REVIEW OF THE DETAILED ENGINEERING DESIGN BY SHENGLI ENGINEERING & CONSULTING COMPANY
LIMITED/KURRENT TECHNOLOGIES LTD RECEIVED ON 02 DECEMBER 2013 BY KPC
S/No
Document No.
Page
No.
Item No
Short Description
KPC Remarks
Position
Agreed
1)
All Documents
General
General
2)
All Documents
General
General
General
3)
PR PROCESS
S/No
Document No.
Page
No.
Item No
Short Description
KPC Remarks
Position
Consultant to clarify
whether the tank inlet
valves, tank vent
valves, etc. are capable
of operating at the
increased flow rates for
the new pipeline.
Consultant to verify if
the surge relief
facilities (tanks) are
adequate to cater for
the increased flow
rates under the new
project.
Consultant to indicate
what documents will
comprise the tender
documents.
Revise to read Bidder
shall allow for all
applicable Statutory
Taxes, duties and levies
applicable in Kenya and
in the country of origin.
Agreed
Differentiate
4)
General
Terminal facilities
5)
General
General
6)
7)
DD-EM-TS-PR-001-A
Opening statement
DD-LINE1R-BD-PR-001A
DD-LINE1R-BD-PR-001A
2.1 ABBREVIATIONS
2.1 ABBREVIATIONS
8)
9)
10)
S/No
Document No.
Page
No.
Item No
Short Description
KPC Remarks
Position
11)
DD-LINE1R-BD-PR-001A
14
3.1 PRODUCTS
DEMAND FORECAST:
Bullet 4
12)
DD-LINE1R-BD-PR-001A
a) Replace threat
with impact
b) Year 2013 is over.
Review and update
the status.
SLECC to review
13)
DD-LINE1R-BD-PR-001A
17
3.3 PRODUCT
SOURCING
14)
DD-LINE1R-BD-PR-001A
18
3.1 PRODUCTS
DEMAND FORECAST:
Bullet 5
S/No
15)
16)
Document No.
DD-LINE1R-BD-PR-001A
DD-LINE1R-BD-PR-001A
Page
No.
19
Item No
Short Description
KPC Remarks
Position
.discharge pressure
limits are not exceeded by
upset pipeline conditions.
Only one oil water treatment
system will be installed in PS9
for concentrate treatment.
New oil water separator
(OWS) will be installed in PS3,
PS5 and PS7.
Clarify upset
conditions
The overview is silent
on PS14.
Consultant to include
PS14 scope of works.
Clarify upset
conditions
Abnormal conditions
21
Consultant to include
design for OWS at PS1,
PS10 and PS14 which
are considered to be in
phase I. Designs for
phase II and III to
ensure that the OWS in
the respective stations
are included.
All upgrade of
firefighting facilities to
be done in Phase I in all
stations
Refer comments on
item 4.1: Steady state
analysis .
KPC: To decommission
existing and design for the
entire station at PS10.
Currently no OWS at PS1
SLECC to correct
17)
DD-LINE1R-BD-PR-001A
23
5.2: PS1
18)
DD-LINE1R-BD-PR-001A
29
19)
DD-LINE1R-BD-PR-001A
30
6.2 PHASED
IMPLEMENTATION:
Phase I
Upgrade of firefighting
systems in PS9, PS10 and
PS12.
20)
DD-LINE1R-BD-PR-001A
30
6.2 PHASED
IMPLEMENTATION:
Phase III
21)
DD-LINE1R-BD-PR-001A
36
6.3.6 PS9
Item in abeyance
Abnormal conditions
SLECC to include.
S/No
Document No.
Page
No.
Item No
Short Description
22)
DD-LINE1R-BD-PR-001A
39
23)
DD-LINE1R-BD-PR-001A
39
24)
DD-LINE1R-BD-PR-001A
40
25)
DD-LINE1R-BD-PR-001A
41
26)
DD-LINE1R-BD-PR-001A
41
KPC Remarks
all the other
documents.
Clarify pilot
operated.
No mention of flow
meters for firefighting
water system.
Consultant to clarify.
a. Clearly specify
applicable codes in
every item used in
the design.
b. Clarify if this
includes foam
handlines and
monitors in the
design.
c. Include fire
suppression system
for switch rooms.
Revise to read all new
facilities.
Connect to the existing
fire alarm system
This basis isnt
sufficient. Design as per
EPA standards defining
drainage catchment
area for the OWS and
dimensions, volume of
largest containment in
the area, highest
precipitation for
Position
SLECC: Agreed
KPC: To provide the location
of the existing fire alarm
system
SLECC to revise in
accordance with EPA
S/No
Document No.
Page
No.
DD-LINE1R-BD-PR-001A
28)
29)
DD-LINE1R-BD-PR-001A
48
30)
DD-LINE1R-BD-PR-001A
49
31)
DD-LINE1R-BD-PR-001A
49
32)
DD-LINE1R-BD-PR-001A
49
DD-LINE1R-RP-PR-002
Short Description
27)
33)
42
Item No
Drawing
KPC Remarks
Position
Agreed
SLECC to review.
SLECC to Clarify
S/No
Document No.
Page
No.
Item No
Short Description
KPC Remarks
FOR 20 PIPELINE IN
PHASE I
Whole document
34)
DD-LINE1R-RP-PR-002
35)
DD-LINE1R-RP-PR-002
11
5.1.2
36)
DD-LINE1R-RP-PR-003
23
4.2.5 Review on
capacity of existing slop
tank
37)
DD-PLN-SPC-PL-001.
