A solar PV project as the starting point for building energy
markets for the poor: lessons learned and strategy for the way forward
A Project Review the Sida/MEM Solar PV Market Facilitation project in Tanzania
Lennart Bngens
ii
Table of Contents 1.1 Background and rationale for evaluation ................................................................... 2 2. The Context and key features of the Solar PV project ....................................... 3 2.1 Introduction ........................................................................................................................... 3 2.2 The designed approach .................................................................................................... 4 2.3 Recapitulation of specific project goals and objectives:......................................... 7 2.4 The approach and objectives adopted and rolled out............................................. 7 3. Findings and Conclusions regarding the projects activities .......................... 9 3.1 Inception phase: .................................................................................................................... 9 3.2 Pre-mid term (early 2006 mid 2008): .....................................................................10 3.3 Mid-Term Review (MTR): ................................................................................................12 3.4 Post midterm and exit ......................................................................................................13 3.5 Issues surfacing during implementation ...................................................................16 4. Discussion and Analysis ............................................................................................ 20 5. Lessons learned and scope for replication ........................................................ 25 6. Way forward for a Sida renewable energy program: ideas for thought .. 28 List of references and interviews ............................................................................... 32 Appendix I LFA ..................................................................................................................... 1
iii List of abbreviations BDS Business Development Services COSTECH Commission for Science & Technology CRDB Cooperative and Rural Development Bank ICB International Competitive Bidding MEM Ministry of Energy and Minerals PV Photovoltaic RAR Results Analysis Report REA Rural Energy Agency SACCO Savings and Credit Co-operative Sida Swedish International Development Agency SIRG Solar Industrial Reference Group TA Technical Assistance TBS Tanzania Bureau of Standards TANAPA Tanzania National Parks TAREA Tanzania Renewable Energy Association TRA Tanzania Revenue Authority VETA Vocational Educational and Training Authority Wp Watt peak
iv Executive Summary: Enhancing energy access in rural areas by supporting markets has been demonstrated as a successful model though requiring specific project management skills. The five-year Sida funded solar PV project in Tanzania, implementation by MEM with TA by the contracted Consultant Camco of UK, was completed in 2011 leaving a considerable imprint in the market. The more quantifiable (measurable) indicators are the i) rapid growth of the market, far beyond expectations, ii) the number of active dealers outside Dar es Salaam has increased substantially, iii) the stock of trained technicians has as well expanded, iv) the solar association (TAREA Tanzania Renewable Energy Association) has become a capable institution to cater for the needs of corporate and individual members, v) a process and organisation (SIRG Solar Industrial Reference Group - a group comprising large PV wholesalers) has been established to address quality issues in the sector, vi) awareness raising was required to prepare the market and most efficiently done through on the ground campaigning, vii) necessary distribution channels were promoted by linking large town suppliers with upcountry dealers. A word of caution should however be raised regarding the level of attribution for some of the indicators. For example, the rapid growth of the PV market draws on a number of factors several exogenous to the project which nevertheless operated in tandem and synergistically lead to growth. More intangible effect of the project is the consolidation of the key players in the SHS (Solar Home System) market seen as their role in supplying quality goods, level of competition and cooperation, the consensus that the counterfeit market must be addressed jointly, the general public is progressively aware of the PV sector reducing the search process for buyers. Further, the transition from project to institutionalized technical training (VETA Vocational Educational and Training Authority) was supported in a later stage and is not to date fully operational but points to the crucial role of searching for sustainable solutions. More importantly the project has proven that markets for the (relative) poor can be developed without direct subsidies for equipment, in stark contrast to prevailing project models at the time of launching. (Though Technical Assistance (TA) was heavily subsidized). The project was set up and implemented in cooperation with the existing institutional framework. A key tenet apart from directly supporting market actors - was to enhance the capacity of the institutions having a core as well as a supporting function in the market. The Ministry of Energy and Minerals (MEM) was the Client and project owner who has overall responsibility for policy. The project worked closely with MEM. TAREAs capacity was directly supported to promote the diffusion of renewable energy. (It is a national association that brings all the key stakeholders together). VETAs involvement in the project will play a major role in the continuing access to skilled PV technicians as the main institution for vocational training in Tanzania. In order to control quality of systems and products, both entering and being sold on the market, the project v has focused on TRA and TBS officers. However, the impact of VETA, TRA, and TBS in the PV sector is not fully achieved depending largely on the commitment to address relevant issues for market growth. E.g. the counterfeit market is an escalating problem in Tanzania that could be blocked by TBS and TRA operations. REA which was not established at the launch of the project has participated in steering committee meetings and is aware of project impact. The project was piloting a number of new ideas for market lead diffusion of renewable energy. This meant among others that a degree of failure was built in the design as the private sectors response to rolled out activities were not fully known in advance. A number of valuable lessons learned have been identified by analysing design, implementation and project management which are summarized below: a) The design and preparation process should be interactive comprising teams from the donor (Sida) and the Client (MEM) to guarantee the objectives of both parties are met and a platform for the Client taking ownership is created. b) Projects piloting or testing novel approaches require additional means of educating the Consultant as a ToR is seldom sufficient for transferring the necessary understanding to the project team for plannning and executing implementation. c) The need for flexible approach with monitoring and feed back to correct any implementation issues is not easy to anticipate beforehand. Hence, project management must include feedback loops of M&E back to project implementation. d) The market needs guidelines on rules of the game regulating obligations such as between suppliers and dealers, and between retailers to consumers. e) The private sector should be consulted on major actions in the sector to verify that activities rolled out will have the intended impact. This is in particular important for capacity building programs that deliver services demanded by the private sector. f) Learning is closely linked to previous experience of the companies as few PV dealers and technicians were new in business coming from other lines of business. Hence, targeting start-ups may require a different set of support packages. g) System approach including multifaceted set of project activities has the highest probability of supporting market growth. Hence, there is need to address market bottlenecks from a variety of angles. (i.e. more than one remedy is required) h) Market supporting institutions should be involved early in project implementation, preferable at the design stage, to ensure sustainability. i) Project impact is not necessarily measured directly as market growth but rather in the establishment of institutional and market conditions (support functions, rules, policy, capability). vi j) The selection of participating MSMEs in any given program must be done as close as possible to market principles. E.g. if dealers are approached, selection criteria applied by the sector should be used rather than only relying on project standards. A possible way forward to support the use of renewable energy technologies: Even though it has proven to be challenging, any future intervention in the renewable sector should try to adopt a market development approach similar to the original design of the PV project. A market development approach (by using for instance the M4P concept, Making Markets Work for the Poor) or the B4D (Business for Development), has a high potential to contribute to broad impact and sustainability in the markets delivery of renewable energy services to people in poverty. With a thorough understanding of each renewable energy market, interventions can be designed in such a way that they bring about systemic change in those markets systems that benefit people in poverty to a larger extent. By applying a market development approach the interventions will focus on underlying causes rather than just symptoms of malfunctioning markets. And the role of a temporary project/programme is to facilitate change in those market systems, not to become a part of the market itself. Given the challenges in the Solar PV project, all future interventions should consider the lessons learned/recommendations/guidelines summarised above. In the case of renewables, the poor are found either as users/customers or in the informal sector as MSMEs. The M4P approach is specifically designed to address underlying causes rather than just focusing on symptoms in malfunctioning markets. It draws on in-depth knowledge of the various players in the markets and their respective function. The term market system defines a wider set of actors that support or interfere with the market in question. The starting point for any program is the existing mass of suppliers, retailers, customers, whose daily activities will determine the impact of any program. Hence, M4P literatures discussion on market system incorporates these actors and other functions necessary for a healthy market development taking into account the Poor. It is recommended that a future intervention will consider the following approaches: 1) Innovation system and renewable energy markets: Improvement and upgrading is more than operational skills and long-term growth hinges on the mobilization of the innovation system to supply knowledge and skills. An intervention may appoint COSTECH (Commission for Science and Technology) to act as the Client for an Innovation System Initiative that would map existing R&D resources, set up criteria for academic research funding of COSTECH s existing funds, set guidelines for diffusion of research funding, how to involve the sector in question to advice on research topics, etc. vii 2) Expansion through establishment of competitive value chains (VCs): Most markets are characterized by their structure as regards the linkages between companies in the distribution channel. A value chain perspective is useful for understanding the development of technology across firms, the value added by each step in supplying goods and services, the importance of interconnectedness among companies to develop a sector (the whole chain has to be targeted). The rationale for developing VCs is based on the premise that small enterprises can grow and become competitive when they have clear and well-developed strategies set by competent and demanding value chain members. 3) A Poor mans perspective: An M4P project may on the other hand focus on the rural setting and how energy could support the inclusion of farmers in the formal economy. Most poor people are constrained by lack of skills and education, which means that inclusion will be a key component. Such a project would need to emphasize the transformative role played by energy in establishing new and competitive rural businesses based on productive use. This may entail the development of rural communities applying a non-grid paradigm that springs from a multitude of renewable energy sources such as micro-grid, solar, biofuel. Starting from a PSD perspective rather than energy would focus attention the role of business and income generation foremost.
