Anda di halaman 1dari 25

A1700 Programmable

Polyphase Meter
Chapter 7 - Installation
M120 001 7S
5.2007

A1700 Chapters
Chapter 1
Chapter 2
Chapter 3
Chapter 4
Chapter 5
Chapter 6
Chapter 7
Chapter 8
Chapter 9

Introduction
Overview
Hardware
Communications
Input/Output
Installation
Software Support
IEC 870 Meter (Special)
T. L Compensation (Special)

M120 001 1
M120 001 2
M120 001 3
M120 001 4
M120 001 5
M 120 0016
M120 001 7
M120 001 8
M120 001 9

Date
14/8/2008

Minor Modification Record


Mode
Removal of Bezel & Bracket

A1700 Meter Users Manual - Chapter 7

_______________________________________________________
CONTENTS
1

SCOPE ............................................................................................................................... 3

FOREWORD ...................................................................................................................... 4

SAFETY ISSUES ............................................................................................................... 5

COMPLIANCE WITH STANDARDS AND EUROPEAN DIRECTIVES ............................ 8

INSTALLATION ................................................................................................................. 9

5.1
5.2
5.3
5.4
5.5
5.5.1
5.5.2

Receiving the Equipment.................................................................................................... 9


Handling.............................................................................................................................. 9
Storage ............................................................................................................................... 9
Installation Site ................................................................................................................... 9
Installing the Meter ............................................................................................................. 9
Mechanical.......................................................................................................................... 9
Electromagnetic Compatibility (EMC)............................................................................... 10

TERMINAL ARRANGEMENTS ....................................................................................... 11

COMMISSIONING............................................................................................................ 11

7.1
7.2
7.3

Initial Checks .................................................................................................................... 11


Power on........................................................................................................................... 11
System Test...................................................................................................................... 12

READ WITHOUT POWER ............................................................................................... 12

8.1
8.2
8.3

Battery Installation ............................................................................................................ 12


Testing the Battery Read Operation ................................................................................. 13
Return of AC Supply ......................................................................................................... 13

AUXILIARY VOLTAGE FOR POWER SUPPLY ............................................................. 13

9.1
9.2

Auxiliary Supply Connection............................................................................................. 13


Technical Data.................................................................................................................. 14

10

FAULT FINDING GUIDE.................................................................................................. 14

11

HAZARDOUS SUBSTANCES......................................................................................... 15

11.1
11.2

Battery .............................................................................................................................. 15
Liquid Crystal Display ....................................................................................................... 15

Figures
Figure 1:
Figure 2:
Figure 3:
Figure 3a:
Figure 4:
Figure 5a:
Figure 5b:
Figure 5c:

Terminal Arrangements .................................................................................................... 16


Relay Contact Output Circuit ............................................................................................ 17
Outline Diagram and Fixing Centres (Standard Terminal Cover) .................................... 18
Outline Diagram and Fixing Centres (Short Terminal Covers) ........................................ 19
Battery Housing or A.C. Auxiliary Supply ......................................................................... 20
Fault Finding Chart ........................................................................................................... 21
3 Phase 4 Wire CT Operated Meters ............................................................................... 22
3 Phase 3 Wire CT Operated Meters ............................................................................... 23

Elster Metering Limited - M120 001 7S - 5/2007

A1700 Users Manual - Chapter 7


______________________________________________________________________________

Elster Metering Limited - M120 001 7S - 5/2007

Installation Instructions
______________________________________________________________________________

Installation Instructions
1

SCOPE
This Chapter covers the installation of all versions of A1700 meters.
For information on installing modules, refer to Chapters M120 001 4 (Communications) and
M120 001 5 (Input/output).
Before installing an A1700 meter Check the meter type is correct for the installation.
Read Section 2 (Health and Safety) and Section 3 (Safety Issues) of this Chapter.

