Anda di halaman 1dari 75

Yarmouk University

Hijjawi Faculty For Engineering Tech

Project Management and


Quality Control
Cost Analysis and Risk
Management
Dr. Mwaffaq Otoom
mof.otoom@yu.edu.jo
Fall 2012
Lecture05

Mwaffaq Otoom

Overview
Cost Budgeting
Risk Analysis

Lecture05

Mwaffaq Otoom

Cost Overruns on Projects

Cost overrun %

300

200

100

-100
1910

1930
1920

1950
1940

1970
1960

1990
1980

2000

Year of decision to build


Lecture05

Mwaffaq Otoom

Sources of Cost Escalation and


Overruns
Uncertainty and Lack of Accurate Information
Changes in Requirements or Design
Economic and Social Factors
Inefficiency, Poor Communication, and Lack of Control
Ego Involvement of the Estimator
Project Contract
Bias and Ambition

Lecture05

Mwaffaq Otoom

Cost Estimating and the Systems


Development Life Cycle
At project
initiation

Cumulative cost

Regions of timecost uncertainty

Lecture05

At project
execution

At project
definition

Contingency
fund

Cost
estimate

Time

Mwaffaq Otoom

System Life Cycle Costs


Life cycle costs (LCC)
All costs of a system throughout its full
cradle-to-grave life cycle, i.e.:

Lecture05

Mwaffaq Otoom

System Life Cycle Costs


Purpose of life cycle cost analysis
To anticipate the realities of operating,
maintaining, and (ultimately) disposing of the
end-item system
To establish target costs for operating,
maintaining, and disposing of the end-item
system.
To design the system so it will meet those
target costs.
Lecture05

Mwaffaq Otoom

Estimating Process
Estimate versus Target or Goal
Estimate: a realistic assessment

Target or goal: a desired outcome, commitment, or


promise.

Lecture05

Mwaffaq Otoom

Estimating Process
Accuracy versus Precision

Lecture05

Mwaffaq Otoom

Estimating Process
Estimating Methods
1.
2.
3.

Lecture05

Expert opinion
Analogy + compensation for differences
Parametric: Formula or Cost Function, e.g.,

Mwaffaq Otoom

10

Estimating Methods (cont.)


4. Cost engineering

Lecture05

Mwaffaq Otoom

11

Cost Engineering Example

Lecture05

Mwaffaq Otoom

12

Cost Engineering Example


(Cont.)

Lecture05

Mwaffaq Otoom

13

Estimation Process
Procedure for larger projects

1.
WBS
information

2.

Project Management
(PM)

Functional Management
(FM)

3.
Work Team Leads
Lecture05

Mwaffaq Otoom

14

Estimation Process
Project Management
6.

Functional Management

Labor and cost


estimates

4., 5.

Work team
Lecture05

Mwaffaq Otoom

15

Estimation Process
Project Management 7., 8.
WBS
information

Functional Management

Work team
Lecture05

Mwaffaq Otoom

16

Estimating Process (contd)


Project Management

7., 8..

WBS
information

Procedure for larger projects, steps 7-8

Functional Management

7. PM: Adds in contingency amounts.


Two possible contingencies
Work team
1. Base estimate = (WP estimates + WP contingency)
(to handle known-unknowns)
2. Final estimate = Base estimate + overheads + project
contingency
(to handle unknown unknowns; PM controls this)
8. PM: Compares bottom-up estimates to top-down targets or goals.
Attempt to reconcile differences.
Lecture05

Mwaffaq Otoom

17

Elements of Typical Budget


I. Direct Costs

Direct Labor (DL)


Charges for labor working directly on project
Direct Overhead on Labor (% of DL)
Labor support: benefits, etc.

E.g., 40%

50,000.00
20,000.00

Direct Nonlabor and Materials (M)


Subcontractors, consultants, travel, telephone, materials,
purchased parts, etc.

10,000.00

Direct Overhead on Nonlabor and Materials (% of M)


Shipping, insurance, security, etc. E.g., 33.33%

3,333.33

Direct Total

83,333.33

II. General & Administrative (% of Direct Total) E.g., 20%


(Indirect overhead)
Corporate overhead: proposals, publicity, president, etc.

