Reliability Standards
Effective January 1, 2006
Version 2.0
Edition 1.0
Contents
TRANSMISSION SYSTEM RELIABILITY STANDARDS ........................................1
CONTENTS........................................................................................................................1
CHAPTER 1: INTRODUCTION.....................................................................................4
1.1
1.2
1.3
GENERAL ..............................................................................................................4
APPLICATIONS AND OBJECTIVES OF THE STANDARDS ...........................................5
SCOPE ...................................................................................................................6
Contents
Contents
Contents
Chapter 1: Introduction
1.1
General
1.1.1
1.1.2
The distinct processes and their related Standards are paramount in ensuring
Reliability in planning the development of an Electric Power System, and in
ensuring its Secure and Robust operation:
1) The Generation Reliability Standard which relates to provision of sufficient
firm Generation Capacity to meet the Demand with a sufficient margin with
allowance for Plant maintenance, Plant breakdown and Plant Unavailability,
i.e., scheduled and unscheduled generating Plant outages, to meet the annual
and daily electric energy demand without the need to disconnect customers at
critical periods or cause interruptions in supply. This is used by Tenaga
Nasional Berhad (TNB) to determine additional generation investment
requirements on an annual basis.
2) Transmission Reliability Standard which relates to provision of sufficient
Transmission Capacity, operational facilities, maintenance activity and coordination with generation and Distribution Functions to enable continued
supply of electric energy to the distribution systems and Directly Connected
Customers. This Standard is used by TNB to determine the investment
requirements for the Transmission System and transmission operational
facilities and implement the necessary measures.
The development and maintenance of Transmission System Reliability Standards
is the duty of TNB Transmission Division under the provisions of the TNB
Licence that includes Generation Reliability Standards. These Standards are also
termed as License Standards.
Chapter 1:Introduction
1.1.3
1.1.4
1.2
1.2.1
1.2.2
1.2.3
1.2.4
The Standards also provide the limits and permissible excursions of key System
parameters enabling secure implementation of operational measures.
Chapter 1:Introduction
1.2.5
1.3
Scope
1.3.1
This document only covers the Transmission System Reliability Standards, which
are the responsibility of TNB Transmission Division. Amendments or changes to
these Standards can only be made with the concurrence of the Energy
Commission (EC) as provided for in the TNB License.
1.3.2
This document is solely concerned with the Standards for the Transmission
System, which includes the Main Interconnected Transmission System (MITS)
and its interface with the Generation Systems as well as the other parts of the
Transmission System which have voltages at 132kV and 66kV. These Standards
are applicable to bulk generation, transmission and delivery of electric power.
These Standards are also reflected in the Malaysian Grid Code which contains all
the technical requirements governing the planning, the development, connection
to, and operation of, the Generation and Transmission System as a whole known
as the Grid System.
1.3.3
Figure 1.1 indicates the contents of the Standards and the subject coverage in
terms of the generation, transmission and distribution Security and Reliability.
Chapter 1:Introduction
TOTAL
POWER
SYSTEMS
G
Generation
Reliability
Standards
Transmission
System
Reliability
Standards
Sufficient transmission
capacity to meet demand
for specified contingencies
Meeting standards
performance limits
Transmission
Reliability
Standards
Transmission
Transmission
Power Quality
Standards
Sufficient transformer
capacity to meet demand
Power quality limits at
interfaces
DG
Distribution System
Distribution Supply
Security and Power
Quality Standards
DG
Distribution
Embedded Distribution
Customers
STANDARDS
CODES
DISTRIBUTION CODE
Main Interconnected
Transmission System
GRID CODE
Generation
Figure 1.1: The outline contents of the Transmission System Reliability Standards
and its relationship with the systems and codes
Chapter 1:Introduction
2.1
2.1.1 The Generation Security Standard for the Peninsular Malaysia Electric Power
System shall be the Reliability Index of Loss of Load Probability (LOLP). LOLP
is defined as the proportion of days per 365 days in a year when insufficient
generating capacity is available to serve the daily peak Loads. Alternatively, the
standard can also be defined in term of Loss of Load Expectation (LOLE) which
is a measure of the time duration in a year when insufficient generating capacity is
available to serve the daily peak Loads. Normally, this is expressed in number of
days per year. For the Peninsular Malaysia Grid System the LOLE is normally set
at one (1) day per year, which translates to a LOLP of 0.0274 (ratio of LOLE to
number of days in a year).
2.2
2.2.1
2.2.2
The Largest Loss of Power Infeed Risk for the Peninsular Malaysian Power
System is defined as the largest single generating unit or a CCGT module or a DC
Link Monopole or power import whichever is the largest. In order to ensure the
System is secure after such an event, TNB facilitates the provisions of sufficient
Spinning Reserve and Reactive Power Reserve to avoid deviation of Frequency
and voltage beyond Normal Operational Limits defined in the Transmission
System Power Quality Standard for more than sixty (60) seconds.
2.2.3
The instantaneous Loss of Power Infeed may exceed that of the Largest Loss of
Power Infeed Risk on very rare occasions which may occur for the loss of a
complete Power Station for contingencies outside the planning or operational
Criteria. This is termed an Infrequent Loss of Power Infeed Risk and is defined as
the loss of the largest single power station. For an Infrequent Loss of Power
Infeed Risk, planning and operational limits may be violated but the Transmission
System shall be planned and operated so that while controlled load loss is allowed,
the integrity of the Transmission System is maintained.
2.3
(b) the connection facilities and the Power Station shall not cause any reduction
in the power quality delivered at the Bulk Supply Points to the Distribution
System and/or to a Users Network.
10
2.3.2.4 The connection of a particular Power Station shall meet the following planning
Criteria set out in paragraphs 2.3.2.5 to 2.3.2.8 under the following background
conditions:
(1) the Active Power output of the Power Station and individual Generating Units
shall be set equal to their respective rated power output, and to the
corresponding full leading or lagging Reactive Power output; and
(2) conditions on the Transmission System shall be set to those which ought
reasonably to be expected to arise in the course of a year of operation. Such
conditions shall include forecast demand cycles, typical Power Station
operating regimes and typical arranged transmission equipment outage
patterns modified where appropriate by the provisions of paragraph 2.3.2.5.
2.3.2.5 The Transmission Capacity for the connection of a Power Station shall be planned
such that, for the background conditions described in paragraph 2.3.2.4, prior to
any fault there shall not be any:
(1) equipment loadings exceeding their continuous rating;
(2) voltages outside the Pre-Disturbance Planning Voltage Limits or Insufficient
Voltage Performance Margins; or
(3) System Instability.
The above performance requirements are summarised in Table 4.12, in section
4.11, under system condition classified as Category A No contingencies.
2.3.2.6 The Transmission Capacity for the connection of a Power Station shall also be
planned such that for the background conditions described in paragraph 2.3.2.4
and for the Secured Event of either an Outage of any of the following:
(1) a single Transmission Circuit or element, a reactive compensator or other
Reactive Power resource;
there shall not be any:
a) Loss of Supply Capacity;
b) Unacceptable Overloading of any Primary Transmission Equipment;
c) Unacceptable Voltage Conditions or Insufficient Voltage Performance
Margins; or
d) System Instability.
The above performance requirements, contingencies and impacts are summarised
in Table 4.12, in section 4.11, under system condition classified as Category B
Events resulting in loss of a single element.
2.3.2.7 The Transmission Capacity for the connection of a Power Station shall also be
planned such that for the background conditions described in paragraph 2.3.2.4
and for the Secured Event of a Fault Outage of any of the following:
11
(1) a Double Circuit Overhead Line (with the exception of 500kV and radial
275kV lines), or
(2) a single Transmission Circuit with the prior outage of another Transmission
Circuit (with the exception of 500kV and radial 275kV lines);
(3) a section of Busbar; or
(4) a single Transmission Circuit with the prior outage of a Generating Unit, a
reactive compensator or other Reactive Power resource;
there shall not be:
(a) cascade tripping; and
(b) System Instability.