A1700 Users Manual - Chapter 7


______________________________________________________________________________

FOREWORD

HEALTH AND SAFETY WARNING

Compliance with Instructions in this Manual


The instructions and information in this manual are provided in compliance with
Section 6 of the UK Health and Safety at Work Act, as amended by Schedule 3 of
the Consumer Protection Act 1987.
The purchaser is responsible for making sure that everyone, whether in his
employment or not, who will be associated with the products supplied by Elster
Metering Systems, and to which these instructions and information apply,
are made familiar with the contents of this manual.
This applies to all persons who may be involved in activities such as unpacking,
inspecting, testing, setting, cleaning, installing, commissioning, operating,
maintaining, decommissioning or disposing of the products.
Safety of Persons using Electrical Products
Employers are reminded that they have a duty to ensure, as far as is reasonably
practicable, the Health, Safety and Welfare at work of all their Employees.
Employers must therefore ensure that employees are informed, trained and
supervised and use proper working procedures to ensure the safety of themselves
and others. The information provided in this manual is intended to ensure that
products are properly installed and otherwise handled in order to maintain them in a
safe condition.
In the UK, employers have duties under the Health and Safety at Work Act 1974 and
the various regulations stemming therefrom.
In countries outside the UK, employers should ensure proper compliance with the
Health and Safety Legislation which is applicable to them.
Putting into Service
Products supplied by Elster Metering Systems have been designed and
manufactured, in accordance with appropriate standards, to operate under specified
conditions, when properly installed.
The purchaser or delegated contractor is responsible for the "Putting into Service" of
any Elster Metering Systems product supplied as "Non-connected". All related
activities must therefore be carried out with due regard to any applicable legislation,
standards and good practice.

Elster Metering Limited - M120 001 7S - 5/2007

Installation Instructions
______________________________________________________________________________

SAFETY ISSUES

WARNINGS

Live parts
The A1700 meter is provided with a 'terminal cover plate' that should always be fitted
on installation. The terminal cover plate provides protection for the main terminals
whilst, for example, modules are being installed. Only if the terminal cover plate is in
place should any attempt be made to remove the meter terminal cover unless all
supplies have been isolated. Failure to follow this instruction may result in electrical
shock or death.
Live parts will be exposed when the terminal cover plate or the main cover is removed.
An optional PP3 rechargeable NiMH battery for read without power may be fitted under
the meter terminal cover. The battery will be connected to either neutral (3 phase 4
wire meters) or B phase (3 phase 3 wire meters). All supplies connected to the meter
must be isolated before any attempt is made to fit or remove the battery and its
container. Failure to follow this instruction may result in electrical shock or death.
Removal of the main cover invalidates the certification of certified meters.
Direct connected meters have electrical connections between the measured voltage
terminals and measured current terminals.
CT connected meters have electrical connections between the measured voltage
terminals.

Warning Labels
A warning label is fixed to the meter, on the top of the terminal cover plate.
The label contains an exclamation mark in a black triangle, to indicate that reference
should be made to the manual.
The label also contains the words "live parts exposed when this cover is removed".
Further warning labels will be fitted where other optional features are present.

Battery Warnings
The meter contains a Lithium manganese dioxide battery. This battery is completely
safe under normal conditions. However, it must never be recharged, disassembled,
heated above 100 C, incinerated, or have the contents exposed to water.
Fire, explosion or severe burns may result if these instructions are disregarded.
In the interests of safety, environmental protection and possible legislation, Lithium
batteries require careful disposal.
Before arranging for the disposal of these cells, users should satisfy themselves that
the proposed means of disposal is both safe and compliant with local legislation
requirements.
continued.......

A1700 Users Manual - Chapter 7


______________________________________________________________________________

WARNINGS (continued)

Elster Metering Systems would like to draw the user's attention to the International
Standard for Lithium Batteries - IEC 60084-4. - which gives further information about
the handling, storage, transport and disposal of lithium cells.
Elster Metering Systems should be contacted by the user should difficulties arise in
arranging proper disposal. They will, if practical, help the user identify safe disposal
means.
The NiMH PP3 battery for read without power is not classified as hazardous waste,
but disposal of these batteries should be in line with local legislation.
The battery must not be disassembled, opened, short - circuited, heated above
+100 C or incinerated. It should not be charged by any other means than installation
into the meter.

Auxiliary Voltage for Power Supply


The maximum voltage for the auxiliary voltage supply is 265V a.c.
The supply must be protected by a suitably rated fuse. (See Section 9.2, Technical
Data).
All supplies connected to the meter must be isolated before disconnecting the cable.
Liquid Crystal Display
Liquid crystals are toxic. If a display is damaged, avoid contact with the liquid. If the
liquid makes contact with the skin it must be washed off immediately with water.
Seek medical advice.

