Mwaffaq Otoom
Overview
Cost Budgeting
Risk Analysis
Lecture05
Mwaffaq Otoom
Cost overrun %
300
200
100
-100
1910
1930
1920
1950
1940
1970
1960
1990
1980
2000
Mwaffaq Otoom
Lecture05
Mwaffaq Otoom
Cumulative cost
Lecture05
At project
execution
At project
definition
Contingency
fund
Cost
estimate
Time
Mwaffaq Otoom
Lecture05
Mwaffaq Otoom
Mwaffaq Otoom
Estimating Process
Estimate versus Target or Goal
Estimate: a realistic assessment
Lecture05
Mwaffaq Otoom
Estimating Process
Accuracy versus Precision
Lecture05
Mwaffaq Otoom
Estimating Process
Estimating Methods
1.
2.
3.
Lecture05
Expert opinion
Analogy + compensation for differences
Parametric: Formula or Cost Function, e.g.,
Mwaffaq Otoom
10
Lecture05
Mwaffaq Otoom
11
Lecture05
Mwaffaq Otoom
12
Lecture05
Mwaffaq Otoom
13
Estimation Process
Procedure for larger projects
1.
WBS
information
2.
Project Management
(PM)
Functional Management
(FM)
3.
Work Team Leads
Lecture05
Mwaffaq Otoom
14
Estimation Process
Project Management
6.
Functional Management
4., 5.
Work team
Lecture05
Mwaffaq Otoom
15
Estimation Process
Project Management 7., 8.
WBS
information
Functional Management
Work team
Lecture05
Mwaffaq Otoom
16
7., 8..
WBS
information
Functional Management
Mwaffaq Otoom
17
E.g., 40%
50,000.00
20,000.00
10,000.00
3,333.33
Direct Total
83,333.33
16,667.00
Budget Amount
Lecture05
100,000.00
Mwaffaq Otoom
18
Project
management
$ 12,550
Cost
Accounts
Basic
design
Hardware
Software
J $31,362
$179,868
$122,228
Materials
M $138,571
Installation
Y $20,352
Assembly
V
Lecture05
$20,945
Mwaffaq Otoom
Procedures
Q $100,846
Specifications
L $21,272
Final
Tests
$10,857
User
Test
X $6,622
System
Test
19
W $4,235
Performance Analysis
BCWS - Budgeted Cost of the Work Scheduled
PV = Hourly Rate * Total
(Planned Value or PV)
Hours Planned
ACWP - Actual Cost of the Work Performed
AC= Hourly Rate * Total
(Actual Cost or AC)
Hours Spent
BCWP - Budgeted Cost of the Work Performed
(Earned Value or EV)
BCWP = BCWS for task completed
BCWP subjective estimate of costs for tasks started but not
yet completed
EV = Baseline Cost * (% of
Complete Actual)
(% Complete Actual) = AC /EAC
Lecture05
Mwaffaq Otoom
20
Performance Analysis
Over budget ?
How much of
project was done?
Under budget ?
21
Performance Analysis
22
Performance Analysis
23
Performance Analysis
24
Example
Parmete Co. is to remove 1,000 parking meters
and replacing them with new ones for which
they will receive $200 per meter. Estimate they
can install 25 meters / day.
For day 18,
Mwaffaq Otoom
25
Example (cont.)
If by day 18, only 400 meters are finished, then
BCWP = 400 x 200 = $80,000
Mwaffaq Otoom
26
Example (cont.)
Scheduled Project Costs
200,000
150,000
Costs
BCWS
100,000
BCWP
50,000
0
0
10
20
30
40
Time
Lecture05
Mwaffaq Otoom
27
Variances
Accounting Variance
AV = BCWS - ACWP
Schedule Variance
SV = BCWP - BCWS
Time Variance
TV = SD - BCSP
SD :- Status Date
BCSP :- date when BCWS = BCWP
Cost Variance
CV = BCWP - ACWP
Lecture05
Mwaffaq Otoom
29
AV
Cost ($1,000)
500
SV
400
BCWS
300
BCWP
ACWP
200
100
0
10
15
20
25
Week
Mwaffaq Otoom
31
Performance Indices
SPI = Schedule Performance Index
SPI = BCWP/BCWS
SPI > 1
CPI > 1
Lecture05
project under-budget
Mwaffaq Otoom
34
Mwaffaq Otoom
35
Example
Assume a project that has exactly one task
The task was baselined at 8 hours, but 11 hours
have been spent and the estimate to complete is
1 additional hour
The task was to have been completed already
Assume an Hourly Rate of $100 per hour
36
Example
Hourly Rate = $100
PV or BCWS = Hourly Rate * Total Hours Planned or Scheduled
Example
SV = Earned Value (EV) - Planned Value (PV)
SV = -$66 ($734 EV - $800 PV)
SPI = Earned Value (EV) /Planned Value (PV)
SPI = 0.91 ($734 EV / $800 PV) [ SPI<1]
CV = Earned Value (EV) - Actual Cost (AC)
CV = -$366 ($734 EV - $1100 AC)
(indicating a cost overrun)
CPI = Earned Value (EV) /Actual Cost (AC)
CPI = 0.66 ($734 EV / $1100 AC) [CPI < 1]
(indicating over budget)
38
BCAC
Lecture05
39
Logon Example
For Logon, the Budgeted Cost at Completion is given by
BCAC = $990,000
Mwaffaq Otoom
40
= FCAC - ACWP
= BCAC/CPI - ACWP
= (BCAC - BCWP)/CPI
Lecture05
Mwaffaq Otoom
41
Logon Example
FCTC = (BCAC - BCWP)/CPI
= (990,000 - 432,000)/.77
= $724,675
Summary: In week 20 we have completed 432,000 of
budgeted work at a cost of 560,000. Given the current
trend, we expect to complete the project at cost remaining
of $724,675 for a final project cost of $1,283,333.
