeration tank, which comprises fine pore diffusers and Membranes immersed. Using suction pumps connected to membrane units, water is sucked out from aeration tank.
Sludge will be retained in the Aeration tank and excess sludge will be pumped/passed to sludge holding tank and then pumped to Filter press when ever MLSS measured is higher than designed.
Permeate of membrane is further treated with chlorinator and stored in final sump.
The waste sludge from aeration tank is passed to sludge holding tank and then pumped through screw pump to filter press and solid cakes formed are carted out
Following are the units proposed for above treatment scheme,
Bar screen chamber coarse (an ultrasonic non-contact type open channel flow measurement meter shall be installed before the bar screen) Oil and Grease separator C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 3 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification Fine Screen (Automatic) Coarse bubble diffuser. Equalisation tank Pump Room Anoxic tank/Aeration tank/MBR tank. Chemical cleaning of membranes Chlorinator Final tank Filter Press with screw pump Sludge holding tank Piping and cabling Units designed and proposed for LT panel
1.5 DESIGN CRITERIA The STP shall be designed on the basis of wastewater flow and quality parameters as in Para 1.2 & 1.3. Vendor to submit an offer for STP with complete design and detail drawing. These values shall form the design criteria for design
a) Equalisation Tank (Balancing Tank) Retention time : Min 5.0 - 6.0 hours based on peak hourly flow of raw sewage.
b) Aeration / Membrane Bio Reactor Tank
Influent BOD5 : 300 mg/lit MLSS : 8000 12000 mg/lit Oxygen requirement : 2.0 kgs per kg of BOD
c) Membranes
Type : Spindle / Sheet - Immersed type Pore size : 0.4 micron Casing material : ABS Operating : Suction 2 way Housing : SS
AUTOMATION OF SYSTEM
It is required to automate the system completely as specified below with scada based support, Level transmitter at equalization tank connecting to PLC and scada controlling the equalization pump and permeate pump. (Link between inlet and out let) Ultrasonic based Flow meter to monitor the flow to fine screen. Electrically actuated valve at fine screen entry to control flow to fine screen with link between level transmitter at screen and valve. Level transmitter at anoxic /aeration tank to control / monitor level and permeate pumps. C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 4 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification TMP display and monitor /control between membrane out flow and permeate pumps. Flow meter at outlet of permeate pump with monitor/control permeate pump in comparison to raw sewage pump.
1.6 SCOPE OF CONTRACT & DESCRIPTION OF WORK
SCOPE OF CONTRACT The tender is invited on turnkey basis for Design, Engg, Supply, Coordinating with construction works, Erection and Commissioning of Sewage Treatment Plant (STP) for MBR technology, to give treated effluent quality as specified.
The schematic drawings attached herewith are preliminary. However, the successful contractor will be required to submit the Detailed Process & Structural drawings (shop drawings) incorporating the thickness of various structural members.
These detailed drawings shall be submitted to Consultants for their comments & approval. Vendor has to submit all the technical details for equipments used for operation of plant to the consultant and should get approval. All the works shall be carried out as per final "valid for construction drawings" only.
Testing of all equipments at his workshop shall be certified from Consultant.
Inspection visit to certify all the equipments before supply shall be arranged for Consultant/PMC.
Complete interconnecting piping between various units as per piping details including supply of all materials like GI pipes, fittings, all valves, gaskets, flanges, nuts and bolts including all materials required for necessary pipe supports, etc., complete.
Supply, erection and commissioning of all the equipments required for the sewage treatment plant as per the individual equipment specification.
All electrical works including all electrical motors for the various equipment confirming to IS 5600 - 1970, cabling, LT panel, starters, etc.,
The scope of work includes coordinating all necessary civil works like construction of panel foundations, cable trenches, cable supports, lighting of entire plant as per drawing etc., complete.
Commissioning of all the equipment after the electricity is supplied will be within the scope of contract.
All temporary sheds, office, go downs, etc. required for storage of materials and for contractors supervisory personnel at site.
C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 5 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification Vendor to submit detail cost sheet for operation and maintenance, inclusive of all consumables, man power and ele power charges for one year with tender.
Vendor to submit the pay back calculation sheet for above technology with Civil, M&E costs including O&M charges.
1.7 DETAILS OF CIVIL WORKS
Civil works (By civil contractor) carried out in the treatment plant are as below which should be coordinated by STP vendor and vendor should furnish required levels and details.
a. Coarse Bar Screen Chamber b. Fine screen c. Equalization Tank d. Anoxic/Aeration / MBR Tank e. Final tank f. Working platform, staircase etc., as per drawing g. Works such as pipe / cable trenches, chambers, equipment foundations, staircase headroom at entry of STP etc., h. Plant room. i. Sludge holding tank.
1.8 DETAILS OF PIPING WORK
Piping works including excavation, back filling, masonry / structural pipe supports, puddle flanges, concrete bedding, pipe specials and GM B/F Valves (Approved or Recommended make only) are all included in the scope of contract.
The quantity and sizes of the pipes shall be vendor design and piping drawing shall be submitted for consultant approval before execution or procurement.
All pipes laid in the plant shall be treated with two coat of anti corrosive paint and one coat of approved IS recommended color based on feeding scope of pipe.
1.9 GENERAL
The scope of STP vendor regarding Civil Works is coordinating necessary hydraulic testing for water tightness/seepage as per relevant IS CODES FOR ALL WATER RETAINING STRUCTURES and hydraulic levels of the units done by civil contractor.
