Anda di halaman 1dari 230

Ministry of Defence

Defence Standard 21-59


Issue 2 Publication Date 27 Oct 2006

Systems Engineering Guide for Naval


Combat Systems
DEF STAN 21-59 Issue 2

Contents

Foreword ...........................................................................................................................................................v
1 Overview ...............................................................................................................................................1
1.1 Introduction .....................................................................................................................................1
1.2 Warning............................................................................................................................................3
1.3 Normative References....................................................................................................................3
1.4 Abbreviations ..................................................................................................................................3
1.5 Combat System Design..................................................................................................................4
1.6 Def Stan 21-59 Combat Systems Engineering Process............................................................10
2 Concept Phase ...................................................................................................................................25
2.1 Introduction ...................................................................................................................................25
2.2 Purpose of the Concept Phase....................................................................................................25
2.3 Requirements Engineering ..........................................................................................................26
2.4 Concept Phase Inputs ..................................................................................................................27
2.5 Concept Phase Outputs ...............................................................................................................31
2.6 Key Concept Phase Processes ...................................................................................................34
3 Assessment Phase ............................................................................................................................41
3.1 Introduction ...................................................................................................................................41
3.2 Purpose of the Assessment Phase.............................................................................................41
3.3 Inputs .............................................................................................................................................43
3.4 Outputs ..........................................................................................................................................43
3.5 Technology Demonstration Programmes / R & D - Technology Survey.................................47
3.6 Key Assessment Phase Processes ............................................................................................47
4 Demonstration and Manufacture Phase ..........................................................................................85
4.1 Introduction ...................................................................................................................................85
4.2 Purpose of the Demonstration and Manufacture Phase ..........................................................85
4.3 Inputs .............................................................................................................................................88
4.4 Outputs ..........................................................................................................................................89
4.5 Organisation.............................................................................................................................................90
4.6 Demonstration and Manufacture Phase Processes..................................................................93
5. In-Service Phase ..............................................................................................................................131
5.1 Introduction .................................................................................................................................131
5.2 Purpose of the In-Service Phase...............................................................................................131
5.3 Inputs ...........................................................................................................................................134
5.4 Outputs ........................................................................................................................................134
5.5 Organisation................................................................................................................................135
5.6 In-Service Phase Process ..........................................................................................................135
6 Termination Or Disposal Phase......................................................................................................153
Unclassified
ii
DEF STAN 21-59 Issue 2

6.1 Introduction .................................................................................................................................153


6.2 Purpose of the Termination or Disposal Phase.......................................................................153
6.3 Inputs ...........................................................................................................................................155
6.4 Outputs ........................................................................................................................................155
6.5 Organisation................................................................................................................................156
7 Integration, Test, Evaluation and Acceptance Process...............................................................165
7.1 Introduction .................................................................................................................................165
7.2 Purpose of the Integration, Test, Evaluation and Acceptance Process ...............................165
7.3 Inputs ...........................................................................................................................................167
7.4 Outputs ........................................................................................................................................168
7.5 Organisation................................................................................................................................169
7.6 Integration, Test, Evaluation and Acceptance Process..........................................................170
7.7 Practical Integration, Test, Evaluation and Acceptance ...................................................................192
7.8 Integration, Test and Trials Stage Documentation .................................................................195
7.9 Integration, Test and Trials Stage Specialist Discipline Support ..........................................200
Annex A Normative References ..................................................................................................................205
A.1 Reference Information................................................................................................................205
Annex B Abbreviations ................................................................................................................................209

Figures

Figure 1.1 The Combat System.......................................................................................................................4


Figure 1.2 The Iterative Spiral of Design Activities ....................................................................................11
Figure 1.3 Generic Combat System Life Cycle ...........................................................................................15
Figure 1.4 Acceptance Process ....................................................................................................................17
Figure 1.5 ILS Activities.................................................................................................................................18
Figure 1.6 Configuration Management through the Life Cycle .................................................................19
Figure 1.7 Systems Engineering Process and Procurement Approach...................................................20
Figure 2.1 Concept Phase Activities ............................................................................................................34
Figure 3.1 Assessment Phase Activities .....................................................................................................42
Figure 3.2 Assessment Phase Process .......................................................................................................49
Figure 3.3 Composition of Systems Analysis Activity ...............................................................................57
Figure 3.4 Composition of System Design Activity....................................................................................59
Figure 3.5 Design Assessment and Selection ............................................................................................69
Figure 4.1 Shift in Emphasis of Demonstration and Manufacture ............................................................86
Figure 4.2 Demonstration and Manufacture Phase, Overall Process.......................................................87
Figure 4.3 Demonstration and Manufacture Organisational Relationships.............................................91
Figure 4.4 Demonstration and Manufacture Phase Activities ...................................................................94
Figure 4.5 Hierarchy of Project Management Activities.............................................................................96
Figure 4.6 Design Change Management Activities...................................................................................103
Figure 4.7 Subsystem/Equipment Demonstration and Manufacture......................................................109
Figure 4.8 Combat System Acceptance Process......................................................................................113
Unclassified
iii
DEF STAN 21-59 Issue 2

Figure 4.9 Combat System Studies in Context .........................................................................................115


Figure 4.10 ILS Activities Conducted during the Demonstration and Manufacture Phase ..................120
Figure 4.11 Configuration Management Baseline .....................................................................................128
Figure 5.1 Combat System In-Service Phase ............................................................................................131
Figure 5.2 In-Service Support Phase, Overall Process ............................................................................132
Figure 5.3 Staged Handover of Support Responsibilities........................................................................133
Figure 5.4 In-Service Support (ISS) Phase Activities ...............................................................................136
Figure 5.5 Combat System Design Modification.......................................................................................146
Figure 6.1 Removal and Disposal, Overall Process ..................................................................................153
Figure 6.2 Removal and Disposal Organisation Relationships................................................................156
Figure 7.1 Combat System Integration, Test, Evaluation and Acceptance............................................165
Figure 7.2 Integration, Test, Evaluation and Acceptance, overall Process ...........................................167
Figure 7.3 Integration Test and Trials Organisational Relationships .....................................................170
Figure 7.4 Stages of Combat System Integration .....................................................................................171
Figure 7.5 Practical Sequence of Integration, Test and Trials.................................................................172
Figure 7.6 Integration, Test, Evaluation and Acceptance Activities .......................................................173
Figure 7.7 Combat System Acceptance.....................................................................................................186

Tables

Table 1.1 Smart Procurement Principal Themes and Def Stan 21-59 ......................................................21
Table 1.2 Smart Acquisition Commercial Practices and Def Stan 21-59 .................................................23
Table 4.1 Project Management Activities ....................................................................................................97
Table 4.2 Systems Engineering Management Activities ...........................................................................98
Table 4.3 Summary of Life Cycle Process Factors .................................................................................102
Table 4.4 Summary of Documentation ......................................................................................................122
Table 4.5 Specialist Discipline Support.....................................................................................................125
Table 5.1 Project Through Life Management Plan (TLMP) ......................................................................137
Table 5.2 Upkeep Policy..............................................................................................................................140
Table 5.3 Summary of Documentation ......................................................................................................150
Table 7.1 Equipment Test and Trials Activities ........................................................................................178
Table 7.2 Subsystem/Equipment Integration............................................................................................179
Table 7.3 Combat System Integration Activities ......................................................................................180
Table 7.4 Ranging Trials .............................................................................................................................185
Table 7.5 Summary of Documentation ......................................................................................................196
Table 7.6 Specialist Discipline Support.....................................................................................................200

Unclassified
iv
DEF STAN 21-59 Issue 2

Foreword
AMENDMENT RECORD

Amd No Date Text Affected Signature and Date

REVISION NOTE

This standard is raised to Issue 2 to update its content.

HISTORICAL RECORD

This standard supersedes the following:

DEF STAN 21-59, Volume 1, Issue 1, Dated 14 January 2005

DEF STAN 21-59, Volume 2, Issue 1, Dated 14 January 2005

Sea Systems Publication 59 Volumes 1 and 2, Issue 3, Dated June 2002

Sponsorship

1. This Defence Standard (Def Stan) is sponsored by the Defence Logistics Organisation (DLO) Agency,
Ministry of Defence (MOD).

2. The complete Def Stan Issue comprises:

Def Stan 21-59 Issue 2 – System Engineering Guide for Naval Combat Systems.

3. If it is found to be unsuitable for any particular requirement the MOD is to be informed in writing of the
circumstances.

4. Any user of this Defence Standard either within MOD or in industry may propose an amendment to it.
Proposals for amendments that are not directly applicable to a particular contract are to be made to the
publishing authority identified on Page 1, and those directly applicable to a particular contract are to be
dealt with using contract procedures.

5. No alteration is to be made to this Defence Standard except by the issue of an authorised amendment.

6. Unless otherwise stated, reference in this Defence Standard to approval, approved, authorised or similar
terms, means the Ministry of Defence in writing.

7. Any significant amendments that may be made to this Defence Standard at a later date will be indicated
by a vertical sideline. Deletions will be indicated by 000 appearing at the end of the line interval.

8. Extracts from British Standards within this Defence Standard have been included with the permission of
the British Standards Institution.

Unclassified
v
DEF STAN 21-59 Issue 2

Conditions of Release

General

9. This Defence Standard has been devised solely for the use of the MOD, and its contractors in the
execution of contracts for the MOD. To the extent permitted by law, the Crown hereby excludes all
liability whatsoever and howsoever arising (including but without limitation, liability resulting from
negligence) for any loss or damage however caused when the Defence Standard is used for any other
purpose.

10. This document is Crown Copyright and the information herein may be subject to Crown or third party
rights. It is not to be released, reproduced or published without written permission of the MOD.

11. The Crown reserves the right to amend or modify the contents of this Defence Standard without
consulting or informing any holder.

MoD Tender or Contract Process

12. This Defence Standard is the property of the Crown. Unless otherwise authorised in writing by the MOD
must be returned on completion of the contract or submission of the tender in connection with which it is
issued.

13. When this Defence Standard is used in connection with a MOD tender or contract, the user is to ensure
that he is in possession of the appropriate version of each document, including related documents,
relevant to each particular tender or contract. Enquiries in this connection may be made of the Authority
named in the tender or contract.

14. When Defence Standards are incorporated into contracts, users are responsible for their correct
application and for complying with contractual and other statutory requirements. Compliance with a
Defence Standard does not of itself confer immunity from legal obligations.

Categories of Naval Defence Standard

15. The Category of this Naval Defence Standard has been determined using the following criteria:

a) Category 1. If not applied may have a Critical affect on the following:


Safety of the vessel, its complement or third parties.
Operational performance of the vessel, its systems or equipment.

b) Category 2. If not applied may have a Significant affect on the following:


Safety of the vessel, its complement or third parties.
Operational performance of the vessel, its systems or equipment.
Through life costs and support.

c) Category 3. If not applied may have a Minor affect on the following:


MOD best practice and fleet commonality.
Corporate experience and knowledge.
Current support practice.

Related Documents

16. In the tender and procurement processes the related documents in each Section and Annex A can be
obtained as follows:

a) British Standards British Standards Institution,


389 Chiswick High Road,
London, W4 4AL

Unclassified
vi
DEF STAN 21-59 Issue 2

b) Defence Standards Defence Procurement Agency


An Executive Agency of the MoD
UK Defence Standardization,
Kentigern House
65 Brown Street,
Glasgow, G2 8EX

c) Other documents Tender or Contract Sponsor to advise.

17. All applications to Ministry Establishments for related documents are to quote the relevant MOD
Invitation to Tender or Contract Number and date, together with the sponsoring Directorate and the
Tender or Contract Sponsor.

18. Prime Contractors are responsible for supplying their subcontractors with relevant documentation,
including specifications, standards and drawings.

Health and Safety

Warning

19. This Defence Standard may call for the use of processes, substances and procedures that may be
injurious to health if adequate precautions are not taken. It refers only too technical suitability and in no
way absolves either the supplier or any user from statutory obligations relating to health and safety at
any stage of manufacture or use. Where attention is drawn to hazards, those quoted may not
necessarily be exhaustive.

20. This Defence Standard has been written and is to be used taking into account the policy stipulated in
JSP430: MOD Ship Safety Management System Handbook.

Additional Information

(There is no relevant information)

Unclassified
vii
DEF STAN 21-59 Issue 2

This page intentionally left blank

Unclassified
viii
DEF STAN 21-59 Issue 2

Systems Engineering Guide for Naval Combat Systems -


Overview

1 Overview

1.1 Introduction

1.1.1 Purpose

1.1.1.1 Naval Combat Systems are highly complex systems. This publication documents the design
engineering strategy that should be used for systems development and procurement. It reflects good
management and engineering practice and is predicated on the adoption of Systems Engineering principles.

1.1.2 Objectives

1.1.2.1 The procurement of a Combat System is required to meet a number of objectives, primarily the
provision of a defined level of Military Capability (MC) within a specified time frame and at an acceptable
cost. A Combat System cannot be engineered in isolation: its interactions with the rest of the warship, other
military systems, the procuring and operating organisations, and industry must also be considered. A Military
Capability is a combination of elements across the Defence Lines of Development, only one of which is the
‘Equipment’ strand.

1.1.2.2 A Combat System design strategy must provide a management framework for Combat System
design that emphasises a whole systems approach and provides advice and guidance to other areas of its
procurement. Its primary objectives are to:

a) Identify the design solution that provides the best Value for Money (VFM);

b) Provide both comprehensive and systematic coverage of all aspects of Combat System design
across all phases of the Combat System life cycle;

c) Facilitate a range of Systems Engineering (SE) and project management activities necessary to
achieve project objectives;

d) State how requirements and constraints are gathered, analysed and transformed into a Combat
System design which not only satisfies the need, but which can also be successfully procured,
developed, integrated, accepted and supported in-service.