1 1. Introduction and background The Sida funded solar PV project was ended in December 2011 after five years of implementation by MEM with TA supplied by the Consultant Camco of the UK. The project supported the development of a rural photovoltaic (PV) market in Tanzania. Markets are increasingly seen as the means to delivering services rather than the state in developing countries. Basic services such as health, education, infrastructure, and energy are supplied by the private sector either through public procurement or directly through the market. The interest in the market as a governance model draws from the inadequate basic service delivery in a large number of sub-Saharan countries. Historically, public goods should be provided free to all (or at least heavy subsidized by the state). The slow progress by public institutions to advance the access to modern energy like electricity in rural areas has sparked the search for alternative approaches. The shift has likewise influenced development thinking on how to supply fundamental services to poor people that would enable pro-poor growth. The basic assumption is that inclusion in markets enables poor people to take part in income earning activities not present in e.g. subsistence farming or barter trade. N.B. the PV project did not directly addressed pro-poor growth and emphasized general market growth to increase access for rural energy users. The project was conceived a decade ago when markets were still young in the development debate. Voices were however raised against traditional project models that by default placed overly emphasis on the project as the instrument for change. Projects were common in most areas of implementing donor grants and loans, even in sectors that had a local private. Involvement of local project implementers was customarily not guaranteed in international procurement under ICB, QCBS conditions. Hence, the sustainability of such projects was questioned citing the termination of projects as a simultaneous end of services provided due to project funding, organisation and prevailing non- market (commercial) conditions. Further, the overarching approach adopted was in line with BDS (Business Development Services) thinking a decade ago that emphasized the critical role of services in building a competent SME sector. Thus, the projects development objective was to increase the access to modern energy through a well functioning market buying and selling goods rather than installing subsidized or free products in a project manner. The BDS paradigm was complemented by a more general market development approach that e.g. stressed the importance of stimulating demand. The project was envisaged to test a market driven model that would use the private sector as the main engine of growth by supporting new and existing companies (i.e. enhancing supply capacity) but at the same time create awareness and understanding of the technology (hence building demand). (A more detailed description of the projects approach and methods follows below in section 2). 2 Although the project was defined as an energy access project for rural Tanzania, its methods bear important lessons for private sector programs in developing countries. In a wider perspective it highlights the design and preparation of sustainable models for development cooperation that aim to build markets for the poor. This review includes a thorough analysis of the projects main achievements taking into account the intentions, approach and implementation arrangements. The main goal is not to pinpoint particular shortcomings but to build a portfolio of lessons learned for designing similar projects in the future. Where mistakes and weaknesses are discussed it is merely to illustrate the donts and pitfalls of working with the private sector. Therefore to establish a dos list for project planners is the ultimate purpose. 1.1 Background and rationale for evaluation The project was designed to test a fairly novel approach to supporting the diffusion of renewable energy: market driven with the private sector taking the lead role. The approach was new - both to Sida and the Client MEM (Ministry of Energy and Minerals of Tanzania) and intended to test sustainable project models that would work closer with key stakeholders and users of the energy technologies and at the same time have a natural exit from the sector. Sidas involvement will be referred to the Embassy of Sweden as the Embassy of Sweden in Tanzania was mainly administering the project. This reports central aim is to capture the main lessons learned from the five- year project by primarily reviewing documentation and conducting analysis of the project but partly complemented by experience and observation over the course of the project implementation 1 . A secondary outcome is to draft the way forward and how insights may be replicated to other subsectors in energy to speed up diffusion through private sector led market growth. A third, as an extension of the former objectives, the report will present a guideline for market driven support. The rationale for this report draws from the need to document the experience gained. The report will complement earlier reviews of the project; the so-called Results Analysis Reports. In order to evaluate and sum up the projects outcome and impact, there were two Results Analysis Reports conducted at the end of the project; one by the project Consultant Camco itself and one by an external consultant contracted by MEM; Dr Byabato. It was deemed necessary to carry out an additional independent review of project that would look beyond project internal impact and focus on the way forward.
1 The Consultant for this undertaking was also hired as the M&E Consultant for the Sida MEM PV project which enabled intermittent follow ups on the project. 3 2. The Context and key features of the Solar PV project
2.1 Introduction The project was a collaborative effort between the governments of Sweden and Tanzania. The planning process started in 2001 and in February 2003, the Ministry of Energy and Minerals (MEM) and Sida (through the Embassy of Sweden) agreed on financing a project for Facilitation of the Solar Photovoltaic (PV) Market Development in Rural Tanzania. Market assessment 2 conducted for planning purposes concluded that the market was ready for a proactive intervention based on the number of wholesalers and dealers active, the status of the solar association, the pro-urban focus of large suppliers, the untapped demand in rural areas (only 1-2 % had access to electricity in 2001), etc. Most large wholesalers based in Dar es Salaam fill various roles as importers and suppliers to regional dealers. This means that wholesalers, suppliers, importers, are applied interchangeably in the report. The goal was to direct the PV sectors activities towards building demand in rural areas, strongly piggy-backing on the projects support activities. The assessment report recommended an approach to support the promotion of PV technology in rural areas 3 by working through existing market actors, and by using currently available organisations and institutions for the implementation of the support. The key rationale comprised the expansion of the rural market by promoting the establishment of dealer networks stretching beyond the three towns of Dar es Salaam, Mwanza, and Arusha. See table 1 below for market size, before and after the project. (Source, project reports, TAREA). The pre-project market was dominated by so-called project sales by large institutions procurement such as ministries, TANAPA 4 , donor projects, TTCL 5 , TAZARA 6 that represented around 80 per cent of sales (Sida, 2002). Hence, most suppliers and dealers were located in the three metropolitan areas as a result of vicinity to buyers.
2 See Sida (2002), The RES Market Report, Swedish Embassy 3 "Rural areas" have in this context been given a broader than usual definition to include also smaller towns and the outskirts of cities/towns. "Rural areas" are characterised by a comparatively low share of users who have access to modern energy services and that a suppressed demand for such services is found in the area. 4 TANAPA (Tanzania National Parks) 5 TTCL (Tanzania Teleommunications Company Limited) 6 TAZARA (Tanzania Zambia Railway Association) 4
Table 1: Pre and post project market sales One immediate effect of the market-driven approach was the substitution of public utility efforts in the field of rural electrification with a free market driven by exchange processes between buyers and sellers. That is, the goods provided or rightly traded on the market should not be seen as a free good that purports to provide a service to the community. That certain services are provided is an indirect effect of the market meeting specific needs among users expressed as demand in the market. The impact on the project of the market-driven approach is the transition from implementation to facilitation by creating an environment whereby the market actors will provide the services needed. This is a cornerstone in the BDS approach. It also leads to focusing attention to a different problem since the project is not supposed to solve the actual energy problem experienced by rural population, but rather to create conditions that help the expansion of rural markets. That in turn will solve the problem. The underlying assumption was that the markets problem-solving capacity must be improved rather than the project specifying the problems to the market. The interactive process between buyers and sellers is seen as one of the critical means to targeting the right problems. 2.2 The designed approach The designed approach refers to the approach presented in program documents (see e.g. MEM, 2002) and in the bidding documents for floating the tender. The rationale for presenting the initial design rather than the one rolled out during implementation highlights the role of various factors affecting the actual implementation. E.g. the model applied may differ because of the private sectors 2004 2005 2006 2007 2008 2009 2010 2011 yearly KWp 100 100 250 300 400 500 1500 2000 0 500 1000 1500 2000 2500 Y e a r l y
s a l e s
k W p Market growth Tanzania project launch 5 response to project intervention, the Consultants interpretation in proposing a solution as well as the impact of issues occurring during implementation. There are a number of market models applicable but the one selected had been successfully used in South Africa to enhance the diffusion of solar energy technologies 7 . The model states that the growth of solar PV market draws on four dimensions (the 4A model). These are: Awareness, Acceptance, Access, and Affordability. If a potential customer is not aware of a product and how it can meet his/her specific needs it is unlikely that he/she will buy it. Acceptance or the desire to buy a certain product is linked to priority, which determines his/her willingness to invest in a product. The issue of access is critical for stimulating the demand for a specific product since time-consuming or cumbersome search processes for a product tend to lower demand. The final step in closing the purchase process is the issue of affordability. These dimensions may be viewed as sequential in the buying process but are at the same time closely interrelated. For example, even to be aware of a product that probably is too costly is highly unlikely since the initial investment deters from further inquiries and may not lead to acceptance. Since solar PV is only affordable in a life cycle cost perspective few customers will undertake the effort to calculate savings but rather be disappointed in the high initial price. This fairly conceptual model was complemented by an actor dimension in order to allocate project resources to address challenges within each A. As regards the division of labour among the actors for affecting these dimensions it was suggested that access and affordability are foremost the responsibility of PV business and financial institutions. Awareness and acceptance naturally follow in a growing market where prior sales work as a steppingstone by its demonstrative effect. However, for approaching new rural customers, substantial awareness creation and promotional activities were deemed necessary. In the original design the following five categories were identified: i) rural market, ii) PV industry, iii) solar network, iv) financial system and v) institutional framework. These categories were selected due to their distinctive role in improving the conditions for a rural PV market. That is, all categories have an effect on the 4As which will drive the market. The implementation arrangements included the recruitment of a consulting company who would carry the overall responsibility for coordinating, supervising, and administrating project activities. The key role attached to the Project Office comprised the facilitation of the interventions required to address the identified weaknesses in the market. Hence, the bulk of the projects budget (SEK 27 million) would be channelled to external service providers. For project
7 Holm D., (2001), Renewable Energy Strategies in South Africa, in Renewable Energies for the South, Science Park Gelsenkirchen 6 monitoring and follow up a Steering Committee 8 was established that would meet annually to discuss implementation issues and advise on possible actions to safeguard that project objectives were met.
The main features of the Institutional Framework: The project was set up and implemented in cooperation with the existing institutional framework. A key tenet apart from directly supporting market actors - was to enhance the capacity of the institutions having a core as well as a supporting function in the market. The project worked with the Ministry of Energy and Minerals (MEM), TAREA, VETA, SIRG, TRA, TBS, REA. MEM was the Client and project owner who has overall responsibility for policy. The project worked closely with MEM. The ministry had the role of project monitoring which in future project will be allocated to REA. TAREAs capacity was directly supported to promote the diffusion of renewable energy. (It is a national association that brings all the key stakeholders together 9 ). The association was established in 2001 and has more than 250 members (March, 2012). Over the years, TAREA has been implementing promotional, capacity building activities, awareness creation, quality control and advocating for sound environment through dissemination of renewable energy technologies. VETAs involvement in the project has the potential to play a major role in the continuing access to skilled PV technicians as the main government institution for vocational training in Tanzania. SIRG (Solar Industry Reference Group), The Solar Industry Reference Group was created not long after the Projects mid-term review. Five solar product importers/wholesalers signed MOUs to become active members of the Group. These companies include Sollatek, Ensol, Zara Solar, Umeme Jua and Aglex. In order to control quality of systems and products, both entering and being sold on the market, the project has focused on TRA and TBS officers. The counterfeit market is an escalating problem in Tanzania. The financial sector was approached in the project, initially lobbying with the retail banks and consumer credit institutions, as accessing loans and credits for purchasing PV systems was very limited. The project later focused on SACCOs
8 The steering committee initially comprised representatives from MEM, the Consultant, TAREA, Sida, Office of the President, UNDP, UNDPs PV project, and private sector. Later both TAREA and private sector were excluded for being beneficiaries of the project. 9 For more information on TAREA see www.tasea.org 7 (Savings and Credit Co-operative) because of the banks inadequate response to establish PV credit lines. There are over 1,800 registered SACCOs throughout the country ranging from community-based initiatives recruiting members who work in the informal economy to workplace-based SACCOs. REA (the Rural Energy Agency) which was not established at the launch of the project it was operational in 2007 - but later participated in steering committee meetings and has become aware of project design and impact. REA does not implement projects as such but administers various funds for development projects; in particular target the cooperation with the private sector.