Scope of contract for piping includes construction of necessary masonry valve chambers min 900 x 900 wherever necessary, removable type MS painted covers and extension spindles for valves.
Make of all piping/Equipments/Motors/Cables and Pumps shall be clearly stated in the offer and shall be approved by Consultant before Supply & Installation. The decision of Consultant in this regard shall be final and binding on the successful Contractor. C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 6 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification
All equipment GA drawings shall be submitted to Consultant for approval prior to fabrication/ ordering. The fabricated and brought-out equipments shall be inspected at Contractor Works by Consultant and shall be dispatched to site only after obtaining clear dispatch instructions in writing from Consultant.
It is obligatory on the part of the intending bidder to visit the site of work prior to submitting the offer and familiarize himself with local/site /soil conditions, availability of men, Materials and Machinery for successful and timely execution of the works. No extra shall be paid in case Contractor fails to ascertain correct site conditions before submitting the offer.
All MS hand railing/ladders shall be given two coats of corrosive resistant paint over a coat of red-oxide primer or approved make and shade, which shall be scope of civil contractor.
Any other item not specifically mentioned in this tender but is essential for proper and successful completion, commissioning and running of the DSTP for its commercial utilization is also to be included in the scope of contract.
Fresh water line shall be provided to STP area but should be coordinated with plumbing vendor.
STP vendor has to coordinate with Main contractor, Plumbing vendor, Electrical contractor, Project management/Builder/Client, Architect and Consultant to establish the plant and to run the plant successfully .
Battery Limits:
1. Sewage Inlet up to STP screen chamber 2. Treated water up to final sump in the STP 3. Exhaust fan capacity and ducting up to terrace 4. Electrical feeder up to LT panel. 5. Fresh water line up to STP.
1.10 EQUIPMENT SPECIFICATION
a) Bar Screen
Type -1 : Manually cleaned with Handrake
Construction : In MS flats of size 20 x 6 not more than 20mm c/c with necessary MS flat 25 x 6 stiffeners. The whole unit shall be given 2 coats of epoxy based paint over a coat of epoxy based primer. C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 7 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification
1 no. MS hand rake shall also be provided with GI pipe rod.
Type - 2 : Mechanically cleaned automatic system
Construction : In SS flats with opening not more than 3 mm with automatic cleaning system based on head loss.
b) Raw Effluent Pumps
Quantity : Refer: BOQ
Duty : To transfer Raw Effluent from Equalisation Tank to Aeration tank./MBR tank
Type : Vertical submersible type pumps
Motor : Built in vortex pump
Material of Construction : Body and impeller in CI
c) Diffusers
Quantity : Refer: BOQ
Fine pore diffusers : Long Membranes of EPDM supported on PVC pipe secured at the ends by SS clams and construction with necessary accessories etc complete.
Coarse bubble diffusers : Pressed PVC pipe with holes on the surface for air ejection with necessary accessories etc complete (for equalisation tank and Final tank)
Duty : To transfer secondary sludge from clarifier to Aeration Tanks & sludge thickener.
Type : Horizontal centrifugal non-clog Self-priming, open impeller, pumps
Motor : TEFC Motor, with IP-55 protection and suitable for 400/440 V, 50 HZ A/c
Material of Construction : Body and impeller in CI
Accessories : Air cock with priming funnel, Flexible Coupling with guard, Base frame, foundation bolts etc.,
f) Chlorinator
g) Chemical Cleaning pumps
h) Back wash pumps Pumps are applied to clean the membrane surface from organic and inorganic loading. Preferred chemicals are NaOCl and citric acid.
i) Suction pumps Suction shall be applied to the header on top of MBR modules and it shall be bank type. Pressure shall be as per design calculation.
Details justifying the duty condition of pumps shall be submitted.
j) Filter press
Type : Automatic hydraulic closing Mechanism and as per BOQ.
1.11 DETAILS OF ELECTRICAL WORKS
GENERAL SPECIFICATION OF EQUIPMENT:
a) 1 NO. LT Panel, cubicle type suitable for floor mounting and comprising incoming power control switch, Ammeters, Voltmeter, Phase Indicating Lamps, MCBs and Starters for the feeders all complete. Also to be provided are two nos. Automatic C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 9 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification Level Controller for actuating the Raw Effluent /Treated effluent. Necessary Auto manual Selector Switches shall also be provided. b) Local push button starters shall also be provided near the Aerator equipments and mounted in weatherproof enclosures. c) Necessary power wiring by armoured PVC Cables or by PVC insulated wire in conduit from LT Panel to equipment motors shall be provided with necessary tray/ support etc complete and internal lighting of entire DSTP Plant as shown in the drawing. d) Necessary earthing as per I.E. rules. e) Lighting shall be as per IS requirements and fixtures shall be PHILIPS make and the make and size of cables used should be approved from consultant. f) Energy meter (approved make) should be provided in the panel g) 3 no spare feeder with MCB suitable for 5 HP shall also be provided in the LT Panel. h) The switchboard shall be metal clad, totally enclosed, rigid, compartmentalized design, floor mounting, air insulated, extensible cubicle type for use on medium voltage power, 3 phases 4 wire 50 cycles system. i) The equipment shall be designed for operation in high ambient temperature and high humidity tropical atmospheric conditions. Means shall be provided to facilitate ease of inspection, cleaning, and repairs for use in installations where continuity of operation is of prime importance.
