www.elsevier.com/locate/ijproman
Abstract
This paper describes how the software programme Computer Aided Simulation for Project Appraisal and Review (CASPAR)
can be used to determine the commercial viability of an agricultural investment. A case study involving the purchase of a farm
and subsequent crop production of tobacco and paprika over a ten-year operation period in a developing country is presented.
Initially a base estimate is prepared and a risk analysis performed. Risks are then mitigated and the risk analysis is performed
again. The results of the risk analysis can then be used as part of the business plan. 7 2000 Elsevier Science Ltd and IPMA. All
rights reserved.
Keywords: Risk management; CASPAR; Investment appraisal; Crop cycle; Risk mitigation
1. Introduction
In this paper risk management techniques are applied
to a hypothetical farm investment in a developing
country. As project management concentrates on a project, rstly the authors consider the term project.
``A project is an undertaking that has a beginning and
an end and is carried out to meet established goals
within cost, schedule and quality objectives'' [1].
In the hypothetical case study the appraisal period is
11 yr, the end of the appraisal period can be dened
as the end of the undertakings life span. Economic
parameters such as the internal rate of return (IRR),
net present value (NPV) and cash pay back time
(CPBT) are calculated.
Not only the investment in a farm and its manage* Corresponding author. Tel.: +44-161-200-4590; fax: +44-161200-8969.
E-mail address: pwmorris@netcomuk.co.uk (T. Merna).
0263-7863/00/$20.00 7 2000 Elsevier Science Ltd and IPMA. All rights reserved.
PII: S 0 2 6 3 - 7 8 6 3 ( 9 9 ) 0 0 0 5 0 - 2
350
Science and Technology (UMIST), can be used to create investment models for all types of projects [2].
CASPAR is normally used to appraise construction
projects such as the Mersey barrage, the Severn tidal
power scheme, industrial plants, toll roads, bridges
and privately nanced prisons. The CASPAR programme is intended for use at the appraisal stage of
the project cycle where project denition is low and
time scale is long.
CASPAR utilises a project network incorporating
the Monte Carlo simulation method of analysis. This
computer software facilitates the preparation of sensitivity analysis plots of cumulative frequency distributions for time and cost. This programme also
enables the user to make small changes to the model
without signicant calculation of the data.
The programme can be used for three main purposes:
. to predict the outcome of the project at appraisal
stage;
. to aid the project manager in controlling the project
throughout its development phase; and
. to monitor the operation phase in connection with
any changes that may occur aecting the forecasts
of nancial results.
The software simulates the interaction between time,
resources, cost and revenue over the entire project life.
A network of interlinking activities each allocated a
cost centre is created in a data le. The resources are
either quantity or cost based and project related.
The computer generates the cash ow from which
nancial parameters, such as the IRR, NPV, payback
period, discounted payback period, net cash balance,
maximum cash lock up, maximum discounted cash
lock up, maximum investment, net return, discounted
net return are obtained.
The software can also simulate the eects of risks
and produce sensitivity analysis of individual risks or
combine the eects of project risk in a probabilistic
analysis utilising a Monte Carlo simulation technique.
3. Sensitivity analysis
Sensitivity analysis is performed by changing the
values of independent risk variables to predict the
economic criteria of the project. A sensitivity diagram can be produced from the results obtained
from the CASPAR programme, which identies the
most sensitive risk variables and the relative importance of each variable. The range of percentage
changes in each variable reect the uncertainty associated with each variable.
The main limitation of the sensitivity analysis is
that no indication of the likely probability of occur-
351
Table 1
Basic model economics outputs
IRR
(%)
NPV
(US$)
NCB
(US$)
MCLU
(US$)
CPBT
(yr)
DCPBT
(yr)
18.87
637 000
5 657 000
3 770 000
5.92
9.07
352
. paprika output;
. interest rate;
. demand/supply situation on tobacco world market
(inuencing the price for tobacco and thus the
tobacco revenue);
. demand/supply situation on paprika world market;
. direct costs of tobacco production;
. direct costs of paprika production.
Changes in independent variables (risks) such as the
quality of tobacco curing management, the possible
destruction of the tobacco crop by hail, the weather and
the demand/supply situation on the tobacco world market and tobacco output have the most signicant eect
on the investment.