Under the conditions described above, it is however acceptable for
planned/controlled loss of load to occur. The above performance requirements,
contingencies and impacts are summarised in Table 4.12, in section 4.11, under
system condition classified as Category C Events resulting in loss of two or
more elements.
2.3.2.8 Under maintenance conditions it shall be assumed that the prior circuit outage(s)
specified in paragraphs 2.3.2.7(1) and 2.3.2.7(4) reasonably form part of the
typical outage pattern referred to in paragraph 2.2.2.4(2) rather than in addition to
that typical outage pattern i.e., only a reasonable typical outage pattern will be
assumed without any double counting or excessive and unrealistic outages being
included.
2.3.2.9 In the event of a contingency more severe than those described in 2.3.2.3, 2.3.2.6
and 2.3.2.7 of this chapter which results in a total generation infeed loss up to the
Infrequent Infeed Loss Risk the Frequency shall not fall below 47.5Hz, with all
defence measures inplace and operational. System performance requirements,
contingencies and expected impacts following more severe or extreme
contingencies than those described in 2.3.2.3, 2.3.2.6 and 2.3.2.7 are summarised
in Table 4.12, in section 4.11, under system condition classified as Category D
Extreme events resulting in two or more elements removed or cascading out of
service.
2.3.2.10 Guidance on typical substation configurations and switching arrangements are
described in Appendix C. However, other configurations and switching
arrangements which meet those Criteria are also acceptable.
2.3.2.11 Variations, arising from a generation customers request, to the generation
connection design necessary to meet the requirements of paragraphs 2.2.1 to 2.2.3
shall also satisfy the requirements of this Standard provided that the varied design
satisfies the conditions set out in paragraph 2.3.2.12(1) to (3). For example, such a
Transmission System Reliability Standards
12
13
3.1
General
3.1.1
The Transmission System is and shall continue to be planned and developed such
that, under both normal System operational conditions or following a Secured
Contingency Event, there will be sufficient Transmission Capacity and capability
available to enable the System to return to normal operation. Normal operation of
the System in this respect means operation of the System within thermal, voltage,
Frequency and stability limits.
3.1.2
3.1.3
In some rare and extreme cases, Unsecured Contingency Events could also lead to
partial or full disruption of the whole System and affect supplies to consumers.
Under such adverse operating conditions, and as part of the special Protection and
defence measures, some generation and/or demand disconnection is permitted to
ensure stable operation of the remaining System in the post-contingency period.
3.1.4
3.1.5
This Chapter 3 also presents the planning and operational Criteria for ensuring
Reliability of the Transmission System. These Criteria apply throughout the
Transmission System and must be met by TNB in planning and operating the
Transmission System. In addition, in those parts of the Transmission System
where the Criteria of Chapter 2 also apply, those Criteria must be met.
14
3.2
15
(5) The output of contributing Power Stations will include its operating reserve
which is calculated in accordance with their ability to provide dynamic
spinning response based on the characteristics of the Plant at that Power
Station;
(a) for thermal units, a typical dynamic response of about 8%, if the actual
response is not available;
(b) for GT units, a typical dynamic response of 10%, if the actual response
is not available;
(c) for hydro units, equally proportionally part loaded to balance the
demand, plus losses, plus interconnection infeed;
(d) power imports from External Systems (e.g., Thailand and/or
Singapore) shall be assumed to be at their typical values as indicated
by reciprocal agreements for the base case Planned Transfer Condition;
(e) a Load power factor of 0.9 or better shall be maintained, if the
measured power factor is not avilable, at the 132kV side of the
132/33kV and 132/11kV transformers; and
(f) for the Planned Transfer Conditions on the Transmission System there
shall not be:
(i) equipment loadings exceeding the pre-fault rating;
(ii) voltages outside the Pre-fault Planning Voltage Limits or
Insufficient Voltage Performance Margins; or
(iii) system Instability,
otherwise remedial planning measures to remove any violations will be
considered.
3.2.1.2 The minimum Transmission Capacity of the Main Interconnected Transmission
System shall be planned such that, for the background conditions described in
paragraph 3.2.1.1, prior to any fault there shall not be:
(1) equipment loadings exceeding the continuous current rating;
(2) equipment Three-Phase Short-Circuit currents exceeding 90% of their ShortTime Current Ratings;
(3) voltages outside the Pre-fault Planning Voltage Limits or Insufficient
Voltage Performance Margins; or
(4) System Instability.
The above performance requirements are summarised in Table 4.12, in section
4.11, under system condition classified as Category A No contingencies.
16
17
18
(4) any single Transmission Circuit with the prior outage of another
Transmission Circuit, Generating Unit, reactive compensator or other
Reactive Power resource, or
(5) the most onerous Loss of Power Infeed
there shall not be:
(a) cascade tripping; and
(b) System Instability.
Under the conditions described above, it is however acceptable for
planned/controlled loss of load to occur. The above performance requirements,
contingencies and impacts are summarised in Table 4.12, in section 4.11, under
system condition classified as Category C Events resulting in loss of two or
more elements.
3.2.2.3 The operational Criteria above are subject to the following exceptions:
(1) Provided that it is in accordance with the appropriate requirements of the
demand connections criteria in part 3.3 of this Chapter 3, there may be an
associated Loss of Supply Capacity due to a Secured Contingency Event, for
example by virtue of the design of the generation connections and/or the
designed switching arrangements at the substations concerned. Typical
examples of this could be:
(a) at mesh substations where the loss of a Double Circuit Overhead Line
would result in the consequential loss of mesh corner Demand Supply
Point transformers;
(b) Demand Supply Point transformers which are teed off circuits that form
part of the Main Interconnected Transmission System and which would
become disconnected following the loss of these circuits.
(2) During periods of Severe Weather conditions or other high System risk
periods, TNB Transmission Division may implement measures to mitigate the
consequences of this risk. Such measures may include reducing output at
certain Power Stations.
3.2.2.4 For the purposes of paragraph 3.2.2.2, it is acceptable to utilise short term post
fault actions to avoid Unacceptable Overloading of Primary Transmission
Equipment which may include a requirement for demand reduction; however this
will not be used as a method of increasing reserve to cover abnormal post fault
generation reduction. Where possible these post fault actions shall be notified to
the appropriate Users. Normally the provisions of the Grid Code, in respect of
Emergency Manual Demand Disconnection will be applied. Additional post fault
actions beyond the Grid Code provisions may be applied, but only where they
have been agreed in advance with the appropriate Users.
19
20
21
(3) Loss of the transmission towers in a Right of Way (involving loss of two or
more double circuit lines);
(4) Loss of a substation; and
(5) Loss of a complete Power Station.
In making the assessment, system performance requirements, contingencies and
expected impacts following Unsecured Contingency Events or extreme
contingencies summarised in Table 4.12, in section 4.11, under system condition
classified as Category D - Extreme events resulting in two or more elements
removed or cascading out of service - shall be considered.
3.2.3.6 Operational Requirements - The Main Interconnected Transmission System shall
be operated with all the special Protection and defence measures in a fully
operational state. If any one or more of these measures are out of service or on
maintenance then specific Operational Planning studies shall be carried out well
in advance to put in place appropriate operating regimes and alternative
measures with a target of reducing the risk.
22
3.3
3.3.1 General
3.3.1.1 The Demand Connection Criteria relate to the planning of demand connections
and provision of sufficient transformer capacity and/or demand transfer facilities
to avoid undue Loss of Supply Capacity for Secured Contingency Outages
included in the Transmission Reliability Standard. These Criteria enable TNB
Transmission Division and the Distributors, Network Operators or Directly
Connected Customers to make necessary investments ensuring the planning,
development and operation of the Transmission and Distribution Systems within
the provisions of Transmission System Reliability and Power Quality Standards,
and the Grid Code both under normal and Secured Contingency Outage
conditions.