STANDARDS:
Following equipments shall conform to the requirements of:
a) Air Circuit Breaker (ACB) - IS 13947 - 1,2 / IEC 60947 - 1,2 b) Moulded Case Circuit Breaker (MCCB) - IS 13947 - 1,2/ IEC 60 947 - 1&2 c) Contactors - IS 13947 - 1,4 d) Miniature Circuit Breaker (MCB) - IS 8828 - 1996/ IEC 898 - 1995 e) Residual Current Circuit Breaker (RCCB) - IS 12640 - 1988 / IEC 1008 f) HRC fuse link - IS 9224 and BS 8 :8 g) Current Transformer - IS 2705 and IEC 185 h) Potential Transformer - IS 3156 i) Relay - IS 3231 & IS 8686 (For Static Relays) j) Indicating Instrument - IS 1248
CONSTRUCTION:
1. The switchboard shall be: a) Sheet steel enclosed, indoor floor mounted freestanding cubicle type. b) Made up of the requisite vertical sections modular type which when coupled together shall form continuous switchboards. c) Dust, vermin and damp proof and enclosure protection not less than IP 52. d) Each feeder/instrument compartment shall be provided with a hinged door interlocked with MCCB/SFU inside the compartment such that door can only be opened when MCCB/SFU in off position. e) Readily extendable as required by the addition of vertical sections after removal of the end covers. C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 10 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification f) Switchboards shall have access to the feeders, bus bars, cable termination, cable alley, etc. as required.
2. Each vertical section shall comprise: a) A front-framed structure of rolled/folded CRCA sheet steel angle section of minimum 3 mm thickness rigidly bolted together. This structure shall house the components contributing to the major weight of the equipment such as circuit breaker cassettes, fuse switch units, main horizontal bus bars, vertical risers and other front mounted accessories.
b) The structure shall be mounted on a rigid base frame of folded CRCA sheet steel of minimum 6 mm thickness and 75 mm height. The design shall ensure that the weight of the components is adequately supported without deformation or loss of alignment during transit or during operation.
c) A cable chamber housing the cable end connections and power/control cable terminations. The design shall ensure generous availability of space for ease of installation and maintenance of cabling and adequate safety for working in one vertical / horizontal section without coming into accidental contact with live parts of the adjacent section.
d) A cover plate at the top of the vertical section, provided with a ventilating hood where necessary. Any aperture for ventilation shall be covered with a perforated sheet having less than 1mm diameter perforations to prevent entry of vermin.
e) Front and rear doors fitted with dust excluding neoprene gaskets with fasteners designed to ensure proper compression of the gaskets. When covers are provided in place of doors generous overlap shall be ensured between sheet steel surfaces with closely spaced fasteners to preclude the entry of dust.
3. The total height of the panel shall not be more than 2300 mm unless otherwise specified and maximum height of switch operating handle shall not be more than 1800mm from FFL. The total depth of the panel shall be adequate to cater for proper cabling space.
4. Doors shall be of minimum 14-gauge sheet steel and covers/partitions of 16G sheet steel. All sheet steel work forming the exterior of switchboards shall be smoothly finished, leveled and free from flaws. The corners should be rounded.
5. The Components in the switchboards shall be so arranged as to facilitate ease of operation and maintenance and at the same time to ensure necessary degree of safety.
6. Components forming part of the switchboards shall have the following minimum clearances: Between phases - 25mm Between phases and neutral - 25mm Between phases and earth - 25mm Between neutral and earth - 19mm
C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 11 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification When, for any reason, the above clearances are not available, suitable insulation barrier / shielding shall be provided. Clearances shall be maintained during normal service conditions.
Creepage distances shall comply to those specified in relevant standards.
7. All insulating material used in the construction of the equipment shall be of non- hygroscopic material treated to withstand the effects of high humidity, high temperature and tropical ambient service conditions.
8. Functional units such as circuit breakers, fuse switches, MCCBs, etc. shall be arranged in multi-tier formation except that not more than two air circuit breakers shall be housed in a single vertical section.
9. Metallic/insulated shrouding shall be provided within vertical sections and between adjacent sections to ensure prevention of accidental contact with:
10. Main bus bars and vertical risers during operation, inspection or maintenance of functional units and front mounted accessories.
11. Cable terminations of one functional unit, when working on those of adjacent unit/units.
12. All covers providing access to live power equipment/circuits shall be provided with tool operated fasteners to prevent unauthorized access.
13. Provision shall be made for permanently earthing the frames and other metal parts of the switchgear by two independent distinct connections.
14. Only CRCA steel sheets shall be used for fabricating the cubicle.
15. Thickness tolerance for sheets shall be as applicable in relevant IS.
METAL TREATMENT AND FINISH:
1. After fabrication the panel shall undergo 7-tank treatment/sand blasting for removing Grease, Rust etc.. 2. The panel shall be coated with zinc chromate primer (Applicable for outdoor panels). 3. After coating of primer, the panel shall be coated with Epoxy powder with shade RAL7032 prior to the approval of shade from Consultants.
1.12 TEST/TRIAL RUNNING AND COMMISSIONING
The Vendor shall have to test the each equipment used for the plant for at least 72 hours continuous running with designed load and to the full satisfaction of Consultants. Any defects found, has to be rectified by the contractor at his own cost immediately and within reasonable time to be decided by client.
