UMM BIRKA SUPER SUBSTATION

2
3
4

T x 2 - 317 255
Field Operations on Cleats & Leads Systems horizontal Lower supports
Preparations (Safe Work Permit, dry air, nitrogen, the intermediate tanks, oil treatment machine,
vacuum pump, covering the transformer with tent or tarpaulin, etc. )
Draining the oil in HV Cable Boxes and Disconnecting HV Links
De-gassing of SF6 in LV GIS and Dismantling of LV Links
Site Tests of FRA and Insulation Resistance
Draining the oil in the main tank
Gas evacuation in the transformer
Preparation for entering the transformer
Entering in the transformer and Performing the modification on cleats & lead system on the active part

5
6
7
8
9
10
11
12

Vacuum for 24 hours, Filling with Nitrogen in order to check the Dew Point Measurement and wait for
the equilibirum
Vacuum and DEW POINT Measurement
Vacuum and Oil Filing into the main tank of the transformer and oil recycling
Quality Analysis of Insulation Oil + Total Dissolved Gas Test
Site Electrical Tests
Vacuuming and oil filling into HV Cable Box
PD Calibration of HighVolt Test Equipment at LV GIS Side, Vacuum on LV GIS
SF6 filling into LV GIS
Induced Over-Voltage Withstand Test and Partial Discharge Measurement
Draining the oil partially in the main tank for disconnection of the tertiary bushings, drianing the oil in
HV Cable Boxes, Re-storing HV links, Vacuuum for 24 hours
Filling the oil into the transformer partially and into HV Cable Boxes
Quality Analysis of Insulation Oil + Total Dissolved Gas Test
Filling SF6 gas into LV GIS
Treating the oil in the main transformer
Resting time for the oil in the transformer and preparations for energising
Pre - Commissioning of the accessories on transformer

13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28

JUBAIL SUBSTATION

29
30
31

32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50

Project: Project1
Date: Wed 10/8/14

T - 801 --- 317 109


Field Operations on Cleats & Leads Systems horizontal Lower supports
Preparations (Safe Work Permit, dry air, nitrogen, the intermediate tanks, oil treatment machine,
vacuum pump, dilo machine - MEGA, storage tanks for SF6, man lift, building up the scaffoldings at
the HV and LV side for dismantling and the tests, etc.)
Draining the oil in LV Oil Cable Boxes and Disconnecting LV Links
De-gassing of SF6 in HV GIS and Dismantling of HV Links
Site Electrical Routine Tests of FRA, Insulation Resistance, pf%, etc.
Dismantling of HV GIS Compartments
Dismantling of all necessary accessories and equipment on the transformer (conservator, bushings,
cooling pipes, the cabinet of MK and MR, Serveron, etc.)
Building up the scaffoldings all around the transformer including in top cover and putting the tent on
the scaffoldings.
Draining the oil in the main tank
Preparation for on-site modifications (removing the bell type main tank, ventilation, etc.)
Performing the modification on cleats & lead system on the active part
Fixing the bell type main tank onto the frame on the bottom part of the transformer
Re-assembling of all necessary accessories and equipment on the transformer (conservator,
bushings, cooling pipes, the cabinet of MK and MR, Serveron, etc.)
Vacuum
Oil Filing into the main tank of the transformer
Re- assmebling of HV GIS compartmens
Quality Analysis of Insulation Oil + Total Dissolved Gas Test
Site Electrical Tests
PD Calibration of HV Test Equipment
Vacuuming and oil filling into LV Oil Cable Box
Vacuuming and SF6 filiing into HV GIS

37 days

Mon 9/29/14

Tue 11/4/14

37 days
37 days
10 days

Mon 9/29/14
Mon 9/29/14
Mon 9/29/14

Tue 11/4/14
Tue 11/4/14
Wed 10/8/14

1 day
1 day
1 day
1 day
1 day
0 days
2 days

Thu 10/9/14
Fri 10/10/14
Sat 10/11/14
Sun 10/12/14
Mon 10/13/14
Mon 10/13/14
Tue 10/14/14

Thu 10/9/14
Fri 10/10/14
Sat 10/11/14
Sun 10/12/14
Mon 10/13/14
Mon 10/13/14
Wed 10/15/14