1.1.3 Scope

1.1.3.1 The Combat System design strategy should use a systematic approach involving the:

a) Gathering of requirements within the context of the required Military Capability (MC);

b) Generation, examination and comparison of system design options;

c) Preparation of formal specifications and MoD documentation as a basis for acquisition;

d) Acquisition of Combat System equipments including new, modified, Non Development Items (NDIs)
and Commercial Off The Shelf (COTS) technology;

e) Integration of acquired equipment items into a coherent system (which itself is integrated with the
platform);

Unclassified
1
DEF STAN 21-59 Issue 2

f) Provision of interoperability with other capabilities and systems e.g. to achieve Network Enabled
Capability (NEC). This involves the Combat System’s integration into the wider MoD Enterprise and
infrastructures;

g) Conduct of testing and trials as a basis for acceptance against requirements;

h) Support of the system whilst in-service;

i) Disposal of the system and its components at the end of its operational life.

1.1.4 Applicability

1.1.4.1 This Defence Standard is directly applicable to Naval Combat System projects. This standard
amplifies AMS Guidance specifically for acquisition activities in the Maritime domain.

1.1.4.2 The strategy can be applied at the inception of a Combat System project or can be introduced at
any subsequent stage in the life cycle. It can be applied to the whole range of Combat System projects,
including so-called greenfield design (i.e. systems for which no precedence has been set in terms of design
or implementation directives), systems largely comprising NDIs, and to Mid Life Update (MLU)/enhancement
studies. During MLUs, the capability of installed Combat Systems can be significantly enhanced, however
the design problems of integrating new technologies, especially the emerging COTS technologies and
standards, and older bespoke technology should not be underestimated.

1.1.4.3 In applying the strategy, individual projects must apply judgement in terms of which design issues
are important, which activities must consequently be carried out and which output products and other project
documents/data must be produced.

1.1.5 Document Structure

1.1.5.1 Throughout this document the following convention applies:

a) Bold type is used to identify labels and text explaining an accompanying figure;

b) Italic type is used for text providing specific guidelines, advice or for emphasis;

c) Normal type is used for explanatory text.

1.1.6 Relationship with other Documents

1.1.6.1 The Acquisition Management System (AMS)

1.1.6.2 The prime source of guidance for the implementation of Smart Acquisition processes within the
DEC, DPA, DLO and DCSA for EP and STP projects is contained in the AMS at www.ams.dii.r.mil.uk or
www.ams mod.uk. The content of this Def Stan uses the basic principles contained within the AMS and
whilst these are unlikely to change, the implementation details may. The AMS is the subject of frequent
update and should therefore be consulted for clarification of that detail.

1.1.6.3 This document is fully compatible with the AMS guidelines and MoD procedures for “Smart
Approvals” as at November 2005.

1.1.7 Intended Readership

1.1.7.1 This document is intended to be used by all Combat System Stakeholders, that is, all parties with a
legitimate interest in the successful design, development, assurance, testing, acceptance, operation and
support and ultimately the disposal of the Combat System.

1.1.8 Use of this Document

1.1.8.1 Def Stan 21-59 represents a coherent corporate strategy for ‘best practice’ in the delivery of
Combat System design. It is both forward-looking in presenting how such studies should be conducted in

Unclassified
2
DEF STAN 21-59 Issue 2

the future, and realistic since it reflects experience gained on a significant number of projects drawing on
both the MoD and industry perspectives.

1.1.8.2 However, whilst this document is intended to identify the range of specific activities which are likely
to have to be conducted in any Combat System design project, the information presented neither mandates
activities nor specific techniques and tools. Every project must decide how the strategy should be
implemented, what activities are key and therefore must be conducted, and what techniques and tools are
acceptable for their conduct.

1.2 Warning

The Ministry of Defence (MOD), like its contractors, is subject to both United Kingdom and European laws
regarding Health and Safety at Work. All Defence Standards either directly or indirectly invoke the use of
processes and procedures that could be injurious to health if adequate precautions are not taken. Defence
Standards or their use in no way absolves users from complying with statutory and legal requirements
relating to Health and Safety at Work.

1.3 Normative References

The Publications shown in Annex A are referred to in the text of this standard. Publications are grouped and
listed in alpha-numeric order.

1.4 Abbreviations

The abbreviations in shown Annex B are referred to in the text of this standard.

Unclassified
3
DEF STAN 21-59 Issue 2

1.5 Combat System Design

1.5.1 Background

1.5.1.1 A Combat System may be defined as:

The set of men and machine resources which comprise the fighting capabilities of a platform.
Essential sub-systems will include weapons, sensors, intelligence and information sources, and the
combat management system.

1.5.1.2 Figure 1.1 illustrates the typical scope of surface ship and submarine Combat Systems and their
domains of interest. It is not exhaustive and recent shifts in defence policy have increased maritime
involvement in Littoral and Land operations and are also increasing the emphasis on interoperability and
network-based capabilities. The Combat System integrates into a cohesive whole, all equipments and
operators that contribute to the platform’s ability to fight as part of a force package.

Above Water Surveillance External Communications

Weapons & Countermeasures

Navigation

Environmental Sensors
Underwater Surveillance

Command and Control


System

Figure 1.1 The Combat System

1.5.2 Historical Approach

1.5.2.1 The traditional method of warship procurement for the Royal Navy has involved the design of a
platform (i.e. the combination of hull, propulsion and control machinery) in parallel with the development of a
Combat System comprising various sensor, weapon and other equipments. The advent of the Smart
Acquisition process and attendant AMS Guidelines has not necessarily removed the potential for
incoherence between these parallel activities but it does provide a common procurement framework for all
the stakeholders to work together to provide the overall Military Capability required.

1.5.2.2 Much of the emphasis in the early stages of the life cycle has been on the selection of suitable
equipments already in existence or under development, including COTS, and on the initiation of
development of further new equipments. These new equipments offer improvements in performance over
current equipments to counter threat developments and exploit technological advances. They have been
developed as distinct projects, which in many cases are separate from the project(s) responsible for
developing the platform Combat System(s).

Unclassified
4
DEF STAN 21-59 Issue 2

1.5.2.3 Integration has seldom been an issue addressed from the outset, more an activity conducted during
the latter stages of Combat System design, possibly using a Shore Development/Integration Facility
(SDF/SIF) prior to installation of the Combat System on board the First Of Class (FOC) platform. This latter
consideration of integration has often resulted in the main emphasis being placed on physical factors rather
than issues such as information flow and Human Factors (HF). It concentrates on tailoring existing in-service
equipments and interfacing new development equipments to achieve a reasonable degree of cohesion in the
whole Combat System rather than designing the separate equipments to work together from the beginning
and thus ensuring compatibility of interfaces and operation.

1.5.2.4 Generally, throughout the Combat System development process, its overall capability has been
somewhat unknown due to performance and other interdependencies. Once integration has been
completed, the approach provides the platform with a combat capability, but possibly with certain shortfalls
as compared with that originally required.

1.5.3 Whole Systems Approach

1.5.3.1 A ‘whole systems’ approach to Combat System design has evolved in order to deliver a coherent
combat capability. This involves consideration of the Combat System as part of a larger system, namely the
warship (i.e. the combination of the platform and its propulsion and Combat System).

1.5.3.2 Warship design encompasses hull design, marine engineering and Combat System engineering. It
includes overall responsibility for Combat System design and not just the physical installation and integration
of the Combat System equipments. Therefore, in order to ensure consistency between the platform and the
Combat System, it is essential to address the Combat System impact on elements of the warship (and
therefore the platform) design and vice versa.

1.5.3.3 Functionally, the purpose of a warship comprises the naval architects’ three primary design
objectives, namely float, move and fight.

1.5.3.4 Following the ‘whole systems’ concept, the Combat System is designed as an integrated whole
from the outset of the project to meet the ‘fight’ aspects of the whole warship requirement. More specifically,
the ‘whole systems’ approach involves:

a) Identification of the need for a new ship/submarine;

b) Scoping of the Combat System requirements including the operational scenarios and operational
Concepts;

c) Definition of the Combat System acceptance criteria;

d) Definition of the required Information Exchange Requirements and interfaces;

e) Identification of Combat System (explicit and implicit) design drivers;

f) Production of clear, consistent and comprehensive specifications which can be used to procure the
Combat System and its constituent subsystems and equipments;

g) Systematic and comprehensive treatment of all SE issues (including ILS, Security and HF) in the
design of the Combat System;

h) Consideration of whole warship design issues (transversal issues) which are common to all platform
systems including the Combat System;

i) Consideration of the through-life cost of ownership and other affordability issues such as ‘spend
profile’ (great importance is now attached to this as in-service costs are usually the dominant costs;
often driven by decisions made early in the design process).

1.5.4 Current Challenges

1.5.4.1 The design of modern Combat Systems brings with it many significant challenges including:

Unclassified
5
DEF STAN 21-59 Issue 2

a) The ability to specify a Combat System sufficiently for acquisition purposes without over-constraining
the solutions preferred by suppliers;

b) The ability to predict and achieve overall capability in a cost-effective way;

c) The integration of the broad range of technical disciplines involved in Combat System design;

d) The identification and management of risk and risk contingencies;

e) Greater interaction between Combat System and warship (e.g. upper deck layout, hull/machinery)
designers if novel hull forms and greater signature control are required;

f) The effective parallel development of the Combat System and new development equipments;

g) The ability to assess more rapidly the impact of changes in operational and other project
requirements (including roles, threat and cost);

h) The intrinsic technical difficulty in addressing certain issues such as the specification and analysis of
non-functional requirements;

i) The changing climate though which enabling technology is advancing. In the past, technological
innovation was typically military-led. Nowadays, the commercial marketplace is driving technological
advance. As a consequence, there is the need to consider the implications of adopting COTS
technologies, open systems etc. including the consequent management of obsolescence and
‘technology refresh’;

j) Consideration of the highly interactive nature of each element of equipment within the Combat
System;

k) Consideration of the capability of each equipment to be able to carry out additional functions to those
that it would have traditionally carried out;

l) The need to partition the Combat System into specialist sub-systems for competitive procurement,
followed by the requirement to assess competing software intensive solutions;

m) Increasing requirements for system inter-operability;

n) Successful Combat System integration with the equipment performing at least as well when
integrated into the Combat System as it does when operated individually;

o) The need for architectural flexibility so that new combat capabilities can be rapidly inserted to meet
new demands and other emerging threats;

p) Addressing issues which provide a benefit across several warship classes – such as common
equipments or equipment modules, shared support arrangements and spares provisioning;

q) Timely and appropriate consideration of logistics and supportability issues including, as part of
system development, Integrated Logistic Support (ILS) and Continuous Acquisition & Life-cycle
Support (CALS);

r) The use of Incremental Acquisition procedures to enhance combat capability when equipment
technology is both mature and required;

s) The use of an alliance-based procurement strategy involving a number of suppliers and a specialist
project manager.

1.5.4.2 To address these current challenges requires the exploitation and harmonisation of a range of
technical (both specialist and generalist) and project management skills.

Unclassified
6
DEF STAN 21-59 Issue 2

1.5.5 Options for Combat System Acquisition

1.5.5.1 Conventional Approach (i.e. MoD as Design Authority (DA)

1.5.5.1.1 The conventional approach to the development of a Combat System essentially involves the
subdivision of the Combat System design into its component subsystems and/or equipments in order to
support separate development and procurement, e.g. an MLU requiring only changes to one specific system.
With this approach, DPA acts as systems authority with responsibility for the overall integration of Combat
System equipments/subsystems and integration of the Combat System in the warship.

1.5.5.1.2 A variant of this approach involves DPA contracting out responsibility for the successful integration
of the Combat System equipments (but not for their procurement) to an external Combat System design
authority.

1.5.5.2 Prime Contractorship and Whole Warship Procurement (i.e. DA placed with the Prime
Contractor)

1.5.5.2.1 The aim of prime contractorship is to transfer risk (particularly the risk associated with the separate
procurement and integration of individual Combat System equipments and, potentially, their life cycle
support) from the MoD to the contractor.

1.5.5.2.2 Coupled with this transfer of risk is the transferral of design authority. Therefore, following the
placement of a prime contract, DPA's ability to influence the design in areas such as the selection of specific
equipments and consideration of the fleet-wide commonality of Combat System components is greatly
reduced.

1.5.5.2.3 Prime Contractorship imposes a discipline on DPA in the need to:

a) Reduce the risk contingencies, which will be held by both the CSM and the prime contractor, to
affordable levels. Tools for reducing these contingencies include applied research, technology
demonstrators and rapid prototyping. These topics are discussed further in Sections 2 and 3;

b) Produce very carefully considered prime contractorship Invitation To Tender (ITT) documentation
which, whilst taking care to avoid mandating equipment, sets requirements which can only be
satisfied by acceptable design solutions;

c) Carefully select potential prime contractors in terms of their ability to handle the transferred risk,
taking into account a broad range of factors including the financial viability of the organisation and
the range of similar projects of comparable monetary value being undertaken;

d) Adopt a strictly ‘hands-off, eyes-on’ approach following prime contract award, relying upon audits
and formal reviews to monitor the system design, including the fulfilment of the requirements and the
maturity of the design solution.

1.5.5.2.4 Prime Contractorship may be extended to encompass the entire warship rather than just the
Combat System. Its aim is to further transfer risk, including the risk associated with the integration of the
hull, machinery and Combat System, from the procurer. This is known as whole warship procurement.

1.5.6 The Relationship between Combat System and Equipment Studies

1.5.7.1 To specify accurately the needs of equipments requiring development and to manage effectively
issues such as their integration with the remainder of the Combat System, the relationship between Combat
System and equipment studies needs careful consideration.

1.5.7.2 The MoD-funded research programme must reflect anticipated future warship projects, their
requirements and design drivers, and current technology shortfalls. CSMs should influence the priorities and
direction of the research programme, in the role of Associate customer, starting at concept phase or earlier.

1.5.7.3 Combat System studies should be timed to precede studies for new development equipments so
that the full totality of the equipment requirement can be actioned. However, the development timescales for

Unclassified
7
DEF STAN 21-59 Issue 2

new Combat Systems will require the conducting of system-level and equipment-level studies essentially in
parallel.

1.5.7.4 Certain new equipments will be developed on a generic basis so that they can be applied to more
than one platform. This places greater emphasis on the need to co-ordinate studies and requirements.

1.5.7 Future Challenges

1.5.7.1 Training

1.5.7.1.1 The Combat System includes the human element comprising the members of the warship
complement who fulfil the fight function by utilising the Combat System. These personnel require training at
various levels ranging from individual operator skills training through to Command Team Training (CTT).
Training initially serves to develop skills, however it must be continued in order to retain and refine skills and
to develop teamwork. Training Needs Analysis, which is part of the HF discipline, establishes the total
training need for a new Combat System. Consideration of training and other areas of HF forms an intrinsic
part of this design strategy.