3.3.1.2 This section of Chapter 3 presents the planning and operational Criteria for the
connection of demand to the Transmission System. In those parts of the
Transmission System where the Criteria of Chapter 2 of this Standard also apply,
those Criteria must also be met.
23
24
4.1
Introduction
4.1.1
This Chapter 4 presents performance criteria and limits used in this Standard for
planning and operation. performance criteria and limits specified in this Chapter
are:
(1) Voltage;
(2) Voltage Performance Margin;
(3) Frequency Limits;
(4) Stability Limits;
(5) Fault Clearing Times;
(6) Short Circuit Limits;
(7) Basic Insulation Levels;
(8) Criteria for Evaluating Unsecured Contingencies; and
(9) Thermal Loading Limits of Transmission Components.
4.1.2
The specified criteria and limits in this Chapter shall be complied with for
planning and operation of the Grid as outlined in Chapter 2 and Chapter 3.
4.2
Voltage
4.2.1
25
4.2.2
525kV (+5%)
500kV (-0.0%)
275kV
289kV (+5%)
275kV (-0.0%)
132kV
139kV (+5%)
Lower Voltages
Note 1 There is no minimum planning voltage provided that, at the Busbar of the same nominal voltage at
the Demand Supply Point from which it is derived, it is possible (for example by tap changing) to achieve at
least 105% of nominal voltage.
Note 2 It is assumed that at the planning stage the load power factor at the 132kV bus is no lower than 0.9 .
4.2.3
Nominal
Voltage
Note 1
Maximum
Minimum
Operational Timescales
Maximum
Minimum
525kV (+5.0%)
475kV (-5.0%)
525kV (+5.0%)
450kV (-10.0%)
Note 2
Note 3
Note 6
275kV
289kV (+5.0%)
248kV (-10.0%)
303kV (+10.0%)
248kV (-10.0%)
132kV
139kV (+5.0%)
145kV (+10%)
119kV (-10%)
(+6.0%)
(-6.0%)
500kV
Less than
132kV
Note1
Note 2
Note 3
Note 4
Note 5
Note 6
(+5.0%)
Note 4
Note 5
26
4.2.4
Planning Timescales
Note 1
Voltage
Rise
Voltage Fall
Operational Timescales
Note 3
Voltage
Rise
Voltage Fall
+10%
-2.5% for
500kV
-5% for
others
Note 2
+10%
-2.5% for
500kV
-5% for
others
Note 4
Following operational
switching less frequent
than specified in ER P28
+3%
-3%
+3%
-3%
Otherwise
According to ER P28
Following Secured
Contingency Events
Note 1 These limits apply at all demand conditions and only to the interfaces between the
Transmission System and customers, and must be applied with the Load response to
voltage change taken into account.
Note 2 This is relaxed to -12% if the fault involves the loss of a section of Busbar, or a mesh
corner, or a Secured Contingency Event which also includes the simultaneous loss of a
500/275kV transformer (Applicable to voltage other than 500kV).
Note 3 Following Voltage Step Change within these limits, it must be possible to restore the
Steady State voltage to 95% of nominal at Demand Supply Points following any manual
and/or automatic facilities available, including switching in or out of relevant Apparatus.
Note 4 This is relaxed to -12% if the fault involves the loss of a Double Circuit Overhead Line, a
section of Busbar, or mesh corner (Applicable to voltage other than 500kV).
27
4.2.5
4.2.6
High voltage
4.3
4.3.1
At the planning stage power transfer within the System and at each specific
demand point shall be limited such that there is a margin of 15% to the maximum
possible transmitted power, under the base case conditions described in Section
3.2.1.1 of this Standard.
4.3.2
At the planning stage power transfer within the System and at each specific
demand point shall be limited such that there is a margin of 7.5% to the maximum
possible transmitted power, under the contingency conditions described in Section
3.2.1.4 of this Standard.
4.3.3
During operation, power transfer within the System and at each specific demand
point shall be limited such that there is a margin of 5% to the maximum possible
transmitted power, under the contingency conditions described in Section 3.2.2.1
of this Standard.
4.3.4
These voltage margin Criteria are in additon to any other voltage Criteria
requirements.
28
4.4
Frequency Limits
4.4.1
4.4.2
The System Frequency could rise to 52Hz or fall to 47Hz in extremely rare and
exceptional circumstances. Therefore the design of both TNB and User's Plant and
Apparatus must enable operation of that Plant and Apparatus within that range in
accordance with table 4.6.
Table 4.6: Frequency excursion limits
Frequency Range
Requirement
47.5Hz - 52Hz*
47Hz - 47.5Hz
4.5
Stability Limits
4.5.1
The relative rotor angle of any two Generating Units in the System must not
exceed 180 degrees at any time.
4.5.2
29
4.6
4.6.1
The following maximum fault clearance times (see table 4.7) are normally
expected from the Main Protection equipment installed in the Transmission
System.
Table 4.7: Maximum Fault Clearing Times
System Voltage (kV) Fault Location
500 and 275
132
Substation
100
Overhead Line/Cable
100
Substation
150
Overhead Line/Cable
150
4.6.2
4.6.3
For operational studies the Protection times in 4.6.2 shall also be used. However,
where the used of fault clearing times in 4.6.2 is found to be limited, the actual
fault clearing times may be used.
4.7
Short-Circuit Limits
4.7.1
The Transmission System shall be planned such that the maximum sub-transient
three phase symmetrical short circuit fault levels are not greater than 90% of the
switching equipment short-circuit ratings, the breaking and making capacities of
switching equipment shall not be exceeded under maximum system short circuit
condition.
4.7.2
For three-phase or single-phase-to-earth faults, the planned maximum subtransient short circuit fault levels shall not be greater than that indicated in the
table 4.8.
30
Circuit Breaker
Short Circuit Rating Break Capacity
50kA, 1s
40kA, 3s for bulk substation
50kA, 1s for Power Station and 275kV within 500kV
substation
31.5kA, 3s
40kA, 3s for Power Station and 132kV within a
500/275kV substation
33
25kA, 3s
20kA, 3s
4.8
4.8.1
1550
275
1050
132
650
33
170
22
125
11 and 6.6
75
31
4.9
4.9.1
For the purposes of determining the types of special Protection and defence
measures the following contingencies which will be considered together with the
appropriate Fault Outage Criteria to be considered are listed in table 4.10 and also
as described under Category D of Table 4.12, in section 4.11,. In all these cases
special Protection and/or defence measures shall be put in place such that whilst
some demand and generation loss may be experienced a total System shutdown
will be avoided.
Table 4.10: Unsecured contingencies to be evaluated
Unsecured
Fault Outage Criteria
Contingency
Note 1
Event
Outage of System
Elements
Stuck Breaker
Fault Single Phase
Fault Initiation
Stuck Breaker
Fault Three Phase
Fault Initiation
32
Unsecured
Contingency
Event
Outage of System
Elements
Loss of substation
(one transmission
voltage level plus
associated
transformers) i.e., loss
of a Busbar
Loss of a complete
Power Station
No thermal overloading
allowed
Underground cables
Strict observation of
equipment continuous rating
Transformers
No thermal overloading
allowed
Switching and
Isolation Equipment
Strict observation of
equipment continuous rating
33
A
No
Contingencies
B
Event resulting
in the loss of a
single element
C
Event(s)
resulting in the
loss of two or
more (multiple)
elements
Contingencies
Initiating Event(s) and
Contingency Element(s)
Yes
No
No
Yes
Yes
Yes
Yes
No
No
No
No
Note (b)
No
No
No
No
Yes
No
Note (b)
No
Yes
Planned/
Controlled
Planned/
Controlled
Note (c)
No
Yes
Planned/
Controlled
Note (c)
No
Yes
Planned/
Controlled
No
Yes
Planned/
Controlled
Note (c)
No
Yes
No
Note (c)
Yes
7. Transformer
Yes
8. Transmission Circuit
Yes
9. Bus Section
Yes
Planned/
Controlled
Planned/
Controlled
Planned/
Controlled
Planned/
Controlled
No
No
No
No
34
Category
D
Extreme event
resulting in two
or more
(multiple)
elements
removed or
Cascading out
of service
Note (d)
Contingencies
Initiating Event(s) and
Contingency Element(s)
Generator
Transmission (Circuit)
Transformer
Bus Section
May involve
substantial loss of
customer Demand
and generation in
a widespread area
or areas
Portions or all of
the
interconnection
systems may or
may not achieve a
new, stable
operating point.