2 days

Thu 10/16/14

Fri 10/17/14

3 days
3 days
0 days
2 days
2 days
0 days
1 day
1 day
2 days

Sat 10/18/14
Tue 10/21/14
Thu 10/23/14
Fri 10/24/14
Sun 10/26/14
Mon 10/27/14
Tue 10/28/14
Wed 10/29/14
Thu 10/30/14

Mon 10/20/14
Thu 10/23/14
Thu 10/23/14
Sat 10/25/14
Mon 10/27/14
Mon 10/27/14
Tue 10/28/14
Wed 10/29/14
Fri 10/31/14

1 day
1 day
0 days
1 day
1 day
0 days

Sat 11/1/14
Sun 11/2/14
Sun 11/2/14
Mon 11/3/14
Tue 11/4/14
Tue 11/4/14

Sat 11/1/14
Sun 11/2/14
Sun 11/2/14
Mon 11/3/14
Tue 11/4/14
Tue 11/4/14

35 days Tue 10/14/14

Mon 11/17/14

35 days
35 days
3 days

Tue 10/14/14
Tue 10/14/14
Tue 10/14/14

Mon 11/17/14
Mon 11/17/14
Thu 10/16/14

1 day
1 day
2 days
3 days
3 days

Fri 10/17/14
Sat 10/18/14
Sun 10/19/14
Tue 10/21/14
Tue 10/21/14

Fri 10/17/14
Sat 10/18/14
Mon 10/20/14
Thu 10/23/14
Thu 10/23/14

3 days

Fri 10/24/14

Sun 10/26/14

2 days
2 days
2 days
2 days
4 days

Fri 10/24/14
Sun 10/26/14
Tue 10/28/14
Thu 10/30/14
Thu 10/30/14

Sat 10/25/14
Mon 10/27/14
Wed 10/29/14
Fri 10/31/14
Sun 11/2/14

3 days
2 days
2 days
0 days
2 days
1 day
1 day
1 day

Mon 11/3/14
Thu 11/6/14
Sat 11/1/14
Sun 11/2/14
Sat 11/8/14
Mon 11/10/14
Tue 11/11/14
Wed 11/12/14

Wed 11/5/14
Fri 11/7/14
Sun 11/2/14
Sun 11/2/14
Sun 11/9/14
Mon 11/10/14
Tue 11/11/14
Wed 11/12/14

11/4

Task

Project Summary

Inactive Milestone

Manual Summary Rollup

Progress

Split

External Tasks

Inactive Summary

Manual Summary

Deadline

Milestone

External Milestone

Manual Task

Start-only

Summary

Inactive Task

Duration-only

Finish-only

Page 1

Nov 15, '14


S

ID

Task Name

Duration

Start

Finish

Sep 27, '14


F

51
52

53
54
55
56
57

Project: Project1
Date: Wed 10/8/14

Induced Over-Voltage Withstand Test and Partial Discharge Measurement


Draining the oil partially in the main tank for disconnection of the tertiary bushings, drianing the oil in
LV Oil Cable Boxes, Re-storing LV links, De-gassing of SF6 in HV GIS, Re-storing HV links, Vacuuum
for 24 hours
Filling the oil into the transformer partially and into LV Cable Boxes
Filling SF6 gas into HV GIS
Treating the oil in the main transformer
Resting time for the oil in the transformer and preparations for energising
Pre - Commissioning of the accessories on transformer

1 day
1 day

Thu 11/13/14
Fri 11/14/14

Thu 11/13/14
Fri 11/14/14

1 day
0 days
1 day
1 day
0 days

Sat 11/15/14
Sat 11/15/14
Sun 11/16/14
Mon 11/17/14
Mon 11/17/14

Sat 11/15/14
Sat 11/15/14
Sun 11/16/14
Mon 11/17/14
Mon 11/17/14

11/17

Task

Project Summary

Inactive Milestone

Manual Summary Rollup

Progress

Split

External Tasks

Inactive Summary

Manual Summary

Deadline

Milestone

External Milestone

Manual Task

Start-only

Summary

Inactive Task

Duration-only

Finish-only

Page 2

Nov 15, '14


S