Lecture05
Mwaffaq Otoom
42
Logon Example
Logon Status & Forecast
1400
FCAC
SD
1200
BCAC
Cost ($1,000's)
1000
BCWS
800
FBCWP
600
FACWP
400
200
0
0
10
20
30
40
50
Week
Lecture05
Mwaffaq Otoom
43
Logon Example
Logon Status & Forecast
1400
FCAC
SD
1200
BCAC
Cost ($1,000's)
1000
BCWS
800
FBCWP
600
FACWP
400
200
0
0
10
20
30
Week
Lecture05
Mwaffaq Otoom
40
50
Scheduled
Revised
Completion
Completion
45
Risk Concepts
The likelihood that some problematical event will
occur
The impact of the event if it does occur
Risk = f (likelihood , impact)
Project is considered risky if at least one factor is
large
Lecture05
Mwaffaq Otoom
46
Risk Identification
Risk tolerance is a function of experience
Risk of Failure
Risk of Opportunity
Lecture05
Mwaffaq Otoom
47
High Risks
Lecture05
Approach is New/Unusual
Technology is New/Unusual
Staff needs training in new Tasks/Skills
Process using New Equipment, Systems or
Procedures
Mwaffaq Otoom
48
Sources of Risk
Any factor of uncertain Probability which can
affect the Outcome is of a Project is a:
Risk Source
Risk Hazard
Lecture05
Mwaffaq Otoom
49
Lecture05
Mwaffaq Otoom
50
Lecture05
Mwaffaq Otoom
51
Identification techniques
Analogy
Checklist
WBS Analysis
Lecture05
Mwaffaq Otoom
52
Lecture05
Mwaffaq Otoom
53
Lecture05
Mwaffaq Otoom
54
Risk Assessment
Risk Likelihood
Qualitative Rating
Lecture05
Mwaffaq Otoom
55
Lecture05
Mwaffaq Otoom
56
Influence Diagram
Lecture05
Mwaffaq Otoom
57
Qualitative
High
Medium
Low
Lecture05
Mwaffaq Otoom
58
Lecture05
Mwaffaq Otoom
59
Lecture05
Mwaffaq Otoom
60
Lecture05
Mwaffaq Otoom
61
Lecture05
Mwaffaq Otoom
62
Lecture05
Mwaffaq Otoom
63
Lecture05
Fixed Prices
FP Incentive Fee
Cost Plus Incentive Fee
Cost Plus Fixed Fee (CPFF)
Mwaffaq Otoom
64
Avoid Risk
Lecture05
Mwaffaq Otoom
65
Lecture05
Mwaffaq Otoom
66
Lecture05
Recognize Tasks
End Item Design
Decouple Activities
Use Design Margins
Mwaffaq Otoom
67
Lecture05
Mwaffaq Otoom
68
Lecture05
Mwaffaq Otoom
69
Lecture05
Mwaffaq Otoom
70
Lecture05
Mwaffaq Otoom
71
Contingency Planning
The Get-Well-Plan
Form
Lecture05
Mwaffaq Otoom
72
Lecture05
Mwaffaq Otoom
73
Lecture05
Requirements Definition
Task Definition
Scheduling
Budgeting
Configuration Management
Change Control
Performance Tracking and Control
Mwaffaq Otoom
74
Likelihood
CS Impact
Contingencies
Trigger Events
Risk Officer
Not the PM
Devils Advocate
Lecture05
Mwaffaq Otoom
75
Lecture05
Mwaffaq Otoom
76
Lecture05
Mwaffaq Otoom
77
Caveats (Beware)
Input to RA is Subjective
Not What Will but Might
Analysis and Planning gives sense of Power
Lecture05
Mwaffaq Otoom
78
Expected Value
Decision Trees
Uncertainty and Payoff Tables
Simulations
Lecture05
Mwaffaq Otoom
79
Questions
Lecture05
Mwaffaq Otoom
80