7. Probability analysis
The results of the probability analysis are shown in
Figs. 2 and 3 for the economic parameters of IRR and
NPV, respectively.
7.1. IRR
The cumulative probability distribution diagram in
Fig. 2 shows that there is a 15.5% likelihood that the
IRR would be less than 40% and a likelihood of
88.5% that the IRR will not exceed 20%.
Compared with the original prediction of an IRR of
18.87%, the results of the probability analysis for the
IRR show a likelihood of a much lower IRR, which
has its mean value at 15.36% (which should replace
the original prediction of 18.87%).
Therefore, the project appears to be very risky based
on the ranges used in the analysis.
7.2. NPV
The cumulative probability distribution diagram in
Fig. 3 shows that there is a likelihood of 18.9% that
the NPV is worse than US$ 4 670 000 and a 84.7%
likelihood that the NPV will not exceed US$ 1 330 000.
The mean value of US$ 925 000 should replace the
original prediction of US$ 637 000.
353
354
8. Risk mitigation
Mitigation of the identied risks is now carried out.
A result of this risk mitigation exercise will be that the
ranges of the variables whose risks were mitigated will
be reduced. Then new results will be calculated and
depicted in new diagrams after sensitivity and probability analyses.
Risk mitigation can be done for all the identied
risks:
. The negative risk of tobacco production management
can be reduced by an extremely thorough search
and recruitment drive for a competent and reliable
farm manager. The recruited farm manager must
make sure that project management tools like quality management, risk management, human resource
management, nance and production management
are used and proper planning and implementation
of plans and monitoring takes place.
. The identication of tobacco curing management as a
signicant risk requires that special emphasis is
made on this activity. The potential of the tobacco
leaf which it possessed at the time of reaping cannot
be improved by curing. Curing alters the leaf into a
dierent state by yellowing (colouring) and drying.
Bad curing can spoil a potentially good leaf. Therefore only negative risks are allocated to curing management. The negative range can be reduced by risk
mitigation measures, good quality management with
a detailed quality plan and work instructions will
help. The farm manager must train and closely
supervise the people who are working in the curing
section. The manager should gather as much knowledge about tobacco curing as possible by consulting
experts in tobacco curing.
. The only risk which can be totally mitigated is the
(negative) risk of destruction of tobacco by hail. The
tobacco farmer can transfer this risk by buying a
hail insurance. Typical premiums for hail insurance
is approximately 2.5% of the total cost of production. The compensation covers the damage of
the crop by hail and, together with the farmers salvage operations, should retrieve the cost of production for the next growing season. The premium
for the tobacco hail insurance is already included in
the cost of production calculation.
. The negative risks of weather can be reduced by the
construction of an irrigation system to mitigate the
impact of droughts. In the case of heavy rains risk
. The advance selling of (part) of the crop on a contract basis reduces the negative and positive risks of
the change in prices of tobacco and paprika (provoked by a change in the demand/supply situation on
the tobacco and paprika world markets ).
. The negative range of the variable direct costs of
tobacco and paprika production can be reduced by
purchasing machinery, equipment and inputs
together with other farmers in order to get discounts, by developing supply options in other
countries and by keeping foreign exchange accounts
in the host country and in a hard currency country,
where this is allowed. Information on upcoming
changes of the labour rates (which are often set by
government) must be gathered and included in the
budget calculations.
Practices of government interference like the prohibition of the export of capital have been abolished
after pressures on the government of many developing
countries from the International Monetary Fund
(IMF) and the World Bank to liberalise developing
country economies. The reintroduction of such
measures would cause the IMF and World Bank to
stop loan payments and therefore would threaten the
stability of the host country government which needs
loans from these institutions in order to stabilise the
economy [6].
355
356
Fig. 6. Cumulative probability distribution diagram (after risk mitigation measures) IRR.
357
tion are shown in Figs. 6 and 7 for the economic parameters IRR and NPV.
9.1. IRR
The cumulative probability distribution in Fig. 6
shows that there is a likelihood of 15.7% that the IRR
is less than 8% and a likelihood of 92.4% that the
IRR will not exceed 33%.
The mean value of the IRR of 23.20% compares
with 18.87% of the original prediction and with the
mean value of 15.36% of the probability analysis
before risk mitigation (and should replace this value).