2.3 Recapitulation of specific project goals and objectives: As stated in the project document (MEM, 2002): The long-term development objective of the project is to improve living standards and community development in rural areas by providing access to modern energy services through an increased access to and demand for PV technology. Although it was argued that access to modern energy services would improve standard of living, the project has not explicitly been measuring the role of solar PV in economic development in rural Tanzania as the project focused solely on its immediate objectives. These were: The overall project objective is to establish market and institutional conditions that enable development of the rural solar PV market (op cit.). The project objective was supposed to be met by fulfilling the sub- objectives specified in the 4A approach applied to the actual implementation. The four As (Awareness, Acceptance, Access, and Affordability), in combination with viewing the market in a wider context as the pillar for growth, was deemed as the appropriate model. For a full list of sub-objectives and deliverables see the projects LFA in appendix I. 2.4 The approach and objectives adopted and rolled out The project opted to address the 4As indirectly by incorporating them into the following project components: i) Business development support to existing and potential PV companies, ii) Development of the Solar Network, iii) Policy and Institutional Development, iv) Stimulation of end-user market through awareness raising and v) Capacity building of MEM (Ministry of Energy and Minerals)/REA (Rural Energy Agency) counterpart personnel. The first component BDS was designed as traditional training activities though the services were outsourced to local providers through a tender process. There were three such tenders floated; one for technical training awarded to TASEA 10
(Tanzania Solar Energy Association), a second for Business Management
10 TASEA has lately (2010) changed name and focus into TAREA to include renewables in general. 8 Training and Consulting Services (WorldAhead) , and finally one for Marketing and Awareness Campaigns (Mariands). However, a number of activities remained the responsibility of the project; market assessment in the regions, planning and launching in the specified regions 11 , impact assessment, involving the financial sector (later more focus on Savings and Credit Co-operatives (SACCOs), supporting the solar network (this was mainly done as capacity building support to TASEA and supporting business linkages between urban suppliers and regional dealers), policy development at district level. The project also added quality assurance as a subcomponent based on the Projects recommendation. To further illustrate activities delivered by the project: i) Identification of appropriate businesses in the regions and districts and bringing them into business relationships with the solar PV product importers in Dar es Salaam. ii) Regional marketing campaigns were later on transferred to the project, as the subcontractors performance was not satisfactory. iii) The project also provided grant financing to a small number of companies that were selected after screening proposals. The grants were earmarked for company specific support in areas such as marketing and training. This component was discontinued in project year three as the project believed that that impact of the company support was limited, not benefiting the PV sector in general to a great extent, but also few high quality proposals were submitted by the sector. The selection process was also viewed as slow and tedious in relation to expected output. The project applied the following set of indicators 12 for measuring outcome: Annual size of the PV market will have doubled from the 2005 baseline of 100kWp; $8,000,000 of revenue will be generated by solar PV companies; 16,000 solar system installations will be made; An active association of solar PV stakeholders will provide regular and quality information and services to its membership; Quality standards for solar PV technology will be established, and a system for monitoring and enforcing compliance will be operational. Regarding the 4 As, the project initially did not stringently applied the indicators to design impact surveys as proposed in the original LFA. This issue will be discussed below in the section on Findings. For more details on the projects methodology see below in section 3.1.
11 The project supported various actors in a region for three months before moving to next region. 12 These were presented in the inception report (ESD, 2006) and comprise a mix of indicators from the original LFA and suggestions by the Consultant. 9 3. Findings and Conclusions regarding the projects activities The review of activities will be presented in a longitudinal perspective as well as addressing certain key issues. The longitudinal follows the projects key milestones, the projects inception period, pre-midterm activities, midterm review, post-midterm and exit. The rationale is the shift in strategy at these milestones. 3.1 Inception phase: This phase had little actual implementation and the main output comprised the Inception Report provided by the Consultant early 2006. The report comprised the status of the Tanzanian Solar market, work plans, project management, and budget estimates. Hence, the actual implementation was presented in this phase as an Inception Report 6 months after project start based on project document (MEM, 2002), ToR, and the Consultants market assessment. In a nutshell, the project applied the following approach: i) recruiting and training dealers and their technicians in rural areas they were not located in rural areas per se but in district towns - to act as outlets for solar PV products. ii) Theses dealers were introduced to major importers/wholesalers during the official launch in each region but also later while in Dar es Salaam for training. iii) Regional campaigns should be carried out for three months in each region using various methods ranging from TV commercials, radio, road shows, etc. iv) A grant scheme for large suppliers to address their marketing challenges in rural areas. v) The network component would address the role and performance of TASEA to support the PV sector. vi) To establish consumer credit for PV systems through supporting the National Microfinance Bank and the CRDB to set up specific credit lines for PV. These would have conditions specified to suit the purchase of PV system by relatively poor people. vii) The policy component should focus on TBS & TRA capacity building to among others establish standard guidelines to facilitate importation of quality PV panels and BoS 13 components. viii) M&E 14 would focus on the following: Sales statistics from suppliers and dealers; Revenues generated from systems sold; Number of solar PV installations; Average sizes of installations made; Method of payment; Level of consumer awareness; Degree of client satisfaction. Main output/impact: The Inception Report presented the capacity building modality for developing market actors: The focus was on enhancing regional dealers capability and their technicians. Dar es Salaam based and other large suppliers were not targeted directly by the BDS component and would benefit indirectly by the improved dealer network. The project contacted several large (urban) based suppliers during this phase to consult and verify the number of existing dealers in regions covered by the project. There was one workshop held
13 BoS (Balance of System) components comprise such as charge controller, batteries, inverters, 14 M&E (Monitoring and Evaluation) 10 in Dar es Salaam where most suppliers participated. However, the main venue proposed for creating business relationships was the regional launches in which Dar-based suppliers, local microfinance agents, local administrative authorities, regional dealers and rural electricians were invited to a two-day workshop 15
presenting the market assessment findings. Main concerns: The Inception report was reviewed by the Embassy of Sweden (see Sida, 2006) that emphasised a few issues. A first concern was the issue of methodology. The inception report portrayed an overall impression as project- driven which manifested itself in the work plan presented for several key activities. The degree of pro-activeness vs participatory approach at various crossroads in the project was raised as a concern. A second and in similar lines concerned the role of the project which had gradually shifted from a Facilitator to rather act as a Doer which would affect the learning process among market actors. Thirdly, how to create a demand for BDS services and at the same time raise the competence of the sector in a market friendly way. It was not clear in the Inception Report whether there would be cost-sharing arrangements (subsidized training) or free training. 3.2 Pre-mid term (early 2006 mid 2008): The project was rolled out initially in Iringa awaiting the approval of the inception report. Iringa region was set up as a pilot using UNEP-GEF 16 funds. The project faced additional delays in the hiring of subcontractors. The procurement that was done through the Ministrys official processes took longer than expected; the tender process was finalized in early 2007 after one year. The capacity building of PV dealers and technicians was originally designed according to the BDS approach whereby the project does not deliver services directly but focuses on facilitation and creating a market for BDS services. This approach meant among others that the project should find external service providers for BDS. After Iringa, Morogoro, Coast followed by Tanga, Kigoma, Rukwa and Mtwara. The methodology applied was in principle the one put forward in the Inception Report. To recapitulate, the roll out was started by a market survey conducted by the project with the purpose of estimating the potential for solar PV in the region. Initially the supplier of services for the market campaigns was supposed to be in charge of these market assessments in cooperation with the project. The project later on assumed the responsibility for these assessments because of the
15 The first day included local authorities only to discuss the market assessment whereas the official launch was during day two with the participation of selected dealers, large suppliers, government (regional) officials. 16 UNEP-GEF. United Nations Environment Programme runs a number of programs to encourage a transition to a green economy. The Global Environment Facility also works to protect the environment through the funding of incremental costs that leads to global environment benefits. 11 suppliers poor performance. Hence the estimate would not focus on the current size of the market. These estimates would be presented and discussed during the launch for each region over two days, starting with a workshop focusing on the regional and local authorities followed by the official launch during day two. Various stakeholders were invited to the official launch including: PV suppliers (mostly based in Dar), regional dealers selected for training, TAREA, Embassy, MEM staff and regional authorities. Presentations were mainly given by the Consultant and regional authorities whereas local and Dar based businesses were not among the presenters. The matchmaking between suppliers and regional dealers mostly took place in coffee&lunch breaks in an informal fashion. The projects approach was to let the potential buyers and sellers meet without interfering in the matchmaking. This would later hopefully lead to a business relationship in which the companies would find the proper forms of cooperating. The projects role was to invite them to the same venue providing a platform for discussions, networking, etc. Due to procurement guidelines competitive bidding by floating tenders was used to identify and select BDS providers. There were tenders for three types of assignments: i) technical training, ii) marketing and organizational skills, iii) market campaigns. Contracts were awarded to three local firms; WorldAhead, MarieAnds and TASEA. The performance of the subcontractors was mainly satisfactory although one project component faced a number of problems. The project concluded this was due to a series of unforeseen events and decided to internalize the activities by establishing a new project team for this activity. The grant scheme was launched but attracted little attention by the PV sector. Only two companies submitted proposal which led to a change of the application process and use of more advertising. Main outcome/impact: The project was successful in testing and rolling out the activities in a pilot region in spite of being stricken by delays not anticipated. Once the procurement of BDS providers was finalized the project rolled according to plans in Tanga, Morogoro, Pwani, Kigoma, Rukwa, and Mtwara. Up to the Mid Term review three regions had been subject to impact surveys: Tanga, Morogoro, and Pwani (Coast). To summarize, the surveys point to the importance of raising awareness which was most efficiently done through radio ads and disseminating flyers and brochures. The regional campaigns would normally have a direct effect on the number of enquiries the dealers had on price quotations, etc. The regional dealers would source from more than one supplier in Dar es Salaam that customarily was a result of the projects business linkage component. Main concerns: The project was delayed in almost all activities during this period. This was not caused by poor project management but the result of unforeseen external events. One of the key factors was the Ministrys procurement policies and slow execution. The regional campaigns tended to exclude dealers in the planning and overly focus on larger cities rather than small towns) (See the MTR 12 and various Impact Surveys. The financial lobbying efforts by the project to convince commercial banks to offer a special credit line for PV systems failed to materialize due to the banks stringent conditions for banks loans (permanent employment, collateral, references, etc). The communication between the project and other key stakeholders was, by and large, poor which delayed addressing these concerns properly. This was partly a result of the delays in establishing the proper M&E for the project such as the mandate and structure of the Steering Committee. 