1 GENERAL
38)
DD-PLN-SPC-PL-001.
3.2
39)
DD-PLN-SPC-PL-001.
3.2
Position
4No. pipelines in a
space of 13m dont
justify two lines to be
in one ditch. Line
1Replacement to be in
S/No
Document No.
Page
No.
Item No
Short Description
KPC Remarks
its own ditch. Revise
appropriately.
There are no Free
issue items in the
contract hence
Engineer will not
supply any materials.
Delete and revise the
section Appropriately.
40)
DD-PLN-SPC-PL-001.
41)
DD-LINE1R-DW-PR008-A
Drawing
42)
DD-LINE1R-DW-PR008-A
Drawing
43)
DD-LINE1R-SPC-PR001-A
44)
DD-LINE1R-SPC-PR001-A
45)
DD-LINE1R-SPC-PR-
46
17.5 RESPONSIBILITY
Position
a. Agreed. SLECC to
include pump start
sequence protection.
b. Agreed. SLECC to revise.
c. Agreed. SLECC to revise.
a. SLECC to clarify
S/No
Document No.
Page
No.
001-A
46)
DD-LINE1R-SPC-PR001-A
47)
DD-PS1-DW-PR-006-A
15
Item No
Short Description
KPC Remarks
Position
system operation
Item 2.3.2B(c)
interlock.
b. Agreed. SLECC to
include pump start
sequence protection.
4.2.2 Operator
Workstation
Drawing
S/No
Document No.
Page
No.
Item No
Short Description
KPC Remarks
Position
compliance to be
included in QA/QC
plan for the CI
dosing.
b. Agreed. SLECC to revise.
c. Agreed.
48)
DD-PS1-DW-PR-007-A
Plot Plan
49)
DD-PS10-DW-PR-002-A
Plot Plan
50)
DD-MLV-DW-PR-002
Drawing
51)
DD-MLV-DW-PR-003-A
Drawing
SLECC to review.
Agreed
a.
b.
c.
d.
Agreed.
Agreed.
SLECC to clarify.
Mandatory.
a. Mandatory.
b. SLECC to review. SLECC
to review size of valves
S/No
Document No.
Page
No.
Item No
Short Description
52)
DD-PS1-DW-WT-001-A
Drawing
53)
DD-PS3-DL-FW-001
&
DD-PS3-SCH-FW-001
54)
All documents
General
55)
DD-LINE1R-CL-FW-001
CALCULATION SHEETS
FOR FIRE PROTECTION
SYSTEM
a) Calculations for
firefighting water.
b) Cooling water calculation
c) Non-dyked spill areas
protection; application
KPC Remarks
floor finish. Should
be concrete screed
finish and
waterproof walls.
b. The size of the
valve chamber is
too big for a 20
valve. Provide 1m
clearance all-round
the valve.
a. There is no
indication where
this pipe leads to.
b. Connection to KPRL
OWS not
permitted.
Provide automated
foam protection
systems complete with
monitors and handlines
for pump shed area,
etc.
This shall apply to all
stations
Complete the risk
assessment and use it
to review suitability of
buildings locations and
safety in all the
stations.
a) Firefighting water
calculations should
not include the
proposed new
tanks. A decision
Position
from the vendor and
design the valve
chamber accordingly or
3000mmx 2500mm
whichever is smaller.
Agreed.
There is no OWS at PS1
a) Agreed.
b) Refer NFPA 11. (KPC to
clarify further).
c) Agreed to review.
d) SLECC: Has based
S/No
Document No.
Page
No.
Item No
Short Description
KPC Remarks
56)
DD-PS09-DW-FW-001A
Drawing
57)
DD-PS09-DW-FW-008A DD-PS10-DW-FW012-A
Drawing
58)
DD-PS09-DW-FW-010A
9A-M-853A/B Hydraulic
turbine
10A-M-853A/B Hydraulic
turbine
Tank farm dyked areas - there
is no foam system protection
a. Provide automated
foam system
protection c/w
monitors and
handlines.
Position
calculations on KS1967.
KPC recommends use of
NFPA 11. To be
Agreed
S/No
Document No.
Page
No.
Item No
Short Description
59)
PD-PS09-SCH-FW-001
Equipment list
Equipment list
60)
DD-PS1-DW-FW-013-A
Drawing
61)
DD-PS10-DW-FW-017A
Drawing
62)
DD-LINE1R-SPC-FW001
GENERAL
SPECIFICATION FOR
FIREFIGHTING
KPC Remarks
b. To apply to all
stations.
To be revised to
include/exclude items
after review of the
comments on
firefighting system
a. Changamwe is not
a terminal but a
pump station.
Revise.
b. The domestic
water and drainage
system are
provided under fire
fighting system for
the station.
Relocate
appropriately.
a) No foam protection
system for dyked
areas, product
reception area etc.
To be included.
b) Review foam tank
capacity to include
above
requirements.
c) Review equipment
list DD-PS10-SCHFW-001
accordingly.
a) The rating of the
pumps is
exceptionally high.
Position
Agreed
a. Agreed.
b. Agreed.
S/No
63)
Document No.
DD-PS1-DW-BR-003-A
DD-PS1-DW-BR-004-A
Page
No.