Necessary Instruments, Gauges, Labour/Supervisory Staff, Laboratory analysis etc., are to be furnished/provided by the vendor at free of cost to client. . C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 12 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification
Vendor has to specify the value added services in his offer letter.
It is necessary for vendor to specify the minimum wastewater required for commissioning of STP with TENDER.
1.13 COMMISSIONING/HANDING OVER
During trial runs as described above, the vendor shall satisfy Consultant in all respects regarding the satisfactory quality of effluent, quality of materials, equipments and workmanship used in the plant.
Only after satisfying itself/ himself regarding the above points, client will take over the plant and such date of taking over shall be deemed as date of completion for all purposes, guarantees, and payment terms mentioned else where in this tender.
The guarantee period described elsewhere in the tender should start from the date of completion.
1.14 TRAINING OF OPERATOR
Vendor shall provide necessary training for operator during commissioning period. Vendor to certify the operator performance to carry over the plant maintenance and operation efficiently after handing over the plant. Client / AM Contractor to provide 3 operators during commissioning stage for training purpose.
1.15 GUARANTEE
The under mentioned clauses shall govern in case of any contrary provisions given elsewhere in the document.
Manufacturer's Guarantees
The manufacturers guarantee for design, workmanship, and performance for all bought out items shall be made available to the owner and shall be valid at least for the entire defects liability period.
In the event of failure of any particular equipment, which fails more than three items during the guarantee period as mentioned in clause below, the contractor shall replace at his own cost that equipment. Manufacturer's/Contractor's guarantee, as mentioned in clause above, for such replaced equipment shall also be made available to the Owner and should be kept at least for one year from the date of last replacement.
Performance Guarantee
The Contractor shall give guarantee for a period of Seven years from the date of successful commissioning of the treatment plant against design, defective materials, workmanship, performance and guaranteed effluent quality. In the event the commissioning of the plant is not possible due to non-availability of effluent, contractor shall be issued mechanical completion certificate by C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 13 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification client/consultant provided each equipment is tested satisfactorily as directed by Consultant. However, the contractor shall have to maintain the plant at his own cost, in such a case for a period for three months beyond which period, if he is required to maintain further, he will be paid extra at mutually agreeable rate. However, the Contractor shall carry out testing and commissioning of the plant during the Defects Liability Period. Any defects found in the workmanship, the Contractor at his own expense shall make materials or performance of the plant good within the time specified by client/consultant.
For this purpose, the retention amount will be as follows:
10% of each RA bill until it reaches 5% of the total value of Contract shall be retained and also treated as performance guarantee. The Successful Tenderer as per general conditions of contract shall be retained till the completion of satisfactory commissioning as stated above. The contractor at his own expense shall start and commission, the plant and prove that it is giving satisfactory service and desired characteristic of the treated effluent, for two months before handing over the plant to the Owner. During this, the contractor shall train the Owners operational stall without any extra cost to the Owner. The Contractor shall also have to guarantee the quality of the treated final effluent to meet the specification mentioned already. In case the quality of treated effluent varies from what is required, the contractor shall rectify the plant at no extra cost so as to achieve the requisite performance guarantee and satisfactory commissioning of the plant to the client/Consultant. Despite the first opportunity given to the contractor to effect rectification so as to achieve compliance, and In case the quality of treated effluent varies again from what is required, the contractor will be given one more opportunity to rectify the plant and bring the treated effluent to the required quality.
If the contractor fails in both opportunities to achieve the required result as aforesaid, then the Architect/ Owners Engineers/ Owner will have the liberty to engage another agency to carry out whatever rectification necessary at the contractors risk, cost and all expenses which will be recovered from any moneys due to the Contractor and in addition, the retention money and Performance bond being forfeited by the Owner.
The contractor shall furnish the figures for average daily consumption of nutrients / Chemicals, if any. All the above guarantees will be based on collection and analysis of samples as mentioned in clause below.
Oxygenation Capacity of Diffusers. The contractor, if directed by Consultant, shall at his own cost prove the Oxygenation capacity guaranteed by him for the diffusers provided by conducting Oxygenation capacity tests on the unit by any standard and internationally recognised method to be approved by the Consultants.
1.16 MECHANICAL GUARANTEES The Contractor shall guarantee for a period of one year for the failure of any particular part of the equipment. In the event of failure of any particular part of the equipment more than three times during the guarantee period, the Contractor shall replace it. In case it is found that the above mentioned failure is due to C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 14 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification some other connected part of the equipment, that part shall also be rectified or replaced by the contractor to avoid such failures in the future. The guarantee for such replaced parts shall be extended by one year from the date of last replacement.
1.17 COLLECTION AND ANALYSIS OF SAMPLES The guaranteed effluent shall be based on complete analysis of samples collected after stabilization of the plant. Min. 2 nos. Raw Effluent and 2 nos. Treated Effluent samples per month shall be collected and got analyzed at the Pollution control Board approved Laboratory and should be submitted to consultant for approval Efficiency of plant and process after secondary clarifier should be presented to consultant by collecting sample at outlet of clarifier and analyzing the sample for BOD 5 days and TSS.
1.18 ANNUAL MAINTENANCE
The contractor shall include in the offer for maintaining the treatment plant including all the consumables etc., qualified personnel shall be posted on the site on shift basis, to take the sampling and carry out the tests. A complete record has to be maintained for all the tests carried out at regular intervals.
