Promotion Management Overrides
1. Concept

In a standard development cycle, all the BI content is created in an Origin (Dev) system and
then moved to other environments. The main challenge faced in this process is updating the
Database credentials as per the destination environment.
To overcome this challenge in BI 4.0 we have Promotion Management Overrides. It was present in BOE
3.1 and was known as LCM Mapping. However in BOE 3.1, Mapping was LCM job specific but in BI 4.0 the
Overrides are system specific.
You can modify the database credentials for OLAP Connection, Universe Connection, QAAWS Connection and
Crystal Reports.


Following is the generalized workflow of LCM Overrides. Database credentials for the entire object in the
subsequent LCM jobs will be modified as per the overrides set.

Promotion Management Overrides
Generated by Jive on 2014-09-22+02:00
2
2. Procedure
Below are the detailed steps with screen shots for the above workflow.

a) For Movement from Dev to QA
1. Login into CMC Promotion Management in Development System.
2. Click on Setting and browse to Manage Systems

Promotion Management Overrides
Generated by Jive on 2014-09-22+02:00
3
3. Highlight the System from which all the content would be migrated to other environments. In
most cases it would be the Dev System. Check the Mark as Origin box.

1. 4. Save the changes.

2. 5. Browse to Overrides Settings.


1. 6. Login into the Origin CMS and Scan for Overrides.

Promotion Management Overrides
Generated by Jive on 2014-09-22+02:00
4

1. 7. Once the scan is completed, select the particular override which you want promote and
change the status from Inactive to Active and save the changes.

1. 8. Select the Override which needs to be promoted and click on Promote Overrides button.
Promotion Management Overrides
Generated by Jive on 2014-09-22+02:00
5

1. 9.In the subsequent screen, select the required destination server (QA system) and click
on login. Enter the credentials of Destination CMS. The Export button will be replaced with
Promote button. Click on Promote to complete the Promotion.

Promotion Management Overrides
Generated by Jive on 2014-09-22+02:00
6
1. 10. Log off from the Origin CMS and Login into the Destination CMS and again scan for
Overrides.
1. 11. We should see the Override which we promoted from the Origin CMS. Highlight the Override and
click on Edit. Make the necessary changes and save it.
Promotion Management Overrides
Generated by Jive on 2014-09-22+02:00
7

2. 12. If the subsequent LCM Jobs contain the same Connection object, the connection
properties will be automatically updated as per setting defined in previous steps.

b) For Movement from QA to Production
Repeat steps 1 through 12, but mark QA server as Origin and Production server as
Destination system.

3. Exceptions & Corrective Actions
1. 1. Object Export through BIAR files
a. Export the Overrides to a BIAR file.
b. Import the overrides biar in the Destination CMS
c. Scan the Destination CMS and edit the imported overrides.
Now you can import LCM BIAR files with objects and overrides will work as expected.

2. 2. Reverse flow of Ad-hoc reports from Production to Development
a. Use a different CMS as your LCM CMS.
b. Mark your Prod system as Origin and follow steps 1 through 12.


4. Related SAP Notes

SAP Note Description
1805615 How to backup and restore the Promotion
Management Overrides Database in BI 4.x
1801682 How to reset the "LCM Overrides database" in BI
4.0
1628154 Promotion Management (LCM) usage across multi
domain environment
1634962 How to import or export a LifeCycle Manager BIAR
file in BI 4.0 using command line utility
1651890 How to export a Job to a LifeCycle Manager BIAR
file in BI 4.0
Promotion Management Overrides
Generated by Jive on 2014-09-22+02:00
8
1651874 How to import a LifeCycle Manager BIAR file in BI
4.0
1777956 BI 4.0: Promotion Overrides not working for
Dashboards
8.

Anda mungkin juga menyukai