Item No
Short Description
KPC Remarks
Position
on 1+1 mode
2. PS10 6 No. each
rated at 170l/s
(612m3/hr) on 3+3
mode.
3. PS12 2 No. each
rated at 130l/s
(468m3/hr) on 1+1
mode
b) Foam water pumps
1. PS9 2 No. each
rated at 160l/s
(576m3/hr) on 1+1
mode.
2. PS10- 2 No each rated
at 220l/s (792m3/s) on
1+1 mode and to use
existing fire pumps.
3. PS12 2 No. pumps
each rated at 30l/s
(108m3/hr) on 1+1
mode and to use
existing fire pumps.
Roads
S/No
Document No.
Page
No.
Item No
Short Description
64)
DD-PS1-DW-BR-006-A
Drainage works
65)
DD-PSXX1 -DW-WT-
Series of documents
66)
Schedule of Prices
LINE1R-TD-001
67)
LINE1R-TD-001
KPC Remarks
Cabro Blocks
pavement
The design for the
waste water pipe is not
necessary. Consultant
should consider open
channel design to allow
clearance of silt during
maintenance
a. Approval by NEMA,
b. Allow for water
recycling from
downstream
chambers into
upstream
chambers for
better flexibility
and worst case
scenarios, e.g. DDPS9-DW-WT-002 &
003-As
a) CMT/CS to clarify
on prequalified
biddersin view of
Legal Notice 114
b) The method shall
be least cost and
not quality and
cost based.
Cost of tender
documents to be in
accordance the
Position
SLECC/Kurrent to seek
NEMA approval.
KPC expressed concern on
the absence of the local
partner to handle local
regulatory matters.
S/No
Document No.
Page
No.
Item No
68)
LINE1R-TD-001-A
69)
LINE1R-TD-001-A
1.1 Introduction
Short Description
KPC Remarks
procurement laws and
recent legislation.
Clarify the purpose of
this clause
a) Compliance with
Kenya Subsidiary
Legislation - Legal
Notice No 114 on
the Public
Procurement and
Disposal
(Preference and
Reservations)
(Amendment)
Regulations 2013
with regard to
participation by
local entities.
b) National
Construction
Authority
certificate for local
firms Class NCA1.
c) Tender Security to
be in accordance
with the law i.e.
should not exceed
2% of the
estimated contract
value.
Position
S/No
Document No.
70)
LINE1R-TD-001-A
Page
No.
7
Item No
Short Description
KPC Remarks
Position
Eligibility Criteria
To be reviewed for a
construction tender
and to include all legal
requirements.
Ensure compliance
with Kenya Subsidiary
Legislation - Legal
Notice No 114 on the
Public Procurement
and Disposal
(Preference and
Reservations)
(Amendment)
Regulations 2013 with
regard to participation
by local entities.
Replace workmen
compensation Act Cap
236 with Workmen
Injury Benefits Act
(WIBA) 2007
a. Include as
requirement for
evaluation of
technical proposal.
b. To be reviewed at
contract signing
Include requirement
for Safety Plan for
project activity
Provide first aid
stations as per OSHA
[2007] and subsidiary
legislation
Provide as per safety
71)
LINE1R-TD-001-A
1.3.2 Local
participation
Local participation
72)
LINE1R-TD-001-A
52
73)
LINE1R-TD-001-A
76
Clause 1 Project
Quality Assurance
System Requirements
74)
LINE1R-TD-001-A
83
Clause 12 Safety
Precautions
Safety Precautions
75)
LINE1R-TD-001-A
87
Clause 12
76)
LINE1R-TD-001-A
87
Clause 29
Fire Precautions
S/No
Document No.
Page
No.
Item No
Short Description
77)
LINE1R-TD-001-A
93
Clause 36 Transport
for the Engineer and
the Engineers
Representative
78)
LINE1R-TD-001-A
94
Clause 39 & 40
79)
LINE1R-TD-002-A
PG/M6
80)
LINE1R-TD-002-A
PG/M7
81)
LINE1R-TD-002-A
C/P/MP 2
82)
LINE1R-TD-002-A
7 to
8
m/times
83)
LINE1R-TD-002-A
C/P/MP11.10 to 11.2
KPC Remarks
plan for the project
Comply with
Procurement rules in
Kenya
Position
Transportation of all
pipe fittings, valves,
etc. to be included in
the transportation of
the mainline pipeline
for ease of payments.
Detail each crossing
individually giving its
length and any other
necessary details such
as chainage/location.
Delete items. Introduce
S/No
Document No.
Page
No.
Item No
84)
LINE1R-TD-002-A
C/P/MR 12
85)
LINE1R-TD-002-A
10
C/P CR 26
86)
LINE1R-TD-002-A
11
Short Description
KPC Remarks
Excavations
Hydraulic Protection
for major river
crossings are known
and require to have
properly designed
protections with their
individual bills of
quantities, for ease of
measurement for
payment purposes, as
follows;
1.
Voi river
2.
Athi river
3.
Any other
major rive, etc.
a. The schedule of
rates and prices
needs to be clear
Position
S/No
Document No.
Page
No.
Item No
Short Description
KPC Remarks
for excavations of
Trenches width e.g.
>0.3m and depth
<0.25m.
b. Also all civil works
including
excavations shall
need to be
measured in locally
agreed method of
measurement (e.g.
CESSM-3) or any
other acceptable
standard.
These sizes are nonstandard and are not
available in the local
market. Review the
design to suit the
appropriate bar size
available in the local
market.
