Cataion Conductivity Problem Rectification Activity Schedule

NO

01
02

03

ACTIVITY FOR RECTIFICATION OF CC PROBLEM

STATUS

Dm tank 2 top valve for air relief opened and refitting done by MMD

Work done by MMD on


dated 01.05.2014

KOH solution sample taken and from tank- 1&2 and it was found normal rang.

Done on dated 03.05.2014

Started Dm water transfer from tank-2 to tank-1 through MB-2 unit with normal

Water transfer work done

range of conductivity. (0.10-0.20 us/cm ) DM tank -1 & 2 conductivity observed

On date 06.05.2014 to

as per swas and it was 0.71us / cm Which were higher side, so we passed water

07.05.2014.

from MB unit once again for better water quality.


04
05
04
05

07

Dm Tank out let to regeneration Pump line valve closed.

On dated 06.05.2014

NOX pump Return line to DM tank-1&2, to be blocked by putting rubber gasket

Work done by MMD

by MMD department.
NOX pump suction and discharge line valve to be closed when it is not in used.

Valve made closed

NOX recirculation valve passing checked with MMD but it found ok not any

Work completed with MMD

passing observed.

Person.

NOX Return blocked by putting dummy gasket in DM tank -1&2

Work done by MMD on


dated 7.05.2014

DM tank-2 Cleaning work started at 11:20 hrs on dated 10.05.2014

with 3

persons of EHS, cleaning completed at 15:30 then inspected it and side mahole

Work

done

on

dated

on

dated

10.05.2014

boxed-up with four bolt by MMD person & DM stream -1 started at 16:30 hrs
08

( MB -1 to DMT-2 ) filling started then two to three time DM tank -2 flushed with
DM water and checked MB conductivity - 0.1 us/cm & also sample taken from
drain of the tank & Checked conductivity 0.1 observed , DM stream-1 stopped at
18:00 hrs it is stand by available on TP - 217 M3.

11
12

13

After cleaning DM tank-2 , MMD closed man hole on dated 10.05.204

Work

done

10.05.2014
Adfter closing man hole, start to fill tank no -2 from through MB-2

Partly filled water

During filling the DM tank -2 observed that air was coming from KOH breather. if

Activity done

breather KOH level would have been sufficient then air would not be come out
from air intake bleather line. then opened blind flange and checked level of
KOH solution , it was down observed .
Due to KOH level down, During breathing, co2 was directly come in DM tank

14

Observation

and KOH solution was bypass so, air intake in DM tank-2 direct and DM water
was contaminant with co2.

14

15

Now we required KOH flaks to make 25% colution and PR also raised .

PR has been raised

When KOH flaks will come we will make a 25 % solution of KOH of 155 kgs flaks

Awaiting for materials

& check its % and then transfer it to KOH breather tank by chemical transfer
pump.

After filling materials, (KOH) we will fill DM water. DM tank -2 and overflow will
16

be done and then will taken in service and checked citation conductivity and

Pending

confirm the problem rectification

Page 2 of 2