as 0002
MRP 2 View: Procurement type E: In house Production
MRP 3 View: Strategy Group. 25: Make-to-order for configurable used for demo
MRP3 View: Availability Check 02: Individual Requirement
Classification view: Attach the variant class
Go to tab classification and select the class type Variants-300 as shown below.
The class CYCLECLASS is created with the class type 300 (Variants) for the material cycle.
Transaction Code: CL01.
2) SYSTEM
3) CYCLEMODEL
4) CYCLEPRIZE
Go to the values tab and maintain the characteristic values and description as per the requirement.
Go to the values tab and maintain the characteristic values and description as per the requirement.
Go to the values tab and maintain the characteristic values and description as per the requirement.
Now the characteristic CYCLEPRICE was created with character format. This characteristic is allowed
for multiple values.
Transaction Code: CT04.
Go to the additional data tab and maintain the table name as SDCOM (which links Sales and
Distribution with Variant configuration) and field name as VKOND.
The
Maintain the
combination.
dependency
editor
for
pricing
the
on
the
required
Also we need to maintain the configuration profile for the material CYCLE.
A configuration profile CYCLE is created for the material CYCLE and set the status as released.
Go to Transaction Code: CU41.
The necessary settings need to be maintained for the configurable material CYCLE to explore in a
sales order.
maintained
in
the
Select one of the characteristics and go for its value and press the icon assign variant condition. Like
wise we can maintain the variants for all the char. Values of the characteristics.
This is the variant as specified as medium range which should have the condition records maintained
for VA00 and VA01.
Finally maintain the condition records for the condition VA00 by using the transaction code: VK11.
The below specified conditions are active for the material CYCLE.
Now let us create a sales order. As the material is a BOM material it should explore with the sub-items
and also should give us the screen to select the required material.
The material CYCLE is exploded with the sub-items and the net value is directly calculated based on
the variants maintained for condition type VA00.
This is the complete overview of the variant configuration for a BOM material.