Question 1
You are assigned to describe the process for selecting a drilling unit for drilling a
well in a water depth of 100m.
a. What type of drilling rig you are going to select and why?
We are going to select Jack-up drilling rig because:
b. What is the process for drilling (brief description) for a dry hole completion?
i) The first step is the insertion of the drilling bit along with the collar and drill pipe in
the hole.
Due to the weight of the thick walled pipes that are above the drill bit (drill
collars), it is cutting inside the rock. There are various types of drilling bits but
the main two working principles are the following:
1) The one disintegrates the rock by compression failure,
2) And the other shear slices off the rock as the bit turns.
ii) The second step is to attach the Kelly and the Turntable and begin drilling.
iii) After that the mud circulates through the pipe and out of the bit in order to float
the rock cuttings out of the hole.
The so called mud or drilling fluid is pumped inside the drill pipe and reaches
the drill bit where it helps it to make the hole.
Reference: http://www.seadrill.com/tcp/modules/module_123/proxy.asp?D=2&C=72&I=2075&mid=147
Afterwards the casing must be cemented by placing the casing pipe sections
inside the hole in order to keep it safe from collapsing. The spacers located
outside the casing pipe keep it centered in the hole. The cement is pumped
inside the casing pipe using a bottom plug, a cement slurry, a top plug and
drill mud. The mud pressure causes the cement to fill the space between the
outer of the spacing and the hole. After the hardening of the cement it is
tested for hardness, alignment and good seal.
Reference: http://www.bbc.co.uk/news/10370479
The process continues with drilling and new casings are cemented. At the
point where the rock cuttings start to appear oil sand from the reservoir rock
the wells final depth may be reached.
Reference: http://www.bbc.co.uk/news/10370479
The drilling apparatus is removed and the following testings are made after
this procedure.
o Well logging The insertion of electrical and gas sensors into the hole
to take measurements from the rock formations.
o Drill-stem testing - The insertion of a device into the hole to measure
the pressures, which will reveal whether reservoir rock has been
reached
o Core samples - Taking samples of rock to look for characteristics of
reservoir rock.
c. What are the main well controls for preventing accidents from abnormal well
conditions and how they work?
An abnormal well condition is the kick which is explained in the previous question
(1b). Because accidents are the results of these abnormal conditions and have
effects on the equipment and on human life there are some well controls that
prevent this kind of accidents.
Practice and employ trained rig crews in the drilling process to control and
maintain density of fluid, pressure, circulation, etc.
An even more dangerous situation is the case of the abandoned well because the
well integrity must be maintained for a longer period of time.
Pressure can be controlled by remote controlled valves with locking mechanisms. A
remote controlled shear-blind ram must be adopted in well intervention equipment.
It must be noted that a number of well controls are used because if one of them fails
the other must be in position to take action.
off the wellbore) vi)Sever the casing or drill pipe ( only in case of
emergencies).
Reference: http://en.wikipedia.org/wiki/File:Blow_Out_Preventer.jpg
BOP
c) Tertiary (A third option if the first two fail. It takes action in underground
situations. Some examples are: i) to drill a relief well to hit an adjacent well
that is flowing and with heavy mud to kill the well ii) rapid pumping of high
density mud iii) pump barite or heavy weighting agents to plug the wellbore
to stop flowing and iv) pump cement to plug the wellbore.
d. You need to submit a drilling plan. What factors you need to consider in order
providing a safe drilling activity to the right place?
The factors need to be considered depend mainly on the location, the climate, the
noise and generally all the factors that can affect the drilling procedure or
equipment. It is essential that the whole procedure is curried out safely.
Equipment is selected with the following way of thinking:
a. Drilling mud
As written in Question 1b it is a relatively complex mixture of fluids solids and
chemicals. The mixture is different for every case in order to achieve the right
physical and chemical characteristics required to safely drill the well. It can also be
water based or oil based. The first one is cheaper and doesnt need any treatment on
the other hand the oil based needs a ship to curry it onshore to treat it and bring it
back for reinjection. So depending on the pressure or even better estimated well
depth the correct drilling mud is selected and if oil based mud is selected a ship to
curry the mud onshore-if the drilling is offshore-for treatment also must be rented. If
6
Due to the fact that the company wants to apply for three licences, which means
to drill 3 wells, they contacted a drilling contractor to estimate the cost for a dry
hole drilling. The drilling contractors submitted the figures shown to Appendix to
the company.
The company had to review the figures and make comments on them since the
Market Cap is 25 MM pounds.
