Cluster Optimization
Regulation
Key word:
HRNO

Huawei Radio network Optimization Team

RRNO

Reliance Radio network Optimization Team

SRNO

Subcontractor Radio network Optimization Team

Chapter 1

Instruction

The purpose of this document is to define the process flow of cluster optimization
and regulation during cluster optimization. This document will guide subcontractor
how to roll out during cluster optimization.
The figuer1 show main flow of cluster optimization.

Figure 1 Main work flow

Chapter 2
2014-11-25

Work Flow and Rule


HUAWEI Confidential

Page1, Total13

Document Title

Security Level: High

Figure 2 show the cluster optimization work flow, it be separated on 3 phases. In


different phase subcontractor will finish partial work and output document.

Figure 2 Work Flow of Cluster Optimization


Huawei RNO Team will detail explain every module and flow.

2014-11-25

HUAWEI Confidential

Page2, Total13

Document Title

Security Level: High

2.1 Phase 1
2.1.1 Work flow of phase 1

Figure 3 Work Flow of Cluster Optimization phase 1

2.1.2 Start Cluster Optimization


Huawei RNO will inform SRNO start cluster optimization if 75% sites on air in this
cluster.

2.1.3 Drive Test


I. Task and Responsibility
SRNO must finish drive test for all on air sites in cluster. Test route must cover
all cells.
DT Engineer must find out problem of antenna swap and missing neighbour
2014-11-25

HUAWEI Confidential

Page3, Total13

Document Title

Security Level: High

during drive test .


Transfer Test data. DT engineer must transfer test data to DA engineer after
finish drive test.
II. Time Point
SRNO must finish DT within half day since receive information from HRNO.
DT engineer must transfer test data to DA engineer within half day.
III. Output
Please output Cluster Test Route in cluster optimization report.

2.1.4 Drive Test Analyze


I. Task and Responsibility
Analyzing Poor coverage problem or coverage holl and give effective solution.
II. Time Point
DA engineer must finish analyzing within half day since receive test data.
III. Output
Phase1 Cluster optimization Report
Problem Report

2.1.5 Antenna Reverse Check , Neighbor Optimization


I. Task and Responsibility
DT engineer must find out these problem and transfer result to DA engineer.
II. Output
Output Missing neighbour Table.

2014-11-25

HUAWEI Confidential

Page4, Total13

Document Title

Security Level: High

2.1.6 Coverage Holl Optimization


I. Task and Responsibility
Data analyze engineer must find out coverage holl area and provide effective
solution.
II. Output
Output figure of signal Rxlevel distributing into cluster Optimization report. Please
refer to cluster optimization report template for detail requirement.

2.1.7 Any problem


I. Task and Responsibility
If there is no problems in phase 1 and coverage performance meet target .SRNO
must submit Phase 1 cluster optimization report to HRNO. After check by
HRNO,SRNO will start phase 2 optimization.
If there are any problem in phase 1 and these problems need deal with by HBSS or
RRNO. Please SRNO submit problem report to HRNO.
II. Time point
SRNO must submit cluster optimization report and problem report to HRNO within
1 day after finish data analyze.

2.1.8 Problem Check


HRNO will check problem report , If no error in report it will be submit to RRNO ;
if any error in report ,Problem report will be return to SRNO until no error in report.

2.1.9 Solve hardware problem


Any hardware problem will be send to BSS engineer and must be solved by
BSS engineer within 1 days.

2014-11-25

HUAWEI Confidential

Page5, Total13

Document Title

Security Level: High

2.1.10 Solve plan problem


Any plan problem will be send to RRNO and must be solved within 3 days.

2.1.11 Transfer
HRNO receive the tuning result from BSS or RRNO, HRNO will inform SRNO
within 1 hour.
SRNO will drive test again for whole cluster, if there are not any problem during
test and coverage performance meet target . SRNO submit phase 1 optimization
report. SRNO will start phase 2 optimization after check by HRNO. And this test
result can be as test data for phase 2 .
If there are any problem during test again or not meet DT performance target ,
The process will be roll out again until there are no problem and meet coverage
performance target.
All phase 1 work shall be finished within 4 days.

2014-11-25

HUAWEI Confidential

Page6, Total13

Document Title

Security Level: High

2.2 Phase 2
2.2.1 Work flow of phase 2

Figure 4 Work Flow of Cluster Optimization Phase 2

2.2.2 Drive Test


I. Task and Responsibility
The final test data for phase1 optimization can be as the test data for phase 2.
II. Time Point
This test must be finished within half day after start phase 2 optimization.