3.3 Mid-Term Review (MTR): The mid term review was commissioned by the Embassy in Fall 2008 as agreed in the Specific Agreement. The Swedish company, SWECO, was awarded the contract. The MTR highlighted the following major outcome/impact of the project: 1) Sales growth has been impressive, 2) Match-making between regional dealers and urban wholesalers was seen a major accomplishment, 3) The entry of new dealers into PV has played a major role in expanding the market, 4) Training for technicians has been successful per se, 5) The campaigns had a positive effect on sales. The MTR disclosed a number of issues regarding the implementation. The MTR was structured around the 4As and boiled down to the following: Awareness: The national awareness campaigns were viewed as less efficient as the regional campaigns. The promotion of the project as such rather than the PV sector was indeed an issue as observed by the MTR team. The regional campaigns were in general effective but poorly planned in some regions, i.e. lack of coordination with regional companies. The issue of actually using trained technicians for installations was highlighted. The MTR team was of the view that both indicators for affordability are considered useless as prices are dictated internationally and therefore should be removed. Additional concerns/issues in the MTR: a) The Provision of BDS: The MTR observed that that there was a lack of commercial viability. It also noted that there was not enough cost-sharing (in reality the only contribution by participants was in kind by offering their time on the training), bookkeeping and similar organizational skills 17 were not appreciated by the dealers, and that more technicians should be trained. b) TBS & TRA should be equipped to enforce quality but the efficiency was questioned by the MTR. The TRA in particular is not addressing the needs of the PV sector. c) The Solar network; it was concluded that the actors were not better connected as a result of project activities. d) The impressive growth rates were discussed whether it was a result of the project or other factors was not clear according to the MTR. Many dealers argue that sales have increased after the project was launched but the market has grown in non-
17 Most dealers have weak organizational skills but do not see the need for enhancing their capacity and consequently view such training as waste of time. 13 project regions as well. The data collected to verify sales is at a national level and does not reveal actual sales by dealers trained in the project. e) New LFA indicators were presented that had a better fit with the activities rolled out by Project. f) Role of project vs. PV (as a technology) and other actors; the concern was that the project was performing activities that should have been done by market actors. It also created confusion in the market as it was not clear what the project, Sida, and MEM actually did in the sector in relation to the private sector. g) The selection of dealers 18 by the project was not adequate as many turned out to be passive (at least more passive than those starting on their own before the project) and not having the required resources to run a solar business like liquidity to stock PV systems. h) Technical training as delivered in the project will not be sustainable. The solution proposed by the MTR was to transfer the technical training to VETA (Vocational Educational and Training Authority). A stakeholders reference group should be established rather than the steering committee already in place, which was deemed less efficient 19 . 3.4 Post midterm and exit The project continued launching in additional regions, in total 14 of 20 regions 20 . The basic approach for launching in new regions basically remained the same in this period with the exception that the marketing campaigns were done by the project 21 instead of a contracted provider. The new or slightly altered activities in this period was: i) The Solar Industry Reference Group (SIRG) that was created not long after the Projects mid-term review, partly as a result of MTR feedback. ii) VETA fee based training, iii) SACCO workshops. iv) exit strategy. SIRG: The group was formed to address to threat posed by the increasing number of panels being imported not meeting quality standards. The SIRG was established by five solar suppliers that include Sollatek, Ensol, Zara Solar, Umeme Jua and Aglex 22 . The main mission formulated by the Group was strategies for enforcing standards for high solar PV quality. The consensus in the Group was that the systems sold by SIRG members should meet the requirements as agree with TBS. The recent entry of opportunistic newcomers selling counterfeit or substandard products was seen as the prime threat to a
18 As a result of the feedback, the project suggested using a checklist established by WorldAhead to improve the selection process but there is no data verifying the actual implementation and success of the checklist. 19 The Steering Committee did not have the mandate to enforce recommendations agreed upon and functioned more as an advisory board rather than controlling the implementation of the project. 20 The project started in Iringa as a pilot using alternative funds due to initial delays with disbursing Sida funds. Hence, Sida funded roll out in 13 regions. 21 The decision to internalize was mainly due to time constraint as procuring a new subcontractor would have been a lengthy process based on the experience of the tender process for the initial BDS providers. 22 There were more companies originally but Rex Solar e.g. left early because of different views on the mission of SIRG. 14 sustainable market. This has also been confirmed by TAREA that had visited a number of shops in Dar es Salaam to learn about the poor technology falsely marketed as cutting-edge products. It is not clear whether these substandard systems were sold under the belief that they actually meet stated specifications or the shops were intentionally misguiding customers. VETA fee based training: The VETA training was an outcome of MTR feedback to establish technical training on a sustainable basis that included charging a fee for participants but also for transferring the training capacity from the project to an existing institution. Capacity building of VETA comprised in principal ToT (Training of Trainers) using a combination of standard training methods by the TAREA consultants and learning by doing. The latter was accomplished by involving the VETA instructors in the project training of technicians. The objective was to enable VETA start offering fee-based solar PV courses. In the course of the project, one VETA branch tried to advertise and run a course but the initiative was terminated because of low demand. The details on the advertising and recruiting have not been clarified so whether this is a classic example of failing to create demand or there is simply no need for PV courses was not evident. SACCO: The SACCO workshops surfaced as an alternative to traditional retail banks credit line, which despite lobbying by the project did not convince the banking sector to offer earmarked PV loans. The banks did not view the PV systems as an eligible collateral and recollecting loans from defaulters was seen as a risky and time-consuming activity not worthwhile pursuing. Hence, the outspread informal credit and savings organisations in Tanzania SACCOs - were identified as a possible means to access credit for purchasing PV systems. The purpose was to introduce PV technology as the appropriate way forward for accessing modern energy services. The meetings invited District Cooperative Officers (DCOs), SACCO leaders and PV dealers. Though marketed heavily by the project the expected output never materialized in most regions; Tanga was one of the few exceptions. Most SACCOs did not want to favour specific use of credit lines for members that should freely choose the purpose of the loan. A part, unintended, success of the workshops was that some dealers managed to use them as sales events and secured a number of orders as a result. Exit strategies: The need for exit strategies was brought to the project teams attention during the last project year as there was a concern that the project would pull out without securing an imprint in the sector. Discussions between the key stakeholders, the Embassy of Sweden, MEM, and the project consultant, led to the development of an exit strategy that addressed a possible post-project scenario of the main activities. Project phase out and sustainability: The exit should ideally be frictionless if the BDS approach had been strictly applied to all activities. Hence, the project displays a mixture of facilitation and doer but the main challenge of the activities actively carried out by the project is the weak demand in the market. The RAR 15 (Results Analysis Report) presented by the Project lists a number of activities and possible exit scenarios. The first activity, identifying and training new dealers, was proactively done by the project with little involvement by the PV sector. As pointed out in the report, few suppliers are actively doing this at the moment. Since the Project was pursuing this as a project activity rather than facilitating the function of entry for newcomers in the market, the handing over of this activity is not straightforward. The methods and resources at hand cannot be transferred to the private sector, which demonstrates the risk of providing services without building demand simultaneously. The second activity, training new solar technicians, started as an outsourced activity but was neither demand nor market driven as the project both identified the participants and provided the training for free. Later the project involved VETA to initiate a sustainable model for training. Support to such training is in line with the BDS approach but VETA is not yet capable and organized to offer PV courses demanded by the sector. The third activity, conducting market campaigns and developing marketing material, was taken over by the project after the MTR feedback. The activity was done in cooperation with rural dealers. Any possible future institution to shoulder this function in the future was however not involved which makes the transition to a sustainable market doubtful. Either TAREA or suppliers could have an interest in pursuing the function of marketing solar PV but the lesson learned from this activity has not, and will not be transferred to any existing institution. Train local authorities, the training aimed at enhancing the awareness and skills necessary for submitting project proposals to fund PV projects in rural areas. This was project driven not having a local counterpart or institution in mind but the Consultant suggests that REA could possible assume the role of educating local authorities. It is stated that REA is aware but has not yet begun. There are three main concerns regarding the sustainability of this activity: i) REAs incentive to start such training, ii) available funding, and iii) is the activity in line with REAs mandate and objectives. TAREA and SIRG, though training and support was initiated by the project, this component targeted the establishment and support to permanent institutions that play a decisive role in building a market. Hence, the transition to a post project situation is inherently easier, which is confirmed by the Consultants evaluation of sustainability. Both SIRG and TAREA have their roles and means of operating in a self-sufficient manner drawing on member contributions or commercial revenues. 16 3.5 Issues surfacing during implementation 23
These issues have been mentioned briefly earlier in the longitudinal review but have been identified as critical for implementation as well as impact. A review of discussions and feedback boils down to the following: 1) discrepancy between the original project methods vs projects implementation approach, 2) sustainability of BDS, 3) performance of the participating dealers and technicians, 4) Supply chain development 5) Building a functioning market. 1) The Sida-MEM project was designed to support the private sector taking the sectors readiness and capacity in consideration. This meant among others that commercial actors should be consulted and part of the implementation and that the Project should primarily act as a facilitator. In theory, the approach adopted and presented in the program document (see MEM, 2002) has a number of advantages compared to traditional projects that are characterized by the project as the key entity implementing and delivering services. However, it was increasingly apparent that the project team was not very familiar to act as a facilitator, as this requires a new mind-set regarding the role of the project office. In reality, the facilitator role was interpreted by the project as contracting out services to external providers. The approach applied by the project was manifested in a number of ways: budgets were shifted from external provision towards internal use of funds, but more importantly the private sector was, by and large, not part of the process as active participants but rather as passive recipients of support 24 . Though the regional campaigns became more consultative in later stages of the project. Nevertheless, the large suppliers were e.g. neither consulted on the design of technical training nor selection of dealers 25 . Hence, adopting the role as facilitator will affect how the project would work with the private sector. It should be observed that the project teams approach was rational, i.e. following the work plan as presented and approved in the inception report. A lesson learned is that the introduction of innovative approaches to project implementation requires novel project management approaches by the Client and the Embassy.
