PREPARED BY:
Dr. Eng. Besim ISLAMI
RES & EE Consultant
Dr. Eng. Edmond HIDO
Albania - EU Energy Efficiency Centre
November 2011
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Contents
1
Summary ................................................................................................................................ 3
2
2.1
2.2
Introduction............................................................................................................................ 5
Background.............................................................................................................................. 5
The Project Development Process .......................................................................................... 7
5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
6
6.1
6.2
6.3
8
8.1
8.2
Environmental Benefits....................................................................................................... 39
10
11
11.1
11.2
11.3
11.4
Page 2
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Summary
The average energy consumption for the period 2008 - 2010 of Elderly House (Social Care
Establishment) is approximately 63,859 kWh/year for heating of rooms and 52,987 kWh/year for
electricity, totally 156.42 kWh/myear.
Based on the information gathered during inspection of this building, the existing condition is very
different from the standard values based on the Albanian Energy Building Code and other design
values. The actual room temperature was much lower than what is required by the above norms.
The reason is that since there was not sufficient quantity of oil, the boiler has been working only for
14 hours a day and not for 24 hours a day as is required for a comfort heating. Consequently, the
average indoor temperature during the day has been about 17 C. This situation needs to be
improved, and as basis for evaluating possible energy efficiency measures, the Baseline is
calculated using room temperature as required by the Albanian Building Standard (see Chapter 4).
The Energy Auditing has identified a considerable energy efficiency improvement potential for this
building.
The energy savings potential for identified energy efficiency and renovation measures is
summarised in the following table, with ranking of measures according to their profitability (NPVQ):
EE Potential - Energy Audit
Elderly House
EE measures
Investment
[]
1.
2.
3.
4.
747 m
Conditioned area:
Net savings
[kWh/yr]
[/yr]
Payback
NPVQ
[year]
14,710
78,417
7,827
1.9
3.94
40
854
87
0.5
2.80
9,830
14,854
1,483
6.6
0.40
11,610
15,922
1,589
7.3
0.32
36,190
110,047
10,986
3.29
By introducing operation and maintenance and energy monitoring, we will avoid increase of the
energy consumption after implementation of the energy saving measures, keep the operation
costs, incl. energy, as low as possible on a permanent basis, and prevent large and expensive
repairs. The investment costs for Operation & Maintenance and Energy Monitorting system will be
1,700 Euro.
5.
1,700
2,800
279
6.1
0.27
The recommended measures with total investment of 37.890 will be paid back in 3.36
years.
For the investment and savings to be valid, all measures should be implemented as one project.
The figures have an accuracy of 15 %.
Page 3
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Unit
Present (baseline)
After measures
Savings
Electricity
kWh
58,587
44,754
13,833
Oil
kWh
107,228
11,014
96,214
The reduction of CO2 emissions achived by implementation of all measures is 175.68 tons/year.
It is recommended to introduce tailored operation and maintenace system and routines to ensure
suitable operational conditions in the building and to keep the operation costs, including energy, as
low as possible on a permanent basis. This should include energy monitoring routines based on
ET-curve and manual, and training of O&M personnel.
The project organisation can start in January 2012. The project implementation can start in June
2012 and will be completed within August 2012.
Dr. Eng. Besim ISLAMI and Dr. Edmond HIDO / the Albania-EU Energy Efficiency Centre (EEC),
as the EE consultants, can offer a turnkey contract for the whole project.
Page 4
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Introduction
2.1 Background
Dr. Eng. Besim ISLAMI and Dr. Eng. Edmond HIDO (the Albania-EU Energy Efficiency Centre EEC), as the EE consultants, have conducted this Pilot Energy Audits according to the Albanian
standard methodology. In addition to this, they have used also the calculation methods and tools
provided by the Energy Saving International AS (ENSI) of Norway.
The ENSI EAB Software was used for the energy calculations (EAB = Energy Auditing of
Buildings). The ENSI EAB Software is a well-know method and tool and is widely recognized
within the EU Member States. In addition, this tool is used to provide the calculations required by
the EU Directive on Energy Performance in Buildings (2010/31/EU).