Evaluation of
these events may
require joint
studies with
neighboring
systems.
Notes:
(a) Applicable rating refers to the applicable Normal and Emergency facility thermal Rating (see table
4.11) or system voltage limit as determined and consistently applied specified in section 4.1 of this
Standard. Applicable Ratings may include Emergency Ratings applicable for short durations as
required to permit operating steps necessary to maintain system control.
(b) Planned or controlled interruption of electric supply to radial customers or some local Network
customers connected to or supplied by the Faulted element or by the affected area, may occur in certain
areas without impacting the overall reliability of the interconnected transmission systems. To prepare
for the next contingency, system adjustments are permitted, including curtailments of contracted firm
power transfers.
(c) Depending on system design and expected system impacts, the controlled interruption of electric
supply to customers (load shedding), the planned removal from service of certain generation, and/or the
curtailment of contracted firm power transfers maybe necessary to maintain the overall reliability of the
interconnected transmission systems.
(d) A number of extreme contingencies that are listed under Category D and judged to be critical will be
selected for evaluation. It is not expected that all possible facility outages under each listed contingency
of Category D will be evaluated.
(e) Normal clearing is when the protection system operates as designed and the Fault is cleared in the time
normally expected with proper functioning of the installed protection systems (see table 4.7). Delayed
clearing of a Fault is due to failure of any protection system component such as a relay, circuit breaker,
or current transformer, and not because of an intentional design delay. Three phase delayed clearing is
when a three phase fault is cleared in normal clearing time followed by a SLG fault cleared after a
delay time (to represent the single pole of a stuck breaker or protection system failure). Typical delay
times are 250 milliseconds
(f) System assessment may exclude these events where multiple circuit lowers are used over short
distances (e.g. substation entrance, river crossings).
35
Version 2.0
Edition 1.0
Contents
36
Contents
TRANSMISSION SYSTEM POWER QUALITY STANDARDS ..............................36
CONTENTS......................................................................................................................37
CHAPTER 1: INTRODUCTION...................................................................................38
1.1
1.2
Contents
37
Chapter 1: Introduction
1.1
1.1.1
In this Standard, Power Quality is defined as the degree to which the Voltage at
the point of connection to the User of the Transmission System is maintained to be
Sinusoidal at declared rated Voltage and Frequency within the stipulated limits.
1.1.2
Major Power Quality Problems that are associated with the Transmission System
is Voltage Sag or Voltage Dip. Voltage sag would occur in the System during the
short-circuit fault. The most severe Voltage Sag would occur at the fault location
and the Voltage Sag effects would be propagated throughout the Systems with the
magnitude of the Voltage Dip attenuated.
1.1.3
Voltage Sag could also be caused by short circuit faults in Users System and
propagated to other Users Systems through the Transmission Systems or through
the Distribution System as the case may be. Majority of problems associated with
harmonics are caused by non-linear loads that draw non-sinusoidal current from
the system and thus causing the supply voltage to be distorted. Frequent switching
of large load such as motors is also another source of power quality problems that
result in voltage flicker to be experienced by other Users.
1.1.4
The approaches to resolving power quality problems depend on the types of the
power quality problems. Both utility and Customers have their individual roles
and responsibilities in resolving power quality problems. Individual Customer
shall ensure that any non-linear load to be connected to the Transmission System
does not produce harmonic currents that would result in voltage at Point of
Common Coupling to be distorted beyond the limits as set out in section 2.4 of
this Standard. Likewise the utility shall continue to monitor and ensure that
Harmonic limits as specified in section 2.4 are complied with.
1.1.5
Voltage sag could affect sensitive loads usually connected at low voltage network
of the Customers installation. Not withstanding the presence of several voltage
transformations from transmission voltage to low voltage, voltage sag caused by
Transmission faults can affect Customers voltage sensitive loads and the effect is
more pronounced during severe three-phase faults on the Transmission System. It
shall be the responsibility of the utility to provide appropriate information on
voltage sag and for the individual customer to ensure sufficient ride-through
capability of the voltage sensitive equipment.
Chapter 1: Introducton
38
1.1.6
The Standards contained in this document specify the Power Quality requirements
of the bulk supply point that delivers electricity supply to the Distribution System
and other bulk supply Users in terms of stable voltage and frequency within
specific limits so that Generator, TNB Transmission equipment or Consumers
equipment directly connected to the Transmission System can operate safely
within its design performance without suffering undue damage or breakdown.
1.1.7
The requirements and limits specified in this Standard shall also be complied with
by all Users connected or intending to be connected to the Transmission System.
1.1.8
1.1.9
In order to achieve the required Transmission Power Quality these Standards will
be used by TNB Transmission in planning, developing, maintaining and operating
the Transmission System as well as in connecting generation and demand to the
System. In turn the equipment utilised by the Generators, TNB Transmission,
Distributors and Customers also need to comply with the provisions of this
Standard. Compliance with these Standards is therefore not optional and where a
connecting partys plant or equipment is likely to be non-compliant at the
planning stage then such plant and/or equipment will not be energised until
appropriate remedial measures are put in place and are fully functional. In
addition, TNB Transmission shall put in place appropriate monitoring facilities to
ensure compliance with the provisions of this Standard as part of its Licence.
1.1.10 In cases where, the nature and operation of the new types of plant and equipment
to be connected to the Transmission System is perceived to be likely to cause
problems to other customers and users of the System, but not fully covered by
this Standard, appropriate remedial measures shall be put in place based on expert
advice within a mutually agreed time period.
Chapter 1: Introducton
39
1.2
Scope
1.2.1
This Standard covers most of the power quality related phenomena generated by
various types of plant and equipment connected to the Transmission System. In
each particular case the Transmission Power Quality that should be maintained is
indicated together with the remedial approach and responsibilities of parties.
Chapter 1: Introducton
40
2.1
2.1.1
Voltage sag, dip or swell is the transient phenomena which can affect the
voltage level and is usually experienced during System faults and the subsequent
recovery period. These phenomena can adversely affect some customer equipment
that are sensitive to such changes. This Standard does not specifically cover
voltage sag, dip or swell.
2.1.2
The voltage sags are caused by faults on the Transmission System due to short
circuits incidents which are cleared by System Protection. The nature and
technical detail of such events is a function of the location of the connection point
on the System, the distance of the short circuit from the connection point and the
short-circuit level at the connection point, the severity (magnitude and duration) of
the short circuit. Voltage Sag may also be caused by short-circuit fault in one
Users System and propagated to other Users Systems through the Transmission
System.
2.1.3
In most cases, the Transmission System faults were cleared within the primary
protection fault clearing time. Statistics of monitored events of voltage sags
indicates that not all faults on the Transmission System affect voltage sensitive
customer demand. However for certain severe fault, the voltage sag may be felt by
voltage sensitive customer up to (three hundred) 300km away from the fault
location.
2.1.4
There is no single Standard for voltage sag but statistical information is available
from TNB Transmission in terms of past records of voltage sag events. If Users
or prospective Users have equipment which are sensitive to voltage sags, they can
request such statistical information from TNB at the application stage to enable
compatibility assessment to be carried out, if necessary. Whenever necessary,
remedial actions may be rendered by TNB and/or the affected Customer through
appropriate Agreement.