The Contractor shall employ a minimum of one operator per shift and one supervisor during general shift based on 3 shifts/day. The senior chemist of the contracting firm shall visit at least once a week for monitoring plant operation.
Also one Senior Mechanical Technician shall visit the plant for inspection and supervision of maintenance of all equipments.
NOTE: Data sheet to be duly filled before submission Provide detailed specification with guarantee details of the equipments, for which data sheet is not filled. Provide efficiency curves and catalogues for the equipments used. Provide as built drawing after completion of project. Vendor to furnish the manual for operation and maintenance with trouble shooting by his experience. Vendor to furnish the list of spare parts, which are frequently required for trouble free operation. Vendor to submit separate drawing and details for cleaning and backwashing of membranes. Vendor to provide warranty of membranes with manufacturer certificate.
C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 15 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification DATA SHEET
Vendor to submit the following in addition with following sheets 1. Plant Capacity : 2. Membrane type : 3. Make : 4. Pore size : 5. Plan area : 6. Depth : 7. MLSS : 8. Flux rate : 9. Power requirement :
Equipment Unit Power Total connected power
Total Connected HP
10. Operational Cost (Approximately):
11. Air requirement for membrane : 12. Air requirement for biological unit : 13. Cleaning system : 14. Chemicals used : 15. Suction pressure : 16. Existing Plant Data 17. Sludge generated in % : 18. BOD committed at exit of MBR : 19. Automation if any : 20. Replacement Guarantee : 21. Country manufacturer : 22. Type of membrane connection to support frame : 23. Membrane material : 24. Value added treatment : 25. Guarantee, process : 26. Sludge management : 27. MBR comprises of : 28. Similar experience :
C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 20 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification 1 Raw effluent pump Grundfos / KSB / Modi (sewage application)/ equivalent make as approved by consultant 2 Sludge pumps J ohnson / kirloskar / equivalent make as approved by consultant 3 Membrane Zenon/Kubota/Hydranautics / equivalent make as approved by consultant 4 Screw pumps Alfa / hydro prakav / equivalent make as approved by consultant 5 Filter press Dinshaw / hydro press / equivalent make as approved by consultant 6 Chlorinator ASIA LMI / equivalent make as approved by consultant 7 UV sterilizer TEFLON / equivalent make as approved by consultant 8 Automatic Screen J ash / equivalent make as approved by consultant
9 Motors Kirloskar / siemens / ABB / equivalent make as approved by consultant 10 i. Galvanised Pipes Tata / J indal / equivalent make as approved by consultant
11 ii GI fittings R Brand (ISI) /Unik /equivalent make as approved by consultant
12 Gate valves/Non-return valves Leader / Zoloto/ equivalent make as approved by consultant 13 Foot valves Leader / Zoloto /equivalent make as approved by consultant
14 Butterfly valve Inter valve / Slim Line / equivalent make as approved by consultant
15 ACB / MCCB / SFU / LBS MERLIN GERIN / ABB / SIEMENS/ equivalent make as approved by consultant 16 CONTACTORS / OLRS TELE MECHANIQUE / ABB / SIEMENS/ equivalent make as approved by consultant 17 MCB / ELCB MERLIN GERIN / MDS / INDO ASIA/ equivalent make as approved by consultant 18 MCB DB MERLIN GERIN / MDS / INDO ASIA/ equivalent make as approved by consultant 19 DIGITAL METERS AE / MECO / ENERCON / equivalent make as approved by consultant 20 Kwh / MDM / MDC METERS AE / ENERCON / L&T/ equivalent make as approved by consultant 21 LED INDICATING LAMPS / PBS TEKNIC / VAISHNO / SIEMENS / equivalent make as approved by consultant 22 SELECTOR SWITCHES KAYCEE / SALZER/ equivalent make as approved by consultant 23 LIGHT FIXTURES & MOTION DETECTORS PHILIPS / WIPRO/ equivalent make as approved by consultant 24 SWITCHES / SOCKETS (MODULAR) OUTLETS IN METAL BOXES ANCHOR ROMA / MDS MOSAIC / ABB/ equivalent make as approved by consultant
A. SECTION A - CENTRIFUGAL FANS FOR VENTILATION & EXHAUST SYSTEM 1.1 Scope 1.2 Codes & Standards 1.3 Construction Features 1.4 Drive Motor 1.5 Cabinet Centrifugal Fans 1.6 Noise & Vibration 1.7 Performance Guarantees 1.8 Data to be provided by the Vendor after award of work 1.9 Technical requirements for Toilet Exhaust Fans
SECTION B - SHEET METAL DUCTING
2.0 GENERAL 2.1 MATERIAL 2.2 THICKNESS OF SHEETS 2.3 LAYOUT OF DUCT 2.4 J OINTS 2.5 ELBOWS & BENDS 2.6 SUPPORTS
SECTION C - DAMPERS & AIR TERMINAL DEVICES 3.1 VOLUME CONTROL DAMPERS 3.2 AIR TERMINAL DEVICES
EQUIPMENT SPECIFICATIONS FOR CENTRIFUGAL FANS FOR VENTILATION & EXHAUST SYSTEM
1.1 SCOPE
This specification covers the general design, materials, construction features, manufacture, shop inspection and testing at manufacturers works, delivery at site, handling at site, erection testing, commissioning, performance testing and handing over of Centrifugal Fans of Ventilation and process plants.
