PROPOSED ISLA LPG CORPORATION HEADQUARTERS

14th Floor City Bank Center, 8741 Paseo de Roxas Ave, Makati City

DIVISION
SECTION

7
07110

THERMAL AND MOISTURE PROTECTION


Sheet Membrane Waterproofing

PART 1 GENERAL
1.1 PROJECT INCLUDES:
A

Toilets

Areas susceptible to leaks

1.2 QUALITY ASSURANCE


A

The Contractor shall guarantee the Work for a period agreed with the
Owner and the Project Manager from the date of acceptance. The
Contractor shall agree to repair or replace defective workmanship,
materials, and accessories during the guarantee period at no additional
cost to the Owner.

All waterproofed areas shall be given twenty-four (24) hours of flooding


test and the Contractor shall at once remedy any evidence of leakage
shown. Plug all drains; build temporary dams at opening so that water
will be 25 mm (1") deep at high point of the waterproofed area. When
directed, remove plugs from drains and mop all surfaces dry, lastly
remove the temporary dams.

PART 2 PRODUCTS
2.1 MATERIALS
A

WATERPROOFING: All applications


manufacturers Specifications.

shall

be

strictly

as

per

1 For ALL DECKS, CANOPIES, GUTTERS and other areas EXPOSED


TO WEATHER and areas susceptible to leaks Use 4.0mm
POLYBOND membrane type waterproofing.
2 For ALL TOILETS and interior areas susceptible to leaks Use
3.0mm POLYBOND membrane type waterproofing.
3 WATERSTOP: Use cementitious
construction and isolation joints.

base

waterproofing,

for

all

2.2 MANUFACTURER
Waterproofing shall be POLYBOND as distributed by ESICOR or approved
equal.

Sheet Membrane, Waterproofing


07110
V.R. Benito Architectural Services

Page 1 / 3

Date 11/06/2009
Rev. Date //

PROPOSED ISLA LPG CORPORATION HEADQUARTERS


14th Floor City Bank Center, 8741 Paseo de Roxas Ave, Makati City

DIVISION
SECTION

7
07110

THERMAL AND MOISTURE PROTECTION


Sheet Membrane Waterproofing

PART 3 EXECUTION
3.1

APPLICATION
A

Special measures must be taken to insure proper performance of the


system. Any moisture that skipped in or entrapped within the system
could cause poor adhesion, and must be removed from the substrate.
Bitumen chill quickly on a cold deck, so components of the system
must be installed rapidly, immediately mopped, well-embedded and
broomed. Bitumen must not be over-heated to compensate for rapid
cooling; hoses and buggies must be insulated.

3.2 STORAGE AND HANDLING OF MATERIALS


The Contractor or his subcontractor shall be duly responsible for the manner
of storage and handling of materials herein stated as follows:
A

Always stand roll goods on end.

Store roll goods in a dry place protected from sun and weather.

Roll out and cut mineral surface and asphalt coated roofing into sheets
and allow them to flatten before use.

Always place roll goods on clean floors or on platform in such a way as


to prevent damage and embedment of foreign matter in ends.

Handle roll goods with care. Dropping rolls on edges or ends


damages and deforms the felt, often preventing proper application.

Store cartons and drums of roofing asphalt on ends on level standing


to prevent flow from containers.

Store paper cartons of roofing asphalt protected from sun and weather
to prevent carton deterioration.

Store all roofing asphalt so it is protected from rain moisture absorbed


into the asphalt that can cause kettle foaming and poor application.

Store all materials containing solvents in dry, cool storage with proper
fire and safety precautions.
Store all emulsions in dry storage at temperature over 40 oF.

Sheet Membrane, Waterproofing


07110
V.R. Benito Architectural Services

Page 2 / 3

Date 11/06/2009
Rev. Date //

PROPOSED ISLA LPG CORPORATION HEADQUARTERS


14th Floor City Bank Center, 8741 Paseo de Roxas Ave, Makati City

DIVISION
SECTION

7
07110

THERMAL AND MOISTURE PROTECTION


Sheet Membrane Waterproofing

Heat proofing of asphalts shall be only within temperature limits


prescribed by manufacturers specifications. Over heating can cause
changes in physical properties and results in inadequate application.

Replace lids tightly on cans of material containing solvent or waterbase materials.

Do broom all felts manually, or hand mop immediately following each


felt layers installation.

Complete installation of all plies of roofing on same day. Do not install


roofing in phases.

End of Section 07110

Sheet Membrane, Waterproofing


07110
V.R. Benito Architectural Services

Page 3 / 3

Date 11/06/2009
Rev. Date //