41
2.2
2.2.1
2.2.2
2.3
2.3.1
The limits of Flicker that are acceptable on the Transmission System are in
accordance with the Engineering Recommendation P28, Issued by The
Electricity Council of UK in 1989 entitled Planning Limits for Voltage
Fluctuation Caused by Industrial, Commercial and Domestic Equipment in the
United Kingdom (ER P28). TNB Transmission Division uses the procedures
contained in this document to plan the connection of Fluctuating Loads and
applies the limits therein in measuring and monitoring the levels of Flicker at such
points of connection.
2.3.2
42
0.8
1.0
Absolute Long
Term Flicker
Severity (Plt)
0.6
0.8
2.3.3
2.3.4
Connection of more than one Fluctuating Load at the same Point of Common
Coupling or addition of further Fluctuating Load at the same location is carried
out on a first come first served basis on the Transmission System. This means
that whilst the first Fluctuating Load may be within the allowable Flicker limits
and not require any Flicker mitigation or compensation equipment, the second
Fluctuating Load which may cause violation of Flicker limits will be obliged to
invest in appropriate Flicker mitigation or compensation equipment. At the
planning stage, in carrying out the assessment of the total Flicker due to more than
one Fluctuating Load connecting at a particular Points of Common Coupling TNB
shall use the methodology described in P28.
2.3.5
In assessing level of Flicker due to a Fluctuating Load at the planning stage the
assessment will be carried out at a realistic Weak System operating condition
giving the minimum number of connections with which that point on the System
can be operated within normal voltage limits with maintenance outages or
following Secured Contingency Events. This condition shall be considered as
representative of the type of System conditions under which the Flicker due to a
Fluctuating Load will be at its highest value as the voltage fluctuations due to the
Fluctuating Load will be at their highest level under such conditions.
2.3.6
43
the values of Flicker Severity measured and observed during the total observation
period. The System overall performance yardstick for the level of Flicker
reduction to be achieved shall be based upon enabling connection of other similar
Fluctuating Load and/or permitting for future extension and development of the
location with further Fluctuating Load installations. The Flicker compensation
method and equipment to be used shall be of a type that does not cause resonance
problems with the existing and intended future developments of the Transmission
System.
2.3.7
If the permissible Flicker limits cannot be met even with installation of Flicker
compensation at a particular Points of Common Coupling at a particular System
voltage level then connection of the Fluctuating Load at a higher voltage level or
elsewhere in the System shall be considered. The connection point of choice will
need to have to experience lower voltage fluctuations than the first connection
point considered under the operational conditions in 2.3.5.
2.4
Harmonics
2.4.1
The limits of Harmonics that are acceptable on the Transmission System are in
accordance with the IEC Standard 61000-3-6 Assessment of emission limits for
distorting loads in MV and HV power systems. TNB Transmission uses the
procedures contained in this document to plan the connection of Loads producing
Harmonics and applies the limits therein in measuring and monitoring the levels
of harmonics at such points of connection.
2.4.2
All plant and equipment connected to the Transmission System, and that part of
the Transmission System at each connection site, should be capable of
withstanding the following distortions of the voltage waveform in respect of
harmonic content. The maximum total levels of Harmonic Distortion at any
connection point on the Transmission System from all sources under both planned
outage and Secured Contingency Event conditions, unless abnormal conditions
prevail, shall not exceed:
(1) at 500kV, 275kV and 132kV, a maximum planning limit for Total Harmonic
Distortion of 3% with no individual Harmonic Voltage greater than that shown
in the table 2.2;
(2) infrequent short duration peaks may be permitted by TNB to exceed the above
levels for harmonic distortion;
(3) TNB will make an assessment for the connection of each Load to the
Transmission System, which may result in harmonic emission limits being
specified for these Loads in the relevant Agreement. The assessment will take
44
into account the position of existing and prospective Users Plant and
Apparatus in relation to harmonic emissions. Users must ensure that
connection of distorting Loads to their User Systems do not cause any
harmonic emission limits specified in the Connection Agreement to be
exceeded; and
(4) Users shall ensure that the Immunity Level of their plant and Apparatus is
compatible with the electromagnetic disturbances present on the System
including harmonics.
2.4.3
2.4.4
If under the operating conditions described in 2.4.3 the Harmonic Distortion and
Individual Harmonic Level due to the Load exceed the limits then harmonic filters
which will reduce the harmonics to an acceptable level shall be installed to bring
the levels within the limits. The System overall performance yardstick for the
level of harmonic reduction to be achieved shall be based upon enabling
connection of other similar harmonic producing Load and/or permitting for future
extension and development of the location with further harmonic producing Load
installations. The harmonic filters to be installed shall be of a type that does not
cause resonance problems with the existing and intended future developments of
the Transmission System.
45
Harmonic
Voltage (%)
2.0
1.0
0.3
0.2
0.2
Order
h
2
4
6
8
10
12
>12
Harmonic
Voltage (%)
1.5
1.0
0.5
0.4
0.4
0.2
0.2
2.5
2.5.1
2.5.2
In all power Systems including the Transmission System, the impedances of each
phase of the transmission lines are unequal due to differences in their physical
geometry, and therefore create a voltage unbalance at the termination points of the
lines. As a general rule, the longer the line the higher this unbalance will be. In
addition the demands connected to each phase at a Demand Supply Point are not
precisely equal as customers connected to individual phases utilise their
equipment at varying times. Also there are large single-phase connected demands
such as railway traction Loads connected at various points. Together these factors
create a level of unbalance between the phases of the transmission lines within the
Transmission System causing the so called negative phase sequence currents to
circulate in the Transmission System which can be harmful to plant equipment if
they exceed certain levels.
2.5.3
46
System. This process requires a change in the physical position of each phase
conductor over the length of the line. Thus a full transposition would involve each
phase conductor to physically occupy a different position at each third of the line
length. This undertaking by itself is sometimes not sufficient to reduce the
circulating negative phase sequence currents due to the connected single-phase
and unbalanced three-phase Loads. In such cases it is necessary to install
compensation equipment at the point of connection of the specific Load to achieve
balanced voltages within specified limits given below.
2.5.4
All plant and equipment connected to the Transmission System, and that part of
the Transmission System at each connection site, should be capable of
withstanding the following distortions of the voltage waveform in respect of Phase
Unbalance at the planning stage.
1) Under planned outage conditions, the maximum negative phase sequence
component of the phase voltage on the Transmission System should remain
below 1% unless abnormal conditions prevail (P29 limit is not exceeding 2%
for 1 minute).
2) Under the planned outage conditions, infrequent short duration peaks with a
maximum value of 2% are permitted for Phase Unbalance, subject to the prior
agreement of TNB under the connection agreement. TNB will only agree
following a specific assessment of the impact of these levels on TNB and
other Users plant and equipment with which it is satisfied.
3) At the terminals of a Users installation or specific Load the unbalance voltage
shall not exceed 1% for 5 occasions within any thirty (30) minute time period.
4) In terms of traction Loads connected to the Transmission System the
acceptable limits of unbalance are in accordance with Engineering
Recommendation (E/R) P24, issued by the Electricity Council of UK in 1984
entitled AC Traction Supplies to British Rail and its successor document P
29 issued in 1990 Planning Limits for Voltage unbalance in the United
Kingdom. TNB Transmission uses the procedures contained in this document
to plan the connection of Loads producing Unbalance and applies the limits
therein in measuring and monitoring the levels of unbalance at such points of
connection.