Modules
Only modules of the appropriate type and supplied by Elster Metering Systems
should be inserted into the two A1700 meter module apertures. Inappropriate use of
these apertures could result in contact with hazardous voltage. See Chapters M120
001 4 and M120 001 5.
continued.......

Elster Metering Limited - M120 001 7S - 5/2007

Installation Instructions
______________________________________________________________________________

WARNINGS (continued)

Operation on Different Power Systems


The A1700 allows for 3 manufacturing configurations for use on the following power
systems:
Configuration 1 - 3
elements
3ph 4w
2ph of 3ph 4w (Note 1)
2ph 3w (Note 1)
1ph 3w (Note 1)
1ph 2w (Note 1)

Configuration 2 - 3
elements
3ph 4w
3ph 3w (Note 1)
Note 2: For this configuration
the yellow phase failure should
be disabled and the phase fail
threshold reduced to about
40%.

Configuration 3 - 2
elements
3ph 3w

The pulse value of the test indicator is that marked on the nameplate regardless of the
power system to which the meter is connected. This means that the pulse rate of the
test indicator at Imax will be less for systems not using all elements.

UNUSED TERMINALS
Note 1: (See configuration table above).
Meters installed with these configurations will have unused main terminals.
To avoid accidental or fraudulent contact with these unused terminals, it is strongly
recommended that either:
1. Full terminal covers without cut-outs are used
2. If terminal covers with cut-outs or short terminal covers are used, then suitable
insulated blanking plugs are fitted into used terminals

A1700 Users Manual - Chapter 7


______________________________________________________________________________

COMPLIANCE WITH STANDARDS AND EUROPEAN DIRECTIVES


A1700 meters and their internal modules delivered to customers for use in European
Economic Area (EU & EFTA) countries are CE marked to indicate compliance with the
requirements of the Electromagnetic Compatibility Directive.
This compliance has been demonstrated by subjecting representative samples of the
product, installed in accordance with the instructions and guidelines given in this
document, to the tests prescribed in the following standards :EN 50081-1: 1992, Electromagnetic compatibility generic emission standard - part 1 :
Residential, Commercial and Light Industry.
EN50082-1: 1992, Electromagnetic compatibility generic immunity standard - part 1 :
Residential, Commercial and Light Industry.
EN60687: 1996, Alternating current static watt-hour meters for active energy(Class 0.2s and 0.5s).
EN 61036: 1996, Alternating current static watt-hour meters for active energy(Class 1 and 2).
EN 61268: 1996, Alternating current static var-hour meters for reactive energy(Class 2 and 3).

The A1700 with the large character display conforms to:


The essential requirements of the directive 2004-22/EC on Measuring Instruments (MID)
The general requirements and particular requirements of EN 50470 Parts 1 & 3, and complies
with Class M2 Mechanical environment and Class E2 Electromagnetic Environment
IEC 62053 - 21

kWh, Class 1 & Class 2 Static

IEC 62053 - 22

kWh, Class 0.2 and 0.5 Static

IEC 62053 - 23

kvarh, Class 2 and 3 Static

IEC 62052 - 11

General Requirements

IEC 62053 - 61

Power Consumption and Voltage Requirements

EN 50470 1-3

kWh Class A, Class B or Class C

The user can therefore be confident that, provided the guidelines and instructions are
properly followed, all units installed will satisfy the requirements for residential, commercial
and light industrial premises.
Elster Metering Systems holds on record the appropriate Declaration of Conformity, and
supporting documentation, against which the CE mark is affixed.
Devices for metering and billing electrical energy described in this manual are supplied for
use in a Fixed Installation only. Devices described are a component of a system only and
therefore outside the scope of European Directives 2002/95/EC RoHS (Restriction of the
Use of Certain Hazardous Substances in Electrical Equipment) and 2002/96/EC WEEE
(Waste Electrical and Electronic Equipment).

Elster Metering Limited - M120 001 7S - 5/2007

Installation Instructions
______________________________________________________________________________

INSTALLATION

5.1

Receiving the Equipment


Check that the meter type is correct for the installation.
Remove the equipment from its container and inspect for damage.
If damage has been sustained in transit a claim should be made immediately to the transport
company and a report sent to the Elster Metering Systems or their branch office or agent.

