No.
1. Earth work open excavation for
etc., complete
Cricket Ground 1x1 3.14/4x136x136x0.30 4355.81
Add for sundries - - - - 4.19
4360.00m3
2. Supplying and filling of sand gravel
36x136x 1
0.30
Add for sundries - - - - 4.19
4360.00m3
3. Preparing the pitch - - - - L.S
4. Preparing the Boundry and pitch - - - - L.S.
lines
LEAD STATEMENT
knowledge.
DATA
No.
1. Open earth work excavation for foundation
(19.25+28.75/2)=48.00/2 = 24.00)
0.33m3 Refilling the sides of foundation with exc. 10.10 m3 3.37
Earth
L.S. Add for sundries --L.S- -- 0.13
27.50
Rate for Rs. 27.50/m3
2. Supplying and filling in foundation &
Vellore District.,
ABSTRACT
No.
1. Leveling the site by supply and filling the
4360m3 and red gravel mix at the ratio of 1:1:1 in 27.50 m3 119900
complete
3. L.S. Preparing the pitch --L.S.- -- 33000
4. L.S. Preparing the boundry and pitch lines etc., --L.S.- -- 24290
Total Rs. 950000