2014-11-25

HUAWEI Confidential

Page7, Total13

Document Title

Security Level: High

2.2.3 Drive Test Analyze


I. Task and Responsibility
In phase 2 ,SRNO must finish solving problems about C/I, Rxqual, BER, and
abnormal event and ensure these performance meet target.
II. Time Point
SRNO must finish analyzing and output report within 3 day after receive the test
data.
III. Output
SRNO must output problem report and cluster optimization report.

2.2.4 C/I, Rxruql , BER, Interference ,Event Optimization


I. Task and Responsibility
Actually these problem will refer to 5 ways
Hardware Problem
TRX Problem
Antenna & Feeder
Interference
Intra-interference
Inter-interference
RF Problem
Parameter Problem
Equipment Problem
Before starting cluster optimization, BSS engineer will clear alarm and solving
80 hardware problem.
So Huawei require SRNO must solve all interference and RF problem during
phase 2 optimization.
SRNO only ensure that inter-interference existing in network, not require find out
interference resource.
II. Output
HRNO require SRNO must output distributing figure for C/I, Rxqual, BER,
2014-11-25

HUAWEI Confidential

Page8, Total13

Document Title

Security Level: High

interference and Event. And Event include 3 parts as blow.


Call Setup Failure
Drop Call
Handover Success

2.2.5 Any problem, Problem Check, Solve hardware, plan problem,


Transfer
These Process is same phase1.

2.2.6 Target

Below show performance target:


C/I Target: shall be more than or equal 12 dB
Rxqual: 95% area shall be less than or equal 4
BER shall be less than or equal 2
Call Drop Rate shall be less than or equal 2%
Call setup Success Rate shall be more than or equal 98%
Handover Success Rate shall be more than or equal 98%
Phase 2 work shall be finished within 4 days.

2014-11-25

HUAWEI Confidential

Page9, Total13

Document Title

Security Level: High

2.3 Phase 3
2.3.1 Work Flow of Phase 3

Figure 5 Phase 3 work flow


In phase 3 optimization include MOS opti and EDGE opti. Huawei will provide
support and training for subcontractor.

2.3.2 Drive Test

I. Task and Responsibility


Because call type is different , SRNO need drive test twice for whole cluster in
phase 3.One is for MOS, another is for EDGE.

2014-11-25

HUAWEI Confidential

Page10, Total13

Document Title

Security Level: High

II. Time Point


SRNO must finish drive test within 1 day after start phase 3 optimization.

2.3.3 Drive Test Analyze


I. Task and Responsibility
SRNO must finish analyze for MOS and EDGE.
II. Output
SRNO must output cluster optimization report and problem report.
III. Time Point
SRNO must finish analyze and output report within 2 day after receive test data.

2.3.4 MOS Optimization


I. Task and Responsibility
SRNO must ensure MOS performance meet target.
II. Output

2.3.5 EDGE Optimization


I. Task and Responsibility
SRNO must ensure each performance of EDGE meet target.
EDGE performance include below:
Call Drop Rate
Call setup Time
Call setup Success Rate
2014-11-25

HUAWEI Confidential

Page11, Total13

Document Title

Security Level: High

Throughput
II. Output
SRNO must output figure of call setup time ,call setup success, drop call and
throughput into cluster optimization report. Please refer to cluster optimization
report for detail requirement

2.3.6 Any problem, Problem Check, Solve hardware, plan problem,


Transfer
These Process is same phase1.

2.3.7 Target

Below show performance target:


MOS fraction must more than 3.2.
EDGE Target
Call setup time shall be less than or equal to 300ms
Call setup success rate shall be more than or equal to 98%
Drop call Rate shall be less than or equal to 2%
Average Throughput shall be more than or equal to 230kbps

2.4 Backup
After finish each phase optimization and achieve the target, Final test data and
report must be upload into server by SRNO.
Each changer for antenna or parameter must be record and Upload by HRNO
every week.

2.5 AC
If all DT performance meet target, SRNO must submit cluster optimization
report to Huawei. Then Cluster optimization will be finished.
2014-11-25

HUAWEI Confidential

Page12, Total13

Document Title

Security Level: High

2.6 Naming convention


The drive test log files shall be named as below:
YYMMDD_Cluster ID_Call Type

Chapter 3 Report and Table Template


If all DT performance meet target, SRNO shall submit cluster optimization report.

3.1 Cluster Optimization Report


Actually Cluster optimization report is aggregate of 3 phase cluster optimization
report.

3.2 Problem Report

2014-11-25