The ENSI EAB Software allows to calculate:
Baseline is a mix of actual/existing situation and key design values (for instance room
temperature),
Page 5
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
the dining room, the laundry, toilets and shower-baths, and two sleeping rooms. In the second
floor of this building there are the sleeping rooms, toilets and shower-baths as well as a medical
room. The second building is a two floors building. In the first floor there are two rooms used for
physical training/exercises and massage for handicap people. In the second floor, there are offices
of this institution and two livingrooms. Both buildings are connected through a corridor, which is
used also as rest or meeting area. The main building is built in the 1932. The walls of the first
floor are made of rocks, while the walls of the second floor are made of bricks. The building has a
pitchid roof, which has been refurbished in the 1999. At the beginning, the destination of the
building has been a vila, while during 1970 it has been adopted as a elderly house. The second
building is relatively new and its walls are made of bricks. This institution is surrounded by a high
fence and has a small garden with trees. This garden is used as a rest area from about 50
elderly/handicap people. The staff of this institution consists of 24 people. In the Figure 1 (page
13) it is shown a schematic layout of the premises and the garden of the Elderly House. In the
Figure 2 (page 14) it is shown a schematic layout of the first floor of the main building of the
Elderly House, the connecting corridor and the second building. In the Figure 3 (page 15) it is
shown a schematic layout of the second floor of the main building of the Elderly House.
The aim of the project is to reduce the energy costs, improve the indoor environment, ensure more
efficient operation and maintenance of the building and the technical installations, etc.
Page 6
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Project Identification
2.
Scanning
Project
Identification
Scanning
Improvement
Potential
3.
Simplified
Auditing
Energy Audit
Detailed Auditing
with guarantee
Business Planning
4.
Business Plan
5.
Implementation
6.
Operation
Project
Management
Maintenance
Implementation
Training
Operation
Energy
Monitoring
Page 7
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Project Organisation
Name of project/building/site:
Address:
Contact person:
Phone:
Role in the project:
Building owner:
Contact person:
Address:
Phone:
Fax:
Role in the project:
Municipality of Korca
Niko PELESHI
Blvd. Republika
082 42004/43353
082 42082/43212
Mayor of the municipality
EE consultant:
Contact person:
Address:
Phone:
Fax:
Role in the project:
The following Standards and Regulations are relevant for energy efficiency and renovation
measures:
Norms, regulations, design and constructions conditions, for heat generation and energy
saving in dwellings and public buildings, 2003
Page 8
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
The Inspection Checklist for Energy Auditing of Buildings provides useful information for describing
the existing situation of the building, technical systems and operation patterns for the Elderly
House in Minicipality of Korca.
Social Care
Year of construction
1932
Weekdays
Saturday
Sunday
Occupancy schedule
24 hours
24 hours
24 hours
(hours/day)
Heating schedule
14 hours
14 hours
14 hours
(hours/day)
Number of occupants (for hospitals, schools, etc. please include the number of patients, respectively students, etc.)
Permanent inhabitants/staff
persons
74
Temporary inhabitants/staff
persons
Norms
17
20
13
17
Page 9
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
911.7 m
Conditioned area
747 m
Total volume
3,095 m
Conditioned volume
459.7 m
Number of floors
2,455.6 m
2
External walls
General evaluation of the condition of the walls
Total area external walls
Wall construction W1
Orientation
Wall area (m)
Wall construction (W1)
U-value (W/mK)
Wall construction W2
Orientation
Wall area (m)
Wall construction (W2)
U-value (W/mK)
Wall construction W3
Orientation
Wall area (m)
Wall construction (W3)
U-value (W/mK)
Wall construction W4
Orientation
Wall area (m)
Wall construction (W4)
U-value (W/mK)
Acceptable
735.6 m
U value (average)
Insulation
Rock
N
14.8
Rock
2.2
NE
E
44.5
Rock
2.2
SE
Insulation
Brick
N
66.0
Brick
1.3
NE
E
44.1
Brick
1.3
SE
NE
E
62.9
Brick
2.6
SE
Wall construction W5
Concrete
Orientation
Wall area (m)
Wall construction (W5)
U-value (W/mK)
N
12.0
Concrete
3.6
S
48.7
Brick
2.6
Insulation
Brick
N
13.4
Brick
6.0
S
64.0
Brick
1.3
Insulation
Brick
N
55.8
Brick
2.6
S
53.6
Rock
2.2
NE
SE
S
13.4
Brick
6.0
Insulation
NE
SE
2.07 W/mK
No
SW
W
31.1
Rock
2.2
NW
W
50.3
Brick
1.3
NW
W
99.8
Brick
2.6
NW
NW
NW
No
SW
No
SW
No
SW
No
SW
Page 10
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Photo 1: Faade and Entrance of the Main Building of the Elderly House
Page 11
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Page 12
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Figure 1: Schematic Layout of the Premises and Garden of the Elderly House
1.