23 These issues surfaced from Annual review meetings, impact surveys, interviews carried out by the Embassys M&E Consultant. 24 There were two exceptions to the rule; these suppliers are also heavily involved in TAREA. Their involvement was a result of their proactive approach and not from formally being invited and linked to the project. 25 The majority of the suppliers were concerned about selection process of dealers and technicians. This seems as a rational standpoint since the involvement of suppliers in the selection was very limited. The paradox is that although the suppliers were served dealers on silver plate there was unduly poor appreciation for the projects effort to search and select dealers on their behalf. In the light of suppliers passive approach to identify new dealers, the common perception is that the few ones they had been working with for a few years would suffice. The most qualified dealers had been in business at least 4-5 years. An additional explanation is that direct intervention in the market requires substantial trust building to gain the acceptance of incumbents. 17 2) Sustainability of BDS: The delivery of BDS (Business Development Services) was viewed as a fundamental for long-term market growth while preparing the project. The project was also expected to contribute to the growth of a BDS market, not just delivery of such services (marketing skills, organizational capacity, book-keeping, procurement, technology, etc). Reviewing the implementation of BDS tells us that the services were both provided for free and delivered by companies/organisations that normally do not engage in BDS services to the PV sector. Further, the project was actively searching for participants rather than the normal procedure where students and trainees look for a training institute based on their needs. This was probably driven by the projects target of having 12 dealers and technicians selected in each region and the projects evaluation of the market as very passive regarding skills development. The difference may seem semantic but had a major impact on the participants attitudes towards the cost and the training itself. The proactive stance by the project led to a reversed position taken by many trainees that believed they were in fact doing the project a favour by participating, which is inconsistent to project objectives. The justification for the proactive stance by the project is the prevailing situation of almost a non-existing market for BDS drawing on a passive attitude among companies and technicians to fund upgrading of skills. This is an effect of not seeing the long-term return of investment for skill development. An additional factor is the history of PV training in Tanzania which had been provided free by a number of earlier donor projects which has ruined the development of a commercial market. These issues led to the projects free training approach explained by the project team as that the BDS component was ill-conceived and that there is no demand for such services. 26 The outspread praxis to receive training for free (if a donor is funding a program) made it difficult to charge a fee for training according to project team. The project would have faced the risk of receiving few participants for the BDS in the case of charging a fee. The role of developing a BDS market in supporting the dealers and technicians in the long term has not been properly addressed in RARs and impact surveys. The free training has surely contributed to the growth of the sector but can unfortunately not be substantiated by empirical evidence apart from the fact that a number of trained dealers are still in business. Further, whether the PV sector is ready 27 for procuring BDS on commercial basis cannot be concluded from project reviews as the project did not succeed to test the hypothesis. The development to shift from direct delivery of BDS by TASEA towards building
26 See Camco RAR (2010) 27 The demand for training is generally low because most dealers dont understand the value of training. This is not project specific but applies to training even offered by the suppliers. A clarification provided by some suppliers was that many dealers are not specialized in solar and often view PV as any other product. Hence, the outspread viewpoint is that selling PV does not require any special skills. 18 VETA capacity was a step in the right direction. VETA is yet to prove that there is a demand for technical training at a fee but also whether VETA has the capacity to manage and deliver the appropriate courses. VETA has up to date only managed to offer training in two centres in spite of the support whereas the Mwanza centres, trained under the UNDP project, offers 6-month courses on regular basis. 3) Performance of the participating dealers and technicians. A key anticipated output of the project comprised increased rural access to PV systems in Tanzania. The project trained almost 200 dealers over five years, the majority new to the solar PV business in geographical areas with few or no presence of PV dealers prior to the project. There is evidence that access has increased from a pure quantitative point of view, whereas there is little data on the actual quality or performance of the dealers 28 . For example, the projects collection of sales statistics focused on large wholesalers and did not rely on sales by dealers across Tanzania. The impact surveys carried out by the project provide fragmented anecdotal data on the projects impact on dealers and technicians. Several Dar es Salaam based PV suppliers (Cloride Exide, Sollatek, Ensol, etc) state that many dealers that were introduced to solar and trained by project have less capacity and interest in pursuing serious PV business. Some suppliers go as far to state that the most successful dealers 29 are those they had even before the project was started. One explanation is that the project facilitated the entry of many newcomers but experienced dealers tend to perform better (source project impact surveys). These surveys also verify that a number of trained technicians (almost 200 trained) continue to do poorly in system sizing and installation 30 . TAREA estimate that around 70 per cent of the technicians are still in business after receiving training but there is no quantitative data on the quality of performance. Whether technicians trained by the project do worse or better than the average PV technician is however not known. Marketing activities by dealers are a sign of a maturing PV sector. However, most dealers are quite passive and do very little proactive marketing. A sit-and-wait approach is prevalent stemming from a sellers market perspective. The few active ones visit SACCO meetings, go to villages, run radio ads, put up poster, distribute flyers, etc. Although the impact of these activities has not been measured in a strict scientific way, data reveals that several of the more
28 TAREA (2009) conducted a follow up study on the level of activity of project dealers that concluded that about 25% had stopped trading solar systems. The study did not analyse the performance of the active dealers. 29 This viewpoint may also come from a NIH, i.e. Not Invented Here approach to solutions that the companies were not consulted in the beginning. 30 This was observed in the projects impact surveys that were qualitative and based on testing a hypothetical installation rather than evaluating actual installations in the field. Hence, there is no general estimate of the situation in Tanzania. 19 successful dealers normally do more marketing than the rest. But there was only one dealer in the sample that had developed his own customized material; dealers tend to use the material provided by the suppliers. 4) The dealer-supplier relationships also change in an emerging market towards more stable relationships. The surveys show that the business relationships are thin and mostly based on the transaction itself. Hence, there is little loyalty to a specific supplier in todays PV market. There are indications that some suppliers 31 try building long-lasting relationships by being more involved in the dealers business. E.g. supplying posters and pamphlets is common, whereas providing training for dealer staff is rare. Credit which is a sign of trust between the companies is not frequent as at the most 20-25 per cent have some form of credit with the supplier. An unwritten rule is that credits are not offered during the first 2-3 years of doing business and thus requires more knowledge of the dealers capacity and attitude towards credit schemes 32 . Dealers stated that the majority of suppliers are based in Dar es Salaam followed by Nairobi 33 and South Africa. The selection of suppliers depends more on availability and prices than loyalty to a certain brand. Suppliers that keep a variety of products (BoS) are preferred. Quality is seldom mentioned as a key factor. Technicians-Users: Although most dealers selected and sent a technician for training not more than 50 % use a project trained technician for installation. This draws from three reasons; most technicians are freelance and not employed per se by the dealer and used on-need basis, many customers prefer to use their own technicians, and that many dealers do not stress the importance of hiring qualified technicians for installations. The relations between technicians and dealers seem to be weak in most cases as the technicians are more loyal to the customers and keep changing dealers. Some customers complained about the level of knowledge among the technicians and said they would probably look for a more qualified technician next time. The use of poorly trained technicians is driven by cost as most trained ones are based in district towns which means the customers must pay for the technicians additional cost to install in the village. The awareness among existing and potential users to properly design and install systems is growing which will favour trained technicians in the future (TAREA, 2012). Supply chain development. The supply chain is dominated by business transactions and moving goods from A to B. The linkages between supplier and
31 The two most active suppliers have been Umeme Jua and Sollatek. Though Umeme Jua is no longer a key actor in the market at the time of writing this report (Nov 2011). 32 Several Dar es Salaam based suppliers state that the turnover of dealers is partly because of failing to pay back credits offered. 33 Dealers in northern Tanzania bordering Kenya (in particular Mwanza and Arusha) were actively sourcing from Nairobi instead of Dar es Salaam. The number of dealers importing from outside EAC are very few. 20 dealers, and between dealers and technician that finally interact with customers are in general weak. That is, each stage in the chain is mostly concerned with its own problems and opportunities as little cooperation goes across the layers. Technical & quality issues are normally sorted out at each level and do customarily not go upstream or down stream in the channel. Long-term cooperation that goes beyond price is yet to find its way into the solar PV supply- chains. E.g. prices as set by the suppliers are only recommended prices and the dealers are free to set any price, which they do. The uninformed customer may end up paying 50% more than a customer who has requested quotations from several companies. Further, although most panels come with a 10-year warranty, very few dealers and technicians inform their customers about this guarantee. To summarize, supplier-dealer relationships have evolved showing signs of maturity. Though stronger business relationships the supply chain is not efficient at controlling quality. Further, the link between dealer technician is not always solid. 5) Building a functioning market rests on the assumption that most market actors follow the rules of the game. The rapid market growth attracted the attention of opportunistic PV companies that recently entered the market. The effect is that the market is increasingly being flooded by substandard systems which quite fast have captured a substantial market share. It draws mostly on unaware customers who dont know their rights and seldom ask for their rights such as warranty. The problem is accentuated by the minor role played by branding in the Tanzanian PV market which is not an issue as most customers value low prices rather than quality 34 . The current efforts by TAREA&SIRG address the issue but rural buyers, by and large, are not aware of their activities. 4. Discussion and Analysis The Sida MEM solar PV project was designed to pilot a market-driven approach for diffusing modern energy technologies to rural Tanzania. It was purposely prepared to avoid the shortcomings of traditional result-oriented donor projects that have tended to focus more on short-term output than sustainability. A key assumption in the project design was that the need for energy services existed but demand was not well articulated and therefore not known to suppliers and dealers. Hence, there was mismatch between demand and supply blocking market growth. Further, effective supply was seen as result of a system rather than the act of individual actors stressing the importance of distribution channels and networks among companies. The function of the system is primarily for efficient delivery of services and products but in the long-term the
34 According to suppliers as well as dealers very few customers request a specific brand while discussing a purchase. The only well-known panel was the 14Wp FEE sold Umeme Jua and Chloride Exide, which has been discontinued since the FEE factory was closed. 21 basis for learning, innovation, and diffusing information. A more hands-on model for matching demand and supply was selected, the so-called 4A model that is demand driven in which supply is a function of improved access to the PV technology. The model assumes that once demand is well articulated, the existing mass of suppliers and dealers will seize the market opportunity. However, the model was adjusted to the case of the Tanzanian PV market, which meant that access has to be supported along with demand creation. The project was a pilot in several respects that focused on testing a number of methods (activities) for stimulating market development. Hence, there was no detailed blueprint on how the project should work with the private sector but rather a guideline provided in the terms of reference for the project. Therefore problems and challenges were addressed along the way, mainly thru discussions between the project team and other stakeholders. But as in real life business, not everything can be anticipated and solved, as shortcomings should be expected. In summary, the project had the following key accomplishment: Awareness and acceptance were addressed through the same activities, as these concepts are viewed as similar in the market. Market campaigns were carried out in all 14 project regions for three months in each region. These campaigns involved regional dealers more after MTR feedback. Unfortunately, the impact of these campaigns has not been measured applying rigorous data collection methods. However, anecdotal interview responses by regional dealers corroborate the positive effect on number of requests and sales (the projects impact surveys). The access to PV systems has improved substantially in all 14 regions as 60 per cent of the dealers, roughly 100, were introduced through the project. Supplier- dealer linkages were supported by inviting suppliers to regional launches and organizing visits for dealers to suppliers while in Dar es Salaam for training. The caveat is that the survey data does not allow for an in-depth analysis of dealer performance such as comparing new entrants with companies that have been in business longer, the role of good relationships with suppliers, the use of trained technicians. Affordability was addressed directly by working with financial institutions and SACCOs to provide credit lines for PV systems. Indirectly, the project contributed to new entrants leading to stiffer competition in the market bringing down prices 35 . The establishment of credit lines never materialized which had little to do with project activities but stems from the risk-averse financial sector in Tanzania. The price per Wp installed has more or less been stable over the course of the project. The solar Network was tackled by supporting the national solar association, TASEA. The strengthening of TASEA (nowadays TAREA) has been successful e.g.
