Anda di halaman 1dari 2

ID

Task Name

Pre-Energization Phase

2
3
4
5
6
7
8
9
10
11
12

13

14
15

16

17
18
19
20
21
22
23

Duration1

(ii) Common Interconnection facility


Transmission circuit 1 -Overall phase reference
check (From E1F to Hongsa)
Transmission circuit 2 -Overall phasereference
check (From EIF to Hongsa)
(iii) Generator Transmission Line
Transmission circuit 1-Overall phase reference
check (Hongsa to Nan)
Transmission circuit 2-Overail phase reference
check (Hongsa to Nan)
(iv) Hongsa Switchyard
Back energization from Nan Substation by
transmission circuit 1
Back energization from Nan Substation by
transmission circuit 2
(v) Generator Metering System
Verification and Accuracy Tests of all meters: .
100% load and power factor 1.0. 50% load and
power factor 1.0. 10% load and power factor 1.0.
100% load and power factor 0.5. 50% load and
power factor 0.5
Check of data exchange between NanMetering
System and EGAT Transmission Facilities
(vi) Generator SCADA System
Tests of communication protocol: - check
transmission of each type of message . check
transmission between the Generator Gateway or
RTU, as applicable, and the EGAT Control
Centers
Database exchange tests: Check exchange of
each individual data as listed in Part I of
Schedule 15
(vii) GeneratorCommunication System
Optical link test (Hongsa - Nan)
PLC link test and tuning (Hongsa - Nan)
Teleprotection equipment test between Hongsa Nan
Data, teleprotection, telemetering and telephone c
(viii) Generator Protective System
Verification of transmission circuit 1 differential
protections: phase to phase comparison

Project: Pre-Energization Phase


Date: Fri 24-10-14

Start

Finish

129 days

Wed 23-07-14

Tue 30-12-14

3 days
3 days

Wed 23-07-14
Wed 23-07-14

Fri 25-07-14
Fri 25-07-14

3 days

Wed 23-07-14

Fri 25-07-14

5 days
5 days

Mon 24-11-14
Mon 24-11-14

Fri 28-11-14
Fri 28-11-14

5 days

Mon 24-11-14

Fri 28-11-14

5 days
5 days

Mon 24-11-14
Mon 24-11-14

Fri 28-11-14
Fri 28-11-14

5 days

Mon 24-11-14

Fri 28-11-14

47 days
5 days

Wed 08-10-14
Wed 08-10-14

Fri 21-11-14
Mon 13-10-14

5 days

Mon 17-11-14

Fri 21-11-14

5 days
5 days

Mon 17-11-14
Mon 17-11-14

Fri 21-11-14
Fri 21-11-14

5 days

Mon 17-11-14

Fri 21-11-14

12 days
12 days
12 days
12 days

Mon 03-11-14
Mon 03-11-14
Mon 03-11-14
Mon 03-11-14

Fri 14-11-14
Fri 14-11-14
Fri 14-11-14
Fri 14-11-14

12 days
6 days
6 days

Mon 03-11-14
Mon 17-11-14
Mon 17-11-14

Fri 14-11-14
Fri 21-11-14
Fri 21-11-14

Jul '14
Aug '14
Sep '14
Oct '14
Nov '14
Dec '14
J
29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 1

ID
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43

Task Name

Duration1

Verification of transmission circuit 2 differential


protections: phase to phase comparison
(ix) Generating unit 1
Verification and calibration of all protections and
protective relays
Initial spinning test by manual start
Balance, vibration and other mechanical tests
Over speed test
General inspection
Generator insulation test
Governor test / adjustment for speed no load
operation
Excitation system verification and preliminary
tests
Short circuit characteristics test
Voltage regulator / adjustment for no load
operation
Open circuit test
Phase sequence test
Residual voltage
Voltage waveform
Start and stop functions including emergency
stop
Generator Stability Data
Synchronization test
Unit Metering System check and Accuracy Tests

Project: Pre-Energization Phase


Date: Fri 24-10-14

Start

Finish

6 days

Mon 17-11-14

Fri 21-11-14

83 days
11 days

Wed 01-10-14
Sun 05-10-14

Tue 30-12-14
Sat 15-11-14

1 day
4 days

Sat 06-12-14
Fri 07-11-14

Sat 06-12-14
Mon 10-11-14

2 days
2 days
2 days
1 day

Tue 09-12-14
Wed 10-12-14
Sat 29-11-14
Mon 08-12-14

Wed 10-12-14
Thu 11-12-14
Sun 30-11-14
Mon 08-12-14

20 days

Sat 01-11-14

Thu 20-11-14

1 day
2 days

Sat 06-12-14
Mon 08-12-14

Sat 06-12-14
Tue 09-12-14

2 days
2 days
2 days
2 days
26 days

Sat 06-12-14
Fri 05-12-14
Fri 05-12-14
Sat 06-12-14
Fri 05-12-14

Sun 07-12-14
Fri 05-12-14
Fri 05-12-14
Sat 06-12-14
Tue 30-12-14

5 days
1 day
52 days

Wed 10-12-14
Mon 08-12-14
Wed 01-10-14

Mon 15-12-14
Mon 08-12-14
Fri 21-11-14

Jul '14
Aug '14
Sep '14
Oct '14
Nov '14
Dec '14
J
29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 2

Anda mungkin juga menyukai