2.
3.
4.
5.
The main building, a two floors building that is facing to the west, where are livingrooms.
The second building, a two floors building, where are offices of this institution, two
livingrooms as well as two rooms used for physical training/exercises and massage for
handicap people.
The oil boilers room and reservoir of oil.
The laundry.
The garden of the Elderly House.
Page 13
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
3.
4.
The main building, a two floors building that is facing to the west, where are livingrooms.
The second building, a two floors building, where are offices of this institution, two
livingrooms as well as two rooms used for physical training/exercises and massage for
handicap people.
The oil boilers room and reservoir of oil.
The laundry.
Page 14
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Figure 3: Schematic Layout of the Second Floor of the Main Building of the Elderly House
Page 15
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Windows
General evaluation of the condition of windows
Total area windows
Orientation
Material
Acceptable
81.8 m
Type 2
U value (average)
Size A x B
Area
Q-ty
m2
5.0 W/mK
Joints
U value
AL
1G
1.2x1.5
1.8
W/m2K
5.0
AL
1G
1.0x2.0
2.0
5.0
AL
1G
1.7x2.0
3.4
5.0
AL
1G
1.0x2.0
2.0
5.0
AL
1G
0.9x2.0
1.8
5.0
AL
1G
0.9x2.0
1.8
5.0
AL
1G
1.0x2.0
2.0
5.0
AL
1G
2.0x1.7
3.4
5.0
AL
1G
1.2x1.5
1.8
5.0
AL
1G
0.9x2.0
1.8
5.0
AL
1G
1.0x2.0
2.0
81.8
5.0
Total
Material 1
Aluminium (Al)
Type 2
Page 16
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Page 17
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Page 18
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Doors
General evaluation of the condition of windows
Total area of doors
Orientation
E
S
S
S
W
Total
Material
AL
AL
AL
AL
AL
Acceptable
21.7 m
U value (average)
Type 2
Size A x B
Area
Q-ty
1G
1G
1G
1G
1G
m
1.4x2.2
1.7x2.5
2.0x3.0
1.0x2.2
2.1x0.9
m2
3.1
4.25
6.0
2.2
1.9
21.7
n
1
2
1
2
1
5.0 W/mK
Joints
U value
W/m2K
5.0
5.0
5.0
5.0
5.0
Page 19
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Pitchid Roof
General evaluation of the condition of the roof
Total roof area
Roof type
Material
type
Acceptable
387 m
U value (average)
Insultaion Insul. thickn. Slab thickn. Avg. temp.
