I.
INTRODUCTION
71
% of total
energy demand
A1
Modern
biomass
Solar
Wind
Geothermal
Small hydro
Oceanic
Total
109
85
40
48
14
539
20
16
7
9
3
100
In maximum with
major policy support
MTOE
% of
total
561
42
355
215
91
69
54
1345
8-12
In 2020
minimum
MTOE % of
total
243
45
3-4
26
16
7
5
4
100
72
Waste
Product
Form
Quantity
(ton per
FFB)
Empty
fruit
bunches
(EFB)
Solid
0.23
Mesocarp
fibers
Shells
Palm oil
mill
effluent
(POME)
POMEbiogas
Solid
0.12
Boiler fuel
Boiler fuel
Solid
Liquid
0.07
0.67
Boiler fuel
Soil
fertilizer
Boiler fuel
None
None
None
Gas
Annual
Quantity,
million MT
9.65
Approx.
Moisture
Content, %
55
Energy
Content,
MJ/kg
6.33
5.92
40
10.64
2.41
10
15.26
6.36
Dry basis
18.50
30.48
54.82
Dry basis
19.81
3.
A3
Capital cost
RM7,050.00
Set up cost
Cost of palm oil waste to start the
x2000kg
RM80.00
plant:
Labor cost: To keep the plant operative palm oil waste has to
be charged every day. Considering the full time job of the
labor per month labor cost has been assumed to be RM1400
for plant size 100cft and RM2800 for plant size 300cft.
RM16,800.00
Price of palm oil waste
x
x30x12
RM1,008.00
Total annual operating cost
RM17, 808.00
73
Fertilizer
Cost of equivalent urea
X179.2kgX4X12
RM34, 406.40
Gas
ir = i1
+ PV (i2 - i1)
PV + NV
i2. The
100cft
149,091.302
11,8267.341
94,573.390
300cft
597,549.62
505,077.767
412,605.861
101,689.512
87,353.463
65,887.41
411,675.832
347,277.667
282,879.496
D3
91,123.249
78,873.055
59,492.854
370,244.181
312,103.588
253,962.98
E3
74
which the investment is expected to pay for itself. Thus when sensitivity analysis has also been performed by considering an
average of 10% increase in the price of raw materials. Then
net cash flow occurs at even rate:
the effects of both the capacity factors i.e. plant output and
Payback period = Cash of the investment/net cash flow per year 10% escalation in prices of different raw materials is evaluated
together.
The calculated value is presented in Table 7
4.0
Conclusions
The conclusions are based on the analysis of results of cost
economics of biogas plant of two different sizes, sensitivity
study covering a number of ranges of capacity factors and
escalation of prices of building and maintenance materials of
the plants. The inflow for the project was considered from the
selling price of gas for gas cylinder and the sludge as fertilizer
on land. Through the net present value calculation, it is found
that the project is viable at all the three discount factor
selected (10%, 16% and 18%) for both 100cft and 300cft plant
sizes. It was also found that the project was profitable even
when evaluated at a capacity factor of 80. The project is even
viable when running at a capacity factor of 80 with a ten
percent escalation of price. Another important feature
considered in this project was the sensitivity analysis. From
the calculations, it can be summarized that the initial
investment could be recovered in 0.3389 years (4 months) and
0.2063 year (2.5 months) for 100cft and 300cft plant
respectively when the capacity factor is 100. While 0.4843
year (5.8 months) and 0.2430 year (2.9 months) is required for
90 capacity factor. Whereas, 0.6423 year (7.7 months) and
0.2956 year (3.5 months) for 80 capacity factor. The bigger
the plant size, the shorter the payback period, and the higher
the capacity factor the shorter the payback period.
Sensitivity Analysis
IRR
111
[7]. Goldenberg et. al. (1998), Energy for a sustainable world, Wiley
Eastern Limited, New Delhi.
[8]. N. H. Ravindranath, D. O. Hall (1995), Biomass, energy and
Environment- A developing countries perspective from India, Oxford
University Press Inc., New York.
[9]. Johansson et.al (1993), Renewable Energy, Island Press, Washington.
[10]. A. Ascherio (2002), Diet fat and risk of CHD: New developments in
Enhancing oil palm industry development through environmentally
technology, Indonesian Oil palm research institute, pp. 60-65.
[1].http://allmalaysia.info/msiacommerce/infrastricture/utilities.asp
[2]. A. Zain-Ahmed, Contemporary issues in energy and buildings in
Malaysia: Focus on R & D and policies, SENVAR+IAESEE 2008:
Humanity +Technology, pp15-23
[3]. Malaysia Energy Data, Statistics and Analysis-oil, Gas, Electricity, Coal,
www.eia.doe.gov
[4]. C. Stefan Christoper, PhD thesis (2003), Survey on alternate energy in
Malaysia
[5]. M.B. Wahid, Oil Palm-Achievements and Potential, Department of
agricultural Technology, Faculty of agriculture, UPM.
[6]. WR (1994-95), World Resources 1994-95, Oxford University Press,
New York.
75
APPENDIX-A
TABLE A1: Capital Cost for 100cft plant
Raw Material
Digging mud (cft)
Brick
Cement
Sand (cft)
Khoa (cft)
RCC Pipe
Rod (per tube)
Wax (kg)
Mason
Labor
Valve (1 in.)
Gas Pipe (ft)
Quantity
700
1300
14
70
35
7. 5
32
2
10
12
1
100
Quantity
1600
2850
27
130
70
10
85
3
Mason
Labor
Valve (1 in.)
Gas Pipe (ft)
20
24
1
200
200.00
150.00
38.00
3. 50
76
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
0
0
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
0
0
0
0
0
0
0
0
0
0
0
350
0
0
0
0
0
0
0
0
0
0
0
38
38
38
38
38
38
38
38
38
388
38
38
38
38
38
38
38
38
38
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
0
0
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
0
0
0
0
0
0
0
0
0
0
0
700
0
0
0
0
0
0
0
0
0
0
0
38
38
38
38
38
38
38
38
38
738
38
38
38
38
38
38
38
38
38
77