1.5.7.1.2 Federated Training (or more precisely, Federation of Trainers) is training controlled centrally by a
Combat Management System or associated equipment which serves to bring together a team or sub-team of
Users and their equipment into a common training process at their place of work. Confederated Training is
the linking of onboard training in multiple geographically-dispersed platforms. These solutions are likely to
require consideration as alternatives to more conventional approaches.

1.5.7.2 Impact of Synthetic Environments

1.5.7.2.1 To stress the Combat System in a manner that the operator is unlikely to meet on a regular basis,
but to which they must be trained to respond, has led to the development of synthetic environments.
Synthetic Environments can be created involving a wide variety of training simulators, war game facilities and
real equipment in live exercises all integrated through the extensive use of protocols such as Distributed
Interactive Simulation (DIS), Aggregate Level Simulation Protocol (ALSP) or High Level Architecture (HLA).
It enables an integrated and potentially global network of interacting systems to be used for training, mission
rehearsal, system development, strategy and tactics development, and evaluation purposes. Synthetic
Environments can comprise real warship combat systems, integration facilities, other land and air platforms
(real or virtual), scenario generation and exercise analysis hubs and the networks which interconnect these
elements. It does not replace ‘training in the field’ but can serve to complement it to develop tactical
procedures and doctrine and the skills at military and, potentially, political, levels.

1.5.7.3 Command and Control Warfare (C2W) and Network Enabled Capability (NEC)

1.5.7.3.1 Command and Control Warfare (C2W) is the term used with the UK operational community to
describe warfare in which new levels of speed, synchronisation, precision and flexibility can be achieved
through the exploitation of battlefield and situation awareness. It relies on the availability of an increased
volume of accurate information regarding both own and opposing forces (covering location, activity, status
etc.).

1.5.7.3.2 Realisation of the ability to conduct C2W imposes requirements on all weapon, sensors and
Command, Control, Communications, Computers and Intelligence (C4I) systems in terms of equipment
characteristics (such as smart weaponry) and personnel training, particularly in the ability of commanders to
react more quickly and decisively. Exploitation of such information enables the operational situation to be
more accurately assessed, assets to be more effectively deployed and tactics to be more appropriately
applied.

1.5.7.3.3 The advent of C2W will lead to new requirements being identified which the existing Combat
System must be capable of supporting. The need to ensure that such flexibility and growth can be supported
without extensive redesign will have an impact upon the SE process.

1.5.7.3.4 Network Enabled Capability (NEC) is MoD’s approach to improving the flow of information from its
source to decision-makers, weapons platforms and operatives in the field who are best placed to deliver the
action required. Its realisation will require developments in areas such as ‘shared situational awareness’,

Unclassified
8
DEF STAN 21-59 Issue 2

‘distributed collaborative planning’, high-bandwidth communications links, resilient information structures with
full information availability, mission-configurable assets and the synchronisation of effects.

Unclassified
9
DEF STAN 21-59 Issue 2

1.6 Def Stan 21-59 Combat Systems Engineering Process

1.6.1 Introduction

1.6.1.1 Before introducing the Combat System design strategy, it is worthwhile summarising the underlying
rationale on which it is based. This serves to set the structure of the document in context and aid an
appreciation of its major themes.

1.6.1.2 Although the “Smart Acquisition” process approach serves as the procurement framework for
exploring SE issues within Def Stan 21-59, the underlying engineering process is largely independent from
the Concept/Assessment/Demonstration/Manufacture/In-Service/Disposal (CADMID) life cycle in which it
operates.

1.6.1.3 To explain the SE process in context, it is necessary to briefly review a number of aspects which
run throughout the Combat System life cycle and provide a useful means of highlighting issues and
structuring information in the sections which follow. These aspects are:

a) Systems Engineering Process, introducing the core process, that is the cycle of design activities
associated with developing the system definition;

b) Wider Perspective, which explains and explores the core process in the context of other key
supporting management and technical functions;

c) Combat System Life Cycle, introducing the framework within which the generic SE process is
conducted. This provides the process ‘template’ which is explored in detail in the main sections;

d) Other Major Themes of the Strategy, which provides an introductory overview of the key themes of
Acceptance, ILS and Configuration Management (CM) which run throughout the Combat System life
cycle;

e) Life Cycle Applications, which relates the generic approach to the specific emphases of the
procurement strategy. This is followed by a brief survey of novel system life cycles and a discussion
of how the generic process may be applied in support of recent developments, in particular, Smart
Procurement.

1.6.2 Systems Engineering Process

1.6.2.1 Core Process

1.6.2.1 The core process which underpins the Combat System life cycle applies a consistent trade-off study
framework that is equally applicable to concept evaluation as it is to decision-making during detailed design
and beyond.

1.6.2.2 The core process is based on accepted SE and design theory (embodied in ISO 15288, Mil Std
499B, IEEE 1220 and EIA 632 standards) and reflects the iteration between the functional and physical
domains, through analysis, synthesis and assessment.

1.6.2.3 This cycle is fundamental to design. It provides the basis for the analytical investigation of
requirements and creative generation of possible implementations. Through repeated iterations of the cycle,
design solutions are generated, developed, evaluated and subsequently consolidated. The result is an
optimum design solution tailored to the requirements and constraints which bound it.

1.6.2.4 This iterative design cycle is depicted in Figure 1.2, which although presenting a simplistic view of
what is a complex set of interacting design activities, illustrates the basic concepts. The design cycle is
shown relative to the ‘information base’, the sum knowledge which is amassed during the design cycle. This
is the suite of information, through which the design is defined, explored, expanded, and then subjected to
trade-offs and consolidation.

Unclassified
10
DEF STAN 21-59 Issue 2

Analyse
Problem
Gather
Information
Synthesise
Solution(s)
Information
Gather Base
Information
Proliferation
Assess
Synthesise
(and Select)
Solution(s)

Gather
Information
Assess
Synthesise
(and Select)
Solution(s)

Gather
Information
Assess Consolidation
Synthesise
(and Select)
Solution(s)

Assess
(and Select)

Figure 1.2 The Iterative Spiral of Design Activities

1.6.2.5 The design cycle recognises that there is a continuum of design activities within which the design at
one level determines the bounding requirements (or constraints) of the next. This infers that the definition of
requirements cannot be entirely independent of the design solution. The scope of the requirements must
also reflect the technology base from which the design solution is composed together with any constraints
applicable to the solution’s operation and support.

1.6.2.6 Requirements Engineering

1.6.2.6.1 Requirements Engineering is the systematic process which transforms the needs, objectives and
requirements of the customer in the context of system utilisation and identified system characteristics into a
complete, consistent and precise form. It involves:

a) Identification of stakeholders;

b) Gathering of requirements and constraints;

c) Refinement of requirements and constraints to address inconsistency and ambiguity.

1.6.2.6.2 Requirements Engineering serves to define and maintain a statement of what is needed by the
customer in terms of functionality and performance in the context of the overall system operational
objectives. It is conducted iteratively with systems analysis and system design to develop realistic
requirements which can be demonstrated as meeting the customer need.

1.6.2.7 Systems Analysis

1.6.2.7.1 Systems Analysis is the systematic consideration of a problem (or system) from complementary
perspectives in order to:

a) Obtain a better understanding of it;

b) Identify the component elements, their inter-relationships and impact on key characteristics and
other system issues;

c) Systematically identify and assess alternative courses of action.

1.6.2.7.2 Systems Analysis serves to generate models of the system requirement as a basis for investigating
system functionality and exploring system partitioning and potential performance within the operational
context of the system. It too is conducted iteratively, with requirements engineering and Combat System
design, to ensure that customer requirements are satisfied and to support the refinement of feasible
alternative solutions.

Unclassified
11
DEF STAN 21-59 Issue 2

1.6.2.8 System Design

1.6.2.8.1 System Design serves to develop candidate physical architectural solutions, consistent with their
position in the hierarchy of system development, which are likely to be capable of meeting both the
operational and functional requirements. It involves:

a) Consideration of the non-functional/design/implementation requirements and constraints covering


both features in the system and how they are to be developed and implemented;

b) Examination and adoption of one or more system structures/architectures;

c) Consideration of HF issues and mandated/candidate equipments.

1.6.2.9 Assessment and Selection

1.6.2.9.1 Where the creative design process generates many potential alternative solutions and options,
some means of evaluating the candidates and determining the optimum is needed. Assessment serves to
define the framework within which trade-off studies are to be performed. Typical criteria for comparison
include technical performance, Availability, Reliability & Maintainability (AR&M), operational effectiveness,
development and support cost and risk. Selection determines the design solution(s) to be taken forward,
either for further detailed design or ultimately as a baseline for development / acquisition.

1.6.2.10 Document Production

1.6.2.10.1 Document Production is a fundamental activity, applicable to all stages of the life cycle. The
documents produced form the total set of outputs from and inputs to each life cycle stage, providing the
essential continuity throughout the overall project. Documents may take the form of textual or computer-
generated reports or model-based representations.

1.6.3 The Wider Perspective

1.6.3.1 The generic SE process must be considered against the tasking activities which underpin and focus
the SE activities described above. These include the SE (Technical) and project management functions, life
cycle process factors, specialist discipline support and Combat Systems studies.

1.6.3.2 Systems Engineering (SE) (Technical) and Project Management

1.6.3.2.1 Overall co-ordination of the above is the responsibility of the SE (Technical) and project
management function which provides:

a) SE Management, to ensure that work is identified and programmed within a defined schedule, that
SE activities are conducted according to a defined and auditable process and that the engineering
and support specialist disciplines are integrated within it and conducted in a coherent manner;

b) Project Management, to ensure that the project is controlled and co-ordinated according to an
agreed suite of management and technical plans and policies the application of which can be
demonstrated. Also, ensuring adequate arrangements are in place for the management of quality
and risk across all contractual boundaries.

1.6.3.2.2 The medium for applying these separate disciplines in a co-ordinated manner demands the
involvement of specialists working within an integrated, multi-disciplinary team. Skills are required in
specialist technical (i.e. product specialists such as sonar and radar specialists, discipline specialists such as
HF and ILS experts, and system specialists, for example in integration), generalist technical (i.e. SE) and
project management domains.

1.6.3.3 Life Cycle Process Factors

1.6.3.3.1 Central to a systems-approach is the consideration of system issues at all phases. During early
conceptual work, the implications of the evolving design on downstream activities should also be addressed
and optimised to the appropriate level of detail. This is achieved through the generic SE process which
serves as a problem-solving template at each step.
Unclassified
12
DEF STAN 21-59 Issue 2

1.6.3.3.2 Thus whenever consideration of the system as a concept is necessary, the requirements/
analysis/design activities should address the consideration of downstream life cycle process factors
including:

a) Produceability, the design should take advantage of optimal manufacturing processes and the
potential for Concurrent Engineering;

b) Integration and Test, the design should be optimised for ease of integration and relevant issues dealt
with in a pre-emptive fashion. This approach is commonly called Design for Integration;

c) Trials and Acceptance, due consideration of the most cost-effective route for acceptance consistent
with the prevailing acceptance strategy (Design for Test or Design for Acceptance);

d) Operation and Support, the design needs to be evaluated for its usability and supportability in the
field, otherwise known as Design for Support;

e) Removal and Disposal, sufficient effort should be applied to consider the strategy for eventual
removal from service and disposal of the system. Design for Disposal will become a more important
issue as environmental legislation tightens.

1.6.3.4 Specialist Discipline Support

1.6.3.4.1 A range of specialisms are central to the Combat System engineering effort, in equipment/ warfare
technologies such as sensors, command and control, communications, infrastructure and networking,
navigation, effectors (weapons, jammers, countermeasures), aviation, and warfare domain areas.

1.6.3.4.2 Furthermore, Combat System studies conducted throughout the life cycle require the consideration
of the evolving design from a wide range of engineering discipline perspectives. This requires specialist
support in the following areas:

a) Architectural design and performance;

b) AR&M;

c) Communications;

d) Information/Data Management, which reduces the risk and costs of system integration by the
management of information transfer and the interfacing between the separately procured parts of the
Combat System;

e) Environmental factors including Electro-Magnetic Environmental Effects (E3);

f) HFI and Operability;

g) Installation and Services;

h) ILS, Logistic Support Analysis (LSA) and CALS;

i) Naval Architecture (for naval systems);

j) Operational Analysis and Effectiveness;

k) Performance;

l) Signatures;

m) Software Development;

n) System Alignment;

o) System Safety;

Unclassified
13
DEF STAN 21-59 Issue 2

p) System Security;

q) Shock and Vibration;

r) Training including training needs assessment and definition of training equipment;

s) Requirements Engineering;

t) Marine engineering, especially where it concerns ships services.

1.6.3.4.3 Naturally, there are trade-offs to be made between competing disciplines and contractual priorities.
This is achieved through system studies introduced as a central activity of the generic SE process.

1.6.3.5 System Studies

1.6.3.5.1 System Studies are those activities which are continued throughout the system life cycle providing
mathematical, physical or logical models of system emergent properties and predictive indications of system
performance across a number of key disciplines. These can be used:

a) For specification through representation of certain facets of the design and verification of information
flow across interfaces;

b) For analysis to further understanding of system behaviour and to provide confidence in the projected
system operation and performance;

c) In support of the assessment and selection of a proposed design or comparison of options against
defined criteria (impact analysis and trade-off studies);

d) To consider dynamic aspects of the system in operation;

e) To prove that technology is sufficiently mature to support the proposed implementation;

f) To support the optimisation of the design;

g) To support acceptance of design aspects which cannot be definitively or practically demonstrated


(e.g. operational effectiveness);

h) To support subsequent analysis of test and trials results;

i) To predict the adaptability of the system against emerging requirements.

1.6.4 Combat System Life Cycle

1.6.4.1 General Framework

1.6.4.1.1 A general framework is useful as a reference to understand the relationships between SE


processes, the system life cycles through which they are applied, and the contractual environment stages
imposed as a result of procurement practice. Together, these aspects determine the role of SE within a
project.