2.5.5
47
2.5.6
If under the operating conditions described in 2.5.4 the Unbalance due to the Load
exceeds the limits then balancing compensation equipment which will reduce the
unbalance to an acceptable level shall be installed to bring the levels within the
limits. The System overall performance yardstick for the level of unbalance
reduction to be achieved shall be based upon enabling connection of other similar
unbalance producing Load and/or permitting for future extension and
development of the location with further unbalance producing Load installations.
The balancing compensation equipment to be installed shall be of a type that does
not cause resonance problems with the existing and intended future developments
of the Transmission System.
2.5.7
Current TNB practice requires that 500kV overhead line with more than fifty (50)
km in length to be fully transposed.
48
2.6
2.6.1
2.6.2
In the case of an arc furnace installation the following restrictions will apply:
(1) No initial arcing is to be carried out simultaneously for any combination of
arcing Loads that lead to a step power magnitude greater than that described in
Section 2.6.1 (1) of this Standard.
(2) Suitable interlocking Systems shall be provided to ensure compliance with (1)
above.
49
50
TERM
Active Power
DEFINITION
The product of voltage and the in-phase component of alternating current
measured in units of watts and standard multiples thereof, i.e.:
1000 Watts = 1 kW
1000 kW = 1 MW
1000 MW = 1 GW
1000 GW = 1 TW
Adequacy
Apparatus
Apparent Power
Availability
Available
Transfer
Capacity
Bulk Supply
Points
Busbar
Connection
Agreements
Glossary and Defintions for Transmission System Reliability Standards and Transmission System Power Quality
Standards
51
TERM
DEFINITION
Embedded Customers and Network Operators
Transmission System excluding External Systems.
connected
to
Criteria/
Criterion
Damping Ratio
(%) =
100
Demand
Connection
Criteria
Demand
Connection
Point
Demand Supply
Point
Directly
Connected
Customers
Distribution
Reliability
Standard
Glossary and Defintions for Transmission System Reliability Standards and Transmission System Power Quality
Standards
52
TERM
DEFINITION
energy to the customers connected to the Distribution System.
Distribution
Code
Distribution
Function
Distribution
Power Quality
Standards
Distribution
System
Distributors
Double Circuit
Overhead Line
A transmission line which consists of two circuits sharing the same towers
for at least one span or more.
Glossary and Defintions for Transmission System Reliability Standards and Transmission System Power Quality
Standards
53
TERM
DEFINITION
Electric Power
System
External
Interconnections
Facility
Contractual
Available
Capacity (in
MW)
Fault Outage(s)
Flicker
Flicker Severity
(Long Term)
Flicker Severity
(Short Term)
A measure of the visual severity of Flicker derived from the time series
output of a Flicker meter over a ten (10) minute period and as such
provides an indication of the risk of customer complaints.
Fluctuating
Load
Glossary and Defintions for Transmission System Reliability Standards and Transmission System Power Quality
Standards
54
TERM
DEFINITION
Frequency
Generating Unit
Generation
Adequacy or
Generation
Security
Standard
Generation
Capacity
Generation
Capacity
Requirements
Generation
Reliability
Standards
Generation
Circuit
The sole electrical connection between one or more Generating Units and
the Main Interconnected Transmission System, i.e. a radial circuit
which if removed would disconnect the Generating Units.
Generation Point A point at which a Generating Unit or a CCGT module, as the case may
be, which is directly connected to the Transmission System, connects to
of Connection
the TNB Transmission System. For the purpose of defining the
boundaries between the Main Interconnected Transmission System and
Generation Circuits, the Generation Point of Connection is taken to be
at point between the HV bushing and circuit breaker as per the Agreement
Glossary and Defintions for Transmission System Reliability Standards and Transmission System Power Quality
Standards
55
TERM
Generator
DEFINITION
A person or company who generates electricity under a licence granted by
the Energy Commission under the Electricity Act 1990 acting in its
capacity as a Generator in Peninsular Malaysia.
Grid Code
A document that sets out the principles governing the relationship between
the GSO, Energy Commission, Single Buyer and all Users of the Grid
System.
Infrequent
Infeed Loss Risk
Insufficient
Voltage
Performance
Margins
Intact System
Largest Loss of
Power Infeed
Risk
Large Power
Stations
Load
Glossary and Defintions for Transmission System Reliability Standards and Transmission System Power Quality
Standards
56
TERM
DEFINITION
installation or equipment connected to the Transmission System.
Loss of Load
Expectation
Loss of Load
Probability
A reliability index that indicates the probability that some portion of the
peak demand will not be satisfied by the available generating capacity as
defined in these standards. It may also be expressed as an expected
duration in a year for which the peak demand is not being met, in which
case it is referred as Loss of Load Expectation (LOLE).
Loss of Power
Infeed
Loss of Supply
Capacity
Main
Interconnected
Transmission
System
Main Protection
Glossary and Defintions for Transmission System Reliability Standards and Transmission System Power Quality
Standards
57
TERM
DEFINITION
an Electrical Power System.
Malaysian
Electricity
Supply Industry
Marshalling
Substations
A substation which connects circuits from more than two line routes.
Network
Operator
Non-Embedded
Customer
Normal
Operational
Limits
Peninsular
Malaysian
Electric Power
System
Performance
Requirements
and Limits
These are the Performance Requirements and Limits derived from the
Standard which describe the performance Criteria and limits applicable
in the planning, operational planning and actual operation of the System
which should be complied with in ensuring Security of the System
together with the required quality of supply.
Phase Unbalance The inequality between the magnitudes of the three phase voltages at a
specific point on the Transmission System where there is an appreciable
difference due to either the inequalities between the Load connected to
each phase and/or the inequalities of transmission line impedances in each
Glossary and Defintions for Transmission System Reliability Standards and Transmission System Power Quality
Standards
58
TERM
DEFINITION
phase due to their geometry.
Planned
Transfer
Condition
Plant
Fixed and movable items used in the generation and/or supply and/or
transmission of electricity, other than Apparatus.
Point of
Common
Coupling
Power Purchase
Agreement
Power Station
Pre-Fault
Planning Voltage
Limits
Prevailing
System
Conditions
Primary
Transmission
Equipment
Protection
Glossary and Defintions for Transmission System Reliability Standards and Transmission System Power Quality
Standards
59
TERM
Reactive Power
DEFINITION
The product of voltage and current and the sine of the phase angle between
them measured in units of voltamperes reactive and standard multiples
thereof, i.e.:
1000 VAr = 1 kVAr
1000 kVAr = 1 MVAr
Reactive Power
Reserve
Registered
Capacity
In the case of a Generating Unit other than that forming part of a CCGT
Module, the normal full load capacity of a Generating Unit as declared
by the Generator, less the MW consumed by the Generating Unit
through the Generating Unit's unit transformer when producing the same
(the resultant figure being expressed in whole MW.) In the case of a
CCGT Module, the normal full load capacity of a CCGT Module as
declared by the Generator, being the Active Power declared by the
Generator as being deliverable by the CCGT Module at the Grid Entry
Point (or in the case of an Embedded CCGT Module, at the User
System Entry Point), expressed in whole MW.
Reliability
Robustness
RSS Rule
A rule used to assess at the planning stage, the resultant Flicker due to a
Fluctuating Load connecting at a particular Point of Common Coupling
and the background Flicker at that point. The assessment is carried out by
obtaining the sum of the square of Flicker from the Fluctuating Load and
Glossary and Defintions for Transmission System Reliability Standards and Transmission System Power Quality
Standards
60
TERM
DEFINITION
the background Flicker and the square root of this sum will yield the total
assessed Flicker at that Point of Common Coupling due to the specific
Fluctuating Load and the background Flicker at that point in accordance
with the procedure defined in P28.
Secured
Contingency
Event
Security
Spinning
Reserve
Standard
Steady State
Supplementary
Services
Glossary and Defintions for Transmission System Reliability Standards and Transmission System Power Quality
Standards
61
TERM
DEFINITION
System
Any User System and/or the Transmission System, as the case may be.