type
m
m
C
1.00 W/mK
Area
U
m
W/mK
387
1.00
Floor (with heat losses to outdoor air, though ground or unheated basement)
General evaluation of the condition of the floor
Total floor area
Acceptable
524.7 m
U value (average)
0.35 W/mK
Type of floor
Type of floor
Floor type 1
Slab on ground
Floor type 2
Suspended floor/Unheated
basement
Floor type 3
Heated basement
Page 20
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Double-pipe
Good
RIELLO
84
Iron
No
Radiators/30
No
Electrical heaters
Quantity
pcs
Capacity
Type of fuel
1996
Oil
1.2 kW
Photo 10: View of the Radiator of the Space Heating System of the Elderly House
Page 21
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Photo 11: View of a Radiator and Bared Heating Pipes of the Space Heating System of the
Elderly House
Page 22
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Installedcapacity
Simult. power
Operation period
kW
W/m
h/week
Pumps, heating
0.40
0.535
50
Fuel pumps
0.18
0.241
50
Total
0.58
0.776
100
Page 23
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
1999
460
Poor, Acceptable
70
Photo 12: View of the Electrical Boiler for Hot Water in the Elderly House
Page 24
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Photo 13: View of the Small Electrical Boiler for Hot Water of the Elderly House
Page 25
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Luminaries
Incandescent
Efficient lighting
Efficient lighting
Total
Quantity
pcs
15
22
10
Installed capacity
kW
1.125
0.264
0.320
1.709
Simultanious power
W/m2
1.234
0.289
0.351
1.874
Lighting
Average power demand
Operation period
Operation period
1.874 W/m2
42 h/week
52 weeks/year
Photo 14: View of a Non Efficient Light in a Office of the Elderly House
Page 26
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Photo 15: View of the Lights in Connection Corridor of the Elderly House
Photo 16: View of the Efficient Lights in a Livingroom of the Elderly House
Page 27
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Photo 17: View of the Efficient Lights in a Bedroom of the Elderly House
Page 28
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
5.7 Various
Various exploitable
Quantity
pcs
Computers
Copiers
Other (TV, radio)
Other (Printers)
Total
4
1
7
2
Installed capacity
kW
1.60
0.40
4.20
0.60
6.80
Average power
W/m2
1.755
0.438
4.606
0.658
7.457
Comments
Various exploitable
Average power demand
4.55 W/m2
30 h/week
Operation period
Operation period
Various unexploitable
Washing machines
Drier
Total
52 weeks/year
Quantity
pcs
4
1
Installed capacity
kW
4.80
6.00
10.80
Average power
W/m2
6.43
8.03
14.46
Comments
Various unexploitable
Average power demand
Operation period
Operation period
14.14 W/m2
30 h/week
52 weeks/year
Page 29
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Photo 18: View of the Washing Machines and the Drier of the Elderly House
Page 30
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
5.8 Outdoor
Outdoor
Outdoor lighting
Installed
capacity
kW
0.120
Average
power
kW
Operation period
h/week
56
Comments
weeks/a
52
Page 31
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Energy Consumption
Electricity
Energy costs
Energy consumption
Specific consumption
7,612.00
61,123.00
67,969.00
81.82
90.99
Energy costs
Energy consumption
Specific consumption
Water consumption
Average Energy
consumption
2008 - 2010
Energy costs
Energy consumption
Specific consumption
Electricity
Oil
13,252.00 /year
129,092.00 kWh/year
172.81 kWh/m
2,809.00 /year
Total
5,150.00
4,345.00
9,495.00 /year
53,780.00
58,259.00
112,039.00 kWh/year
71.99
77.99
3
2,228.00
Electricity
Oil
4,281.00
60,859.00
48,550.00
81.47
64.99
3
1,791.00
Electricity
Oil
5,412.00
58,587.00
58,259.00
78.43
77.99
0.1077
1,949.00 /year
11,138.00 /year
109,409.00 kWh/year
146.46 kWh/m
2,404.00 /year
Total
5,882.00
2,381.00
149.98 kWh/m
Total
6,857.00
Water consumption
Present tariffs
3,126.00
Water consumption
Year 2010
Total
5,640.00
Water consumption
Year 2009
Oil
11,294.00 /year
116,846.00 kWh/year
156.42 kWh/m
2,387.00 /year
30.09.2009
For calculating the price of 0.0998 /kWh, we have used the average 2008 - 2010 quantities of
kWh for each of the energy source (electricity and oil) consumed for space heating multiplied by its
respective present tariff.
The electricity and fuel oil consumption are used in order to meet different services during the last
three years, and so it is possible to see the trends in energy consumption in total. In order to
describe the energy consumption, the Energy Auditing Team has visited the Helderly House and
has opened the recorded financial book in order to read the energy consumption for different
energy commodities as has been already described in the respective Chapter.
Page 32
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Oil
Calorific value
9.71
Unit
kWh/liter
The present tariffs and calorific values are used in the further calculations.