1.6.4.1.2 A Generic Combat System Life Cycle is very similar to the AMS CADMID cycle and is presented
schematically in Figure 1.3. This shows the typical SE life cycle activities against the overall sequence of
phases described below.

Unclassified
14
DEF STAN 21-59 Issue 2

Definition Realisation Utilisation Disposal

SYSTEMS ENGINEERING (TECHNICAL) AND PROJECT MANAGEMENT

SDF/SIF HATs SATs

REQUIREMENTS COMBAT SYSTEM IN-SERVICE REMOVAL &


ENGINEERING TEST & TRIALS OPERATION DISPOSAL

SYSTEMS SYSTEM
ANALYSIS INTEGRATION

SYSTEM EQUIPMENT
DESIGN TEST & TRIALS

COMBAT SYSTEM
DEVELOPMENT
IN-SERVICE
SUPPORT
SUBSYSTEM/ EQUIPMENT
DEVELOPMENT & PRODUCTION

LIFE CYCLE PROCESS FACTORS

INTEGRATED LOGISTIC SUPPORT (ILS)

(THROUGH-LIFE) SYSTEMS STUDIES, SPECIALIST DISCIPLINE SUPPORT, CONFIGURATION MANAGEMENT

Figure 1.3 Generic Combat System Life Cycle

1.6.4.1.3 All technical systems may be considered in terms of a sequence of life cycle phases which may be
described as:

a) Definition, where the system as an idea is developed and defined to the point at which it can be
implemented;

b) Realisation where the system is implemented as previously defined;

c) Utilisation where the system is put into operational use and where it remains for most of its life time;

d) Disposal where the system has served its useful life, is no longer needed and is removed,
dismantled, and disposed of.

1.6.4.1.4 The generic system life cycle embraces the established ‘V’ model of system development and
shows this in relation to other notable SE themes which run across the generic phases. Though not explicitly
shown on this diagram, system development comprises further levels of the ‘V’ model development cycle for
subsystem, equipment, and component development as appropriate.

1.6.4.2 Definition Phase

1.6.4.2.1 The initial phase is primarily concerned with developing and refining the system as a concept, to a
point where it can be efficiently and cost-effectively implemented. This refinement of the system concept is
typified by the iterative application of the requirements engineering, systems analysis and system design
activities central to the SE process model described earlier.

1.6.4.2.2 This phase may also see the design progressed to a level of detail from which development can
commence. In this context, system development may entail the development of new or modified items, or
the acquisition of Non-Development Items (NDIs) or the use of COTS technology. The system comprises
architecture, elements of infrastructure and the applications and equipments delivering actual operational
capability.

Unclassified
15
DEF STAN 21-59 Issue 2

1.6.4.3 Realisation Phase: Implementation of the Physical System

1.6.4.3.1 Realisation of the system as a physical implementation is achieved through the acquisition of
system components (referred to as configuration items) and their progressive integration and test.
Component equipments are first tested as stand-alone items which are then brought together in groups
through system integration. The process culminates in the test and trials of the fully integrated system as a
whole.

1.6.4.3.2 The physical integration process is managed through a sequence of test and trials which ensures
that the system is operationally acceptable before going to sea. This is achieved through a structured
regime of shore-based trials (often conducted at a SDF/SIF), Harbour Acceptance Trials (HATs) and Sea
Acceptance Trials (SATs), which collectively provide the basis for demonstrating compliance with the
requirements for certification/acceptance.

1.6.4.3.3 The mix of equipments/components will inevitably dictate the overall approach to integration, test
and trials, the policy for which would have been formulated prior to the realisation phase.

1.6.4.4 Utilisation Phase: In-Service Operation and Support

1.6.4.4.1 Following the certified hand over to the eventual user, the system will enter its operational lifespan.
During this time it will be operated and maintained. Additionally, it may be subject to minor improvements
and updates, to maintain its performance, or major upgrades to enhance its capability. Any additional
development will need to be achieved through a comparable ‘V’ model development cycle as before, unless
it has been planned for ‘ab initio’ as part of an Incremental Acquisition approach.

1.6.4.5 Disposal

1.6.4.5.1 The final phase of the life cycle is removal and disposal in which the system leaves operational
service. This may be due to external factors such as changing government policy or platform/ equipment
obsolescence or internal factors such as component failure/obsolescence.

1.6.5 Other Major Themes of the Strategy

1.6.5.1 Acceptance

1.6.5.1.1 As the Combat System Acceptance Authority, the DEC is responsible for outlining his Acceptance
Strategy at the beginning of the Concept phase and ideally at Gate Zero. Factors that determine it include
the Acquisition Strategy (e.g. Incremental, service or equipment oriented), the Acquisition Strategy (e.g. the
placing of DA responsibility), when certain requirements need to be met in order to satisfy the Capability Gap
and what Military Capability will be required to achieve the In-service Date. This Acceptance Strategy is
developed by the IPT, with the DEC’s agreement, and captured within an Integrated Test and Evaluation
Plan (ITEAP). System Acceptance occurs when the system acquired by the IPT satisfies the SRD. In-
Service Date (ISD) is declared when the Military Capability provided by the system (across all Defence Lines
of Development) is assessed as available for operational use.

1.6.5.1.2 The ITEAP should detail the process by which evidence of compliance with the requirements will be
accumulated throughout all project stages and ultimately be presented to the DEC for his Acceptance and
transfer to Customer 2 and the DLO. A typical acceptance process that could be adopted as a basis for a
Combat System ITEAP illustrated in Figure 1.4.

Unclassified
16
DEF STAN 21-59 Issue 2

Requirements Management of the Acceptance Process Formal


Allocation and Visibility of progress towards Acceptance/ Cumulative
Decomposition Progressive Acceptance Acceptance

Combat System

Validation of System/Compliance with Requirements


RE Acceptance
Verification of System Design
SA Test
Lower-level Evidence of
Subsystem/Equipment Verification Compliance with
Requirements, Lower-level
partitioned by the
SD Integration
Subsystem/ Subsystem/ Requirements for
System Design Equipment Equipment Formal Acceptance
Contracts Deliverables

Subsystem/Equipment

Validation of Equipment/Compliance with Requirements


RE Acceptance

Verification of Equipment Design


SA Test

Verification
SD Integration

Implementation

Figure 1.4 Acceptance Process

1.6.5.1.3 The acceptance process can be thought of as ‘closing the square’, satisfying Combat System
design requirements cascaded down the subsystem/equipment hierarchy by the accumulation of acceptance
evidence produced from lower level acceptance events. At each level, verification of the transformations
between requirements, analyses, design, implementation and test activities ensures traceability of
requirements to eventual products. This verification mechanism supports certification and acceptance.

1.6.5.1.4 Visibility of the progress towards acceptance is an important consideration. Reviews are a major
element in the acceptance process, especially in determining whether acceptance evidence generated
satisfies requirements. The acceptance process has therefore to deal with both success and failure of
acceptance events and link in to general management processes to initiate and be involved in recovery
programmes if defects and deficiencies arise.

1.6.5.2 Integrated Logistic Support (ILS)

1.6.5.2.1 The Through-Life Cost (TLC) of supporting an equipment is generally equal to or more than the
initial cost of procurement. Through-Life cost is therefore a significant factor in acquisition decisions and
hence needs to be managed in a disciplined way. ILS is the accepted discipline for managing support costs,
for causing support considerations to influence the design or selection of equipment and for delivering and
monitoring a consistent support environment for the fielded equipment. Figure 1.5 identifies the major
themes of ILS which are shown relative to the project phases throughout which ILS activities are conducted.

Unclassified
17
DEF STAN 21-59 Issue 2

Develop Determine/Deliver Maintain Terminate


Support Strategy Support Support Support

IN-SERVICE UPKEEP

IN-SERVICE ASSESSMENT

LOGISTICS SUPPORT ANALYSIS (LSA) including the LSAR Facilities


Preventive Skills Training
RCM
Tasks
Use Support & Test
Req Study Design FMECA MTA LORA
Corrective Package Handling
Final LSAR
Tasks Storage & Transportation

TECHNICAL DOCUMENTATION

Doc Design Data Capture Generate Documentation


Verify Verify Delivery Use Update Archive
Planning & Preparation Data Modules Production

INTEGRATED SUPPLY SUPPORT PROCEDURES (ISSP) SUPPLY SUPPORT


Codify Screen Scale Plan Order Invoice
Procurement MODIFICATIONS

LIFE CYCLE COSTING (LCCs)


Initial LCC LCC Revise LCC Final LCC

FMECA - Failure Modes Effects and Criticality Analysis; RCM - Reliability Centred Maintenance; MTA - Maintenance Task Analysis;
LORA - Level Of Repair Analysis; LSAR - Logistics Support Analysis Record; LCC - Life Cycle Costing

Figure 1.5 ILS Activities

1.6.5.2.2 It is MoD policy that the discipline of ILS is applied to all system/equipment procurement and
addresses a wide range of support areas. The ILS elements, as defined by the ILS Def Stan 00-60, are:

a) Maintenance Planning;

b) Supply Support;

c) Support and Test Equipment (S&TE);

d) Managing AR&M data;

e) Facilities;

f) Manpower and HF;

g) Training and Training Equipment;

h) Technical Documentation;

i) LSA.

1.6.5.2.3 The list however is neither exhaustive nor prescriptive and the applicability of each element will vary
between projects.

1.6.5.2.4 The LSA process generates data which shall generally be held in a single relational database called
a Logistic Support Analysis Record (LSAR).

1.6.5.2.5 Within this guide, ILS is considered as a project management function whereas LSA is considered
as a composite of SE activities also addressed in their own right, for example HF, training etc. Though there
may be some overlap between subject material, the underlying objective is to co ordinate a concerted set of
activities which address all the main priorities as part of an overall SE strategy.

1.6.5.3 Configuration Management (CM)

1.6.5.3.1 CM is the process of identifying and managing changes to the system design as it evolves. The
objective is to ensure that proposed changes are necessary and appropriate, that the integrity of the system
is maintained and that correct records are kept.

Unclassified
18
DEF STAN 21-59 Issue 2

1.6.5.3.2 CM during early stages of the life cycle serves to keep track of requirements, specification and
plans, so that the design task is co-ordinated through an auditable process. It therefore provides the set of
baselines against which change can be assessed, controlled and implemented. From the development and
production stage onwards, CM becomes a significant issue due to the proliferation of requirements,
specifications, physical deliverables, test and acceptance data.

Configuration Baselines

REQUIREMENTS
FUNCTIONAL
PHYSICAL
VERIFICATION
ACCEPTANCE
SUPPORT

SDF/SIF HATs SATs

REQUIREMENTS COMBAT SYSTEM IN-SERVICE


ENGINEERING TEST & TRIALS OPERATION

SYSTEMS SYSTEM
ANALYSIS INTEGRATION

SYSTEM EQUIPMENT
DESIGN TEST & TRIALS
IN-SERVICE
COMBAT SYSTEM SUPPORT
DEVELOPMENT

SUBSYSTEM/ EQUIPMENT
DEVELOPMENT & PRODUCTION

Figure 1.6 Configuration Management through the Life Cycle

1.6.5.3.3 CM provides the mechanisms through which the design can be taken through development and
production in a controlled manner. This is achieved through imposition of CM baselines across each of the
SE activities as depicted in Figure 1.6. The baselines provide a progressive scheme which records the
status of the design, development, production, integration and test processes with rigour so that the design is
supported by an auditable regime.

1.6.5.3.4 Each of the baselines should be reviewed at the point in the project review cycle at which they are
first instantiated and thereafter audited at each formal review. The project review cycle provides the
structure through which project baselines and change control processes are formally audited. The baselines
provide a solid foundation for the impact assessment of engineering change requests through which change
control can be effected. Each baseline represents a particular aspect of the design evolution and should be
synchronised so that the design itself moves forward through the formal process of reviews.

1.6.5.3.5 CM is equally important during the in-service phase when technology refresh, technology insertion
and major upgrade may be required. It serves to assist in ensuring that unchanged parts of the system
perform as they did previously and that any changed parts of the system meet their respective requirements.

1.6.6 Life Cycle Applications

1.6.6.1 Flexibility of a Generic Approach

1.6.6.1.1 The acquisition approach adopted for a project inevitably influences the practical implementation of
the SE process. In general terms, the SE approach is largely independent of the acquisition approach. This
point is illustrated in Figure 1.7 which implies that the acquisition approach affects the organisational
structure more than it affects the underlying process.

Unclassified
19
DEF STAN 21-59 Issue 2

APPLICATION OF THE GENERIC SYSTEMS ENGINEERING PROCESS


Concept Realisation Operation Disposal

During the concept design stages, the SE process should be During the realisation and operational stages, the SE
iteratively repeated to generate and investigate candidate process provides the basis for change impact investigation
design solutions. These are then subject to trade-off study to and definition and implementation of design enhancements
identify the optimum solution(s) for realisation and modifications

ORGANISATIONAL ARRANGEMENTS, Downey


Concept Feasibility Project Development Integration In Service Disposal
Definition & Production Test & Trials Support
EAC Approval EAC Approval EAC Approval

Concept Stage Feasibility Stage PD Stage


Consolidation Consolidation Consolidation
MOD intra- MOD Project and MOD Project and Contract Award to Hand Over to Operating
mural studies/ three consortia two consortia a single consortia/ NSC Authority hand
rainbow team conducting parallel conducting parallel organisation (or ISS Contract to over to DESO and
studies studies MOD retained single consortia/ agents in industry
CSDA) organisation

ORGANISATIONAL ARRANGEMENTS, Smart Acquisition


Concept Assessment Demonstration & (Integration In Service Disposal
Manufacture Test & Trials) Support
‘Initial Gate’ approval ‘Main Gate’ approval

Consolidation conducted within the IPT through the


Systems Engineering process

Integrated Project Team (IPT) formed from DEC, DPA, IPT needs to manage competition for IPT moves under Operating
and Industry (where need for competition permits) Combat System Development and control of DLO Authority hand
empowered to conduct trade-offs within scope of authority Integration. IPT must devolve supported by over to DESO and
responsibility for implementation to the agents in industry
Industry
successful contractor

Figure 1.7 Systems Engineering Process and Procurement Approach

1.6.6.2 Acquisition Approach

1.6.6.2.1 Def Stan 21-59 provides guidance information on SE issues with reference to the Combat System
life cycle. The equivalent Smart acquisition phases are also shown at the bottom of this diagram. This
provides a useful framework for system acquisition using terms in common usage throughout the MoD and
the defence industry.