16,667.00

Budget Amount
Lecture05

100,000.00
Mwaffaq Otoom

18

Project budget subdivided into control


accounts
ROSEBUD

Project Budget $ 356,755

Project
management
$ 12,550

Cost
Accounts

Basic
design

Hardware

Software

J $31,362

$179,868

$122,228

Materials

M $138,571

Installation

Y $20,352
Assembly

V
Lecture05

$20,945
Mwaffaq Otoom

Procedures

Q $100,846
Specifications

L $21,272

Final
Tests

$10,857
User
Test

X $6,622
System
Test
19
W $4,235

Performance Analysis
BCWS - Budgeted Cost of the Work Scheduled
PV = Hourly Rate * Total
(Planned Value or PV)
Hours Planned
ACWP - Actual Cost of the Work Performed
AC= Hourly Rate * Total
(Actual Cost or AC)
Hours Spent
BCWP - Budgeted Cost of the Work Performed
(Earned Value or EV)
BCWP = BCWS for task completed
BCWP subjective estimate of costs for tasks started but not
yet completed
EV = Baseline Cost * (% of
Complete Actual)
(% Complete Actual) = AC /EAC
Lecture05

Mwaffaq Otoom

20

Performance Analysis

Over budget ?

How much of
project was done?

Under budget ?

21

Performance Analysis

22

Performance Analysis

23

Performance Analysis

24

Example
Parmete Co. is to remove 1,000 parking meters
and replacing them with new ones for which
they will receive $200 per meter. Estimate they
can install 25 meters / day.
For day 18,

BCWS = 18 x 25 x 200 = $90,000


Lecture05

Mwaffaq Otoom

25

Example (cont.)
If by day 18, only 400 meters are finished, then
BCWP = 400 x 200 = $80,000

Schedule Variance = BCWP - BCWS


= -$10,000
Note: -$10,000 does not represent a cost savings, but
rather that the project is 2 days behind schedule
Lecture05

Mwaffaq Otoom

26

Example (cont.)
Scheduled Project Costs
200,000

150,000

Costs

BCWS
100,000

BCWP

50,000

0
0

10

20

30

40

Time

Lecture05

Mwaffaq Otoom

27

Variances
Accounting Variance

AV = BCWS - ACWP
Schedule Variance
SV = BCWP - BCWS
Time Variance
TV = SD - BCSP

SD :- Status Date
BCSP :- date when BCWS = BCWP

Cost Variance
CV = BCWP - ACWP
Lecture05

Mwaffaq Otoom

29

Logon Project (Week 20)


Logon Project Status
600

AV

Cost ($1,000)

500

SV

400

BCWS

300

BCWP
ACWP

200
100
0

10

15

20

25

Week

SV = BCWP - BCWS = -$80,000


Lecture05

Mwaffaq Otoom

31

Performance Indices
SPI = Schedule Performance Index
SPI = BCWP/BCWS
SPI > 1

work ahead of schedule

CPI = Cost Performance Index


CPI = BCWP/ACWP

CPI > 1
Lecture05

project under-budget
Mwaffaq Otoom

34

Logon Project (Week 20)


SPI = BCWP/BCWS
= 432/512 = .84
CPI = BCWP/ACWP
= 432/560 = .77
Project is behind schedule
With budget overrun
Lecture05

Mwaffaq Otoom

35

Example
Assume a project that has exactly one task
The task was baselined at 8 hours, but 11 hours
have been spent and the estimate to complete is
1 additional hour
The task was to have been completed already
Assume an Hourly Rate of $100 per hour

36

Example
Hourly Rate = $100
PV or BCWS = Hourly Rate * Total Hours Planned or Scheduled

PV = $800 or ($100 * 8 hours)


AC or ACWP = Hourly Rate * Total Hours Spent

AC = $1100 or ($100 * 11 hours)


EV or BCWP = Baselined Cost * % Complete Actual

EV = $734 or (baseline of $800 * 91.7% complete)


(NOTE % Complete Actual (below) to get the 91.7% )
(% Actual Complete = 11 hours spent /12 hours estimated to finish)
37

Example
SV = Earned Value (EV) - Planned Value (PV)
SV = -$66 ($734 EV - $800 PV)
SPI = Earned Value (EV) /Planned Value (PV)
SPI = 0.91 ($734 EV / $800 PV) [ SPI<1]
CV = Earned Value (EV) - Actual Cost (AC)
CV = -$366 ($734 EV - $1100 AC)
(indicating a cost overrun)
CPI = Earned Value (EV) /Actual Cost (AC)
CPI = 0.66 ($734 EV / $1100 AC) [CPI < 1]
(indicating over budget)