Clarify revetment.
Use appropriate term
for all stations.
For all disposal of
unsuitable excavated
material consultant to
specify that the
disposal shall be to the
nearest approved
dump site.
This applies to all
stations.
For all filling to
87)
LINE1R-TD-002-A
45
C/PS3/CR 11.17
C/PS3/CR11.20
88)
LINE1R-TD-002-A
14
C/PS1/CR 8
Concrete Revetment
L=224m
89)
LINE1R-TD-002-A
42
C/PS3/CR 8.4
90)
LINE1R-TD-002-A
42
C/PS3/CR 8.5
Filling to excavations
Position
SLECC to review.
SLECC to clarify
SLECC to include.
SLECC to include.
S/No
Document No.
Page
No.
Item No
Short Description
KPC Remarks
Average thickness0.25m
91)
LINE1R-TD-002-A
all
C/PS1/MP 32
C/PS1/E 24
C/PS1/IC 46
92)
LINE1R-TD-003-A
2.1.2 Construction
Method Statements
and Procedures
93)
LINE1R-TD-003-A
94)
LINE1R-TD-003-A
excavations, consultant
to specify that the
borrow material shall
be from the nearest
approved borrow site.
This applies to both the
pipeline and the
stations.
2 years operational and
Consultant to make it
maintenance spares and
very clear in the tender
special tools for all mechanical document that the
equipment.
contractor must give a
comprehensive list of
a. Commissioning
spares for
every
equipment
b. 2-year
operating
spares for
every
equipment
The Contractor shall prepare
Change Employer to
and submit to the Employer
Engineer. Revise all
for approval
documents to reflect
the same.
At all times during site
Contractor to comply
construction, the Contractor
HSE legal and
shall comply with the
administrative
Employers site safety
framework in Kenya
procedures.
The contractor shall take a
Decommissioning
suitable method to clean up
procedure should be
of the existing Line-1 for
as per EMP in ESIA
decommissioning.
report for the project.
Position
SLECC to review
Agreed
S/No
Document No.
Page
No.
Item No
Short Description
KPC Remarks
a. Incorporate
comments under
related documents.
b. Include
comprehensive
outline of tasks.
No advance payment.
Delete all reference to
advance payment.
Position
reports approved by NEMA.
KPC to clarify
95)
LINE1R-TD-003-A
2.3.2 Firefighting
system
96)
LINE1R-TD-003-A
98
and
102
Advance payment
97)
SLOP MANAGEMENT
DD-LINE1R-RP-PR-003
A
13
4.1 Introduction
Composition of slop to
be based on 30% &
70% for products A & B
as basis for calculations
MSP has the final
boiling point elevated
by 5oC from 205oC to
210oC and not 10%, for
AGO import at 66 and
release to the
marketers at 60 hence
60C
98)
DD-LINE1R-RP-PR-003
A
14
4.2.1 Calculation on
Allowable MSP
concentration in AGO
1) Calculation formula
99)
DD-LINE1R-BD-PR-001
38
7.4 CORROSION
INHIBITOR INJECTION
PACKAGE
SLECC: To review.
100)
Hydraulic Protection
DD-PLN-DW-WE-020-A
Drawing
KP784, KP785
S/No
Document No.
101)
DD-PLN-SPC-WE-001-A
Page
No.
7
102)
DD-PLN-SPC-PL-001
50
103)
DD-LINE1R-DW-CI-001A
Item No
Short Description
KPC Remarks
Position
23.2 CONTRACTORS
RESPONSIBILITIES
a. Specifications
notes for materials
are not standard.
For example Class
35 for structural
concrete and Class
25 for Blinding
concrete may not
be economical.
b. Control room
buildings and
equipment specs
are not yet agreed
S/No
Document No.
104)
DD-LINE1R-MTO-CC001A
105)
LINE1R-TD-001
106)
107)
Page
No.
Item No
Short Description
Material takeoff
1.2.2 Mandatory
requirements:
Item F
LINE1R-TD-001
1.3.2 Local
participation
LINE1R-TD-001
10
KPC Remarks
upon since the
consultant has not
concluded the Fire
risk assessment.
More detailed
designs are
required for
control rooms as a
safety and disaster
recovery facility
with bigger safety
margin.
c. Specifications for
civil works to be
submitted.
Justify the large
painting areas for
underground piping in
the stations.
KPC to advice further
on this facility
Position
S/No
Document No.
Page
No.
Item No
Short Description
KPC Remarks
108)
109)
LINE1R-TD-001
10
110)
LINE1R-TD-001
11
1.6 Preparation of
Technical Proposal
Item 1.6.3
111)
LINE1R-TD-001
12
1.6 Preparation of
Technical Proposal
Item 1.6.4
112)
LINE1R-TD-001
12
1.7 Preparation of
Financial Proposal Item
1.7.1
113)
LINE1R-TD-001
14
Item 1.10
Evaluation of Technical
Proposal
114)
LINE1R-TD-001
16
Item 1.11.3
115)
LINE1R-TD-001
16
Item 1.11.4
Position
S/No
Document No.
Page
No.
Item No
Short Description
KPC Remarks
selection process
The formulae for determining
the Financial Score..
1.13.2 Negotiations will
include a discussion of the
Technical Proposal,
framework
Amend to reflect least
cost based.
Amend the whole
clause to suit a
construction contract
and not a service
contract.