1.6.6.2.2 The earlier stages (Concept and Assessment) are conducted to perform increasingly detailed
design studies following the generic SE process introduced earlier. These consider a multiplicity of
engineering issues and their implications throughout the subsequent stages of the life cycle. Each of the
early stages is followed by consolidation activities which serve to rationalise the output products produced by
competing consortia (where parallel stage activities are invoked).

1.6.6.2.3 Development and Manufacture, including integration, test, and trials are the combined stages
during which the operational Combat System is implemented and accepted. Component equipment is many
and complex. Control and co-ordination of separate system and equipment programmes and other Lines of
Development demands the imposition of a formal project review cycle to synchronise inter related activities
across the system hierarchy.

1.6.6.2.4 Once operational, the Combat System will be subject to continuing In-Service support throughout its
operational lifetime. Finally, when it is no longer viable to support the system to provide the required
operational capability it will be subject to removal from service, perhaps along with the platform, for eventual
disposal.

Unclassified
20
DEF STAN 21-59 Issue 2

1.6.7 Advanced Life Cycle Applications

1.6.7.1 Smart Acquisition and Def Stan 21-59

1.6.7.1.1 Since the underlying SE process which underpins the Combat System design strategy guide is
generic, Def Stan 21-59 already embraces many of the principles of Smart Acquisition listed below and can
be applied as described in Table 1.1.

Table 1.1 Smart Procurement Principal Themes and Def Stan 21-59

Topic Description Def Stan 21-59 Approach

Whole Life A holistic approach whereby any new or Def Stan 21-59 advocates a ‘whole
Systems Approach modified system or capability is systems’ approach whereby the Combat
considered and justified in relation to the System is considered in relation to the
overall military capability. platform role(s) through Operational
Analysis and associated Effectiveness
modelling.

Furthermore, the SE Generic Process


serves to consider equipment level issues
and their impact on the overall system.
Through-Life issues are considered from
the earliest stage, when design freedom is
greatest and issues with significant cost
impact can be best addressed.

Project Initiation Formalisation of ‘concept’ to: Def Stan 21-59 endorses the pre-feasibility
objectives and activities as an integral part
• Set out the project boundaries; of the Concept stage.

• Identify key stakeholders;


Further emphasis is given on the need to
• Scope the requirement; tailor the SE process to meet the needs of
the procurement strategy.
• Produce initial through-life cost
estimates;

• Develop strategies for


procurement, support,
technology insertion and
approval.

Co-operative The formation of integrated teams Def Stan 21-59 demands the identifying
Stakeholder (including industry where applicable) at and consulting with project Stakeholders
Involvement the earliest stages of a project to agree through the Requirements Engineering
and achieve common goals. process.

The formation and constitution of integrated


teams is addressed in Project
Management.

Concurrency and To combat delays in the approvals This needs to be considered when tailoring
Project Approvals process which conflict with the desire to the Guide to the individual project needs.
Strategies quickly field rapidly advancing Coherent, concurrent system and
technology. equipment development can be managed
with Def Stan 21-59.

Improved To assist project stakeholders in defining Requirements Engineering is a central


Requirements essential requirements and achieving a theme of the Strategy. The process though
Management balance between performance, in- which requirements trade-offs are achieved
service date, costs, risks and through-life is illustrated and explained by the Generic

Unclassified
21
DEF STAN 21-59 Issue 2

Topic Description Def Stan 21-59 Approach

supportability. SE Process described earlier.

Rapid Pull Through To address and embrace emerging Def Stan 21-59 encourages liaison with the
of Technology technology from both COTS and applied MoD- and Industry-funded applied research
research domains. and TDPs. Guidance on COTS insertion is
provided in Annex B, Project Management.

Integrated Integrated Cost Forecasting and Whole-life cost estimation is advocated by


Estimating and definition of In-Service Target Date Def Stan 21-59 from Concept phase so that
Predicting (ISTD). n affordable system results.

Incremental Planned upgrade (particularly for Incremental Acquisition requires the


Acquisition electronics and software), to deliver early progressive delivery of capability in a
capability and exploit advancing manner which balances military need,
technology through a series of technology maturity and budgetary
manageable steps. considerations. Enabled by Design base
lining, CM and other through-life technical
and managerial processes advocated by
this standard.

1.6.7.1.2 In addition, Smart Acquisition advocates the adoption of improved commercial practices to promote
a more flexible approach to defence procurement as described below in Table 1.2.

Unclassified
22
DEF STAN 21-59 Issue 2

Table 1.2 Smart Acquisition Commercial Practices and Def Stan 21-59
Topic Description Def Stan 21-59 Approach

Partnering Development of a closer relationship Def Stan 21-59 advocates closer working
Approach/ between MoD and Industry: between MoD and industry though it does
Teamwork in Pricing not explicitly suggest partnering since the
• to improve flexibility and precise arrangements are project specific
responsiveness particularly to
support incremental acquisition;
• to improve the time taken to get to
contract and improve estimating.
Performance To assess contractor performance Def Stan 21-59 encourages the adoption of
Evaluation against business process maturity for business processes which are SE CMM
future reference. compliant.

Enhanced Enhanced scope for competition for In- In-Service Support organisational
Competition Service Support contracts as a result of considerations are discussed in In-Service
improved definition of IPRs. Support.

Electronic The use of Electronic Data Interchange Electronic Data Management is central to
Commerce (EDI) to improve tracking of orders and the co-ordination and control of the Combat
deliveries and streamline payment System and Platform design and build
systems. process. Other aspects of electronic
commerce lie outside the scope of Def
Stan 21-59.

Low Value Improved efficiency of the purchase of Not applicable to Def Stan 21-59.
Procurement low value items.

Reproach through Contractual remedies for unsatisfactory


Liquidated Damages Performance though the informed use of
Liquidated Damages (LDs).

Unclassified
23
DEF STAN 21-59 Issue 2

This Page Intentionally Left Blank

Unclassified
24
DEF STAN 21-59 Issue 2

Systems Engineering Guide for Naval Combat Systems -


Concept Phase

2 Concept Phase

2.1 Introduction

2.1.1 The Acquisition Management System (AMS)

2.1.1.1 The prime source of guidance for the implementation of Smart Acquisition processes within the
DPA, DLO and DCSA for EP and STP projects is contained in the AMS at www.ams.dii.r.mil.uk or
www.ams.mod.uk. The content of this Def Stan uses the basic principles contained within the AMS and
whilst these are unlikely to change, the implementation details may. The AMS is the subject of frequent
update and should therefore be consulted for clarification of that detail.

2.1.2 Pre Gate Zero Responsibilities

2.1.2.1 Before starting the Concept Phase, i.e. prior to Gate Zero and the establishment of formal DPA
procurement activity, Customer 1 (i.e. the DEC) is required to conduct several activities. These are listed in
the DEC Desk Officers’ handbook. Primarily the DEC must establish a Capability Need based on a
Capability Gap identified from egg a MILCAP shortfall or emerging threat. This Capability should be
expressed in a Single Statement of (User) Need (SSON) that is traceable to the JETL or a METL (Joint /
Maritime Essential Task List). This in turn should be decomposed into an initial set of User Requirements
captured within an initial User Requirement Document (URD). Complementing this URD should be a
Customer Supplier Agreement (CSA) which directs the IPTL or Project manager on how the DEC wishes the
project to be managed within the principles of Smart Acquisition (egg for defining the Performance / Cost /
Time (PCT) envelope). The CSA should state the budget, its spend profile, when the DEC expects project
programme milestones to be met and with what confidence. The DEC must also have established initial
coherency of his requirements within the overall MoD programme and established consensus across DECs
for issues potentially affecting interoperability and integration into the battlespace.

2.1.2.2 As well as agreeing a CSA with the IPTL for the procurement of Equipment Capability, the DEC
should also put in place a set of coherent CSA or funded Tasks with other potential Stakeholders to deliver
the other Defence Lines Of Development (DLOD) that contribute to the total Military Capability (MC) to be
satisfied by the URD. The Joint Customer 2 Handbook identifies the respective responsibilities for DEC,
IPTL and Customer 2 (i.e. both Pivotal Management (PM) and Core Leadership (CL)) and their DLOD
development activities. It is particularly important that the Operational Concepts and Doctrine element is
started early. These should not just provide a justification for the URD but describe ‘HOW’ the User intends
to exploit the capability between its expected In-Service Date (ISD) and Out of Service Date (OSD). Ideally,
Analytical Concepts should have been produced by the appropriate Warfare Centre or Doctrine Cell before
Gate Zero and delivered to the IPTL.

2.1.2.3 Analytical Concepts have limited value to procurement activities and it is essential that they are
developed into Applied Concepts (a Concept of Employment (CONEMP) if relating to a single system, a
Concept of Operations (CONOPS) for a number of systems) and regularly updated to inform each Project
Phase. The output from this work stream must be produced in accordance with JDCC procedures and be
coherent concepts being developed in related capability areas.

2.2 Purpose of the Concept Phase

2.2.1 The aim of the Concept phase is to identify which options are suitable to close an identified
capability gap and should be considered further. On behalf of the IPTL, the CSM must gather evidence to
inform the Investment Appraisal Board (IAB) at Initial Gate (IG) that there is good reason to proceed to the
Assessment Phase and that the release of further public money to do so is justified. It is not the purpose of
the Concept phase merely to ‘get through’ IG. The requirements of the IAB at IG are stipulated in the Smart
Unclassified
25
DEF STAN 21-59 Issue 2

Approvals Handbook. The activities and outputs expected of a Project in the Concept phase of the CADMID
cycle are detailed in the AMS.

2.2.2 The primary constraint on the project during the Concept phase is that the Customer (i.e. DEC)
must not approve expenditure above 2% of the total procurement cost or £10m, whichever is the lower. The
CSM must inform his DEC if this is likely to happen.

2.2.3 To progress Combat System design on a sound basis it is essential that a rigorous Systems
Engineering (SE) process is applied to Project activities from the outset so that they are managed as
coherent whole and form a firm basis for later decisions. It is important that:

a) A ‘whole systems’ approach is adopted;

b) Discipline is used in the conduct of all activities and the processing of project data;

c) Premature focusing on a single design is avoided.

It is also important that the following are clearly identified, understood and documented:

a) The User Requirement and in particular the Key User Requirements (KUR);

b) The operational scenarios;

c) The operational Concepts;

d) The project’s context within the wider MoD programme, including related equipment projects
and contributing Defence LoDs;

e) Design constraints;

f) The overall Project programme;

g) The project Stakeholders;

h) The management processes to deliver the programme.

2.2.4 There is a significant impact on later phases if the Concept phase is not properly conducted or if
issues are not effectively progressed.

2.3 Requirements Engineering

2.3.1 The Concept Phase has to concentrate on defining and refining the User’s Requirements and
identifies Value For Money (VFM) issues that could affect the selection of design solution options in the next
phase. In this predominantly Requirements Engineering process there needs to be a clear understanding of
the division of responsibilities and the lines of accountability for the various aspects at this early stage.
User’s Requirements are owned by the DEC who has ultimate responsibility them. He is assisted by his
Requirements Manager (RM) who, although normally resident within the IPT and functionally responsible to
the IPTL, is ultimately accountable to his DEC. The CSM however is normally directly accountable to his
Project Manager or IPTL within the DPA. A contractor should never draft the URD.

2.3.2 During the Concept phase the RM assisted by the CSM, shall devise the Concept of Analysis
(COA) to be applied during the Combined Operational Effectiveness and Investment Appraisal (COIEA) to
be applied to the solution options in the Assessment phase. Critical to this is the identification of the Key
User Requirements in the Concept Phase. KURs are those Military Capability requirements or constraints
identified from within the wider set of user requirements which are assessed as key to the achievement of
the mission, or which are for some reason assessed as of particular interest to management. The CSM shall
ensure that any design solutions produced are in sufficient detail that the COEIA costings can be based on
pertinent and technically viable solutions.

2.3.3 The COA should reflect the trading philosophy employed for associated Balance of Investment
decisions and the strategy established by the DEC in his CSA for PCT envelope management.

Unclassified
26
DEF STAN 21-59 Issue 2

2.3.4 Requirements Studies

2.3.4.1 To assist in the Requirement Engineering process it is usual to conduct one or more Requirements
studies to:

a) formalise any earlier conceptual studies on the identification of a clear operational need;

b) implement a survey of any relevant activities in the MoD-funded research programme, any Generic
Technology Demonstrator Programmes (Generic TDPs), Operational Analysis and other studies,
and any other Industry Initiatives.

2.3.4.2 They also provide confidence that the technologies do, or will, exist to support the conclusions of
the concept studies, provide justification for enhancements to research programmes (both intra murally and
extra-murally) and underpin succeeding assessment studies.

2.4 Concept Phase Inputs

2.4.1 The AMS identifies initiators of the Concept phase to be:

a) Funding;

b) JDCC outputs;

c) Technical Opportunity;

d) Capability Gap;

e) Threats;

f) Opportunity;

g) Constraints.

Important sources of material to inform the Concept Phase include:

2.4.1.1 Existing Source/Background Material

2.4.1.1.1 Much existing, useful material is available which the CSM should collate. It includes:

a) Previously produced URDs for related and similar projects;

b) Any data already produced for the new/updated Combat System and its associated platform(s);

c) Baseline Combat System and platform data relating to the nearest comparable system (and from
which the new system may potentially be evolved);

d) Joint and Naval staff papers (including white papers, intelligence briefings, The Equipment
Programme (EP), related high-level studies etc.);

e) US, NATO, EU study results and position papers including, if appropriate, potential collaborative
partner publications;

f) Published data available in the public domain (including defence publications, technical journals,
industrial data sheets etc.);

g) Miscellaneous industrial information.

