Boiler (05/08/2014)
S.No
1
Deficiency
BFW Pump-A is running horizontal vibration
Proper support to be provided for the PG,PS and PT which is located in
the burner platform area.
NSW lines to be erected for Aux. boiler loads cooling
BFW Control valves are passing
In the upstream of drain valve in HSD tank O\L is having leak from
welding
Main steam valve passing
Hand rail to be provided for AH bypass damper control valve platform
area
Wind box flange leak (burner platform area)
Deaerator LCV bypass valve handle key missing
Agency
TP(Costruction)
Remarks
TP(Costruction)
Completed
As per drawing completed, To be checked with
O&M
Not in Scope
Within aceptable limit
To be welded when oil tank is in empty
condition
To be rectified after steam blowing
TP(Costruction)
Not in Scope
TP(Costruction)
TP(Costruction)
Completed
Completed
TP(Costruction)
To be provided
TP(Costruction)
TP(Costruction)
TP(Costruction)
2
3
4
5
6
7
8
9
TP(Costruction)
TP(Costruction)
TP(Costruction)
TP(Costruction)
TP(Costruction)
15 Hand rail to be provided for drum mounted safety valve platform area TP(Costruction)
Not in Scope
TP(Costruction)
Not in Scope
TP(Costruction)
17
Furnace west side opening to be closed near wind box. Flame visible
from outside and flue gas coming out through this opening
TP(Costruction)
To be completed on 28.10.14
to be checked
Completed
After pegging steam charging same to be
checked
Motor faulty trip alarm is to be incoperated in DCS for any Trip on elec.
Fault
23 FD fan B winding temperature reading fluctuating
24 FD Fan A running at 307 RPM when scoop position is 0%
25 Boiler drain inching valve feed back is not showing in DCS
22
The following thermocouple are to be erected in the air and flue gas
duct TPDsg47-604,TPDfg47-605, TPDfg47-606,TPDfg47-603 etc
Inst(Construction)
To be completed
Inst(Construction)
Inst(Construction)
Inst(Construction)
Completed
Completed
Completed
Inst(Construction)
Not in scope
Inst(Construction)
Drawing to be revised
Drawing to be revised
Completed
Inst(Construction)
Inst(Construction)
Inst(Construction)
To be completed
Wall blower already completed, LRSB and
pegging steam will be charged on 27.10.14
To be completed
Drawing to be revised
Inst(Construction)
Completed
Inst(Construction)
Inst(Construction)
Inst(Construction)
Completed
Completed
To be completed on 28.10.14 ,during boiler light
up condition
Inst(Construction)
To be completed on 27.10.14
Elect (construction)
To be completed
Elect (construction)
Not in Scope
Elect (construction)
TP(Costruction)
Completed
To be completed after steam blowing