After risk mitigation the project appears to be very
promising as it shows a better value for the IRR than
the value of the original prediction.
9.2. NPV
The cumulative probability distribution in Fig. 7
shows that there is a likelihood of 17.9% that the
NPV is worse than US$ 635 000 and a likelihood of
86.9% that the NPV will not exceed US$ 3 365 000.
358
Table 2
Original prediction and mean value of probability analysis (IRR and NPV)
Original prediction
Mean value of probability analysis before risk mitigation
Mean value of probability analysis after risk mitigation
IRR (%)
NPV (US$)
+18.87
15.36
+23.20
+637 000
925 000
+1 592 000
Table 3
Key nancial indicators (after risk mitigation)
IRR (original prediction) (%)
Mean value of IRR of probability analysis (after risk mitigation measures) (%)
NPV (original prediction) (US$)
Mean value of NPV of probability analysis (after risk mitigation measures) (US$)
Cash pay back time (yr)
Discounted cash pay back time (yr)
Net cash balance (accumulated net cash ow after yr 11 of appraisal period) (US$)
Maximum cash lock up (US$)
Equity invested (US$)
Maximum borrowing (in yr 6 of appraisal period) (US$)
Bank loan for investments in yr 11 of project appraisal period (US$)
18.87
23.20
637 000
1 592 000
5.92
9.07
5 657 000
3 770 000
3 500 000
5 783 000
3 424 750
11. Conclusions
Risk management can be applied to any investment
project. Projected cash inows and outows form the
359
basis of a project's economics. The commercial viability of a project can be assessed initially on the basis of
those economics. Once a base model has been developed the eects of risks on any activity can be simulated. The ranges used in this simulation will be based
on experience and past data or in some cases be subjective. The results of risk analysis, both sensitivity and
probability can identify the quantitative eect on a
projects economics should such risks occur. Mitigation
of some commercial risks identied in these analyses
can be reduced by laying o risks through insurance
cover, hedging currencies and selling produce on a
contract led basis.
Although the CASPAR programme was initially
developed to appraise construction projects having
both a construction and operation (revenue generation) period the programme can be used to appraise
any type of investment where costs and revenues can
be allocated to a network of activities.
The risk analysis and subsequent risk mitigation
provides information to potential lenders or equity
providers to the project and forms part of the business
plan. Promoters of projects providing this type of risk
analysis are far more likely to receive a positive response from lenders than those Promoters oering
only a projects economics.
In the case study presented the analysis of the ranges
and distributions chosen indicated an optimistic outcome regarding the projects commercial viability.
The two crops of tobacco and paprika were considered in the case study, however, the same risk management framework and CASPAR programme can be
used to analyse the risks for any type of agricultural
investment and form the basis for a risk mitigation
exercise.
References
[1] Haynes ME. Project management: from idea to implementation.
London: Kogan Page, 1990.
[2] Guide to CASPAR: version 3.10. Project Management Group,
Department of Civil and Structural Engineering, UMIST,
Manchester, 1989.
[3] Pouliquen LY. Risk analysis in project appraisal. World Bank
Occasional Papers No. 11. International Bank for
Reconstruction and Development, 1972.
[4] Gittenger JP. Economic analysis of agricultural projects. The
economic development of the world bank. 2. Baltimore: The
John Hopkins University Press, 1994.
[5] Merna A, Dubey R. Financial engineering in the procurement of
projects. Asia Law and Practice 1998.
[6] Merna A, Njuri C. Financing and managing projects. Asia Law
and Practice 1998.
[7] Bannock G, Manser W. International directory of nance. 2.
London: Penguin Books, 1995.
[8] Franke A. Risk analysis in project management. International
Journal of Project Management 1987;5(1).
360
Tony Merna is a part time lecturer in the Centre for Research in the
Management of Projects, UMIST and senior partner of Oriel Group
Practice. After graduating he was involved in the planning, construction and supervision of major highways and infrastructure projects
in southern and central Africa. From 1979 to 1988 he was a project
manager on a number of major infrastructure and process facilities
in the Middle East and south-east Asia. During the last 11 years he
has been involved in advising both UK and international organisations on methods of implementing and nancing turnkey/concession/franchise/BOOT contracts for process, water, transportation
and infrastructure facilities.