5.2

Handling
In its container the equipment is very robust and no special handling precautions are
required. Some care should be taken when the equipment is unpacked to avoid marking
or scratching it.

5.3

Storage
If the equipment is not required for a prolonged period, the meter should be returned to
its original packing (including plastic bag) and stored in a dry place.
Storage temperature:

-25 C to +70 C

Humidity:Annual mean 75% (for 30 days spread over one year, 95%)

5.4

Installation Site
The site should be free from excessive vibration and preferably have a clean, dry
atmosphere.
For optimum viewing of the display the meter should be mounted at eye level and within
30 of the vertical.
Avoid mounting the meter in direct sunlight.
Note that the meter is constructed to BS EN 61010 -1 Safety Class II (All Insulated) and
that no Safety Earth is required.

5.5

Installing the Meter

5.5.1

Mechanical
1. The meter must be securely fixed to the wall using all three fixing positions. (See
Figure 3). The top fixing can be used in three positions
2. The current terminals will accept a cable size of 35 sq. mm maximum. The screws
are M6 pinch screws and should be tightened to a torque of 2.2 N m (minimum), 2.8
N m (maximum)
3. The voltage terminals (for transformer connected meters) will accept a cable size of 5
sq. mm maximum. The screws are M3 pinch screws, which should not be tightened
more than 0.45 N m
4. The auxiliary terminals will accept a cable size of 1.5 sq. mm maximum. The screws
are M2.5 pinch screws, which should not be tightened more than 0.34 N m. In order
not to stress the retainer inside the terminal the cable size must not be less than 0.4
sq. mm minimum. Single strand wire is recommended but if multi strand wire is used,
it must not be folded prior to insertion into the terminal

10

A1700 Users Manual - Chapter 7


______________________________________________________________________________

5. An appropriate fuse must protect any auxiliary output circuits that are connected to
an a.c. supply
6. For direct connected meters, ensure that the voltage connection links are correctly
positioned
7. Check that all screws are tight
8. Fit the terminal cover plate and terminal cover, See Figure 3 (standard terminal
cover), Figure 3A (short terminal cover and DIN standard accessories terminal
cover)

5.5.2

Electromagnetic Compatibility (EMC)


The A1700 meter has been designed and tested for compliance with the EMC Directive.
It is, however, the responsibility of the installer for ensuring that a system conforms to the
Directive.
In order to assist the installer the following guidelines are given: 1.
2.
3.
4.
5.
6.
7.

Keep a.c. circuits and d.c. circuits separated by a minimum of 50mm where possible
Where a.c. and d.c. circuits must cross, do so at right angles to each other
The cables for each circuits must be bunched together to minimise the loop area
enclosed
The cables for the relay outputs and auxiliary inputs must use a twisted pair
Where the environment is electrically hostile screened, twisted pair cable may be
required. The screen must be connected to earth at one point only
Ancillary equipment must also be CE marked
If interposing relays are used (a.c. or d.c.) then these must be correctly and
adequately suppressed

WARNINGS
Cables for the auxiliary terminals should be routed straight down or routed sideways
using the two knock-outs in the terminal cover. They should not cross the centre line.
Cables at potential greater than 40V should remain segregated from those at lower
voltages.
The Installer is responsible for ensuring that all connected cables are adequately rated
for the application and all voltage and signal circuits are adequately protected by fuses.
It is recommended that direct connected meters are protected by fuses equal to the
meter rating i.e. 100A fuse for a 100A meter. Failure to do so may result in damage or
fire.

Elster Metering Limited - M120 001 7S - 5/2007

Installation Instructions
______________________________________________________________________________

TERMINAL ARRANGEMENTS
Figure 1 shows the general terminal arrangements of the meter.
The terminal functions are as follows: a.
b.
c.
d.

Terminal 1, 2 & 3
Terminal 4, 5 & 6
Terminal 7, 8 & 9
Terminal 10 &11

Phase A
Phase B
Phase C
Neutral

NOTE 1: These are the phase current and voltage terminals.


NOTE 2: Meter connections must always be made as detailed on the diagram
supplied with the meter.