1.2 CODES AND STANDARDS
The design, materials, construction, manufacture, inspection, testing and performance of centrifugal fans shall comply with all currently applicable statues, regulations and safety codes in the locality where the equipment is to be installed. The equipment shall also conform to the latest applicable Indian or equivalent standards. Other international standards are also acceptable, if these are established to be equal or superior to the listed standards. Nothing in this specification shall be construed to relieve the VENDOR / CONTRACTOR of this responsibility.
1.3 CONSTRUCTION FEATURES
1.3.1 CASING
The casing shall be of welded construction, fabricated from heavy gauge material. It shall be rigidly reinforced and supported by structural members. The seams shall be permanently sealed air tight. Split casing shall be provided on larger sizes of fans as per manufacturing standard or if specified in technical data sheets.
The impeller shall have die formed blades welded to the rim and back plate. Rim shall be spun to have a smooth contour. Shaft sleeves shall be provided, if necessary. If required, intermediate stiffening rings shall be provided. The impeller shall be statically and dynamically balanced.
1.3.3 GENERAL
1.3.3.1 Belt driven fans shall be provided with V belts, V-belt pulleys and belt guards.
1.3.3.2 Pulleys shall have minimum two (2) grooves to prevent start-up failure and premature belt failure. Pulleys shall be statically and dynamically balanced. Belts shall have a minimum service factor of 1.5.
1.3.3.3 Common base frame for belt driven fans shall be with adjustable rails for motors.
1.3.3.4 Bolts, nuts and washers used shall be of non-corrosive material and of superior quality.
1.3.3.5 Bearings shall have minimum life of 50,000 hours.
1.4 DRIVE MOTOR
The motor shall be as per IS: 325 and with class "F" insulation, totally enclosed fan cooled, horizontal induction foot mounted type and rated not to draw starting current more than 6 times normal running current. Fan motors shall be suitable for 415 volts, 50 cycles, 3-phase, squirrel - cage, totally enclosed fan cooled with IP-55 protection. Motor shall be selected for quite operation and the speed of the motor shall not exceed 1400 RPM. Drive to fan shall be provided through belt- drive arrangement. Belts shall of the oil-resistant type. Fan motor shall be suitable for variable speed by variable frequency drive application. . The motor C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 26 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification shall be capable of handling the required starting torque of the pumps. Speed of motor shall be compatible with the speed of the pump. The cooling fans shall be directly driven from motor shaft. Motor situated outdoors or exposed to the weather shall be weather protected. Motors shall be enclosed type and shall have dust tight construction with suitable means of breathing and of drainage to prevent accumulation of water from condensation. Drain holes shall exclude bodies greater than 6mm diameter.
All components shall be of adequate mechanical strength and robustness and shall be constructed of metal unless otherwise approved. All motors shall be dynamically balanced.
The enclosure shall be designed to provide an effective sealing between the primary and secondary air circuits. Motor winding shall be vacuum impregnated with heat and moisture resistant varnish glass fiber insulated. Two independent earthing points shall be provided in accordance with IS:3043 on opposite sides of the motor for bolted connection. The cable boxes and termination shall be designed to enable easy disconnection and replacement of cables.
(Motor should be part of scope with manufacturer & should not be supplied separately by ACMV Contractor)
1.5 CABINET CENTRIFUGAL FAN
Fan contained within the cabinet shall be licensed to ear the AMCA Air and Sound Certified rating seal. Fan shall be DIDW forward or backward curved with fan scroll, belt drive or direct drive assembled within a cabinet. Cabinet shall be constructed of Galvanized Steel material. Cabinet shall be Panel Construction assembled together by means of fasteners for ese of dismantling for service and maintenance. Welded cabinets are not acceptable. Cabinet shall be capable of taking on added acoustic insulation, if required to meet the acoustic noise levels specified.
Noise level produced by any rotating equipment individually or collectively shall not exceed 65 dB (A) measured at a distance of 1.5 meters from the source in any direction. The overall vibration level shall be as per zones A and B of ISO 10816-1. Balance quality requirement shall be G 6.3 conforming to ISO 1940/1.
1.7 PERFORMANCE GUARANTEES
Performance parameters to be guarantee by the VENDOR / CONTRACTOR and tolerances permitted shall be as indicated in specifications. Bidder shall confirm acceptance of these by indicating values in data sheet attached along with the document. Fan or any portion thereof is liable for rejection, if it fails to give any of the guaranteed performance parameters.
Bidder to note that all fan performance curves shall be AMCA certified. Contractor shall also submit corrected performance curves for the fan considering the as installed condition of the fan at site.
1.8 DATA TO BE FURNISHED BY THE VENDOR / CONTRACTOR AFTER THE ISSUE OF PURCHASE ORDER / AWARD OF CONTRACT
1. Schedule of drawings and documents to be submitted for review, approval and information with submission dates.
2. Quality Assurance Plan (QAP).
3. General arrangement and section drawing with all dimensions and complete part list with codes and materials of construction. This drawings shall include all data indicated in technical data sheets. C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 28 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification
4. Foundation drawing with static and dynamic loads, unbalanced forces and moments, if any, pocket details . etc.,
5. Drawing showing fabrication and constructional details of the fan.
6. Fan rating chars or tables with selection marked.
7. Performance curves for fans with duty point marked (AMCA Certified, as well as installed condition at site).
8. Torque-speed curve for fans.
9. Erection, operation and maintenance manual with lubrication schedule.
1.9 TECHNICAL REQUIREMENTS (Exhaust & Fresh air Units)
Sl. No Description EXHAUST UNIT FRESH UNIT 01 Area Serving STP STP 02 Type of Unit Necessary test certificates should be attached for AMCA Certification. Double Skin Cabinet Type- DIDW Forward Curved Fan with AMCA Certification Double Skin Cabinet Type- DIDW Backward curved Fan with AMCA Certification 03 Total air flow rate cfm 12000 Cfm 12000 Cfm 04 Exhaust air qty / Fresh air qty 10000 Cfm 10000 Cfm 05 Fan external static pressure mm wg. Total static should be calculated at filters in dirty condition & not at moderate condition. 30 mm 30 mm C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 29 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification 06 Suggested Fan motor KW 7.5 KW 5.5 KW 07 Type of fan motor TEFC Squirrel Cage TEFC Squirrel Cage 08 Rough Filter Required Required 09 Noise level 10 a) At the outlet of the fan 70 dB A 70 dB A 11 b) Any where around the unit at 1.5 M distance 65 dB A 65 dB A 12 Quantity ( Nos ) 1 1 13 Fan Outlet Velocity - m / sec 8 to 8.5 m/sec 8 to 8.5 m/sec
C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 30 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification SECTION-2 15800 SHEET METAL DUCTI NG WORKS
TECHNICAL SPECIFICATIONS FOR SHEET METAL DUCTING WORKS (FABRICATION AS PER IS STANDARDS)
FABRICATION OF DUCT AS PER IS STANDARDS WITH A PRESSURE OF 500 PA
2.0 GENERAL
This section involves the supply, fabrication and installation of Site fabricated sheet metal works, installation procedures, leak testing of ducts, air distribution system like grilles & diffusers, flexible connection, volume control dampers, fresh air louvers etc.
Sheet metal ducting required for the project is shown in drawings forming part of these specifications. These drawings indicate the duct sizes and configuration required to meet design flow requirements and also to provide the Contractor with necessary data for bidding; they are not meant to serve as working drawings which will have to be prepared by the successful contractor, giving due attention to the structural features of the building and to other site requirements. Drawings so prepared shall be subject to the approval of the consultants/Architect. No extra charges shall be payable to the Contractor for changes from tender drawings necessitated by above factors or for any other reasons whatever.
Dimensions of duct sections are inside dimensions of bare ducts, where ducts required to be lined or insulated on the inside surface, these dimensions will have to be enlarged so that the cross sectional area is not reduced as compared to those indicated in the drawings.
All civil works involved including the drilling of holes for fixing the grip bolts and any chipping and finishing of the ceiling/roof slab, if found unavoidable, shall be carried out by the successful contractor at no extra cost.
2.1 MATERIAL
Sheet metal used for ducting shall be plain galvanized sheets conforming to grade ISS 655. Only new, fresh, clean and bright GI sheets shall be used. The galvanization on the sheets shall not be below 150 grams per sqm. The Owners/Architect reserve the right to reject-summarily-sheets not meeting these requirements.
2.2 THICKNESS OF SHEETS
The thickness of the sheets to be used for rectangular ducting shall be as follows
Maximum size of the duct mm Thickness - mm Upto to 750 MM 0.63 MM 751 to 1500 MM 0.80 MM 1501 to 2250 MM 1.00 MM C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 31 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification 2251 & above 1.20 MM
2.3 LAYOUT OF DUCTS
General layout of ducts may be taken from the drawings but this section is responsible for avoiding interfacing with other sections not specifically shown on the drawings. Actual measurements shall be taken at site before ductwork is fabricated.
Any necessary changes or additions to layout of the duct work to accommodate structural, duct, piping, electrical or equipment conditions etc., where opening in the wall / roof for duct work have been provided by others, make full use of such openings by fabricating duct work to fit them or if necessary provide offsets and transitions to suite location of ducts and may be altered if changes is made before installation.
Where building conditions require duct shape to modify, ducts must have same cross sectional area indicated in the drawing and width of the duct shall not exceed 6 times depth except with special approval.
2.4 JOINTS
The fabrication of the ducting including details of transverse joint connections, bracing, seams, etc., for longitudinal joints, etc., will be generally as per ISS-655- 1963; the intent being to obtain duct pieces that are robust and rigid enough to preclude flutter, buckling, etc., and to avoid air leakages.
For duct - to - duct joints MS angle iron flanges with neoprene gasket shall be used. Irrespective of the size the ducts, angle iron flanges shall be only used for duct-to-duct joints & no sheet metal joints shall be acceptable.
All duct joints shall be made tight and the interior surfaces shall be smooth. Necessary gaskets of rubber or similar material shall be used to secure tightness of joints.
2.5 ELBOWS & BENDS
Elbows, bends, offsets, etc. should be fabricated with a width to radius ratio of not less than 1.0 to 1.5. Alternately, turning vanes should be provided at intervals so chosen that the aspect ratio of the various sections so formed by the vanes will be at least five.
Turning vanes shall be provided at branch take-offs and collars wherever possible. Similarly, straightening vanes shall be provided in all the collars unless and except in cases where conditions at site do not permit their installation.
2.6 SUPPORTS
All supports for ducting shall be provided by the contractor. MS angles, rods and other sections shall be used as required for the purpose. The supports shall be C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 32 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification taken independently to the building structure support. All bolts, nuts, rivets, washers, etc., used for duct joints shall be of GI and not MS. All MS angles, flats, etc., used for flanges, stiffening, etc., shall be finished with two coats of Aluminium paint. These requirements shall apply to supporting arrangements / members also.