System
Instability
Total System
Demand
Tenaga Nasional
Berhad (TNB)
Thermal Rating
TNB
Distribution
Glossary and Defintions for Transmission System Reliability Standards and Transmission System Power Quality
Standards
62
TERM
TNB
Transmission
DEFINITION
Transmission Division of Tenaga Nasional Berhad(TNB).
Transmission
Adequacy or
Transmission
Security
Standard
Transmission
Capacity
Transmission
Circuit
Transmission
Equipment
Outage
Transmission
Function
Transmission
Investment Plan
Transmission
Power Quality
Transmission
System Power
Quality
Standards
Glossary and Defintions for Transmission System Reliability Standards and Transmission System Power Quality
Standards
63
TERM
DEFINITION
Transmission System can operate safely within its design performance
without suffering undue damage or breakdown.
Transmission
System
Reliability
Standard
Transmission
Security
Standard
Transmission
System
The TNB Transmission System which comprises all the 500kV, 275kV,
132kV and 66kV elements but excludes Generation Circuits, transformer
connections to lower voltage Systems and External Interconnections
between the Transmission System and External Systems.
Unacceptably
High or Low
Frequency
Conditions
Unacceptable
Overloading
Unacceptable
Voltage
Conditions
Unavailability
Glossary and Defintions for Transmission System Reliability Standards and Transmission System Power Quality
Standards
64
TERM
DEFINITION
Unsecured
Contingency
Events
User
User System
Weak System
Glossary and Defintions for Transmission System Reliability Standards and Transmission System Power Quality
Standards
65
66
Appendix A
BACKGROUND TO THE STANDARDS
A1 Purpose
A1.1 The purpose and the objective of this appendix is to provide the background to
development and application of the Transmission System Reliability Standards
and Transmission System Power Quality Standards and their relationship to other
documents, technical codes and regulations governing the generation,
transmission, bulk delivery, distribution of electric power to all Users.
A1.2 The functions of Peninsular Malaysia Electric Power System, a comparison of
Peninsular Malaysia Standards with international standards, and the outline
contents of the Peninsular Malaysia Standards are shown in Figures A1 to A3.
Generation
Generation Circuit
Bulk
Production
Generation Point
of Connection
Main Interconnected
Transmission System
Bulk
Transport
Transmission
Demand Point
of Connection
1. Transmission System
Reliability Standards
2. Transmission System
Power Quality Standards
Demand Supply
Point
DG
Distribution System
DG
Distribution
Embedded Distribution
Distribution
Distribution Supply
Security and Power
Quality Standards
Customers
67
Generation
Generation
Security
Standard
Generation Circuit
Generation
Connection
Criteria
Generation Point
of Connection
Main Interconnected
Transmission System
Transmission
Demand Point
of Connection
Transmission
Security
Standard
Transmission
Security
Standard
Transmission
Planning &
Design Criteria
Transmission
System
Reliability
Standards
Demand
Connection
Criteria
Quality of Supply
Standard
(Bulk Supply)
Demand Supply
Point
Distribution
Security
Standards
DG
Distribution System
DG
Customers
Transmission
System Power
Quality Standard
Distribution Supply
Security and Power
Quality Standards
Distribution
Power Quality
Standards
Embedded Distribution
Distribution
Generation
Security
Standard
Typical
International
Standards
Peninsular
Malaysia
Standards
Fig A2: The Reliability and Power Quality Standards applicable to the Peninsular
Malaysian Interconnected Transmission System shown in comparison with
International Security and Quality of Supply Standards
68
Generation Circuit
Generation Point
of Connection
Transmission
Security
Standard
Main Interconnected
Transmission System
Transmission
System
Reliability
Standards
Transmission
Demand Point
of Connection
Transmission
System Power
Quality Standard
Demand Supply
Point
Distribution
Supply
Security and
Power
Quality
Standards
DG
Distribution System
DG
Embedded Distribution
Distribution
Peninsular
Malaysia
Standards
Customers
GRID CODE
Generation
Security
Standard
Sufficient transformer
capacity in accordance with
the size of demand
Limits of voltage, frequency,
harmonics, Flicker etc. variations
for specified contingencies
Fundamental
Contents of the
Standards
DISTRIBUTION CODE
Generation
Fig A3: The outline contents of Reliability/Security and Power Quality of Supply
Standards
69
70
Compliance with these limits enables secure and safe operation of the System
within the capability of the equipment constituting the System as well as
connected equipment.
A2.4 The Transmission System Reliability Standards and Transmission System Power
Quality Standards mentioned above therefore determine a defined level of
Reliability and quality for electric power that is delivered at the bulk Demand
Supply Points where the Distribution System is connected to the Transmission
System as well as the points where Users are directly connected.
A2.5 The provision of levels of Transmission System performance in accordance with
these Standards is the duty of Transmission Function of Tenaga Nasional Berhad
(TNB) under Condition 13 of the TNB Licence granted under the Electricity
Supply Act, 1990 on 1st September 1990.
71
72
(4) This Standard includes the Transmission System Power Quality Standards,
which specify the quality of the bulk supply to be delivered to the Distribution
System, at the bulk Demand Supply Points where the Distribution System is
connected to the Transmission System, and to Directly Connected Customers
to the Transmission System, in terms of voltage and Frequency within specific
limits so that Generator or consumer equipment directly connected to the
Transmission System can operate safely within its design performance without
suffering undue damage or breakdown. Consequently these Standards also
determine the investment required in provision of Supplementary Services
such as Reactive Power, Active Power response, Automatic Generation
Control (AGC), hot standby generation, fast start generation, demand control
and black start by TNB Transmission. They also indicate the investment
required both in the Transmission System and Distribution Systems for
containing harmonics, voltage unbalance as well as the permitted types and
levels of special Loads adversely affecting the power quality and requirements
for compensation Plant to limit their adverse effects. Compliance with these
Standards is the responsibility of TNB Transmission Division and the
interfacing Generating Companies, Distributors, Network Operators and
Directly Connected Customers. Ensuring compliance of all parties with these
Standards is the responsibility of TNB Transmission Division.
A4.3 These Standards only covers the Transmission System Reliability Standards and
Transmission System Power Quality Standards, which are the responsibility of
TNB Transmission Division. Discussion of proposals to amend or change these
Standards is ensured through Energy Commission (EC) by TNB. The
compatibility between the Standards contained in this document and Distribution
Supply Security and Power Quality Standards is ensured through the Energy
Commission (EC) by TNB.
A4.4 The Transmission System Reliability Standards and Transmission System Power
Quality Standards included in this document have been derived from previous
documents reflecting the Reliability and power quality practices developed and
adopted through the years and against which investments have already been made
to ensure compliance. These documents include:
(1) TNB Operation Planning Standards July 1998
(2) Guidelines of Power Quality Control for Connection to the Grid System (Issue
2 July 1998 and Revision 2004)
(3) Generation Planning Criteria and Methodology (Rev1/2002, November 2002)
(4) TNB Transmission Network Planning Manual (April 1998)
(5) Planning Criteria, Study Assumptions and Methodology 1998
(6) Voltage Control Policy 2000
Appendix A Background to the Standards
73
74
75
76
(for example, the overloading of lower voltage connections). In such cases TNB
will notify the affected parties. Reinforcement or alternative operation of the
Transmission System to alleviate inadequacies of equipment or Systems not
owned or operated by TNB would be undertaken where it is agreed by both TNB
and the affected parties.
A4.15 Given the continuous development of the power System, while it is a requirement
for TNB to provide sufficient Transmission Capacity to meet the planning Criteria
contained within these Standards, it does not follow that the Transmission
Capacity should be reduced so that it only meets the minimum requirement of
those Criteria. For example, it may not be beneficial to reduce the ratings of lines
to reflect lower loading levels which have arisen due to changes in the generation
or demand patterns.