35 The prices per Wp installed dropped slightly in early phases but have in the post-midterm remained the same (i.e. around USD 12-13). Without competition prices would probably have been even higher. International prices for panels have fallen considerable in 2010-2011 whereas battery prices have gone up. 22 by supporting SunEnergy, the associations magazine which today is self- sustaining through advertising revenues, developing a strategic plan, establishing the SIRG, holding an annual Solar Day, upgrading the web site, etc. TAREA is acknowledged in the sectors and members have grown from 60 to 280. A functioning PV association is probably one of the key imprints accomplished by the project. Policy was addressed in two ways by the Project: i) controlling quality of products entering into the market by educating TBS and TRA officials. This comprises not policy setting per se but implementation of existing government policy that so far has been poor at enforcing quality standards adopted in the sector. The outcome of TBS&TRA training is to date not known as concerns are raised whether trained officials will apply the knowledge gained. ii) Sensitizing and training local governments to incorporate solar in development plans. This component has been far more successful as a number of districts have installed solar as a result of project activities. This is also not policy as such but stimulating demand as the policy guidelines already allowed the local governments to procure appropriate energy solutions for schools and health centres. The implementation of the project has been guided by several factors: the original design, the Consultants capacity and interpretation of project outcome, red-tape and procurement guidelines applied, the Clients (MEMs) capacity and involvement, the M&E framework - project internal as well as external. The original design of the project as presented in MEMs program document (MEM, 2002) provided a detailed outline on how the 4A approach combined with the creation of a BDS market would support market growth. The overall approach is drawn from the role of commercial markets to deliver services and goods. However, these markets should not be left to the vagaries of markets forces only as supporting functions and rules play a critical role in achieving sustainable growth. The design may have underestimated the time required and need for stimulating BDS demand. Although there is plenty of evidence that direct delivery of BDS is not sustainable, still the importance of BDS is not acknowledged in the current market. Probably, the initial phases should have confronted the existing need for BDS to evaluate whether BDS contributes to success in the market or not. For instance, what are the underlying causes for poor performance? An in-depth analysis might have revealed that poor and good performers are not differentiated by the demand for BDS. That is, learning is not characterized by accessing formal educational and training institutes. Alternatively, project implementation should have been more flexible to respond to market constraints. The capacity and interpretation of the project team was integral in project roll out due to the specific nature of the design. The role as a facilitator, only, was not fully clear in hindsight. The interaction with various market actors could have provided the project more insights into the business problems the project 23 intended to address. E.g. instead of proving free training over the full life of the project as the project did not see any demand for the services should have addressed the underlying problem in the BDS market: what is needed to stimulate demand in BDS? The question may be rephrased as why companies do not invest in upgrading their skill base? Reviewing the projects performance using the dichotomy doer or facilitator, the project team undoubtedly felt more comfortable delivering services directly rather than facilitating external provision. This is based on how the private sector was involved, handling of subcontractor relations, and the proactive stance taken. Further, more worryingly was the approach to do things isolated from the market and supporting institutions, as the exit of the project will not smoothly take place by transfer of functions to the market. A lesson learned is that a project with a novel approach or a method that differs from mainstream should include discussions with the winning company to make sure that work plans and methodologies proposed by the consultancy firm are in line with the original intentions. Procurement guidelines adopted for identifying and selecting service providers may not have been conducive to sustainability. Supporting functions to markets should ideally reside in permanent institutions in contrast to those specifically developed for the project. Governmental tenders although in extensive use may not comprise the proper channel for long-term support to markets. The project basically attracted consulting firms only to supply services (TASEA provision of services was in fact a consultancy carried out by two members). It would have been more appropriate to single-source a few institutions or having the tender documents specify eligibility for tendering the training such as having been operating in the PV sector for a number of years. The subcontractors selected may exit from the PV sector once the project is discontinued. An exception is the case of TASEA consultants who were involved in solar before the project and will most probably be engaged in solar energy in future as well. The solar sector may indirectly gain from their experience in training technicians by applying lessons learned in their permanent positions. The Client is the Ministry of Energy and Mineral (MEM) that had the overall responsibility to coordinate and overview implementation as project owner. MEM assumed quite a passive role in the project 36 demonstrated in weak interaction and control of the Projects implementation. The funds for strengthening and building MEMs capacity were never used as intended and diverted for other purposes. The effect was that the number of reviews of the project and comments by MEM at AR and steering committee meetings were indeed limited. MEMs participation was limited 37 to steering and annual review
36 MEMs performance was affected by the lack of a formal functioning PIU and turnover of staff. 37 Selected MEM staff was part of the field trip to Lushoto and Tanga initiated by Sida in November 2010 which although close to the end of the project contributed to substantial learning about the project. 24 meetings which provided a weak basis for learning about the project. The effect of the low involvement has been the message to the Project to go ahead as planned with little reflection on modifying the approach. This problem was also highlighted by the timely arrival of the Paris declaration in 2005 that limited the Embassys extent of hands-on interference with project implementation. E.g the issues highlighted within the Sida M&E should be brought to the attention of MEMs PIU and not directly the responsible project team, which complicated a direct impact 38 on implementation. Further, MEM has not been active in the projects exit strategy which currently is left to the private sector and TAREA to address. M&E framework and setup: The projects M&E was not formulated at any detail in the terms of reference leaving considerable scope for interpretation by both MEM and the Project. First, the inception report dealt cursory with impact surveys disclosing no details on methods or link to the LFA. The inception report even presented an LFA that had a number of deviations from the one provided in the bidding documents. The most critical change was the step away from establishing market and institutional conditions towards objectives that tended to emphasize quantitative indicators 39 such as sales of panels, revenues, etc. The support to the solar association and enforcing of standards were acknowledged whereas indicators for supporting conditions essential to market growth were lacking. From an M&E perspective measuring the symptom of market growth, i.e. sales, is a very different undertaking than analysing the root cause for market development. Secondly, this lead to a delay of the projects impact surveys that started in September 2008. This may not have affected the outcome of the surveys negatively as the delay benefited the studies to incorporate more dimensions of impact. Thirdly, the overall division of labour as regards, M&E among Sida, MEM, and the Project was neither spelled out explicitly in the original program document nor in the contracts 40 . Fourthly, partly as a result of the confusing roles and MEMs poor monitoring capacity, there was no explicit and independent M&E carried by MEM manifested in less than adequate
38 The model may have worked if the Client, MEM, had been more involved, The feedback from Sidas M&E had little impact as MEMs PIU did not follow up on the issues emphasised. MEMs PIU was mainly concerned with screening invoices which although comprised an evaluation whether activities were delivered as agreed did not include M&E of outcome and impact. Hence, MEMs evaluation did only focus on what had been done at not on how and possible effects. The observation that MEMs engagement was poor has not included an analysis of the cause for the performance such as lack of resources, skilled and motivated staff. 39 The weaknesses of the projects M&E in particular missing links to the original LFA were brought to the PCAs attention in early 2007, highlighted in the MTR, and brought up in numerous discussions at ARs, etc but in the end very little changed in terms of the projects reporting. 40 This was evident in e.g. the Consultants request to include Sidas M&E consultant in the impact surveys. 25 feedback 41 to the Project. Fifthly, Sidas M&E was mainly performance monitoring rather than impact monitoring based on Project reporting. Hence, Sidas monitoring consultants experience of the Tanzanian PV market and design of the project was instrumental in conducting a balanced evaluation 42 of projects progress reports. Finally, the exit strategy should have been part of the design. The institutions and organizations assuming the functions carried out by the project should have been on board from the beginning. Ideally, these institutions should have delivered the BDS from the onset instead of the Project as in the original project design drafted in the program document. This is verified in the projects exit strategy presented in the RAR and earlier progress reports, which verifies the difficulties to transfer project functions and skills to local institutions. 5. Lessons learned and scope for replication Lessons learned stretch from design, implementation, sustainability, and impact. The key to designing market-driven projects is actually to make the project less visible favouring the growth of existing institutions and organizations. The BDS approach is not a fad, which can be seen in off-springs like the M4P approach that has come out of the extensive experience of BDS projects. As the approach hinges on supporting existing functions in the market, including policy, infrastructure, norms, etc., the preparation of the project design draws on comprehensive insights of the market supported. This can only be acquired from a consultative approach in which key stakeholders are involved. The project was formulated under the aegis of BDS to spearhead the PV market. The experience points to a few lessons. The project delivered the BDS in an efficient manner but was less successful in creating a commercial market. This partly draws on the design and unrealistic assumptions as the need for business services was assumed rather than verified by extensive research. The guidelines such as the projects ToR - should probably have stressed BDS market creation rather than BDS delivery. That is, if the project had e.g. been given the sole task of stimulating demand rather than provision of such services, implementation as well as impact on the sectors sourcing of services would surely have resulted in a different scenario than the one predicted in the exit strategy (see the projects RAR). On the other hand, stimulation of demand - indirectly leading to capacity development - is a slow process which probably had led to a low number of dealers and technicians being trained. From a sustainability viewpoint this may