38

Forecast Cost At Completion


FCAC = Forecast Cost At Completion
= % by which on schedule x BCAC
= (ACWP/BCWP) x BCAC
= BCAC/CPI
where

BCAC
Lecture05

= Budgeted Cost At Completion


Mwaffaq Otoom

39

Logon Example
For Logon, the Budgeted Cost at Completion is given by
BCAC = $990,000

At week 20, BCWP = 432 whereas ACWP = 560


we are running 560/432 = 1.30 times over budget

FCAC = 1.3 x 990,000 = $1,283,333


Lecture05

Mwaffaq Otoom

40

Forecast Cost To Complete


FCAC = FCTC + ACWP
FCTC = Forecast Cost To Completion
= Forecast Cost At Completion - ACWP

= FCAC - ACWP
= BCAC/CPI - ACWP
= (BCAC - BCWP)/CPI
Lecture05

Mwaffaq Otoom

41

Logon Example
FCTC = (BCAC - BCWP)/CPI

= (990,000 - 432,000)/.77
= $724,675
Summary: In week 20 we have completed 432,000 of
budgeted work at a cost of 560,000. Given the current
trend, we expect to complete the project at cost remaining
of $724,675 for a final project cost of $1,283,333.
Lecture05

Mwaffaq Otoom

42

Logon Example
Logon Status & Forecast
1400
FCAC
SD

1200

BCAC

Cost ($1,000's)

1000

BCWS

800

FBCWP
600

FACWP

400
200
0
0

10

20

30

40

50

Week

Lecture05

Mwaffaq Otoom

43

Logon Example
Logon Status & Forecast
1400
FCAC
SD

1200

BCAC

Cost ($1,000's)

1000

BCWS

800

FBCWP
600

FACWP

400
200
0
0

10

20

30
Week

Lecture05

Mwaffaq Otoom

40
50
Scheduled
Revised
Completion
Completion

45

Risk Concepts
The likelihood that some problematical event will
occur
The impact of the event if it does occur
Risk = f (likelihood , impact)
Project is considered risky if at least one factor is
large

Lecture05

Mwaffaq Otoom

46

Risk Identification
Risk tolerance is a function of experience
Risk of Failure

Risk of Opportunity

Lecture05

Mwaffaq Otoom

47

Risk Identification (Cont.)


Ways to identify project risks
Chronology
Type of work

High Risks

Lecture05

Approach is New/Unusual
Technology is New/Unusual
Staff needs training in new Tasks/Skills
Process using New Equipment, Systems or
Procedures
Mwaffaq Otoom

48

Sources of Risk
Any factor of uncertain Probability which can
affect the Outcome is of a Project is a:
Risk Source
Risk Hazard

Lecture05

Mwaffaq Otoom

49

Sources of Risk (Cont.)


Internal Risks
Market Risk
Technical Risks

Lecture05

Mwaffaq Otoom

50

Sources of Risk (Cont.)


External Risks

Lecture05

Mwaffaq Otoom

51

Identification techniques
Analogy
Checklist

WBS Analysis

Lecture05

Mwaffaq Otoom

52

Identification Techniques (Cont.)


Process Flowcharts
Brainstorming and Cause and Effect Diagrams

Lecture05

Mwaffaq Otoom

53

Cause and Effect Diagram

Lecture05

Mwaffaq Otoom

54

Risk Assessment
Risk Likelihood
Qualitative Rating

Composite Likelihood Factor (CLF)

Lecture05

Mwaffaq Otoom

55

Sources of Failure and Likelihood

Lecture05

Mwaffaq Otoom

56

Influence Diagram

Lecture05

Mwaffaq Otoom

57

Risk Assessment (Cont.)


Risk Impact
What happens if a Risk Hazard Materialized
Specified in Terms of
Time
Cost
Performance Measure

Qualitative
High
Medium
Low
Lecture05

Mwaffaq Otoom

58

Risk Assessment (Cont.)


Risk Impact (Cont.)
Numerical measure Between 0 and 1.0
0 NOT Serious
1.0 Catastrophic

Composite Impact Factor (CIF) is the Impact from


Multiple Risk Sources, Simple Weighted Average
CIF = (W1)TI + (W2)CI + (W3)SI

Lecture05

Mwaffaq Otoom

59

Impact Values for Technical, Cost,


and Time

Lecture05

Mwaffaq Otoom

60

Risk Assessment (Cont.)