2.4.1.2 If either an evolutionary approach to the design of a new Combat System is envisaged or an update
to an existing Combat System is being undertaken, then the following information should be collected on the
baseline Combat System/platform and constituent equipments:

Unclassified
27
DEF STAN 21-59 Issue 2

a) Acceptance Criteria;

b) Risk register, system specification(s), subsystem specifications and coherence specification(s);

c) URDs of related capabilities;

d) Technical information (BRs, CBs, specifications) on all relevant Combat System equipments;

e) Naval Weapon Harbour Trial (NWHT) and Naval Weapon Sea Trial (NWST) reports;

f) Alteration and Addition (As & As) details;

g) Link and interface documentation including Combat System-platform interfacing;

h) In Service Availability, Reliability, Maintainability (AR&M)/Integrated Logistic Support (ILS) data;

i) Design policy information;

j) Configuration status and management information (covering both hardware and software);

k) The assessment of the current contractors' capability to develop software as an initial and then
ongoing element of a software process improvement programme within that organisation;

l) The assessment of contractors both as suppliers and as potential prime contractor to gain an
understanding of the suppliers' capability, and therefore gain an understanding of the subcontract
risks;

m) Software development metrics, if appropriate.

2.4.1.3 Agencies

2.4.1.3.1 Many agencies have potential to contribute to the input data. These include:

a) Sponsors of the ARP: DEC, FBG, RAO, and DEC as Equipment Capability sponsors

b) Defence Science & Technology Labs (Dstl), Qinetiq, Industry partnerships (e.g. ® NITEWORKS).

c) DPA (Project clusters, Support Groups; e.g. Integration Authority), DLO and DCSA.

2.4.1.4 Research Programme

2.4.1.4.1 Much work relevant to future Combat Systems and their design is undertaken as part of the MoD-
funded research programme. Its use can limit risks, improve capability and contain development costs.

2.4.1.4.2 MOD-funded research is organised under 7 headings known as “Outputs” with the majority of the
expenditure being on:

a) Output 3, the provision of specialist advice and analysis, including OA, to support capability
management in the ECC area;

b) Output 6, to ensure the availability of appropriate and sufficiently mature technology in the UK
defence supplier base to meet UK needs.

2.4.1.4.3 DCDS(EC) sponsors Output 3 research which is contracted through the Research Acquisition
Organisation (RAO), Shrivenham. This research is often used to inform the User Requirement.

2.4.1.4.4 Output 6 research is owned by the DPA’s Deputy Chief Executive and is managed by the FBG with
support from the RAO. Its priority is closely aligned to future capability requirements as defined by the ECC.
It invests in ‘promising but low maturity’ technology (typical TRLs of levels 1-3) with a view to developing
them typically to TRLs of level 6 in the supplier base - so that industry and IPTs can manage any remaining
risk and exploit the technology. It does not take on technology development or specific project work that
Unclassified
28
DEF STAN 21-59 Issue 2

may be more appropriately funded through the DPA Equipment Programme or the DLO Short Term
Programme (STP).

2.4.1.4.5 MOD-funded research is undertaken either in-house by Dstl (for research of a sensitive nature or
involving International Research Collaboration), by Universities or by industry, including QinetiQ. Advice on
the scope of research already undertaken which may be of relevance to a project and the contracting of new
research in support of a project can be obtained from the RAO and FBG.

2.4.1.4.6 Output 6 does not take on technology development and specific project work that may be more
appropriately funded through the EP or DLO STP. Thus project funding is likely to have to be used to fund
any technology development beyond TRL 6. Technology demonstration programmes can be undertaken to
mature technologies to TRLs 4 to 7. Where it is undertaken exploitation plans should be drawn up which
address issues including: the area and extent of applicability; risks and benefits if used; alternatives and
considerations if not used; how industrial involvement, exploitation and acceptance of the programme will be
achieved; and alignment with the project's technical, managerial and programme objectives.

2.4.1.5 Use of Research and Generic Technology Demonstrator Programme Output

2.4.1.5.1 TDPs are programmes, which have the aims of producing hardware to bridge the gap between
research and development and to demonstrate the feasibility of using new technology to meet a specific
operational requirement. They can range from Combat System-level to equipments or significant equipment
functions. TDPs also reduce the risk contingencies associated with introducing the new technology down to
affordable levels.

2.4.1.5.2 Generally, successful TDPs are exploited by industry through the development of new or enhanced
equipments. TDPs often serve as the basis for equipments for inclusion as part of the Combat System
design. DECs, RMs and CSMs should make themselves aware of the currently funded and anticipated
TDPs.

2.4.1.6 International Collaboration

2.4.1.6.1 Outside the UK there are extensive military programmes. DECs, RMs and CSMs must make
themselves aware of such programmes, through the government to government mechanisms such as the
US/UK information exchange programmes, and evaluate the applicability of such programmes to the
development of UK Combat Systems.

2.4.1.6.2 On behalf of UK MOD, Dstl participates in a range of International Research Collaboration (IRC)
programmes, including at the US/UK bipartite, NATO level, TTCP, AUSCANZUKUS, and other multinational
arrangements. Information on technical exchanges relevant to a particular project can be sought from Dstl
Naval Systems.

2.4.1.7 Industrial Technology Development Programmes

2.4.1.7.1 For non-military purposes there are industrial Research and Development (R&D) programmes, both
within the UK and abroad that could be sensibly applied to meeting the defined operational needs. Through
a programme of meetings with industry, DECs, RMs and CSMs should make themselves aware of the
development of such products and should explore their applicability to Combat System development. This
will include, but not be limited to, monitoring the progress of open systems and Commercial Off The Shelf
(COTS) technology.

2.4.1.7.2 The S+T Director in MoD is the owner of Output 5 of the research programme whose remit is to
undertake technology-watch activities and provide advice across MoD on global S+T advances and to
interpret and communicate their relevance to MOD. This work is undertaken by Dstl.

2.4.1.7.3 In order that the MoD can be made aware of emerging industrial developments in technology, the
MoD personnel may be required to enter into commercial confidentiality/non disclosure agreements with
industry. Before entering into such arrangements, the CSM must seek advice and approval from his IPT
Commercial Officer.

Unclassified
29
DEF STAN 21-59 Issue 2

2.4.1.8 Scenarios for Operational Analysis

2.4.1.8.1 Scenarios for analysing and determining the operational requirement and assessing candidate
solutions should be derived from those devised by the Studies Assumptions Group (SAG). These represent
the range of operations in which the UK might expect to be involved and cover peacetime, non-warfighting
operations and warfighting operations, rapid reaction scenarios, short duration and enduring operations. The
most relevant scenario(s) should be selected for exercising the capability under consideration. Detailing of
the scenarios is required for specific OA studies in terms of geographical area, timeframe, ORBATs,
operational demand such as concurrency of capability, etc.

2.4.1.9 Combat System Engineering Database

2.4.1.9.1 The Combat System Engineering Database (CSED) is a MoD database generated circa 2000 with
information on legacy submarine and surface ship weapon and sensor equipments. It covers:

a) Performance parameters (outfit level);

b) Engineering data (physical and ships services);

c) Trials;

d) Cost (outfit level);

e) Documentation;

f) Hazards, including safety and RADHAZ;

g) AR&M.

2.4.1.9.2 It constitutes a source of information, which may be useful for Combat System studies. Further
information may be obtained from DLO/TES WLS.

2.4.1.10 Contributory Factors

2.4.1.10.1 All appropriate factors that contribute to the emergence of the need for a new or updated
Combat System should be documented. These can include:

a) Need to replace obsolete equipment and provide a necessary capability;

b) New defence policy;

c) New/enhanced actual or potential threat;

d) Weakness in present equipment;

e) New equipments available which offer significant benefits (e.g. support cost) over existing
equipments;

f) Advances in technology;

g) Need to fulfil defence roles at lower overall cost;

h) Industrial proposals;

i) Foreign collaboration.

2.4.1.11 Shared Data Environment

2.4.1.11.1 The IPT should set up a Shared Data Environment (SDE) during the Concept phase to serve
as the central repository of, or signpost to. all relevant Combat System design information. The SDE should
provide ready and easy access to information such as:
Unclassified
30
DEF STAN 21-59 Issue 2

a) The AMS, BRs, CBs, Def Stans, SSPs, STGPs etc.;

b) JSPs, CESG documents, Central Staff documents, DCIs, SSIs etc.;

c) Industry publications from individual companies;

d) Technical publications etc.;

e) Relevant yearbooks and defence periodicals;

f) Symposia and conference proceedings etc.;

g) International and national standards (BS, EU, ISO etc.);

h) Relevant Government documentation, Acts etc.

2.4.1.11.2 It is essential that all this information is under configuration management and access controlled
to allow the appropriate visibility. It must not only allow visibility of the latest information available but also to
historical versions which have been used for requirement specification and interoperability with legacy
systems. Where a conflict arises in precedence of specific documentation, the CSM should resolve it by
consultation which must be auditable.

2.5 Concept Phase Outputs

2.5.1 The Concept phase should produce the following outputs:

a) A compelling IG Business Case for IAB submission justifying a value for money recommendation as
to whether or not to proceed to the next Project phase;

b) Whole Life Cost Plan / Cost Of Ownership (COO);

c) A stable URD with clearly identified KURs;

d) Capability Model within MODAF;

e) An outline SRD with initial Key System Requirements;

f) A Through-Life management Plan (TLMP);

g) Assessment phase PCT analysis/Plan;

h) A Risk Management Plan and Risk Register;

i) Draft Systems Engineering Management Plan (SEMP) defining how technical activities are to be
integrated;

j) An Interoperability Strategy;

k) A Standardisation Implementation Plan;

l) A COA;

m) A Master Data and Assumptions List (MDAL) and any other Design Assumptions Register;

n) Initial Through Life Costings (N.B. (b) above);

o) System Options;

p) Collaboration opportunities with Industry;

q) Outline definition of the Combat System acquisition/approvals strategy;


Unclassified
31
DEF STAN 21-59 Issue 2

r) Draft coherence specification identifying common Combat System design issues; reference to all
transversal issues e.g. HF, security, safety etc.;

s) Mandated equipment list preferably within the SRD. The mandating of any equipment needs to be
justified. There are frequently circumstances (e.g. security systems, or for support reasons i.e.
commonality with other ship classes) where there is a clear case for defining equipments that should
be incorporated in the new Combat System. Equipments should only be mandated if it is known for
certain that they will form part of the Combat System;

t) An initial set of policy papers (either drafted or scoped) to formulate and define how Combat System
design issues should be progressed;

u) High-level computer models exploring the feasibility and detail of practical Combat System
solutions;

v) An initial assessment of the Combat System design options in terms of technical performance,
AR&M and operational effectiveness;

w) Combat System design options record documenting design solutions, problems encountered and
resolved, any assumptions made, the results of design reviews etc.;

x) Anomaly reports specifying problems encountered in the analysis of requirements and Combat
System models, their resolution and action;

y) A clear definition of the work required during the subsequent assessment phase together with
supporting ITT documents (assuming that the work will be placed by a competitive tender) and
associated assessment criteria;

z) Draft phase review documentation containing ‘MoD eyes only’ information on potential contractors
(especially prime contractors);

aa) A first approximation of the implications in terms of cost and timescale of development, procurement
and through life support of the Combat System;

bb) First pass estimates of manning levels for the Combat System design options.

2.5.2 During Concept phase, the project file should be initiated. This serves as a configuration-controlled
repository of all significant project-related information.

2.5.3 Additionally projects are required to satisfy the joint DPA/DLO’s Technical Assurance criteria for
Project Review and Assurance (PR&A), the IAB’s general requirements (see SMART Approvals Handbook)
and any specific IAB requests.

2.5.4 Organisation

2.5.4.1 Approach

2.5.4.1.1 Concept Phase studies may be undertaken:

a) Internally within DPA complemented by uniformed User representatives and supported by intra-
mural studies and industrial specialist contractors;

b) By a ‘rainbow’ team of contractors led by DPA and complemented by other specialists (e.g.
uniformed user representatives). Rainbow teams are composite teams of Combat System design
staff drawn from the range of contractors with relevant experience and capability and who may be
formalised into an Integrated Project Team;

c) By an industrial contractor following competitive tendering and overseen by a small MoD team
supported by uniformed user representatives and, if necessary, contractor project support.

Unclassified
32
DEF STAN 21-59 Issue 2

2.5.4.1.2 In accordance with the aims and principles of Smart Acquisition, normally only one team would
conduct concept studies.

2.5.4.2 The Integrated Project Team (IPT)

Under Smart Procurement principles the IPT Leader (IPTL) is empowered to manage and conduct
procurement activities to deliver products that meet the URD and requirements of his Customer 1 as
stipulated in their CSA. The IPTL is not allowed however to act unilaterally in areas that involve other
Stakeholder involvement, in particular where trade-offs are being considered and interoperability is affected.
The IPTL’s approach must involve the participation of all stakeholders including user, customers 1 and 2,
and industry representation (where competition permits) from the earliest opportunity. Whilst Def Stan 21-59
acknowledges the need for co-operative stakeholder involvement, it is the responsibility of the CSM to
ensure that organisational requirements and constraints are wholly appropriate to the needs of the project
within the prevailing management regime.

2.5.4.3 Team Capability

2.5.4.3.1 Within an IPT, there should, as a minimum, be members capable of supporting the following
functional roles for Combat System management:

a) Requirements Manager. An expert User responsible for representing the DEC, Customer 2 and the
interests of the eventual Combat System users. As well as taking the lead for requirement issues he
should also be responsible for advising the DEC and IPTL on Service Acceptance. This expert
would typically be an experienced Naval Officer with authority to engage other IPT RMs on both
Maritime and Joint User issues;

b) Combat System Manager. The CSM has responsibility for the whole project. Management of
certain elements may be delegated, either internally or externally via a contract, but the CSM still
retains responsibility for the project as a whole;

c) The Technical Co-ordinator. Responsible for controlling and directing the SE process and
monitoring and reporting of the technical quality of the work typically across the engineering
disciplines;

d) ILS Manager. Responsible for co-ordination and monitoring of all life cycle support activities and
specifically the AR&M and training programme;

e) Programme Manager. Responsible for advice and assistance in planning, maintenance of


administrative controls against schedules and budget, and monitoring quality of deliverable plans,
schedules and contractual matters to the extent to which he is so qualified;

f) Quality Assurance (QA). Responsible for ensuring that the correct quality control processes are in
place both internally to the MoD and external in any subcontract organisation. This QA role will also
encompass any on-site Quality Assurance Representative (QAR), role required by the contract.