COMMISSIONING

7.1

Initial Checks
Check that the supply rating on the nameplate and the meter configuration agree with the
system supply being used.
Check that the connections shown on the connection diagram agree with terminal block
arrangement.
Check that the wiring connections are correct and that there is no danger of the low voltage
signal circuit coming into contact with high voltages.

7.2

Power on

WARNINGS
Live terminals will be exposed if the terminal cover and terminal cover plate are
removed.
The circuit board under the main cover may be at line potential. Contact with this circuit
board may result in electrical shock.

Observe all Safety issues in Section 3.


Check that the terminal cover plate and terminal cover are fitted.
Switch on the a.c. supply.

11

12

A1700 Users Manual - Chapter 7


______________________________________________________________________________

7.3

System Test
The liquid crystal display on the meter should immediately show data. The meter may
then start to autocycle through any register data programmed for the autocycle mode.
Two indicators, in the form of pulsing LEDs are provided. The right indicator monitors
active energy and left indicator monitors reactive energy.
The LED's will be continually 'ON' if the connected active/reactive load is below the
anti-creep threshold, but will pulse at a rate proportional to load if above that level.

READ WITHOUT POWER


A1700 type PB****S***
Read without power is supported by an Optional Battery Housing with a PP3, NiMH, 9V
rechargeable battery that fits under the terminal cover (See Figure 4). The battery connects
to the meter terminal block via a four pin connector which is mechanically polarised and
has a locking mechanism. Data can be viewed on the LCD by pressing the display
pushbutton or read via the optical communications port.
WARNING Use only the battery supplied with the meter. If a voltage of greater than 16V
(d.c. or a.c.) is connected to the battery connection an internal fuse will operate. Normal
meter operation will not be effected. The fuse is not accessible externally and it will be
necessary to return the meter to Elster Metering Systems to replace the fuse.

8.1

Battery Installation
1.

Observe all safety precautions in Section 3 of this manual

2.

Make all required connections to the meter (see Section 5)

3.

If meter commissioning is required before the Battery Housing is fitted, this should
be carried out first. However all meter supplies must be isolated again before
proceeding to the next stage (See Section 3 on Safety Issues)

4.

Plug the lead from the Battery Housing into the four pin socket in the terminal block
(See Figure 4) making sure it clicks into place. Note that the connector is
mechanically polarised

5.

Hang the Battery Housing on the terminal cover screw fixing bosses (See Figure 4)

6.

If the battery is known to be charged, the battery function can now be tested (See
Section 8.2)
If the battery is discharged, then it should be connected to the energised meter for at
least 48 hours before conducting the battery function test

Elster Metering Limited - M120 001 7S - 5/2007

Installation Instructions
______________________________________________________________________________

8.2

8.3

Testing the Battery Read Operation


1.

With all meter supplies removed, press the display pushbutton and keep it pressed
until the display activates (in about 2 seconds). Note that during this 2 second period
the red test indicators will be on

2.

Further presses of the display pushbutton will cause the display to step through the
normal display list (default and consumer displays)

3.

Once the battery operation has been activated, data can also be read via the optical
communications port using a PC and probe

4.

If, after 30 seconds, the display pushbutton has not been pressed or the optical port
has not been used, battery operation will be deactivated

Return of a.c. Supply


If the meter a.c. supply returns while the Read Without Power battery function is active,
the meter will immediately terminate the function and start a normal power-up
The display will show ELSTER METERING and both red test indicators will initially be on.
If the optical communications port is being used when the a.c. supply returns the
communications session will be interrupted. The communications session must be
restarted when the meter is fully functional

AUXILIARY VOLTAGE FOR POWER SUPPLY


A1700 type PB****T***
A1700 meters designed for auxiliary power operation are fitted with a four pin connector
to enable the meters to be energised from a single phase a.c. supply which is
independent of the measurement voltages.
The connector which is mounted in the terminal block (See Figure 4) is mechanically
polarised and has a locking mechanism.
In order to facilitate installation, a cable terminated with a mating connector is supplied
with the meter.

9.1

Auxiliary Supply Connection


1.

Observe all safety precautions in Section 3 of this manual

2.

Remove the meter terminal cover and terminal cover plate

3.

Make all required connections to the meter (see Section 5)

4.

Using the cable supplied, push the connector into the mating socket (See Figure 4) in
the terminal block until it clicks into place

5.