Amend the whole
clause to suit a
construction contract
and not a service
contract.
Amend to reflect least
cost based.
Indicate where
Appendix A is provided.
116)
LINE1R-TD-001
17
Item 1.11.5
117)
LINE1R-TD-001
18
118)
LINE1R-TD-001
18
119)
LINE1R-TD-001
18
120)
LINE1R-TD-001
18
121)
LINE1R-TD-001
122)
LINE1R-TD-001
General
20
APPENDIX TO GENERAL
INFORMATION (GI)
a)
b)
c)
d)
General
Item B
Item M
Item O
Provide a clause on
mandatory site visit.
a) Items to be cross
referenced to the
General
Information.
b) Revise method of
selection to be
least cost.
c) Revise scoring
criteria to reflect a
construction
contract and not a
service contract.
d) Delete formulae for
Position
SLECC to revise
SLECC to revise to read
when the Engineer issues
notice to commence in
accordance with the
conditions of contract.
Agreed to include a
mandatory site visit
a) Agreed to revise
b) Agreed to revise
c) Agreed to revise
d) Agreed to revise
S/No
Document No.
123)
Cost Estimate
124)
Page
No.
2
Item No
125)
Electrical - General
Fault Levels
126)
Electrical - General
127)
PR PROCESS
Document Numbering
DD-EM-TS-PR-001
and DD-BD-PR-001
Short Description
1. PS1 Changamwe
Terminal and Pump
Station;
2. PS 5 Mtito Andei Pigging
& Pump Station;
KPC Remarks
financial score.
Contractor to include in
his rates the applicable
taxes and duties.
a. Number of fibre
cores to be
changed from 8
cores to 96 cores
b. Burying of FOC to
be below pipe and
200 mm away from
edge of pipe.
a. Fault Levels
supplied by M/S
Kenya power not
incorporated in
electrical design
basis.
b. Calculations have
not been provided.
Consider provision of
Civil works in Kenya
Power side of
substation like
foundation for support
structures and
equipment/metering
buildings in substations.
The Consultant to use
the correct naming of
the stations.
Position
KPC to communicate a
provisional sum for the KPLC
sub-station civil to be
included by SLECC in the
BoQ.
S/No
Document No.
Page
No.
Item No
Short Description
3. PS9 Nairobi
International Airport
Bifurcation Station
Embakasi Terminal, JKIA
Storage Terminal and
4. PS12 Moi International
Airport Birfurcation
Station
1. PS9 KPC Terminal Station
No. 9 Embakasi
2. PS10 KPC Terminal Station
No. 10 Nairobi
128)
DD-BD-PR-001
129)
DD-BD-PR-001
17
3.3 PRODUCT
SOURCING
Product Sourcing
130)
DD-BD-PR-001
21
5.1 PIPELINE
131)
DD-BD-PR-001
22
and
23
132)
DD-BD-PR-001
27
5.8 PS12
KPC Remarks
Position
a. Revise the
paragraph as PS 1
S/No
Document No.
Page
No.
Item No
Short Description
KPC Remarks
Position
is not a storage
facility but a pump
station.
b. Revise DPK to JETA1
What is the effect of
cavitations on the high
point
Pumps are not
necessarily to be
supplied by Flowserve.
133)
DD-BD-PR-001
134)
DD-LINE1R-DW-PR005A-007A
135)
DD-LINE1R-RP-PR-001A
Roughness of pipeline
inner wall
136)
DD-LINE1R-SPC-PR002-A
137)
DD-LINE1R-SPC-PR-001
138)
DD-LINE1R-DL-PL-001
139)
DD-LINE1R-SPC-PR002-A
14
Utility connection to
pumps
140)
DOCUMENT NUMBER:
DD-PS1-DAT-EL-011
and DOCUMENT
NUMBER: DD-LINEIR-
1 of
2
Inlet/outlet drawings
Provide utility connection to
pumps to allow for flushing
with service water
15 Cont. Output Rating:
3200kW (To suit driven plant)
Agreed to replace
costomer with contractor.
Replace flowserve with
vendor.
Agreed to revise the
statement
Agreed to revise
S/No
141)
Document No.
Page
No.
SPC-EL-009
PIPELINE
DOCUMENT NUMBER: 4
DD-PLN-SPC-PL-001
Item No
142)
DOCUMENT NUMBER:
DD-PLN-SPC-PL-001
143)
DOCUMENT NUMBER:
DD-PLN-SPC-PL-001
21
Short Description
KPC Remarks
During removal of
existing structures such
as fences, walls and
gates the consultant
should ensure that
photographs of the
existing walls, fences,
lawns and gates are
taken to avoid claims
from owners that the
restoration has not
been done properly.
From KP: 139.98-229.67km,
a. Clarify why the
pipeline needs to cross the
trenches within the
Tsavo National Park (both east
National Parks
and west park), and from KP:
should be deeper
426.61-434.12km needs to
than others.
cross the Nairobi National
b. BoQ to be revised
Park. The approval from
accordingly
relevant authorities shall be
obtained before construction.
Depth of pipeline trench
within National Park shall be
deeper for safety reasons as
per chapter 8.2 and relevant
drawings. And it is the
responsibility of Contractors
to follow the requirements of
the relevant authorities.
All cut-down trees shall
Clarify. The Contractor
remain the sole property of
should ensure that they
the Engineer. Trimmed trunks obtain permit to cut
shall either be stacked along
trees from KFS and that
Position
Information to Consultants
during implementation.