2.5.4.3.2 These roles must be contained within the team, even when the study is largely undertaken by a
contractor so that concept studies can be correctly scoped, design issues and anomalies resolved, results
interpreted, technical progress monitored and an informed customer base developed and maintained.
However, several roles are normally fulfilled by a small group of individuals who each wear ‘more than one
hat’.

2.5.4.4 International Collaboration/Co-operation

2.5.4.4.1 The consideration of all new requirements and projects should include an evaluation of the
possibilities for establishing joint requirements and common development and/or production projects with
other countries. The DEC has responsibility for initiating and setting up international agreements for
information and technical exchange.

Unclassified
33
DEF STAN 21-59 Issue 2

2.6 Key Concept Phase Processes

2.6.1 The Concept Phase serves to develop the URD, which the required Combat System seeks to
address. This need is reflected through requirements, which are subjected to analysis to identify all
significant design issues. Design studies are conducted to draw up and assess a broad range of potential
candidate design solutions, which can be subjected to COEIA.

SYSTEMS ENGINEERING (TECHNICAL) Management Policies and Plans


and PROJECT MANAGEMENT Systems Engineering Management Plan

NEEDS LIFE CYCLE DESIGN ASSESSMENT


DEFINITION PROCESS FACTORS and SELECTION

Produceability Technical Performance


REQUIREMENTS
ENGINEERING Integration and Test Strategy AR&M Assessment
Acceptance and Trials Policy COEIA
SYSTEMS Support Plans Design Selection
ANALYSIS
Disposal Plans Design Validation
Definition of Systems Design
CONCEPTUAL Concept Options
DESIGN

SYSTEM STUDIES Prototyping and Modelling

DOCUMENTATION URD Production

SPECIALIST DISCIPLINE SUPPORT Configuration Management


Human Factors ILS Safety Security

Figure 2.1 Concept Phase Activities

2.6.2 Important activities in the Concept phase are to:

a) Clarify, identify and refine the need for a new or replacement capability;

b) Gather requirement statements and all relevant data (including applicable policies, objectives
and constraints) for the proposed Combat System from all parties with a legitimate interest in it;
all requirements acquired should be recorded in a DOORS database;

c) Document and analyse the operational scenarios within which the Combat System will have to
provide a capability and how the User intends to employ it within those scenarios as stated in
his Applied Operational Concepts;

d) Better define the Performance Cost Time (PCT) envelope by gaining and promoting a thorough
understanding of the problem-space, potential solutions and the interactions between their
different issues;

e) Generate an initial range of candidate design solutions which could potentially satisfy the
identified need, to assess these solutions, their associated Costs and Risks, ascertain the
design drivers and shortlist the most promising options for subsequent COEIA. The design
solutions must meet the requirements, be technically viable and result in an affordable Combat
System;

f) Identify any possible changes or enhancements required in the capability of other systems or
subsystems with which interoperability or integration may pose a risk. This may lead to new
equipment and funding requirements for these other project;

g) Produce an initial SRD and other documentation to support the development of the URD;

h) Identify Needlines and produce draft Information / Service Exchange Requirements.


Unclassified
34
DEF STAN 21-59 Issue 2

Conceptual design should identify architectural issues and whether possible equipments (or whole system
solutions) are available.

2.6.2.1 Through Life Management Plan

2.6.2.1.1 The Project must produce a TLMP i.a.w. the AMS. Prior to Gate Zero the DEC should have
produced an embryonic TLMP that is aligned with his CSA agreed with the IPTL.

2.6.2.2 Stakeholder Responsibility Matrix (SRM)

2.6.2.2.1 The IPTL and CSM shall produce a Stakeholder Responsibility Matrix and form funded business
agreements with those stakeholders to ensure delivery of the DLODs. This is particularly important to
ensure that Government Furnished Assets (GFA) associated with Combat System interfaces are managed.

2.6.3 Systems Engineering (Technical) and Project Management

2.6.3.1 Use of a SEMP is central to the Combat System engineering strategy. This document defines the
intended conduct and implementation of SE (Technical) and project management activities on a Combat
System design project. Many of the activities of technical and project management are common to each of
the phases covered in this guide. The SEMP should form part of the TLMP.

2.6.3.2 Risk Management Plan

2.6.3.2.1 As part of the joint DPA /DLO Project Review & Assurance (PR&A) process, the IPT must show that
they have identified and managed Project Risk sufficiently to provide confidence that further public money
can be released.

2.6.3.3 Approvals Strategy

2.6.3.3.1 The adoption of a streamlined approval process consistent with the Smart Approvals Handbook is
mandatory.

2.6.3.4 Costing

2.6.3.4.1 All Risks and Assumptions should be associated with an entry in the MDAL.

2.6.3.5 Standards

2.6.3.5.1 The imposition of specific standards on a particular supplier, particularly retrospectively, can cause
high costs. However, for successful networking and eventual NEC, adherence to common standards is
essential. The CSM should aim to structure the project such that the costs and benefits of standardisation
are identifiable. He should comply with the JSP 600 policy statements on CIS Standards and produce an
initial Standardisation implementation Plan prior to IG. Advice can be sought from PDG/DStan, the
Integration Authority and real-time combat system networking experts.

2.6.3.6 Needs Definition

2.6.3.6.1 Needs Definition is driven by VCDS’s Capability Working Groups and their capability management
processes. Director Equipment Capability (Customer 1) is responsible for establishing the Operational need
in liaison with service Operational and Engineering branches, and scientific advice including Operational
Analysis. MILCAP is a primary source for the identification of the need for new or enhanced capability.

2.6.3.7 Concept of Operations (CONOPS) and Concept of Employment (CONEMP)

2.6.3.7.1 As part of the URD, it is essential that the operational Applied Concepts are developed and
delivered to a programme that supports the Equipment Capability procurement. It is the DECs responsibility
to facilitate this e.g. by funded tasks or CSAs with Customer 2. The Joint Customer 2 Handbook identifies
the respective responsibilities for DEC, IPTL and Customer 2 (i.e. both Pivotal Management (PM) and Core
Leadership (CL)) and their activities. The updating of Combat System capability implicitly changes the Ship’s
or Submarine’s capability and possibly its role. The production of new Applied Concepts (e.g. CONOPS and
Unclassified
35
DEF STAN 21-59 Issue 2

CONEMP) is the responsibility of the appropriate Warfare Centre/Doctrine Cell, under JDCC procedures and
guidelines. It must not be placed with a Contractor. It involves:

a) Outlining of the warship roles (a role is the prime operational objective of the warship at any one
time) and missions (a mission is the series of roles performed from leaving base to returning to base
and the durations that those roles are performed);

b) Outlining of typical scenarios (a scenario is a description of the circumstances (features and events)
external to the warship within which key attributes may be tested);

c) Considering the threat of likely opposing forces.

2.6.3.8 Requirements Engineering

2.6.3.8.1 Requirements Engineering is the integrated and systematic process which transforms the needs
and wishes of the Customers for an MC into a complete, consistent and precise form for a System design.

2.6.3.8.2 Requirements Engineering combines the activities of Collection, Collation and Control – to promote
Sufficiency. The process is Iterative and Interactive – it initiates the design process and adds numeracy to
requirements statements in formal documentation. The working framework (organisation/structures) must
encourage a pro-active attitude, offer flexibility and support multiple domain perspectives.

2.6.3.8.3 Requirements Capture, Requirements Engineering and Requirements Management are now all
mainstream activities under Smart Acquisition for both functional and non-functional requirements using the
preferred MoD toolset. Further information is available on the AMS and guidance can be sought from the
DPA Procurement Development Group who sponsor a Requirements Managers focus Group (PDG PM2
ABW x34188).

2.6.3.8.4 The RM shall place both the Requirement Database (RDB) and requirements definition documents
(e.g. URD, SRD) under project configuration control from the earliest phases of the project to ensure that the
evolution of the Combat System requirements can be subject to a formal design audit.

2.6.3.9 Scenario Analysis

2.6.3.9.1 Within the context of requirements engineering, scenario analysis serves to identify the events (in
the environment) to which the system must respond and the envisaged operational usage of the system (in
terms of tasks, which must be performed). It can therefore be used to assist in the acquisition of
requirements (e.g. those concerning system-environment interaction) or with their verification/validation.

2.6.3.10 User Requirements Specification (URS)

2.6.3.10.1 Historically a URS has been used to provide more detail to the requirements for Command
Systems/Combat Management Systems. The Command System/CMS provides the crucial Control
Room/Ops Room Command Team interface at the heart of any combat system. The production of a
separate URS for this very complex and User-dominated system was regarded as a distinct activity. Under
Smart Acquisition this distinction is no longer recognised.

2.6.3.10.2 The URS has not been replaced by the URD. A summary of what the URS’s intended purpose
was, is included here to illustrate the issues that still need to be addressed in some way, either by MoD or by
Industry. In the area of Human Factors, Style guides (Ref STG Publications 10 & 11) and techniques such
as Task Analysis are now recognised as constraints on a CMS design.

2.6.3.10.3 Level 00 of a URS (also termed the ‘scoping document’) was produced to cover:

a) High-level explanation of the host platform roles;

b) High-level analysis of the command task capability;

c) Combat System description and boundary definition;

Unclassified
36
DEF STAN 21-59 Issue 2

d) Context Diagram (a context diagram graphically indicates the boundary of a system and identifies
the interaction between the system and elements of its environment. It is a standard notational
device of systems analysis and is a feature of several methods including the Yourdon Structured
Method), top-level processes (man and machine) and supporting explanation.

2.6.3.10.4 Subsequently Level 0 of a URS was produced for a later project phase to cover:

a) Statement of the command task capability requirement;

b) Definition of the high-level tactical data capacity;

c) Consideration of equipment fit implications;

d) Consideration of HF;

e) Analysis of implication for the whole warship project.

2.6.3.10.5 The URS was a major source of both User and System requirements for the Combat System.

2.6.3.11 Capability Modelling

2.6.3.11.1 Modelling techniques can be employed to address experimentation, completeness and


consistency of User requirements. Advice on modelling tool-sets and techniques and their relative suitability
should be sought from established MoD sources, as some may be freely available to the project through
corporate licence agreements. Lock-in to proprietary modelling tools must be avoided. NITEWORKS is
available for project use.

2.6.3.11.2 User Needlines and if possible Information Exchange Requirements (IER) should be modelled
e.g. in JIFM or iSMART (or earlier TULIP).

2.6.3.11.3 Whatever modelling is conducted for the User’s MC requirements an output from that modelling
must feed into Integration Authority’s MODAF to provide a high level view of the ‘system of systems’
architecture.

2.6.3.12 System Requirement Specification

2.6.3.12.1 The Concept phase should identify the scope of possible, wide ranging solutions to the MC
being sought and how they will be investigated and assessed during the Assessment Phase. As part of this
exercise an initial view of what is required of the new/updated system can be obtained. This can start the
formal specification of system requirements in an SRD. This will need to bound the scope of the (equipment)
system being acquired and the contributions required from other Defence LoDs.

2.6.3.13 Concept of Analysis (COA)

2.6.3.13.1 The Concept Phase must produce a COA. This should detail how the various Combat System
design solution options will be assessed in the Combined Operational Effectiveness and Investment
Appraisal (COEIA) during the Assessment phase and what criteria will be used. Responsibility for the COA
and COEIA is shared between the DEC and IPT.

2.6.3.14 Specialist Discipline Support

2.6.3.14.1 A number of specialist activities which have significant downstream implications on the cost
and effectiveness of the evolving Combat System need to be considered during the Concept phase as
follows:

a) Air Engineering;

b) Alignment;

c) AR&M;

Unclassified
37
DEF STAN 21-59 Issue 2

d) CM;

e) Cost;

f) Documentation;

g) EMC, RADHAZ, Tempest, Magnetic and Nuclear Survivability;

h) Environmental Factors;

i) HF/Operability;

j) ILS/Supportability;

k) Installation and Ship Services;

l) Information Management, Interface/Data Management;

m) Modelling;

n) Mutual Interference;

o) Naval Architecture;

p) Operational Performance/Effectiveness;

q) Safety;

r) Security;

s) Shock and Vibration;

t) Software Development;

u) Structural Engineering;

v) Training;

w) Integration into the Battlespace;

x) C4I;

y) ISTAR.

2.6.3.15 Configuration Management (CM)

2.6.3.15.1 CM is a central theme of the strategy, important during the early phases to keep track of
requirements, specification and plans which define the Combat System baseline design.

2.6.3.15.2 Def Stan 05-57 is the overriding standard for CM in the MOD.

2.6.3.16 Data Management

2.6.3.16.1 To ‘design for integration’, an initial consideration of how information passing between systems
is to be managed standard definitions of application data elements, co-ordinate systems, network interfaces,
network protocols, and application protocols reduce both implementation risk, integration risk, and test tool
costs. An initial review is needed to establish whether currently established standards and documentation
processes are likely to apply or whether there would be benefit in moving to a new regime.

Unclassified
38
DEF STAN 21-59 Issue 2

2.6.3.16.2 The information and interface management issues will be reflected in the phase outputs in the
draft coherence specification and they may also require specific studies to be undertaken in the Concept
Phase. These issues are unlikely to impact on the costings for this phase, but they will impact on risk.

2.6.3.17 Human Factors (HF)

2.6.3.17.1 The Combat System is an integration of personnel and technology. Consideration of the
human contribution to Combat System capability is required, starting at Concept phase.

2.6.3.17.2 The approach defined in STG publications 10 & 11, Human Factors Guide for Management
and Design in Royal Navy Combat Systems, is intended to ensure that greater account is taken of the
human element in generating the URD by emphasising that warships and their systems (including the
Combat System) are to be designed to be compatible with their users. The aim of this approach is to
enhance system effectiveness, increase manpower retention, reduce manning, enhance safety and reduce
cost.

2.6.3.17.3 The Concept phase should produce an initial Human Factors Integration Plan (HFIP).

2.6.3.18 ILS Issues

2.6.3.18.1 An initial draft of an ILS plan and ILS Task 201 (Use Study) should be produced in accordance
with Def Stan 00-60.