A4.16 All parties connected to the Transmission System and/or to the Main
Interconnected Transmission System in Peninsular Malaysia shall comply with the
provisions of this Standard in planning, developing, maintaining and operating
their individual Systems as related to their specific connections and Plant.
Compliance is an essential part of ensuring secure and robust operation of the
Peninsular Malaysia Electric Power System and is therefore not optional as these
Standards represent the minimum requirements necessary to achieve the
appropriate Adequacy, Security and Robustness.
A5 Summary
A5.1 As described above and illustrated in Figures A1 to A3 of this Appendix A and
Figure 1.1 of the Transmission System Reliability Standards, there will be many
parts of the TNB Transmission System where more than one set of Criteria apply.
In such places the requirements of all relevant Criteria must be met.
A5.2 In each of Chapters 2 and 3 of the Transmission System Reliability Standard,
planning is the first to be set out, followed by operational Criteria. The planning
Criteria set out the requirements for the Transmission Capacity for the TNB
Transmission System. The planning Criteria also require consideration to be given
to the operation and maintenance and so refer to the associated operational
Criteria. The operational Criteria are used in real time and in the development of
plans for using the Transmission System to permit satisfactory operation.
A5.3
77
LEVEL 1
LEVEL 2
LEVEL 3
LEVEL 4
OPERATIONAL
SECURITY
MANAGEMENT
SYSTEMS
AUTOMATIC
VOLTAGE AND
FREQUENCY
REGULATION EQ.
DUPLICATE
MAIN PROTECTION
TRIPLE GRADING
UNDER
FREQUENCY
LOAD
SHEDDING
BACK-UP
PROTECTION
FAIL-SAFE
FAULT REMOVAL
EMERGENCY
AUXILIARY
SUPPLIES
FAST
RECLOSURE
FOR FAST
RESTORATION
ISLANDING
AND
HOUSE LOAD
OPERATION
MANUAL AND
UNDER VOLTAGE
LOAD
SHEDDING
EMERGENCY
FAST START
GENERATION
AUTOMATIC
FAST ACTIVE &
REACTIVE POWER
RESERVES
PERFORMANCE
MONITORING AND
FAULT
IDENTIFICATION
OPERATIONAL SECURITY
MANAGEMENT SYSTEMS
AND
PLANNED AUTOMATIC
RESERVES FOR FIRST
CONTINGENCY LEVEL
LAYERS OF PROTECTION
TO RAPIDLY REMOVE
THE FAULT
TO PREVENT TOTAL
SYSTEM BLACKOUT
IN MULTIPLE
CONTINGENCIES
TO ENSURE FAST
RECOVERY FROM
SEVERE
CONTINGENCIES
78
Appendix B
GUIDANCE ON THE ECONOMIC JUSTIFICATION OF
GENERATION AND TRANSMISSION CONNECTIONS
B1 General Principles
B1.1
B2 Guidelines
B2.1
Appendix B for Transmission System Reliability Standards Guidance on Economic Justification of Generation and
Transmission Connections
80
Appendix B for Transmission System Reliability Standards Guidance on Economic Justification of Generation and
Transmission Connections
81
Appendix C
GUIDANCE ON SUBSTATION CONFIGURATIONS AND
SWITCHING ARRANGEMENTS
C1 General Guidance
C1.1 The key factors which must be considered when planning a substation include:
i)
Security and Quality of Supply
Relevant Criteria are presented in Chapters 2, and 3 of the Transmission
System Reliability Standards and Chapter 2 of the Transmission System
Power Quality Standards.
ii) Extendibility
The design should allow for the forecast need for future extensions.
iii) Maintainability
The design must take account of the practicalities of maintaining the
substation and associated circuits.
iv) Operational Flexibility
The physical layout of individual circuits and groups of circuits must permit
the required power flow control.
v) Protection Arrangements
The design must allow for adequate protection of each System element.
vi) Short Circuit Limitations
In order to contain short circuit currents to acceptable levels, Busbar
arrangements with sectioning facilities may be required to allow the System
to be split or re-connected through a fault current limiting reactor.
vii) Land Area
The low availability and/or high cost of land particularly in densely
populated areas may place a restriction on the size and consequent layout of
the substation.
viii) Cost
C1.2 Accordingly the design of a substation is a function of prevailing circumstances and
future requirements as perceived in the planning time phase. This appendix is
intended as a functional guidance for substation layout design and switchgear
arrangements. Variations away from this guidance are permissible provided that
such variations comply with the requirements of the Criteria set out in the main text
of the Transmission System Reliability Standard.
Appendix C for Transmission System Reliability Standards Guidance on Substation Configurations and Switching
Arrangements
83
C3 Marshalling Substations
C3.1 Marshalling Substations should:i)
have a double Busbar design (i.e. with main and reserve Busbars such that
Transmission Circuits may be selected to either);
ii) have sufficient Busbar sections to permit the requirements of paragraphs
2.3.2.3 and 3.2.2.2 of the Transmission System Relaibility Standards to be
met;
iii) have Transmission Circuits disposed between Busbar sections such that the
main Busbar may be operated split for fault level control purposes; and
iv) have sufficient facilities to permit the transfer of Transmission Circuits from
one section of the main Busbar to another.
84
for the extendability will depend on the circumstances as perceived in the planning
time phase.
Appendix C for Transmission System Reliability Standards Guidance on Substation Configurations and Switching
Arrangements
85
275kV
TNB Transmission
User
Generation Spur
275kV/132kV
Generation
Loop-in Loop-out
TNB Transmission
User
G
G
LV
Appendix C for Transmission System Reliability Standards Guidance on Substation Configurations and Switching
Arrangements
86
132kV
Network
Connection
132kV
TNB Transmission
132kV
Main Intake
Substation
Switching
Station
11kV
User
North
Busbar
275kV
South
Busbar
500/275kV Transformers
750MVA
North
Busbar
500kV
South
Busbar
Appendix C for Transmission System Reliability Standards Guidance on Substation Configurations and Switching
Arrangements
87
Appendix D
ADDITIONAL CRITERIA TO LIMIT THE COMPLEXITY OF
TRANSMISSION CIRCUITS
D1 General Principles
D1.1 This appendix defines three restrictions to be applied by TNB Transmission when
Transmission Circuits are designed, constructed or extended. These restrictions are
intended to ensure that the time required to isolate and earth circuits in preparation
for maintenance work is kept to a minimum and is not disproportionate to the time
required to carry out maintenance work. The restrictions also limit the potential for
human error.
D2 Requirements/Restrictions
D2.1 The three restrictions to be applied to Transmission Circuits are as follows.
i)
The facilities, for the isolation and earthing of Transmission Circuits and
Transmission Equipment, shall not be located at more than three individual
sites;
ii) The normal operational procedure, for the isolation and earthing of
Transmission Circuits and Transmission Equipment, shall not require the
operation of more than six (6) circuit-breakers; and
iii) No more than three (3) transformers shall be connected together and
controlled by the same circuit breaker.
D2.2 A site, in this context, is defined as being where the points of isolation at one end of
a Transmission Circuit are within the same substation such that only one authorised
person is required, at the site, to enable the efficient and effective release and
restoration of the circuit.
D2.3 If the design of a substation is such that two circuit-breakers of the same voltage are
used to control a circuit (e.g. in a mesh type of substation), for the purposes of the
above restrictions the two circuit-breakers are to be considered as a single circuitbreaker. This also applies where duplicate circuit-breakers control a circuit
including those used for Busbar selection.
D2.4 Switch disconnecters are not rated for fault breaking duty and should not be
included in the design of new Transmission Circuits and substations. Where the
Appendix D for Transmission System Reliability Standards Additional Ciriteria to Limit the Complexity of
Transmisison Cicuits
89
Appendix D for Transmission System Reliability Standards Additional Ciriteria to Limit the Complexity of
Transmisison Cicuits
90