Agreed
a. Agreed to maintain
standard depth.
b. Agreed to review
Agreed to revise the
BoQ items accordingly.
S/No
144)
Document No.
Page
No.
Item No
Short Description
KPC Remarks
there should be
consultation with the
plot owners on the
ownership of cut down
trees.
A tentative period in
which the engineer
should approve
backfilling of trench
should be given to
avoid and/or minimize
accident.
The thickness of steel
pipe along the National
Parks is provided as
508 x 9.5.This thickness
is the same as those of
river crossings, schools
and tarmac roads.
Please clarify.
a. Clarify the
enhanced
thickness.
b. BoQ to be revised
accordingly
DOCUMENT NUMBER:
DD-PLN-SPC-PL-001
41
15 BACK-FILLING OF
THE TRENCH
DOCUMENT NUMBER:
DD-PLN-SPC-PL-001
12
4.4.3 Detailed
distribution of steel
pipe
145)
Line 1R Corrosion
Control
DD-LINE1R-SPC-CC-001
23
146)
DD-LINE1R-SPC-CC-002
c) LITTLE
Colour: Red
Colour: Cream
a) Clarify
b) Include training for
KPC Engineers in
the scope of supply
Position
Agreed
a. Agreed to remove
ambiguity since in some
instances the client is
the contractor when
procuring from a
vendor.
S/No
Document No.
Page
No.
Item No
d) 6.2 Tags
e) 9.1 Corrosion
Coupons (CC)
f) 9.2 Electrical
Resistance
Probe(ER)
147)
DD-LINE1-SPCH-CC-001
148)
PLN
DD-PLN-SPC-CC-001
149)
150)
Short Description
Item 5
Item 5: Survey
Chainage
5&7
Survey
KPC Remarks
Position
c) Give a % numerical
value
b. Agreed
c. SLECC to provide a
numerical figure.
d. Agreed to provide
separate tags.
e. Agreed to make it clear
that the contractor shall
provide the inserting
and retrieval tools as a
complete package.
d) Each ER and CC
e) To be supplied
complete with
inserting and
retrieval tools
f) To be supplied
complete with
inserting and
retrieval tools, data
downloading
equipment and
manipulation
software
One set for each type
(CC & ER)
Give GPS coordinates
corresponding to the
chainage
Within the consultants
scope and findings
should be tabulated
and reported to the
Engineer in the DED
a. CP Station: Provide
detailed design for
ground bed
locating, sizing and
TR capacity for
Engineers
approval.
b. Thereafter, locate
Agreed
Agreed.
S/No
Document No.
Page
No.
Item No
151)
152)
10
153)
11
Item 9.5.1
Item 9.6.3, 9.6.4 &
9.6.5
Item 9.7.4
154)
13
17
Short Description
KPC Remarks
SLECC recommendation
Cable to Pipe Connections
solid-state de-coupler
Current density for 3LPE of
10A/m2
Cased Crossings
Position
Agreed
Agreed. Use the cost
effective method.
Agreed
S/No
Document No.
Page
No.
155) DD-PLN-SPC-CC-002
156)
16
Item No
Short Description
157) DD-PLN-SPC-CC-003
Cross-head or annular
extrusion technique
3LPE heat shrinkable
158) DD-PLN-SPC-CC-004
159)
Document Title
Appendix A: Item 1
PATING
Coating Schedule
Scope
CP commissioning Procedure
160) DD-PLN-SPC-CC-004
17
KPC Remarks
These are missing
in all the
documents.
As agreed earlier in
PED: normal & soft
padding
As agreed in PED:
extrusion technique
Specify DFT for
copolymer adhesive or
be explicit on DD-PLNSPC-CC-002
Correct to painting
Explain the alternative
Document not
considered adequate in
addressing precommissioning data.
No reference to:
a. Effectiveness of
temporary CP
before ICCP
connection;
isolation of SA
b. Effectiveness of
electrical isolation
c. Holiday test
records
d. Soil resistivity
records
e. 3rd party
crossings/parallelis
m effects as
measured
Position
Agreed
Wrong statement. To be
deleted.
Agreed: SLECC to improve
the document.
S/No
Document No.
Page
No.
Item No
Short Description
KPC Remarks
f.
162) DD-PLN-MTO-CC-001.A
163) DD-PLN-MTO-CC-003.A
Heat shrinkable
164) DD-PLN-MTO-CC-004.A
165) DD-PLN-SPC-PL-001
1 &4
166)
167)
Item 1 &3.2
Whole doc
35
Item 10.4
Natural/native
potential
measurements
g. Etc.
Purpose and
installation details
ambiguous/not clear
for the application.
Distinguish Junction
boxes and test stations
for each purpose.
Generate detailed drgs
for current drain points
to the pipeline, etc as
per the detailed design.
Should be based on
detailed design for CP
station capacity and
ground bed sizing
No mention of epoxy
and copolymer
quantities
Segregate for each
paint scheme colour
Position
Clarify underlying
reason(s) for either and
both
Simply specify
specify
S/No
168)
169)
Document No.
Page
No.
5
Item No
Short Description
KPC Remarks
Position
Item 3.2-1
DD-PLN-SPC-PL-001
Item 4.4.2
Contradiction and
dismissal:
no mention of design
life of the pipeline,
no clear CI design
dosing scheme and
costs based on water
content data in
product,
no regular pigging
design and interval for
the water
displacement,
No CA calculation and
additional steel cost,
no clear final holiday
level estimated for the
installed pipeline and
the CP design
correlation at end of
life of the pipeline.