Electricity
Oil
Water
Year 2008
0.0923
1.087
0.898
Price
Year 2009
0.0958
0.90
0.875
Year 2010
0.113
0.97
1.34
Unit
/kWh
/liter
/m3
Page 33
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Baseline is a mix of actual/existing situation and key design values (for instance room
temperature),
Page 34
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Table 1: ENSI EAB Software - Heating before and after implementation of EE measures
Page 35
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Heating
Ventilation
DHW
Fans & Pumps
Lighting
Various
Cooling
Total
Actual
Actual
Before EE
After EE and
Calculated
Measured
Baseline
renovation
[kWh/myear]
[kWh/myear]
[kWh/myear]
[kWh/myear]
111.3
0.0
26.0
2.4
4.1
29.2
0.0
173.1
85.5
0.0
70.9
0.0
156.4
162.7
0.0
26.0
2.4
4.1
29.2
0.0
224.4
17.7
0.0
26.0
2.4
1.8
29.2
0.0
77.1
Note: The average yearly energy consumed for heating of the building, provided by oil boiler, and
electricity, during three years 2008 - 2010, was estimated to be 85.5 kWh/m (63,860.00 kWh).
This consists of :
electricity used for heating
oil used for heating
According calculations of the actual building geometry, the total heating area is about 747 m.
Note: For outdoor lighting, the actual consumption is 349 kWh/year.
The Actual and Measured Columns in the above table illustrates the situation when the energy
consumption, for the representative (average energy consumption for the period 2008 - 2010), is
measured only for the space heating (supplied by oil & electricity) as well as the lighting, domestic
hot water and various exploitable (supplied by electricity) and not for each budget item separately.
There is no ventilation and cooling in this building. During the whole period, the building was not
heated enough to keep proper room temperature.
Page 36
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
The energy savings potential for identified energy efficiency and renovation measures is
summarised in the following table, where the measures are ranked according their profitability
(NPVQ):
Investment
Net savings
[]
1.
2.
3.
4.
747 m
Conditioned area:
[kWh/yr]
[/yr]
Payback
NPVQ
[year]
14,710
78,417
7,827
1.9
3.94
40
854
87
0.5
2.80
9,830
14,854
1,483
6.6
0.40
11,610
15,922
1,589
7.3
0.32
36,190
110,047
10,986
3.29
By introducing operation and maintenance and energy monitoring, we will avoid increase of the
energy consumption after implementation of the energy saving measures, keep the operation
costs, incl. energy, as low as possible on a permanent basis, and prevent large and expensive
repairs. The investment costs for Operation & Maintenance and Energy Monitorting system will be
1,700 Euro.
5.
1,700
2,800
279
6.1
0.27
The recommended measures with total investment of 37.890 will be paid back in 3.36
years.
Energy savings divided into savings per energy carrier:
Energy carrier
Unit
Present (baseline)
After measures
Savings
Electricity
kWh
58,587
44,754
13,833
Oil
kWh
107,228
11,014
96,214
Comments/explanations:
The above table shows that compared to the baseline, an energy savings of 110,047 kWh/year
could be achieved.
The average consumption of electricity for the past three years is 58,587 kWh/year.
From the evaluation and calculations done, the amount of electricity equal to 12,115 kWh/year is
used for providing the space heating.
Page 37
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
After the implementation of the EE measures, for providing the space heating, the Elderly House
will consume less energy. The savings will be in:
1. Oil in the amount of 96,214 kWh,
2. Electricity in the amount of 12,115 kWh.
After the implementation of energy efficiency lighting, the Elderly House will consume less
electricity. The savings will be in the amount of 1,718 kWh.
Besides these, it is important to stress that the indoor environment (indoor temperature) of the
Elderly House will be considerably improved. This will contribute to a much better living conditions.
Thus, during the heating season, the average indoor temperature will be about 17.73 C (the
livingroom and office will have a temperature about 20 C). In the actual conditions, the average
indoor temperature of the Elderly House is about 17 C.
Page 38
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
1.
2.
3.
4.
5.
8.2 Measures
Measure No.
1 Thermal insulation of the external walls
Existing situation
The existing walls are rock of 550 mm, solid bricks of 380 mm, 250 mm, 120 mm and concrete of
120 mm with plastering of 20mm in both sides.
U=
2.2 W/mK (rock 550 mm)
U=
1.3 W/mK (solid bricks 380 mm)
U=
2.6 W/mK (solid bricks 250 mm)
U=
6.0 W/mK (solid bricks 120 mm)
U=
3.6 W/mK (concrete 120 mm)
Description of measure
The improved walls will be rock of 550 mm, solid bricks of 380 mm, 250 mm, 120 mm and
concrete of 120 mm with polystyrene layer of 80 mm with plastering of 20mm in both sides.