41 A brief analysis of MEM official reporting to the Consultant indicates that there were very few concrete suggestions by the PIU that could redirect implementation. Most feedback from MEM was in fact Sida comments that were accepted as credible and passed on to the Consultant. 42 Sidas M&E did not include any field visits until late in the implementation, which further allowed the project to deviate from the design as the projects reporting tended to focus on pros rather than cons during implementation. 26 have been a preferred model. The role of the project, to facilitate, has to be envisaged in the type of activities delivered by the project team. Hence, the type of activities proposed by the project consultant in the inception report should have raised an alarm flag that the project was diverting from the BDS approach. An additional lesson learned is to check whether the implementing organisation has understood the pillars of market-driven support. A further challenge in a country such as Tanzania, where most markets, institutions, policy-making have historically been exposed to heavy donor influence, comprises the perception of market-driven development. The influence of free money in the sector will affect commercial actors decisions which is a remainder that any intervention is in fact a subsidy that should be short term and catalytic. The presence of free technical training for PV technicians has, by and large, become the norm in the sector which will require substantial effort to break. A future intervention in the PV sector should probably address the type of support needed to create incentives for market actors to upgrade their skill base. Projects piloting or testing novel approaches require additional means of educating the Consultant as a ToR is seldom sufficient for transferring the necessary understanding to the project team for planning and executing implementation Although the design is predetermined, the implementation has to allow for significant extent of flexibility to accommodate for the markets response to the support activities. The implementation should be based on an interactive approach in which M&E feeds into the design. An additional lesson learned is that how to support markets without distortion is not what is being done (such as training x number of technicians) but rather how it is being implemented (such as the technicians demanding the training rather than being selected by the project) that determines its sustainability. Correcting implementation arrangements is to a great extent dependent on the establishment of a rigorous M&E framework that provides the proper input to stakeholders. The feedback will seldom originate from the market, particularly if services had been provided free of charge 43 . Intermittent discussions between the Client, the Implementing Agency, and the donor are necessary to avoid falling in the classic trap inherent of projects sourcing implementers through tender procedures. The vulnerability of the procurement procedures is that once a consultant is a selected and the proposal is accepted there is not much the Client can change 44 . The dynamics of markets highlight the need for a flexible approach, which was demonstrated in the implementation of the Sida-MEM PV project. The project brought on new
43 The context for delivering appropriate services is fundamentally different if the service provider is actually directly paid by the participants as opposed to third party reimbursement and free participation. E.g. if the providers client had been the dealers instead of the project, the training had been organized differently. 44 The norm in tender procurement is to either reject a proposal or accept as it is. To use the proposal for negotiations between the client and the consultant is not common, as this would give the winning bid an unfair advantage towards the ones that were rejected. 27 actors as a result of feedback, e.g. VETA, SIRG, etc, but was regrettably less flexible in adapting the methodology. Sustainability in market-driven projects applying a BDS or M4P approach correlates not only to the exchange of goods between buyer and seller. The exchange is the core function of a market but draws on a number of factors to establish a sustainable market that leads to an optimal balance between demand and supply. The implicit assumption in the BDS model is the role of upgrading skills and knowledge to sustain growth. Hence, the explicit demand for capability building through accessing services (external to company) comprises an indicator of a maturing market. Nonetheless, developing markets are still characterized by MSMEs operating informally mostly learning by doing in an experience-based fashion. This focuses additional attention to the design and implementation of projects supporting the skill base of such companies as few formal resources are spent on learning. Further, long-term growth draws on the existence of a number of functions to support the market exchange. The PV project emphasized BDS, networking, and policy as the pillars of sustainability. A key lesson learned is that the imprint by direct intervention in the market place is most probably short-term whereas the institution building such as TAREA will have more profound and far-reaching effect on the market. Hence, private sector capacity should, as stressed earlier, take the detour through building institutions and guidelines, although direct support may reap quick rewards. The market needs guidelines on rules of the game regulating obligations such as between suppliers and dealers, and between retailers to consumers. A corollary is that project impact is not necessarily measured directly as (short-term) market growth but rather in the establishment of institutional and market conditions to sustain growth (support functions, rules, policy, capability). Further, the private sector should be consulted on major actions in the sector to verify that activities rolled out will have the intended impact. This is in particular important for capacity building programs that deliver services demanded by the private sector. It is also important that private sector and market supporting institutions should be involved early in project implementation, preferable at the design stage, to ensure sustainability. Closer consultations with the private sector would as well mitigate potential market distortion activities such as the selection of participating MSMEs which should be done as close as possible to market principles. E.g. if dealers are approached, selection criteria applied by the sector should be used rather than only relying on project standards. Learning is closely linked to previous experience of the companies as few PV dealers and technicians were new in business coming from other lines of business. Hence, targeting start-ups may require a different set of support packages as support to market hinges on the level of market maturity; e.g. supporting variety in immature market by facilitating the entry is often effective whereas consolidated markets with large actors need a different approach such as supplier development programs for MSME suppliers. 28 The role and function of the institutional framework: Supporting market growth and market actors is necessary but not sufficient as long-term development can only be sustained if the proper institutions are in place. The key lesson is to focus attention the function played by various institutions and not the institution per se. The existence and function of a sector association is of outmost importance for addressing general issues and creating joint programs. TAREA which recently expanded into renewables in general will constitute a key partner for future projects. The Project established and supported a number of functions but did not address such as consumer advocacy, university-business cooperation, warranty and guaranty issues, and certification of dealers and technicians.
6. Way forward for a Sida renewable energy program: ideas for thought Even though it has proven to be challenging, future interventions in the renewable sector should try to adopt a market development approach similar to the original design of the PV project. A market development approach (by using for instance the M4P concept, Making Markets Work for the Poor) or the B4D (Business for Development), has a high potential to contribute to broad impact and sustainability in the markets delivering renewable energy services to people in poverty. The concept stems from Making Markets Work for the Poor, in short M4P, which is designed for improving the understanding of market systems that involves poor people, and how to bring about systemic change in those markets systems to benefit the poor to a larger extent. In this case of renewables, the poor are found either as users/customers or in the informal sector as MSMEs (Micro, Small and Medium sized Enterprises). The poor found in the MSME sector comprises, in a relative sense, not the poorest segments of the population, as there is normally adequate liquidity and solidity to set up and run a micro or small business establishment. The MSMEs are as well potential or existing suppliers of renewable energy services and products. The M4P approach is specifically designed to address underlying causes rather than just focusing on symptoms in malfunctioning markets. It draws on in-depth knowledge of the various players in the markets and their respective function. The term market system defines a wider set of actors that support or interfere with the market in question. The approach is indirect in the sense that support should normally not be given directly to companies but to market supporting functions by facilitating activities performed by existing institutions. However, targeted support to specific companies in the market can be justified if it leads to innovation, increased competition, piloting of a new market features. The general rule is to establish and support institutions, regulations, praxis, and so forth that affect the interplay among market actors, i.e. building a platform so the market can learn how to sort out issues. A caveat may be that overly focus on 29 the P might block the formation of dynamic and growing markets which normally comprise a mixture of small and large firms. The inclusion of micro or small firms in the value chains that also include large companies is often crucial for overcoming low-level equilibrium markets featured by little incentive and opportunity to develop. Below follows some suggestions on the way forward: 1) Innovation system and renewable energy markets: The M4P approach in a wider sense could be applied in a programmatic manner to embrace stakeholders not normally visualized in energy programs and projects. The sustainability of any sector depends on the totality of resources available and developed to drive the sector forward in a systemic fashion. Improvement and upgrading is more than operational skills and long-term growth hinges on the mobilization of the innovation system to supply knowledge and skills. Sida SAREC has substantial experience of mapping and supporting such as systems, particularly in Tanzania. COSTECH (Commission for Science and Technology) is currently considering the support to an energy innovation system. Preliminary meetings have been held with stakeholders. The advantages of including three program areas; Research, PSD, and Energy in one cross-cutting project would primarily fall in the facilitation to address the underlying causes for poor economic development in rural areas. COSTECH could act as the Client for an Innovation System Initiative that would map existing R&D resources, set up criteria for academic research funding of COSTECH s existing funds, set guidelines for diffusion of research funding, how to involve the sector in question to advice on research topics, etc. 2) Expansion through establishment of competitive value chains (VCs): Most markets are characterized by their structure as regards the linkages between companies in the distribution channel. A value chain is in fact a method/approach for analysing the chain of activities between e.g. a producer and wholesaler up to the sales point. A value chain perspective is useful for understanding the development of technology across firms, the value added by each step in supplying goods and services, the importance of interconnectedness among companies to develop a sector (the whole chain has to be targeted). The rationale for developing VCs is based on the premise that small enterprises can grow and become competitive when they have clear and well-developed strategies set by competent and demanding value chain members. The performance of downstream companies is often dictated by the norms set in the channel (chain) set by larger upstream companies. This enables them to target and access market opportunities for selling their outputs. Addressing issues in the value chain may also focus on embedded services. The establishment and growth of MSMEs are crucial in the long term to develop any given market. Hence it is important to understand the formation of MSMEs and the drivers for upgrading skills and capabilities. Barriers to enter must be assessed such as bureaucracy, skills and capital required, type and level of technology, access to information and search processes. 30 Some questions arise: are there certain types of value chains which imply more learning opportunities for MSMEs in than others, or does the companys experience determine whether a producer/trader succeeds in upgrading? What type of relationships characterizes the value chain? How is information shared and diffused in the VC? These and similar questions will form the basis for preparing a VC Initiative. The initiative should probably be hosted by REA but could also be set up under the Private Sector Foundation. 3) A Poor mans perspective: An M4P project may on the other hand focus on the rural setting and how energy could support the inclusion of farmers in the formal economy improving access to basic necessities such as financing, education, and information. Most poor people are constrained by lack of skills and education, which means that inclusion will be a key component. Such a project would need to emphasize the transformative role played by energy in establishing new and competitive rural businesses based on productive use. This may entail the development of rural communities applying a non-grid paradigm that springs from a multitude of renewable energy sources such as micro-grid, solar, biofuel. Starting from a PSD perspective rather than energy would focus attention the role of business and income generation foremost. The benefits at the individual level will be downplayed unless these form the impetus for demand. The challenge with community-based projects mainly resides in reaching wider impact beyond targeted pilot communities. A possible approach is to support the diffusion of generic technologies that could be adopted nation- wide with the required M4P framework in place. A key question is whether expansion of energy services should be pro-poor or neutral?
