Earned Value Management is a methodology used to measure and communicate the real physical
progress of a project taking into account the work complete, the time taken and the costs incurred to
complete that work.
Earned Value helps evaluate and control project risk by measuring project progress in monetary
terms.
We spend time and materials in completing a task. If we are efficient we complete the task with time
to spare and with minimum wasted materials. If we are inefficient we take longer and waste
materials.
We also plan how we will accomplish the task. How long it will take, the resources we need and the
estimated costs.
By taking a snap-shot of the project and calculating the Earned Value metrics we can compare the
planned with the actual and make a subjective assessment of the project progress.
By extrapolating the curves and further calculation we can also estimate the costs to project
completion and the probable completion date.
The basics of Earned Value can best be shown on the ubiquitous 'S-Curve'.
The S-curve in its simplest form is a graph showing how project budget is planned to be spent over
time.
We can complicate the graph by showing the actual costs of doing the work over the same period.
And also on the same graph we can show how the value of the product of the project increases over
the same period.
The three curves on the graph represent:
Budgeted Cost for Work Scheduled (BCWS) - the budgets for all activities planned to be
completed.
Actual Cost of Work Performed (ACWP) - the real costs of the work charged against the
completed activities.
Budgeted Cost of Work Performed (BCWP) - the planned costs of the work allocated to the
completed activities. This is the Earned Value.
The BCWS curve is derived from the Work Breakdown Structure, the project budget and the Project
Master Schedule. The cost of each Work Package is calculated and the cumulative cost of completed
Works Packages is shown based on the planned completion dates shown in the Master Schedule.
The ACWP curve is found by actual measurement of the work completed. Actual costs recorded
from invoices and workmen's time sheets. This appears a daunting task but it can be very simple
with sufficient planning and organising.
The BCWP is calculated from the measured work complete and the budgeted costs for that work.
Earned Value = Percentage project complete X Project Budget
Variances
Schedule and cost variances can both be calculated in monetary terms from the data needed to
produce the S-curves.
Schedule variance is the difference between the Earned Value and the planned budget.
SV = BCWP - BCWS
Cost Variance is the difference between the Earned Value and the actual costs of the works.
CV = BCWP - ACWP
Performance Indices
Schedule Performance Index and Cost Performance Index give indications of the health of the
project. Is the project on time, in budget or what?
Schedule Performance Index is a ratio of Earned Value and the planned value of completed works. A
SPI < 1 is not good
SPI = BCWP / BCWS
Cost Performance Index is a ratio of Earned Value and the actual costs of completed works. A CPI <
1 is not good
CPI = BCWP / ACWP
Estimate At Completion
The EAC gives an idea of the final costs of a project. It takes into account the original budget
(BAC), the Earned Value and the Cost Performance Index of the already completed works.
EAC = ACWP + ((BAC - BCWP)/CPI)
Develop a Project Master Schedule showing when every Work Package will be carried out.
Allocate budget costs to each Work Package (the lowest level of WBS).
In 'PMI-Speak', the WBS is an output from the Scope Definition Phase, part of Scope Management.
And the development of the WBS to WP level is called 'decomposition'.
Develop a Project Master Schedule
A Project Master Schedule shows the calendar time it will take to complete the works. It shows all
activities and major events, like milestones and shows the logical relationship between the Work
Breakdown Structure elements (at the most detail level, this will be the Work Packages).
Allocate budget costs to each Work Package
The computation of budgeted costs will depend on the financial management systems employed by
the 'Performing Organisation'. However the two principle cost elements are labor and materials.
To assist in estimating labor costs it is usual to devise an Organisational Breakdown Structure
(OBS). Similar to a WBS, the OBS shows the resource and competence groups necessary to
complete the works. At the lowest level, the OBS shows individuals engaged on the project.
By combining the WBS and the OBS we can obtain a good visual overview of the project. A matrix
can be drawn with the WBS along the top and the OBS along the side. At each intersection, detailed
plans can be made regarding the tasks and the cost of labor.
Because the project scope has been decomposed to individual Work Packages it is a relatively simple
exercise to estimate the cost of materials from Bills of Materials and suppliers quotations.
Then total the costs for each Work Package.
Very important point:
For cost control within the project, internal to the performing organisation, actual costs to the
performing organisation is used.
Quantities installed - Physically counting the number of an item installed compared to the
planned total quantity.
Percent complete - An estimate by the actual persons responsible for completing the Work
Package.
Effort by support services - Tasks that cannot be easily quantified like logistics and the work
by project planners; which are more a function of time can be measured by time lapsed
compared to planned total time allowed.
Tied to contract terms of payment - Usually related to progress of the works except for the
initial down payment.
Two point measurement - Limited to two predefined measurement points. E.g, 50% when all
materials on site, 50% on completion of the Works Package.
Single point measurement - In a project where there are numerous small value Work
Packages, the measurement point could be 100% on completion only.
Total
20
10
20
20
10
15
100
Total
20
10
20
20
10
15
100
18
10
17
18
10
79
Spend variance
-1
15
21
Example 1
Comparing the measured (actual) spend with the baseline planned spend is of very little use without
some indication of the amount of work done.
Task A is underspending by 2; Are we saving money, or behind schedule. On the other hand, Task B
is overspent by 1; are we overbudget or ahead of schedule. While task G hasn't even started yet; at a
guess behind schedule.
Reports to management are usually at a high level, they see an underspend of 21%, congratulate the
PM and divert some of the management reserve!
Example 2
A
Total
20
15
20
10
75
18
10
17
18
10
79
Cost variance
-1
-5
-2
-4
The earned value compared with the actual cost of doing the work necessary to acheive that earned
value, provides a measure between planned and actual costs. The difference is called Cost Variance.
If the cost variance is negative, more money was spent doing the work than was planned. In the
example, the earned value of the work complete was 75 but the actual cost of doing th work was 79,
a cost variance of -4 or -4/75 = -5.3%
Example 3
A
Total
20
10
20
20
10
15
100
20
15
20
10
75
Schedule variance
-5
-5
-15
-25
Planned value compared with earned value measures the volume of the work planned against the
work completed. The difference is called Scedule Variance. If the schedule variance is negative, the
work is late. in the example the schedule variance is -25 or -25/100= -25%
Variance analysis and trend projection are two important tools used by the project manager to control
projects.
Using earned value techniques the project manager can monitor both schedule and cost variances as
well as predict trends using Cost Performance Index and the Schedule Performance Index.
The astute project manager will also calculate a set of Critical ratios at a selected level of the Work
Breakdown Structure.
One useful ratio combines the schedule progress versus actual progress with the budgeted cost
versus the actual cost.
(Actual Progress/Scheduled Progress) X (Budgeted Costs/Actual Costs)
This critical ratio is a good measure of the general health of a project as it combines both schedule
and cost in that a poor performance in one is compensated by a good performance in the other.
A critical ratio greater than 1 is good, less than one is bad.
furthermore the project manager should also set control limits on the various critical ratios. If the
ratios are outside the limits then corrective action is necessary.