U=
0.36 W/mK
Calculation of savings (by ENSI EAB Software)
Energy savings:
747 m
=
0.0998 /kWh =
Investment:
Design/Planning
Project Management
Components
Installation
Control and testing
As-built documentation
Other expenses
Taxes, VAT
Total investment
104.976
78,417
7,827
865
585
6,120
3,650
480
430
270
2,310
14,710
0
7,827
30
kWh/myear
kWh/year
/year
/year
/year
years
Page 39
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Measure No.
2 Energy efficient lamps
Existing situation
Only 15 of the existing lamps are incandescent lamps, having a powe r of 1.51 W/m2.
Description of measure
The improved lamps will be efficiency lamps, having a power of 0.3 W/m2.
Calculation of savings (by ENSI EAB Software)
Energy savings:
747 m
=
0.108 /kWh =
Investment:
Design/Planning
Project Management
Components
Installation
Control and testing
As-built documentation
Other expenses
Taxes, VAT
Total investment
1.143
854
92
0
0
29.6
2
1
0
0
7.4
40
5
87
2
kWh/myear
kWh/year
/year
/year
/year
years
Page 40
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Measure No.
3 Double glazing windows
Existing situation
The existing doors & windows are aluminium frame with single glass.
U=
5.00 W/mK
Description of measure
The improved doors & windows will be aluminium frame with double glass.
U=
2.80 W/mK
Calculation of savings (by ENSI EAB Software)
Energy savings:
747 m
=
0.0998 /kWh =
Investment:
Design/Planning
Project Management
Components
Installation
Control and testing
As-built documentation
Other expenses
Taxes, VAT
Total investment
19.88
14,854
1,483
580
370
4,130
2,500
270
230
180
1,570
9,830
0
1,483
25
kWh/myear
kWh/year
/year
/year
/year
years
Page 41
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Measure No.
4 Thermal insulation of pitchid roof
Existing situation
The pitched roof of both buildings has been refurbished in 1999 and the condition is good.
U=
1.00 W/mK
Description of measure
Thermal insulation with a layer of 60 mm of glass wool, placed above the ceiling.
U=
0.36 W/mK
Calculation of savings (by ENSI EAB Software)
Energy savings:
747 m
=
0.0998 /kWh =
Investment:
Design/Planning
Project Management
Components
Installation
Control and testing
As-built documentation
Other expenses
Taxes, VAT
Total investment
21.31
15,922
1,589
kWh/myear
kWh/year
/year
450
380
6,940
1,180
340
250
230
1,840
11,610
0
1,589
25
/year
/year
years
Page 42
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Measure No.
5 Operation & Maintenance and Energy Monitoring
Existing situation
Lack of O&M routines and energy monitoring.
Description of measure
Establishment of O&M routines and energy monitoring, manuals, training, purchase of monitoring
equipment.
Calculation of savings (by ENSI EAB Software)
Energy savings:
747 m
=
0.0998 /kWh =
Investment:
Design/Planning/Training
Project Management
Components
Installation
Control and testing
Taxes, VAT
Total investment
3.75
2,800
279
kWh/myear
kWh/year
/year
850
574
180
10
40
46
1,700
0
279
15
/year
/year
years
Page 43
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Environmental Benefits
Calculated savings in delivered energy and related reductions in CO2 emissions are as follows:
Oil
District
Heating
Electricity
Energy carrier
78.43
143.54
59.91
14.74
Savings (kWh/ma)
18.52
128.80
3.31
1.35
61.30
173.88
175.68
Page 44
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Milestone
(dd.mm.yy)
01.01.2012
15.02.2012
Calculation by contractors
20.03.2012
10.04.2012
Evaluations
01.05.2012
10.05.2012
15.05.2012
Contractor preparations
30.05.2012
Implementation
01.06.2012
Implementation finished
30.08.2012
Commissioning
15.09.2012
01.09.2012
20.09.2012
Final commissioning
15.10.2012
Page 45
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
2.