Issues to consider at the preparatory stage The lessons learned from the PV market facilitation project highlight a number of conditions that will affect the design of an intervention. i) The maturity or size of the market will set the scene for the type of support needed. Very small markets may need demand creation interventions whereas larger markets may lack coordination, standards, low RoI, etc. ii) The existence of a driver for development expressed by buyers, legislation/standards, competition. Markets with no articulated drivers will seldom excel and on contrary reach a status quo early. iii) A joint platform for lobbying, awareness, and addressing challenges such as a sector association is paramount for sorting out general issues that individual companies cannot lobby in a credible manner. iv) Cooperation among key stakeholders requiring an understanding that they are all in the same boat and joint efforts is the only solution. v) The local innovation system for a specific technology sets the parameters for capability development in the long run. Local academic and industry R&D are important to adaptation and acceptance of technology. vi) Linking of small and large firms in value chains are a major means for creating rural markets and upgrading the MSME segment. vii) Institutions that support and guide the market to develop fair trade. 31 Is the government ultimately responsible to deliver energy services? If so, the challenge is to see how the governmentin collaboration with the private sector, communities, and outside partnerscan meet this fundamental responsibility. The tradition has been that the access to electricity is a service that should be provided by the government. The pendulum as swung to the extreme in some countries leaving it to the market. Even if the government has failed to provide energy to the poor it does not mean it should leave everything to the private sector as the energy markets need guidance. REA has started to follow the PPP paradigm. Technology choice should be left to the private sector although there may be guiding principles by government institutions to secure minimum standard of products and services.
32 List of references and interviews Interviews Camco, Jeff Felten, TAREA, Matthew Matimbi Ensol, Hamisi Mikate Sollatek Davis&Shirtliff Cloride and Exide TaTEDO, E. Sawe Aglex, Rex Solar, Frances Umeme Jua, D.Light, Pepijn Steemers Costech, Bakari Omari University of Dar es Salaam (Pr. Kimambo, Pr. Kivaisi) Solar Sasa
References: MEM (2003), Facilitation of PV Market Development in Rural Tanzania, project document, MEM Sida (2002), The RES Market Report, Swedish Embassy Tanzania Sida (2006), Comments on the ESD Inception report, the Sida/MEM project on the Facilitation of PV Market Development in Rural Tanzania, Lennart Bangens Camco (2011) , Sida/MEM Solar PV Project: Results Analysis Report, MEM TAREA (2009), Report on Tanzania Solar PV market Tends study for 2008-2009, Sida-MEM Solar PV project
Impact Surveys (Camco): a) Dodoma-Survey 210610 b) Kigoma-Survey 090909 c) Pwani-Survey 151008 d) Lindi Survey_ 220311 e) Mtwara-Survey 070409 f) Singida_Tabora_Manyara_Ruvuma Surveys 280611 33 g) Tanga-Survey h) Rukwa_Mbeya-Survey 220910 i) Morogoro j) Where is the 14 th region
Camco progress & WP reports a) P&WP 2006 b) P&WP 2007 c) P&WP 2008 d) P&WP 2009 e) P&WP 2010/11
1 Appendix I LFA Intervention Logic Measurable/ Verifiable Indicators Means of Verification Important Assumptions Observed Impact Development Objective Increased demand for modern PV technology to meet basic electricity needs in rural areas as a means to improve living standards and community development. Increased uses of PV systems in rural areas such as households, SMMEs, schools and health clinics. Statistics, surveys, reports, evaluations, REA data The uptake of PV has increased substantially though the effect on development has not measured Immediate Objective Market and institutional conditions created to enable a transformation of the rural energy use towards an increased diffusion of solar PV systems The yearly market for PV systems in rural areas has doubled in 5 years. The number of PV outlets in regional capitals have doubled in 5 years. Statistics, surveys, evaluations, REA data A market can be created for solar PV systems in rural areas. The market has grown rapidly and is at exit 10 times larger than at pre-project. Outputs
1. Awareness created 1a) PV market customers have increased knowledge of PV systems. 1b) There is access to independent consumer information 1c) Policy makers and sector ministries have incorporated PV options in regular planning procedures
2. Acceptance achieved 2a) End-users are actively 1. PV systems are considered as a viable option to traditional energy sources. Consumer information centres established. PV systems included in government policies, guidelines and planning procedures.
2. Number of requests and phone-calls. Number 1. Surveys in rural areas, site visits, sector policies, guidelines and procedures
2. Market survey
The presence of a market economy in the rural areas and market potential are not over-estimated.
Overall government policies continue to favour market- oriented initiatives.
Financial actors are willing to consider credits for PV systems. a) The RAR states that awareness is widespread though there is no reference study to substantiate the level of awareness. Consumer information is provided by TAREA. A number of local authorities have started to plan for PV as a means to electrify health centres. At this stage any wider conclusions regarding general awareness will remain a mere conjecture, as the data has not been collected. b) The RAR provides data on the number of firms and technicians trained but little information on the 2 demanding PV systems and PV information 2b) Marketing in and to rural areas have increased 2c) Rural PV technicians present
3. Access improved 3a) Sales outlets established in a number of regional capitals 3b) Distribution channels and store-keeping of PV systems in place 3c) Installation in rural areas offered 3d) Increased availability of credits for PV systems
4. Affordability improved 4a) The costs in the PV industry are reduced by 40% in 5 years. 4b) Consumer prices have been reduced by 25% in 5 years.
5. Increased demand for PV systems increased by 20% annually.
6. The Solar Network has expanded and includes coordination, cooperation and linkage activities. of rural PV technicians trained and in operation.
3. Number of PV outlets in regional capitals, availability of installation services, availability of credits for PV systems
4. Costs reduced by 40%, and prices reduced by 25% in a 5-year period.
5. 4,500 systems (200 kWp) sold through the private market in rural areas in 5 years
3. Market surveys, REA statistics
4. Cost and price statistics, market surveys
5. Market surveys, sales statistics
Market actors are willing to cooperate.
New Energy Policy approved
REA is established status such as level of activity, fundi linked to dealers, money spent. There is additional information to be found in the impact surveys that reveal that most dealers are still active (70%), and inquiries increase considerable after market campaigns (not quantified), a small number of dealers have printed brochures. Dealers and technicians exist in almost all district towns in Tanzania but how aggressively they market in rural areas is not known. c) The project has succeeded in establishing outlets in almost all district towns though the quality of services has not been evaluated. Around 60 % of the dealers trained i.e. 100 started solar business as a result of the project. Many dealers identified suppliers through the project but few stay loyal to a specific supplier. The few that have strong ties with the supplier may be offered services and discounts not available to new and unknown dealers. Credit systems are not available as 99% are cash sales. d) The RAR discloses little information on cost reductions more than that profit margins among dealers could be as high as 50%. Regarding price reductions: retail prices falling from USD 15/Wp in 2005 to USD 12 in 2011. 3
7. Mini-ESCOs have been established on a pilot- basis.
6. More actors involved in the Solar Network, and regular coordination and linkage activities performed
7. At least 100 mini- ESCOs offering portable solar lanterns on a renting-basis are in operation. 6. Project reports, interviews, documented network activities
7. Project reports, site visits Whether the average rural buyer can afford PV more in 2011 than in 2005 remains unanswered as purchase power and cost of living has not been addressed. e) TAREA has grown its membership base from 60 to 280 over the course of the project. TAREA was reorganised, appointing a new executive secretary, as well as inviting renewable energy actors outside solar. TAREAs expansion is surely a result of the projects continued support in combination with the appointment of new management. As regards linkages and cooperation the project did not explicitly address this in general but focused on supplier-dealer relationships. The formation of SIRG may be viewed as an effort to jointly solve problems facing the sectors. f) The pre-project annual market, estimated in 2002, was a mere 100 kWp and largely project driven. Rapid market growth coincided with the launch of the project in 2006. The LFA specified that demand for PV systems would increase by 20% annually but this was projected under a slow growth scenario as pointed out by Camco (2011a). The market rose to 450 kWp in 2008 and according to a 4 TAREA survey to 1.5 MWp in 2010. The project has surely contributed to the fast rise but there is no study conducted on the drivers for growth, in particular those external to the project. g) The mini-lantern component was dropped from the project due to the market situation. h) SIRG is a sign that a number of firms have realized the need for cooperation to address joint issues.
Activities 1. Business development support to PV companies; 2. Development of the Solar Network; 3. Policy and institutional development; 4. Stimulation of end-user market Activities are performed as agreed in Annual Plans of Operation. Plans of Operation, monitoring reports, follow-up reports, annual review reports A) BDS successfully delivered though the BDS market has not been created. Transfer of activities to VETA has been initiated but long- term impact is not known. B) The dealer networks have expanded quantitatively whereas the quality of supplier-dealer links is not known. C) Policy per se not addresses but the local authorities sourcing of PV has increased. Key institution developed is TAREA. D) Project activities successfully built awareness and demand though the handing over of the function to e.g. PS, TAREA or REA is not fully known. Inputs