Anda di halaman 1dari 5

Insulation works

Cost of labour
Total area to be insulated 800.00 m2
Production per day 40 m2
Total crew = 1fab+1 fitt+2 helpers 6 nos Hours per day 10 hrs
Number of days required 20.0 Rate per hour 19 AED
Total manhours required 1200.00 hours
Cost of labour 22800.00 AED
Cost of materials M2 Wastage Rate per m2 Wastage Total 840
Area of 75mm thick insulation 800.00 5% 42.00 AED 105% 35280.00 0
Area of 40 mm thick insulation 0.00 8% 0.00 AED 0% 0.00 0
Area of 25mm thick insulation 0.00 8% 0.00 AED 0% 0.00 0
Total cost of materials 35280.00 AED
Rate of accessories 5.00 AED/m2
Total cost of accessories 4000.00 AED Insulation works
Total material dry cost 39280.00
Labour 28.50 AED/m2
Overhead 10% 125% Material 61.38 AED/m2
Cladding works
Total area to be cladded 800.00 m2
Production per day 40 m2
Total crew = 1fab+2 fitt+2 helpers 4 nos Hours per day 9 hrs
Number of days required 20.0 Rate per hour 19 AED
Total manhours required 720.00 hours
Cost of labour 13680.00 AED
Costing sheet
Cost of materials
Cladding works
Total area including 800.00 m2
Cost of sheet per m2 26.00 AED/m2 Labour 17.10 AED/m2
Cost of sheets 20800.00 AED Material 38.75 AED/m2
Cost of accessories 4000.00 AED
Total cost of materials 24800.00 AED
Overhead 15% 125%
tr 10000
Total cost of project 131475.36 AED (25% OH included)
Cost of mobilisation 3000.00 AED Including transportation
Omanisation 1500.00 AED Area 800.00
Contingency 1500.00 AED
Transportation costs 2000.00 AED
Total 139475.36 AED/m2 OMR 14589.47
Rate 174.34 AED/m2
Final rate 18.237 OMR/m2
64080.00
Rate per tank: 1823.6841
64080.00
64080.00
36480.00
36480.00
600
m2
Costing : Rockwool & GI sheet Cladding
CLAD: 0.6mm Al cladding 32.00 AED/m2
CLAD ACCS, 4.00
INS: 34.00 AED/m2
INS ACCS: 4.00
0.00 2125
Labor CLAD 17.10 AED
Labor INS: 28.50 AED
Wastage : 108%
O.H.P. on materials : 115%
O.H.P. on Labor : 115%
Mat. Cost Lab. Cost Total
Ins Cladding
W/O.H.P+w
ast W/ O.H.P. Aed
Tank surface 75 0.60 880.00 880.00 39280.00 4000.00 24800.00 4000.00 22800.00 13680.00 89523.36 41952.00 131475.36
880.00 880.00 39280.00 4000.00 24800.00 4000.00 22800.00 13680.00 89523.36 41952.00 131475.36
43280.00 28800.00 Total cost in AED 139475.36
Total cost OMR 14589.473
72080.00 36480.00 3815.9 Rate/m2 AED 174.34
Rate/m2 OMR 18.237
Ins. Acc
Cost
NA
per m2
Description Qty
CLAD
THK
(mm)
Ins Area
10%
Total
Labour cost
Dia
INSU
THK
(mm)
Length
Cladding
Area
Ins.Mat Cost
Al Ansari bitumen storage tank
20%
Cladding acc
cost
Rockwool 75 mm thick, 100Kg/m3
ADDI.NAL:
Cladding
Mat Cost
25%
per m2