The total pipeline
corrosion control
scheme not holistic for
common goal.
No reason for the
rounding off of the wall
thickness from
calculated hoop stress,
T. The design basis, DDLINE1R-BD-PR-001-A,
item 7.3 not consistent
with the quotes.
Consultant to clarify
S/No
Document No.
170)
171)
172)
173)
174)
175) DD-PLN-DW-PL-006
176) DD-PLN-DW-PL-008
Page
No.
44
Item No
Item 16
Short Description
KPC Remarks
Position
Agreed.
Agreed
Agreed
Agreed
Agreed SLECC to review
Agreed type 2
S/No
Document No.
Page
No.
Item No
Short Description
177) DD-PLN-CL-CC-001.A
Item 4
178) DD-LINE1R-SPC-MA003
13
Item 9
179) DD-LINE1R-BD-EL-001
14
Item 9.1
180) DD-LINE1R-BD-IN-001A
KPC Remarks
thickness and special
cases
Design life for CP or for
the installed pipeline?
Clarify
What documents?
Please show.
1. Clarify if meant
Main Pump
Motor.
2. No description of
VFD and an
outline of how it
works in the
document.
3. How the control
philosophy
interlinks with I &
C.
4. No specification
and data sheet
docs for the
proposed VFD
Page 9 of 20. SLECC has
proposed the following
control modes, i.e.
Remote (SCADA), Local
remote (HMI), Local
remote (touch screen),
Local equipment
control. The following
mode should be added:
Local control from PCS
Position
Agreed
S/No
Document No.
Page
No.
Item No
Short Description
181) DD-LINE1R-BD-IN-001A
11
182) DD-LINE1R-BD-IN-001A
13
183) DD-LINE1R-SPC-IN-002
184) DD-LINE1R-SPC-IN-002
Item 8.2
185) DD-LINE1R-SPC-IN-002
186) DD-LINE1R-SPC-IN-002
25
KPC Remarks
Panel by use of Push
buttons (e.g. Pump
start, pump load, etc).
Page 11 of 20. Add
item 5.1.4. Local Panel
control. This level of
control provides direct
control of pumps,
valves, etc from the
PCS panel by use of
push buttons.
Page 13 of 20. Item
6.20. An ESD shall be
initiated by. Add
Flame detection in
pump shed.
Add to the
specifications the
statement The Pump
monitoring system
shall have internal
safety barriers.
On item 8.2, add the
statement An ESD
shall be initiated by
flame detection in the
mainline pump shed.
Add the specification:
The Preferred PLC
Control system- 1.
Schneider 2. Allen
Bradley.
On documentation,
page 25 of 27, there is
a statement An
Position
Agreed
Agreed.
Agreed
Agreed to correct
S/No
Document No.
187) DD-LINE1R-SPC-IN-003
188) DD-LINE1R-SPC-IN-004
189) DD-LINE1R-SPC-IN-006
Page
No.
Item No
Short Description
190) DD-LINE1R-SPC-IN-006
191) DD-LINE1R-SPC-IN-007
192) DD-LINE1R-SPC-IN-009
Specification for
Instrumentation installation
KPC Remarks
operation and
maintenance manual
giving all information
required to operate
and maintain the
interface detector shall
be submitted by the
supplier. Interface
detector should be
changed to Process
control system.
Add : Preferred makes1. Rotork.
Add preferred makes:1. Rotork.
All references to
explosion proof class
Exd should be EExd.
Preferred makes:
a. Rosemount
b. Siemens
c. ABB
d. Honeywell
Fire alarm panel: To
comply with standards
EN-54, and NFPA 72.
a. Item 6.2 lists free
issue items. Delete
as there shall not
be free issue items
b. - Item 6.3: Please
delete the word
Morendat from
The scope of work
for the
Position
Agreed
Agreed
Agreed
Agreed
Agreed
a. Agreed
b. Agreed
S/No
Document No.
Page
No.
Item No
Short Description
193) DD-LINE1R-SPC-IN0011
194) DD-LINE1R-SPC-IN0012
195) DD-MLV-DW-PR-004A
Pig signaller
196) DD-MLV-DW-PR-015-A,
013A, 012A
197) DD-MLV-DW-PR-015-A,
013A, 012A
BLOCK VALVE
Block Valve KM 153.5
198) DD-PS1-MTO-PR-002-A
Item 34
199) DD-PS1-SCH-PR-001-A
Item 14
Re-Injection Pump
KPC Remarks
instrumentation
installation of
Morendat Pump
station.
This item should
undergo a factory
acceptance test
witnessed by owners
Engineers.
This item should
undergo a factory
acceptance test
witnessed by owners
Engineers
Remove: TO
MORENDAT P.S from
drawing labeled: PLAN
ON INSPECTION
CHAMBER.
Put chainage: KM in
drawing.
Delete this chamber
since isolation will be
from KM 172 (PS4) and
137.37.
Block valve KM153 will
not be accessible at
night.
Clarify comment:
including backstop
Demonstrate how the
capacity and head of
re-injection pump has
been arrived at
Position
Agreed
Agreed
Agreed
Agreed
SLECC to review the location
and explain the necessity of
the block valve at this
location.
SLECC to adjust accordingly
S/No
Document No.