Connect the cable with the brown identifier to the live terminal of the auxiliary supply
via a suitable fuse (Auxiliary voltage surge at switch on 4A for 0.002 seconds)

6.

Connect the cable with the blue identifier to the neutral terminal of the auxiliary power
supply

7.

Note that the routeing for the cables should follow the EMC guidelines in Section 5.2.2

8.

When the installation has been completed commissioning can commence. Note that
the meter will not function if the auxiliary power supply is not energised.

13

14

A1700 Users Manual - Chapter 7


______________________________________________________________________________

9.2

Technical Data
Auxiliary Voltage Operating Range
Minimum:
70V
Maximum:
265V
Frequency:
50Hz or 60Hz
Burden
Single phase:

1.9W 4.17VA

Surge current
Auxiliary voltage surge current at switch-on:

4A for 0.002 seconds

Insulation
Between
a) The auxiliary voltage and the measurement voltage:
b) The auxiliary voltage and the measurement current:
c) The auxiliary voltage and relay outputs:

1kV a.c. for 60 seconds


2.5kV a.c. for 60 seconds
4kV a.c. for 60 seconds

External cable supplied for the auxiliary voltage connection: 4kV a.c. for 60 seconds

10

FAULT FINDING GUIDE


Because of the integrated nature of the design of the A1700 meter, it is not possible to fault
find without specialised equipment.
It is therefore recommended that faultfinding is limited to deciding whether the fault is
inside or outside the meter. If the meter is not functioning correctly, the fault finding guide
in Figure 5a should be followed.
For transformer operated meters, if the meter is not registering correctly the fault finding
guide in Figure 5b or 5c should be followed.
Faulty meters should be returned to Elster Metering Systems for examination and repair.

Elster Metering Limited - M120 001 7S - 5/2007

Installation Instructions
______________________________________________________________________________

11

HAZARDOUS SUBSTANCES

11.1

Batteries
If the main cover is removed from the meter then a Lithium manganese dioxide battery
will be exposed. An optional PP3 Nickel Metal Hydride battery is also used to support
Read Without Power.
These batteries are completely safe under normal conditions. However, they must never
be recharged except in accordance with Manufacturer instructions, disassembled, heated
above 100C, incinerated, nor have the contents exposed to water.
Fire, explosion or severe burns may result if these instructions are disregarded.
In the interests of safety, environmental protection and possible legislation, these
batteries require careful disposal.
Before arranging for the disposal of these cells, users should satisfy themselves that the
proposed means of disposal is both safe and compliant with local legislation
requirements.
Elster Metering Systems would like to draw the user's attention to the International
Standard for Lithium Batteries - IEC 60084-4. - which gives further information about the
handling, storage, transport and disposal of lithium cells.
The user should contact Elster Metering Systems should difficulties arise in arranging
proper disposal. They will if practical, help the user identify safe disposal means.

11.2

Liquid Crystal Display


Liquid crystals are toxic. If a display is damaged, avoid contact with the liquid.
If the liquid makes contact with the skin it must be washed off immediately with water.
Seek medical advice.

15

16

A1700 Users Manual - Chapter 7


______________________________________________________________________________

17
18
19
20
21
22

RL1 N/O
RL1/3 COM
RL3 N/O
RL2 N/O
RL2/4 COM
RL4 N/O

Optional Relays 1 to 4

Terminal 1, 2 & 3
Terminal 4, 5 & 6
Terminal 7, 8 & 9
Terminal 10 &11

Figure 1:

Phase A
Phase B
Phase C
Neutral

Terminal Arrangements

Elster Metering Limited - M120 001 7S - 5/2007

Installation Instructions
______________________________________________________________________________

Relay 1
Relay 2
Relay 3
Relay 4

Figure 2 :