Minimum thickness of structural members employed for supports shall be as per IS 800. Where ducting is supported from ceiling/roof slab, Anchor grip bolts shall be used to fasten the suspension rods to the ceiling/roof slab.
The distance between the two supports shall not be more than 1.5 meter.
All civil works involved including the drilling of holes for fixing the grip bolts and any chipping and finishing of the ceiling/roof slab, if found unavoidable, shall be carried out by the successful contractor at no extra cost
Duct Silencers Material
The outer casing shall be out of min. 22G galvanized steel in accordance with ASHRAE recommendations for high-pressure rectangular ductwork. Seams shall be lock formed on Pittsburgh lock machine.
Interior elements of silencers shall be out of min. 22 G galvanized perforated steel. The inner side of the perforated sheet shall be backed by R P Tissue to prevent fibre fly over.
Acoustic fill shall be fibre glass (not mineral wool) of density not less than 40 Kg/m2 sufficient to obtain specified acoustic performance and shall be packed under 10% compression to eliminate voids due to vibration and settling. Material shall be inert, vermin and moisture proof.
All material of construction and acoustic fill shall be incombustible as per IS 3144.
Airtight construction shall be provided by use of non-hardening duct sealing compound at site by the air-conditioning contractor.
Acoustic Performance
Silencer acoustic ratings shall include insertion loss and self-noise power levels and shall meet or exceed minimum performance specified by the Acoustical Consultant. Contractor shall provide computer selection for the silencer supplied at site, which indicates db reduction at different octave B band frequency.
A. Aerodynamic Performance
Static pressure drop through silencers shall not exceed those listed in the silencer schedule at the indicated airflows. C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 33 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification
B.Transitions
Testing
After completion all duct systems shall be tested for air leakage.
The entire air distribution system shall be balanced to supply the air quantities as required in the various regions and rooms to maintain the specified room conditions. The final balance of air quantities and its temperatures through each grille, register or diffuser shall be tested and recorded as specified in Section Test Readings and submitted to the project manager for approval.
3.0 VOLUME CONTROL FIRE DAMPERS & AIR TERMINAL DEVICES
3.1 VOLUME CONTROL DAMPERS
Provide splitter damper in each supply take-off. Make turning vanes, dampers, deflectors, and splitters of same material of ducts. Splitters shall be full depth of branch duct and 1 1/2 times branch width.
Dampers shall be placed in ducts and at every branch of supply or return air duct connection whether or not indicated on the drawings, but shall be provided for the proper volume control and balancing the system.
All duct dampers shall be made out of MS channels with robust construction and tightly fitted. They shall be provided with suitable links, levers and quadrant as required for their proper operation, control or setting to any desired position. Dampers and their operating devices shall be made robust, easily operate and accessible through suitable access doors in the ducts. Every damper shall have clear indication showing the damper position at all the times. Dampers shall be placed in ducts and at every branch (whether or not indicated on the drawings) for the proper volume control and for balancing the system.
3.2 AIR TERMINAL DEVICES
3.2.1 GENERAL
Provide Air Terminal Devices of sizes & type as shown in the drawings. All the accessories like adapter box with an extended round collar to connect the flexible duct as shown in the drawings shall be within in the scope of contractor.
All supply and return air grilles and diffusers shall be as per the approved list furnished in the document. Consultants / Project Managers reserves right to choose the best. The grille shall be provided with powder coated paint of approved color. Further, the contractor shall submit a sample of grilles & diffusers for the approval.
C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 35 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification 3.2.2 MATERIAL
All air terminal devices mentioned in the tender documents / drawings shall be made out of extruded aluminum sections with very high quality finish. Grilles & diffusers shall be of extruded aluminium from hard stock free from pits and spots joints shall be hairline. The color of powder- coated finish shall be as per Unisys/Project Managers approval.
3.2.3 SIZING
Grilles / Diffusers shall be sized within limits of sound pressure level NC- 32 curve as a typical room having average room attenuation of 8 dB.
3.2.4 CONSTRUCTION
Supply air grilles shall be 15/30-degree deflection & of Powder coated extruded aluminium construction. They shall be complete with Volume control dampers of aluminium mounted directly on grilles. The vanes at the front shall be horizontal while those at the rear shall be vertical. The width of the perimeter flanges shall be 32 mm. The vanes shall be 3 mm thick and 25 mm deep.
Return air grilles shall also be Powder coated extruded aluminium construction. They shall incorporate horizontal vanes, which shall be fixed. The perimeter flanges shall be 32-mm width. The vanes shall be 3 mm thick and 25 mm deep. The pitch of vanes shall be 20 mm.
C.R.Narayana Rao Owners Engineers - TCE Architects & Engineers 36 TIDEL Park Coimbatore Ltd., Sewage Treatment Plant Part 1B - Technical Specification APPROVED MAKES OF THE FAN 1. NADI 2. KRUGER 3. NICOTRA APPROVED MAKES OF THE MOTOR 1. ABB 2. SIEMENS 3. GEC APPROVED MAKES OF GI SHEET 1. TATA 2. SAIL 3. J INDAL APPROVED MAKES OF AIR TERMINAL DEVICES 1. RAVISTAR 2. AIRMASTER 3. CARYAIRE