Page
No.
Item No
Short Description
KPC Remarks
Position
(Q=10M^3/HR,
h=600m).
LINE1R-TD-001
200)
30
201)
30
202)
31
203)
31
204)
TENDER DOCUMENTS
FORPROCUREMENT,
CONSTRUCTION,
TESTING
ANDCOMMISSIONING
Form of tender
Performance guarantee
The tender, together with
your written acceptance
thereof, shall constitute a
binding contract between us.
Appendix to form of
tender
205)
Conditions of contract
Part II
Item 1.1a(v)
206)
1.1b(i), (iv)
207)
4.1
208)
5.2
Engineers representative is
SLECC
BOQ replaced with schedule
of prices
Agreed
Agreed
Agreed.
209)
210)
6.2
6.3
provided to or deleted
Delete the words "drawings
or" in lines 3 and 4
211)
6.4
212)
6.5
213)
7.1
214)
7.2a
215)
8.1
216)
11.1
217)
12.1
contractors general
obligations to be after
conditions of contract.
Reinstate the deletion
Reinstate the deletion
Agreed
1. KPC position is for SLECC
to retain words
"drawings or" in lines 3
and 4 of clause 6.3. This
is because the contract
is not an EPC contract as
SLECC are the designers.
2. SLECC position is to
delete the words
"drawings or"
3. Agreed SLECC to retain
the words.
Agreed
218)
15.2
219)
220)
19.1(xv)
19.1(v)
221)
55.1
222)
55.2
223)
58.4
224)
60.8
225)
60.11(a)
226)
60.11(b)
227)
70.1
228)
80(1)
229)
80(2)
230)
80(3)
231)
80(4)
instead of schedule of
prices
Replace with Engineers
Board of Kenya (EBK)
Agreed
Delete as this is
repeated in
contractors general
obligations
Delete as this
contradicts the
consultancy contract.
Delete as this
Agreed
Agreed
Agreed
Agreed
Agreed
Agreed
Agreed
Agreed
Agreed
Agreed
contradicts the
consultancy contract.
Delete as this
contradicts the
consultancy contract.
Programme to be submitted
within 14days
232)
80(5)
233)
80(6)
234)
81
235)
Contractors general
obligations
Clause 2
236)
Involvement of Engineer in
vetting the procurement
process of the contractor
237)
O&M manuals to be
submitted where required.
238)
15
Agreed
Delete
Delete
Agreed
Agreed
Agreed
239)
18
240)
23
241)
31
242)
33
243)
34
Engineers
Representative
Contractor shall provide one
quickset level, tripod, a multimeter and torch, 5 meter
staff, one 30 meter steel tape,
one 30 meter linen tape, 6
ranging rods for the exclusive
use of the Engineer.
The Contractor shall provide
at each site two four-wheel
driven SUVs with dedicated
drivers for the transportation
of the personnel of the
Engineers Representative
The levels of benchmarks shall
be based on local harbor
datum.
Signboard to be display, at the
junction of the access road
leading to the Site of the
Works
Office for Engineer and
Engineers Representative
Agreed
Delete as it contradicts
the contract.
Agreed
Clarify meaning
1. Specify
location for the
offices
including the
main site
management
office.
2. Specify rating
for the 4
desktops.
Laptop to be i5
processor and
not intel
Pentium.
244)
35
245)
36
246)
247)
Form of Agreement
3. Conference
rooms to
accommodate
20 people
Delete para on
consultants
accommodation.
Delete all.
Agreed
Agreed
Recommend
1. Contract
agreement
2. For of tender
3. Appendix to
form of tender
4. Conditions of
contract part II
5. Conditions of
contract Part I
6. Negotiation
minutes
7. Specifications
8. Drawings
9. BOQ
10. Schedule of
rates and
dayworks
11. Schedules and
annexes
248)
Signing by parties
249)
Tender Security
250)
251)
Performance
guarantee
252)
253)
254)
Advance Guarantee
LINE1R-TD-002
255)
256)
257)
258)
Agreed
Agreed
Agreed
Agreed
Agreed
SLECC to review
Agreed
Agreed
Agreed
Agreed
259)
PG/M7
260)
Add PG/M7
261)
Add PG/M8
262)
263)
Pipeline mechanical
bills 1.3
C/P/MP7
264)
C/P/MP8
265)
C/P/MP9
Ball gear
266)
C/P/MP11.1 to 11.4
Crossings in m/times
267)
C/P/MP11.5
268)
C/P/MP11.10 to 11.12
269)
C/P/MP11.1 to 11.9
Crossings
270)
C/P/MR13
Engineer
Delete as there will be
no free issue items
double cabs.
Agreed
Agreed
Agreed
Agreed
Agreed that railway should
not be cut and SLECC to
propose proper method.
Agreed
271)
General
272)
C/P/MP16
273)
274)
C/P/MR12 to MR15
C/P/MP17
275)
C/P/MP18
276)
1.4Provisional and
Prime Cost Items
MR
Undertake non-destructive
testing of process, drain vent
and firewater piping in
accordance with the Project
Specifications
Supply and install cathodic
protection, all in accordance
with specifications and
detailed drawings
Allow US$ 1,000,000.00 (One
Million) for payment to KPLC
for power
supply/upgrade
277)
General
Electrical
278)
Tender Document
Electrical
Agreed
Agreed
Agreed
SLECC to include
Supply of PS 10
(66KV/3.3KV
280)