Terminal Pair
a (Com)
18
21
18
21

Relay Contact Output Circuit

b
17
20
19
22

17

A1700 Users Manual - Chapter 7


______________________________________________________________________________

M
o

7
1

in
m
l
a
d
o
stru
b
c
e

r
c
in
m
h
ve
o
b
tlya

re
i
u
q
w
b
td

trli
c
fn
o
e

ti
n
o
rm
e
p
u
g

y
d
n
a
w
re
sc
3

.
0

3
.5

3
1

.7
9
1
5

.6
8
7

.0
1
8

18

H
E
L
B
A
C

.8
3
2

S
E
L
O

x
0
9
6
IX
.D
5
H
E
L
B
A
C

3
5
1
P
.D
S
E
L
O

B
A
.C
5

D
Y
R
T
N
E
L
IA

.1
9
5
.
0
4
1

.
0
5
1

30.0

173.5
81

194.5
174.5

278.6

23.8
cable holes
5.5 dia x 6.3 deep
59.1
cable holes
9.0 dia x 31.5 deep
Cable entry
5.5dia

Figure 3:

140.0
150.0

Outline Diagram and Fixing Centres (Standard Terminal Cover)

Elster Metering Limited - M120 001 7S - 5/2007

208

19

Installation Instructions
______________________________________________________________________________

173.5
81

194.5
174.5

220

80
23.8
140
150

Short Terminal Cover

81.0

35.0

100.0

80.0

60.0 74.0

Short Terminal Cover for DIN Standard Accessories

Figure 3a:

Outline Diagram and Fixing Centres (Short Terminal Covers)

208

20

A1700 Users Manual - Chapter 7


______________________________________________________________________________

Socket for battery read


without power or auxiliary
a.c. supply

Figure 4:

Battery Housing or A.C. Auxiliary Supply

Elster Metering Limited - M120 001 7S - 5/2007

Installation Instructions
______________________________________________________________________________

Display
OK

a.c.
Supply
OK

Check
Wiring/Fuses

Check
Wiring/Fuses

Repair
Aux
Equipt

Repair
Wiring

Y
Y
LED
Pulsing
OK

Current
Supply
OK

Relay
Output
OK

Aux
Equipt
OK

Y
Y
Relay
Wiring
OK

Meter
OK

Replace
Meter

Y
END

Check metering load greater than the anti-creep threshold

For meter models with relays fitted

Figure 5a:

Fault Finding Chart

21

22

A1700 Users Manual - Chapter 7


______________________________________________________________________________

3 Phase, 4 Wire CT Operated kWh Meters


Fault Finding Chart

Meter
Registers
Reverse
Energy

LED
Pulses at
1
/3 Rate

LED
Not Pulsing

Any One
CT Connected
in Reverse

No Current
Applied
to Meter

Any of Two
Phases of Voltage
or Current
Connections are
Interchanged
(See Table 1)

Register
Reading is
Low

All Three CT
Connections are
Reversed. (LED
Pulses Full Rate)

Check Meter
Voltage Fuses

Any Two CT
Connections are
Reversed
(LED Pulses 1/3
Rate)

Check
Programming of
Register Cat.
VT Ratio
CT Ratio
CT Error

Reverse Phase
Sequence on
Voltage or Current
(See Table 2)
LED Pulses 1/2 Rate

Table 1
Voltage Connection Current Connection
A B C
A C B
B A C
A B C
C B A
A B C
A C B
B A C
C B A

B C A
C A B

A B C
A B C
A B C

Represents Wrong Connection

Figure 5b:

Table 2
Voltage Connection
Current Connection
B C A
A B C
C A B
A B C

Standard Connections
Voltage: A B C
Current: A B C

3 Phase 4 Wire CT Operated Meters

Elster Metering Limited - M120 001 7S - 5/2007

A B C
A B C

Installation Instructions
______________________________________________________________________________

3 Phase, 3 Wire CT Operated kWh Meters


Fault Finding Chart

LED
Not Pulsing

LED
Pulses at
1
/2 Rate

No Current
Applied
to Meter

B Phase
Connection
Loose or Missing

Meter
Registers
Reverse
Energy

Both the CT
Connections are
Reversed

Check Meter
Voltage Fuses

Check
Programming of
Register Cat.
VT Ratio
CT Ratio
CT Error

Any of the Two


Phases of Voltage
or Current are
Interchanged
or Reversed

Voltage Connection
A B C
A B C
A B C

Current Connection
C A
A C
A C

A C B
B A C
C B A

A C
A C
A C

Represents Wrong Connection


Represents Reversed Connection

Figure 5c:

Register
Reading is
Low

3 Phase 3 Wire CT Operated Meters

23

Anda mungkin juga menyukai