Please determine if:
a. The costs submitted from the drilling contractor are sufficient to enable the
company to apply for the three licences.
Market Cap = 25MM
For the Fumlar Target, 13,725 ft.:
For the Forties Target, 6,000 ft.:
For the Forties Target, 8,200 ft.:
The costs submitted from the drilling contractor are not sufficient to enable the
company to apply for the three licenses because they exceed the market cap by
3.925MM
2b. In the case that the cost is near to the market cap value or exceed it, please
propose ways that the cost could be reduced considering data given in Kells
environmental statement report.
Some ways to decrease the cost in order to be equal with the market cap are the
following:
1. The pricing for every kind of cost stated on the tables are budgetary cost
estimates and not a proposal to conduct turnkey operations. A way to reduce
the cost, is by estimating the actual cost on a specific type of contract, or
even better a different contract for every step of drilling.
2. As stated on the tables All drilling tangibles supplied by ADTI. Since
tangible costs are borne by the general partner (manager) while intangible
costs are borne by the limited partners (investors), usually to be taken as tax
deductions. In the event of a dry hole, however, all costs become intangibles.
So with these tax deductions we decrease the market cap even more.
3. Try to look for alternatives. For example the rig rate has a value of 310000
dollar/day. Is there another cheaper rig available for the specific well that can
also meet the requirements? A jack up rig maybe that costs less? Another
point with the same way of thinking is the casings. Are there any
alternatives? What else is it possible to be changed? Maybe the drilling mud?
Is it possible to use the cheaper water based mud? If oil based mud must be
used because the well is deep, is it possible to use water based mud and
switch afterwards to oil based?
4. Study the market. Try to find other similar estimations made in the past for
other wells or use already completed contracts in order to debate the
estimations that were given to you. Maybe this is not their final price but the
asking starting price.
5. The final point is to try to reduce the working days. Because everything is
based on working days it is essential to try to find ways to reduce it.
2c. Define the main parameters that made the cost reduced and explain your
approach
The main parameters that made the cost reduced as they did in other cases are the
following:
1)
2)
3)
4)
5)
2d. Based on your proposed approach, is it possible for the company to apply for
the licensing round based on the new data?
Since the ways to drop the final cost are multiple I believe that it is very important to
get the new reviewed tables and calculate the new decreased working plan. Also
since the deeper well will be 100% included in the market cap special attention must
be put there. Also if the final price is not acceptable then it isnt in the best interest
of the drilling contractors not to take the proposed job.
Question 3:
Whilst drilling a 12 1/4" hole section of the new well the following drilling data is
being recorded and provided to the company man. At what point in time would
you have suggested that the bit be pulled and why? Assume an average trip time
of 8 hrs. , a rig rate of 400/hr. and the bit type selected above had been run in
hole. Decision based on the cost of the bit.
TIME ON BOTTOM
(hrs)
1
2
3
4
5
6
7
8
9
10
11
12
FOOTAGE DRILLED
(ft)
34
62
86
110
126
154
180
210
216
226
234
240
Where:
C
10
72,58
56,98
48,18
45,24
39,61
36,11
32,86
33,80
34,07
34,62
35,42
11
Based on the above calculations, we conclude that the point in time that the bit
must be pulled off is at 8 hours, because at that point we have the smallest amount
of overall cost per foot.
Question 4:
4a.Plot the following pore pressure/depth information on a Pressure - depth
diagram (pressure x axis, depth at y axis).
DEPTH BELOW DRILLFLOOR
(ft)
0
1000
5000
8000
8500
9000
9500
PRESSURE
(psi)
0
465
2325
3720
6800
6850
6900
Pressure vs Depth
10000
9000
8000
7000
6000
5000
4000
3000
2000
1000
0
0
2000
4000
6000
8000
4b.Calculate the pore pressure gradients in the formations from surface to:
8000ft, 8500ft, 9500ft.
Gradient pressure=
1) Gradient pressure=
2) Gradient pressure=
=0.465
=0.80
12
3) Gradient pressure=
=0.726
4c.Determine the mud weight (in ppg) required to drill the hole section down to
the following depth assuming that a maximum of 200 psi overbalance on the
formation pore pressure is required.
Where:
P = Hydrostatic Pressure
0.052 = gravitational force
MW = average fluid density
TVD = true vertical depth
1)
2)
3)
4d. If the mud weight used to drill down to 8000ft were used to drill into the
formation pressures at 8500ft, what would be the over/underbalance on the
formation pore pressure at this depth?
o At 8000 ft
Mud pressure:
MW=9,423ppg (from part 4c1)
13
14