Keep the operation costs, incl. energy, as low as possible on a permanent basis
3.
Operation: daily, weekly and monthly activities that are repetitive within a one-year period for
building and technical installation systems that shall satisfy given functional demands and
requirements.
Maintenance: all activities and efforts put forward in a period of more than one year.
Repair: repairing what has been broken or damaged back to its original standard or quality.
In order to operate and maintain the building properly, it is necessary to know:
How the installations are supposed to operate
Which installations require maintenance
How to operate and maintain the installations
When to operate and maintain the installations
Who is responsible for the work
This documentation should be presented in the Operation and Maintenance Manual.
The total costs for the proposed measure - implementing the operation and maintenance routines
and energy monitoring sum up to 1,700 Euro for this project.
Page 46
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
Thermal insulation
Window
Door
Boiler
Heating system
Water
Electric boiler
Description
Control of light bulbs and cleaning,
Control of all electrical sockets, plugs and
keys,
Control of electricity consumption and give
conclusion.
Control and repair the thermal insulation of
external walls and attic floor.
Control and repair of windows operating
system,
In winter control than windows are closed,
Repair any damage immediately.
Control and repair of doors operating system,
In winter control than doors are closed,
Repair any damage immediately.
Control and repair of boiler operating system,
Control of oil consumption and give
conclusion.
Control and cleaning of radiators, valves and
pipes.
Control and cleaning of taps,
Control of pipe lines,
Control of water consumption and give
conclusion.
Control of sanitary hot water temperature,
Control of boiler electrical system.
Time
Every month
Every three months
Every month
Every end of winter
Every month
Every day
Every month
Every day
At beginning of winter
Every day of winter
At beginning of winter
Every 15 days
Every three months
Every month
Every day
Every three months
As a conclusion: The monitoring will be carried out weekly, and the reporting monthly. It is
necessary that the responsible personnel will report to the Elderly House director.
Dr. Eng. Besim ISLAMi and Dr. Eng. Edmond HIDO, as the EE consultants, will provide training to
introduce the routines to the operation and maintenance personnel.
Page 47
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
The ET-Curve shows what the energy consumption should be (the target value) at different
outdoor temperatures. If the weekly consumption is more than 10 % outside the target value,
actions should be taken to identify the cause and make corrections.
Page 48
PROJECT NAME
ENERGY AUDIT REPORT IN ELDERLY HOUSE - KORCA
User instructions
Registration and calculation forms
ET-Curve
Deviation checklist
The energy registrations will be done by the existing meters for water and electricity, as well as by
new meter for oil. The average outdoor temperature will be measured by a new temperature
logger that will be installed at the building site.
The weekly routines should be done by the operation and maintenance personnel at the building:
1. Read the energy meters in the building and calculate the specific energy consumption;
2. Register the outdoor mean temperature for the corresponding period;
3. Plot these two registrations in the ET-Diagram.
The readings from the meters will be included in the following table:
Week
0
1
3
4
Reading
Date
Reading
Time
21.07.08
28.07.08
08:00
08:00
Week
Electical Meter
Medium
Reading Accumulated
Temperature (kWh)
(kWh)
0
12,765
0
21
13,276
511
Price
(Lek)
0
6,132
Oil Meter
Reading Accumulated
(Litre)
(Litre)
76.5
0
76.5
0
Price
(Lek)
0
0
Water Meter
Reading Accumulated
3
(m3)
(m )
54.2
0
57.7
3.5
Price
(Lek)
0
31.5
By ploting the registered weekly energy (electricity and oil) consumption and weekly mean
temperature in the ET-Diagram, the ET-Curve will be prepared. Any deviations from the ET-Curve
indicate some malfunctioning equipment or any wrong operation settings. The O & M personnel
should identify the cause, and implement the required repair or adjustments.
Regular reporting to the Elderly House director.
Dr. Eng. Besim ISLAMi and Dr. Eng. Edmond HIDO, as the EE consultants, will provide training to
introduce the routines to the operation and maintenance personnel.
If the operation and maintenance personnel cannot find the cause for the deviation, the Dr. Eng.
Besim ISLAMi and Dr. Eng. Edmond HIDO, as the EE consultants, can assist on reimbursable
basis.
Page 49