Risk Consequence
Function of Likelihood and Impact
Risk Consequence Rating (RCR)
RCR = CLF + CIF CLF (CIF)
Risk Consequence = (Impact) * (Likelihood)

Lecture05

Mwaffaq Otoom

61

Risk Response Planning How to


Deal with the Problem

Transfer the Risk


Avoid Risk
Reduce Risk
Contingency Planning
Accept Risk (Do Nothing)

Lecture05

Mwaffaq Otoom

62

Risk Likelihood, Risk Impact, and


Expected Value Consequences

Lecture05

Mwaffaq Otoom

63

Transfer the Risk


Transfer Partly or Fully from Customer to
Contractor or Vice Versa
Use Contract Incentives

Lecture05

Fixed Prices
FP Incentive Fee
Cost Plus Incentive Fee
Cost Plus Fixed Fee (CPFF)

Mwaffaq Otoom

64

Avoid Risk

Alter the Initial Project Concept


Change Contractors
Incorporate Redundancies
Change Safety Procedures
Better to Reduce Risk to Acceptable Level Than
Eliminate Payoff Opportunity

Lecture05

Mwaffaq Otoom

65

Reduce Risk Technical Performance


Best Technical Team
Perform Analysis of Key Technical Parameters
Models and Simulations

Use CASE Tools


Parallel Development on High-Risk Tasks
Incentive the Technical Team
Consultant for Critical Reviews and Assessments
T&E

Lecture05

Mwaffaq Otoom

66

Reduce Risk Technical Performance


(Cont.)
Reduce System Complexity to a Minimum

Lecture05

Recognize Tasks
End Item Design
Decouple Activities
Use Design Margins

Mwaffaq Otoom

67

Reduce Risks Meeting Schedules


Create Master Project Schedule
Schedule Risky Tasks Early to Allow Time to
Recover
Focus on Critical and Near-Critical Activities
Best People on Time-Critical Tasks

Lecture05

Mwaffaq Otoom

68

Reduce Risks Meeting Schedules


(Cont.)
Incentive for OT
Do High Risk Activities in the Project Network
in Parallel
Organize Project Early with Adequate Staff

Lecture05

Mwaffaq Otoom

69

Reduce Risk Meeting Project Cost


Identify and Monitor Cost Drivers
Perform Design Alternative Reviews and
Assessments
Validate System Design and Performance
Maximum Use of Proven Technology and
COTS

Lecture05

Mwaffaq Otoom

70

Reduce Risk Meeting Project Cost


Systems Engineering
Build Test Models to Verify Design
Focus on Meeting the Minimum Requirements
and Nothing More

Lecture05

Mwaffaq Otoom

71

Contingency Planning
The Get-Well-Plan
Form

Lecture05

Mwaffaq Otoom

72

Accept Risk (Do Nothing)


Not All Risks are Severe or Fatal
Cost Benefit Analysis
Not for Risks which are Potentially Severe

Lecture05

Mwaffaq Otoom

73

Risk Management is Project


Management
Another Tool for PM
Supplements

Lecture05

Requirements Definition
Task Definition
Scheduling
Budgeting
Configuration Management
Change Control
Performance Tracking and Control
Mwaffaq Otoom

74

Risk Management Principles


Create Risk Management Plan
Create a Risk Profile

Likelihood
CS Impact
Contingencies
Trigger Events

Risk Officer
Not the PM
Devils Advocate
Lecture05

Mwaffaq Otoom

75

Risk Management Principles (Cont.)


Calculate a Risk Reserve
Risk Time RT
Risk Cost RC

Monitor Risk Continuously


Establish Communication Channels
Document Everything of any Value for Lesson
Learned

Lecture05

Mwaffaq Otoom

76

Expect the Unexpected


Do All You Can
Cannot Cover every Contingency
Bonapartes Principle came along before
Murphys Laws, i.e., Something Surely Will Go
Wrong Plan for It to Occur

Lecture05

Mwaffaq Otoom

77

Caveats (Beware)
Input to RA is Subjective
Not What Will but Might
Analysis and Planning gives sense of Power

Managing not Eliminating


Stifles Imagination
Brute Force Approach to Technology

Micromanagement is Never Appropriate

Lecture05

Mwaffaq Otoom

78

Risk Analysis Methods

Expected Value
Decision Trees
Uncertainty and Payoff Tables
Simulations

Lecture05

Mwaffaq Otoom

79

Questions

Lecture05

Mwaffaq Otoom

80

Anda mungkin juga menyukai