Start
10:00 AM
End
11:00 AM
Purpose
2014 Construction Meeting #10
Distribution/Attendance:
City of Ithaca
Downtown Ithaca Alliance
Sasaki Associates
Labella Associates
Vacri Construction / ACP
Power & Construction Group
Verizon
NYSEG Gas
DDS
NYSEG Electric
Next Time
10:00 AM
Prepared By
Jessica Buckley
Location
Commons Project Office 215 East State St Ithaca, NY
(Present at meeting unless noted: A absent)
Michael Kuo, Jessica Buckley, Nicole Mason
Tammy Baker
Susannah Ross, Eamonn Hutton (A)
Dan Walker, James Matzat (A)
Ralph Avery, Andy Breznay, Matt Thomas (A), Roberto DeVincentis (A),
Bob Belavigna - ACP
Lou Zupan, Bill Planert, Brian Planert (A)
James Edwards, Dave Comer (A)
Doug Stafford (A), Jack Barker, Dawn Stillwell
Jeff Bubb (A), Flint Brann, Andy Gana
Jack Czapranski, Dennis Kuhn A()
Item / Description
1. SITE MANAGEMENT
1.1. Vacri / ACP, PCG are to submit typical
pedestrian traffic M&P plan; include list
of signage available on site; DDSs plan
received
1.2. NYSEG Gas: Provide as-build info to the
project office on a weekly basis to
minimize future conflicts
1.3. New temp lighting plan to be issued
2. CRITICAL PATH ITEMS
2.1. HH at Aurora St installed; Coordinate with
PCG for electric panel installation; Signal
project work to be coordinated
2.2. TTC Telecom: Schedule F.O. switch over
date
2.3. TTC Alley Storm: LaBella to issue FD;
Areaway at #156 to be abandoned
2.4. 119 E State Vault Infill: Scheduled to be
backfilled (06/11)
2.5. Pavilion / Gateway Footings: Review
open items for footings; Establish start
Notes
Vacri/ ACP & PCG are to provide by email
prior to next meeting