Anda di halaman 1dari 4

ENVIRONMENTAL QUALITY

REPORT:
AUGUST 2013
FOR

PROJEK MENAIKTARAF JALAN DAN JAMBATAN


DI SG.NEROK, KOTA TAMPAN AIR (MUARA)
JALAN LENGGONG/GERIK, DAERAH HULU PERAK
PERAK DARUL RIDZUAN

Project Proponent:
JABATAN KERJA RAYA
NEGERI PERAK

Prepared by:
SHAZEME ENTERPRISE (M) SDN. BHD.
No. 1, Gerai RPA, Simpang Empat
Jalan Bagan Datoh
36400 Hutan Melintang
Perak Darul Ridzuan

TABLE OF CONTENTS

Section

Title
1.0
2.0
3.0
3.1
4.0

INTRODUCTION
MONITORING PROGRAMME
RESULT MONITORING
Water Quality
SUMMARY OF RESULTS AND RECOMMENDATION
APPENDICES
-

STANDART OF DOE
A COPY OF RESULT
LIST OF PLATES

LIST OF FIGURE
Figures
1.

Title
Location of sampling Stations

LIST OF TABLES
Table

Title

Table 2.1

Description Of Sampling Stations (RW 1)

Table 3.1

Result Of Water Monitoring (RW1)

ENVIRONMENTAL QUALITY REPORT: AUGUST 2013


PROJEK MENAIKTARAF JALAN DAN JAMBATAN DI SG.NEROK, KOTA
TAMPAN AIR (MUARA) JALAN LENGGONG/GERIK, DAERAH HULU PERAK
PERAK DARUL RIDZUAN

1. INTRODUCTION
The proposed project is a construction of Projek Menaiktaraf Jalan Dan Jambatan Di
Sg.Nerok, Kota Tampan Air (Muara) Jalan Lenggong/Gerik, Daerah Hulu Perak,Perak Darul
Ridzuan. The construction period will complete in 1.5 year (18 month) times. The
Environmental Quality Report (EQR) is a requirement under condition of the document
construct as being carried out throughout the completion of the project must completed by
Shazeme Enterprise (M) Sdn. Bhd. as the main contractor for this proposed project.
The progress for overall of construction work for this project till August 2013 is about 95%
completed.

2. MONITORING PROGRAMME
2.1 Itemize inside B.Q is to conduct monthly of river water quality. The description
and location of the sampling station for the water sampling points was labelled
RW1 respectively.
Table 2.1: Description Of Sampling Stations (RW1)
STATION
RW1

LOCATION
Downstream Of Sungai Nerok river

The analysis of water samples is carries out by EWPT LABORATORY SERVICES


SDN. BHD. Which registered by Institute Kimia Malaysia (L/1029/2453/94).
Other accredited laboratories may also be engaged for the samples analysis as
and when required.

3.1 Water Quality


Water sampling from RW1 station location was carried out on 5th August
2013. The result of the sample analysed is shown in table 3.1
Table 3.1: Results Of Water Monitoring (RW1)
PARAMETER

RW1

pH Value @25 degree Celsius

6.42

BOD-5 test @20 C : mg/l

<1

Chemical Oxygen Demand : mg/l

<1

Suspended Solids (total) : mg/l

<1

Turbidity : (FAU)

37

Oil and Grease : mg/l

<1

Ammoniacal Nitrogen : mg/l

0.o2

Dissolved Oxygen : mg/l

7.69

Escherichia Coli : MPN/100ml

From the table 3.1 shown that the result of all parameter as being tested
is under DOE standart A limit and the limit of EPA Recommended for
Escherichia Coli in to the water quality is 235 count/ 100ml.
4. SUMMARY OF RESULTS AND RECOMMENDATION
The monitoring was conducted for a month of August 2013 shown that the
result for the sampling at river and silt trap outlet during construction
activities carried out at the proposed project site currently does not pose any
significant impact to the surrounding population and environment.