2.6.3.19 Information System Security (INFOSEC)

2.6.3.19.1 Security can have a profound impact on the Combat System design, e.g. use of COTS.
Combat System security must be addressed in the Concept Phase.

2.6.3.19.2 An infosec appraisal should be drafted during the Concept Phase and early liaison established
with both the Security Accreditor, and CESG.

2.6.3.20 Safety Requirements

2.6.3.20.1 The adoption of a safety management procedure is now a mandatory and legal requirement on
all IPTLs. It is required to encompass both platform and Combat System aspects.

2.6.3.20.2 For systems which will contain Ordnance, Munitions & Explosives, the following apply:

a) JSP 520 Pt 1 – OME Safety Management System;

b) JSP 520 Pt 2 - Operational Procedures.

2.6.3.20.3 The Defence Ordnance Safety Group (DOSG) web site:


www.ams.dii.r.mil.uk/content/docs/dosgweb contains further guidance.

2.6.3.20.4 For issues concerning Platform safety, the DOSG Technical support (DOSGTS) Safety
Management Office (SMO) should be consulted. Relevant standards are as follows:

a) Ships – JSP 430;

b) Air – JSP 553;

c) Land – JSP 454.

2.6.3.20.5 The procedure to generate the ‘Safety Case’ is described in the AMS and will be devised at the
warship level.

2.6.3.20.6 The mandated procedures are contained in:

a) POSMS – Project-Oriented Safety Management System;

Unclassified
39
DEF STAN 21-59 Issue 2

b) POEMS – Project-Oriented Environmental Management System.

2.6.3.20.7 The safety case serves to demonstrate that the whole warship meets agreed safety objectives.
It should ensure that a clear audit trail exists from design through procurement, operator and upkeep to
disposal. In addition, a summary of the safety case, known as the safety case report, is prepared to assist in
the reviewing of performance and the provision of authority to proceed to the next phase of the life cycle.

2.6.3.21 Concept Phase Consolidation

2.6.3.21.1 The purpose of the consolidation phase is to ensure that all initial threads are brought together
to form a firm basis for the Assessment Phase. It is generally dependent on the implementation of the SE
process as determined by the project SEMP and the extent of Concept Phase activities undertaken by
Industry.

Unclassified
40
DEF STAN 21-59 Issue 2

Systems Engineering Guide for Naval Combat Systems -


Assessment Phase

3 Assessment Phase

3.1 Introduction

3.1.1 The Acquisition Management System (AMS)

3.1.1.1 The prime source of guidance for the implementation of Smart Acquisition processes within the
DPA, DLO and DCSA for EP and STP projects is contained in the AMS at www.ams.dii.r.mil.uk or
www.ams.mod.uk. The content of this Def Stan uses the basic principles contained within the AMS and
whilst these are unlikely to change, the implementation details may. The AMS is the subject of frequent
update and should therefore be consulted for clarification of that detail.

3.1.2 The Assessment Phase serves to develop candidate Concept Phase designs in more detail,
subjecting them to trade-off studies considering time, risk, cost and performance, until the detail is sufficient
to take a single design solution forward into Demonstration & Manufacture. Following consolidation, the
result is a Systems Requirements Document (SRD) and systems and subsystem specifications together with
a framework of policies and plans to support the Business Case for Main Gate (MG) approval by the IAB.

3.1.2.1 Assessment is sometimes split into two or more Assessment Phases. This is usually done in order
to manage risk and implement the Procurement Strategy which down-selects from say, three bidders /
industrial partners / consortia in Assessment Phase 1, down to two in Phase 2 and ending in the selection of
one design to take forward to Demonstration & Manufacture (D&M).

3.2 Purpose of the Assessment Phase

3.2.1 The aim of the Assessment Phase is to down-select to a single technological option and reduce risk
to an acceptable level for Main Gate (MG). The CSM, on behalf of the IPTL, must gather evidence to inform
the Investment Appraisal Board (IAB) at MG that there is good reason to proceed to the D&M Phase and that
the release of further public money to do so is justified. It is not the purpose of the Assessment Phase
merely to ‘pass through’ MG. The requirements of the IAB at MG are stipulated in the SMART Approvals
handbook. The activities and outputs expected of a Project in the Assessment Phase of the CADMID cycle
are detailed in the AMS.

3.2.2 The primary constraint placed on the Assessment Phase is that expenditure shall not exceed the limits
set at the Initial Gate approval without resubmission for a change to those limits. The CSM must inform his
DEC if this is likely to happen.

3.2.3 For the “Acquisition of equipment capability by conventional means”, the AMS Handbook describes
the activities to be carried out during Assessment as follows:

• Produce the SRD, defining what the system must do to meet the User needs as stated in the URD;

• Establish & maintain the linkage between the User and System requirements;

• Identify the most cost-effective technological and procurement solution;

• Develop the SRD, trading time, cost and performance to devise a balanced technological and timely
solution;

• Reduce risk;

Unclassified
41
DEF STAN 21-59 Issue 2

• Refine the TLMP including detailed plans for the Demonstration Phase and through-life
management;

• Produce the Main Gate Business Case.

3.2.4 For a Combat System, the Assessment Phase aims to build on the achievements of Concept Phase
and reduce risk by:

a) Producing credible system solutions to meet the requirements;

b) Validating these solutions through extensive modelling;

c) Documenting the implications in revisions to the requirements definition and enhancement to the
system specification;

3.2.5 Establishing a realistic Cost Of Ownership (COO) and Through Life Cost. This includes developing
the MOD’s spend profile to take account of all the remaining project phases.

ASSESSMENT Stage Consolidation &


e.g. MoD Project and two competing consortia Tender Selection
Assessment Outputs
SRD
SYSTEMS ENGINEERING (TECHNICAL) Contract Management Plan
and PROJECT MANAGEMENT
CONSOL- Risk Management Plan
REQUIREMENTS SYSTEMS SYSTEM
IDATION SEMP (Update)
ENGINEERING ANALYSIS DESIGN Updated Requirements
Assessment Inputs Gather Database/ Requirements
URD Information Definition Document
Contract Management Plan Analyse
Mature
Risk Assessment Problem ITT for D&M System & Subsystem
Requirements Database/ Synthesise Specifications
Solution(s)
Requirements Definition ITT & Related Documents
Document Information
for Demonstration &
System Specifications Base Manufacture
Concept System models
Selected
TENDER
Assessment Tasks
Contractor for
Assess and Document SELECT’N
Select and Report Demonstration &
Manufacture
ASSESSMENT & SELECTION DOCUMENTATION

Figure 3.1 Assessment Phase Activities

3.2.6 Figure 3.1 shows Assessment Phase activities based on the generic Systems Engineering (SE)
process. This is common between the Concept and Assessment Phases and provides a consistent basis for
activities prior to contract award. During the Assessment Phase, the SE process conducted during Concept
is repeated. This time the emphasis is on developing and defining candidate designs in sufficient detail,
subjecting them to a trade-off studies, in order to select one design solution to take forward into D&M.

3.2.7 Assessment Phase activities

3.2.7.1 The activities during the Assessment Phase follow-on from those initiated in the Concept Phase but
with increasing levels of detail until the first indications of physical solutions become available and the
baseline Combat System design is established. This is reflected by the finalisation of the User Requirement
Document (URD), its Key User Requirements (KURs), the System Requirement Document (SRD), its Key
System Requirements (KSRs), an initial specified design (system and subsystem specifications) and mature
Through Life Management Plan (TLMP). Throughout the Assessment Phase, the evolving design solution is
explored using through-life models, which provide confidence that the design will achieve the required
performance to time and budget within project constraints. Most assessment work will be conducted by
contractors on behalf of MOD; the major MoD activity is to retain full awareness of the progress, to enable
the correct choice for Demonstration & Manufacture in terms of both design solutions and participating
contractors.

Unclassified
42
DEF STAN 21-59 Issue 2

3.2.7.2 Following consolidation, the result is a definitive specification of the Combat System, its subsystems
and equipments and its platform interfaces. This is supported within a hierarchy of plans defining the
development and production, integration, trials, operation, and support strategies. In accordance with the
Smart Approvals Handbook the package will be submitted for approval by the Investment Approval Board
(IAB) and Secretary of State if necessary, and forms the basis for the Development and Manufacture
contract.

3.2.7.3 The detailed activities are all iterative and include:

a) Expanding the definition of the Combat System requirements and design activities to produce a set
of acceptable physical options that are good candidates for meeting the SRD;

b) Documenting the candidate designs, and any issues associated with mandating any part of the
equipment solution, highlighting technical, programme and cost risk and the implications of the
mandated levels of safety on the proposed designs;

c) Assessment of the performance of the proposed Combat System designs within real world scenarios
- this will require the use of computer modelling techniques, thereby laying the groundwork for
Combat System acceptance trials;

d) Ensuring that the correct level of emphasis is given to Integrated Logistics Support (ILS) activities by
considering supportability issues as an integral part of the system design process;

e) Obtaining COO and Whole Life Costs for each candidate design including the costs associated with
contributing Lines of Development and any impact on other system and capabilities;

f) Conducting cost trade-off analysis on the system design options to ensure that the most cost-
effective solutions are given priority and that the Combined Operational Effectiveness and
Investment Appraisal (COEIA) for the MG business case is supported;

g) Exchanging information with the platform design team to ensure compatible development;

h) Developing the integration strategy;

i) Developing the Interoperability strategy (aka CIS Integration Strategy (CISIP)).

3.2.8 Political Decisions

3.2.8.1 Combat System costs, and those of the platform itself, are likely to make their procurement the
subject of intense media and political interest. In such cases all IPT staff, including the CSM, must not
exceed their remit given to them by previous IAB approvals and their CSA with the DEC. The division of
procurement responsibility between CDP and VCDS is fundamental to the success of Smart Acquisition.
The IPTL and DEC should act in accordance with directions from their respective line managers.

3.3 Inputs

3.3.1 The level of detail collected during the Concept Phase will determine how much additional data
collection effort is required during the Assessment Phase. As a minimum, all the assumptions and
conclusions from earlier work should be reviewed. If the requirements exist in a structured database, under
full Configuration Management, only periodic updates will be required.

3.4 Outputs

3.4.1 Competing Consortia

3.4.1.1 As part of their tenders for D&M, the competing consortia’s deliverables should include:

a) Contract Management Plan (CMP);

b) Risk Management Plan and initial Risk register;

Unclassified
43
DEF STAN 21-59 Issue 2

c) Quality Plan;

d) Project Management Plan;

e) System Engineering Management Plan (SEMP);

f) Development and Manufacture Management Plan;

g) Integration, Test and Trials Management Plan;

h) Acceptance Management Plan (sometimes linked in with the management of requirements as a


Requirements and Acceptance Management Plan (RAMP));

i) Upkeep and Support Management Plan;

j) Availability, Reliability and Maintainability (AR&M) Management Plan;

k) Safety Management Plan;

l) Security Plan for the production of the Accreditation Documentation Set (ADS);

m) Requirements Database (RDB)/Acceptance Database, DOORS;

n) System Specification, (including those for Integration, Development and Training Facilities);

o) Coherence Specification;

p) Subsystem Specifications;

q) Interface Specifications and draft Interface Control Documents;

r) Test and Acceptance Criteria against each System and Equipment requirement supported by some
form of Verification Cross Reference Index (VCRI);

s) Integrated Support Plan (ISP);

t) Training Plan;

u) Capability Roll-Out Plan;

v) A list of Government Furnished Assets (GFA);

w) Standardization Implementation Plan (SIP);

x) Payment Milestone Plan;

y) Compliance Matrix referencing their response to each ITT and Statement of Work requirement.

3.4.2 Outputs - CSM’s Team

3.4.2.1 The Assessment Phase will produce documents from several sources, from which the MoD
assessment team will generate:

a) ITT Response assessment criteria;

b) COO and Whole Life Costs;

c) Evidence to give a high level of confidence that the required capability of the Combat System design
is achievable;

Unclassified
44
DEF STAN 21-59 Issue 2

d) Documentation to support the clear definition of the system required by the MoD which can be
written into a comprehensive SRD;

e) Draft subsystem specifications sufficient to issue to Industry for the Demonstration & Manufacture
phase. These must not disallow any satisfactory Combat System design;

f) Thorough project and SE management controls and plans for the remainder of the project, including
funded business agreements (e.g. with other IPTs) to support interface management and the supply
of GFA;

g) The SEMP which shall address the ‘system-wide’ or transversal issues such as:

• Requirements,

• System Analysis and Design, including design configuration management,

• Integration,

• Interoperability,

• Human Factors (HF),

• Performance,

• Availability Reliability and Maintainability (AR&M),

• ILS,

• Risk,

• Safety,

• Quality,

• Security, et al;

h) A draft integration strategy identifying options for integration and development activities;

i) Draft Combat System acceptance trials policy document plans;

j) A clear definition of, and programme for, the work required during the D&M Phase;

k) Comprehensive cost and timescale estimates for Combat System development, including COEIA
data.

3.4.3 Outputs - Lines of Development

3.4.3.1 There are eight recognised ‘Defence Lines of Development’ (DLODs) (reference Joint Customer 2
Handbook) which must be addressed in order to deliver the MC required by the URD. They are:

a) Training;

b) Equipment (the subject of most of this section);

c) Personnel;

d) Infrastructure;

e) Concepts and Doctrine;

f) Organisation;
Unclassified
45
DEF STAN 21-59 Issue 2

g) Information;

h) Logistics.

3.4.3.2 Equipment Capability (EC) is the primary focus of this Def Stan, however it is essential that an SE
approach is applied to all DLODs, both individually and collectively. Delivery of EC and elements of Logistics
is the responsibility of the IPTL and CSM. Delivery of other non-EC lines is the responsibility of other
stakeholders outside the DPA and who the DEC should have tasked. The DEC normally delegates the
responsibility of managing the programming and coordination of all the DLOD deliverables to the IPTL. He,
in turn, may subsequently delegate similar responsibilities to the CSM for all DLOD issues related to Combat
System user requirements.

3.4.4 Outputs - Consolidation

3.4.4.1 The multitude of data (some conflicting) resulting from the Assessment Phase must be compiled
into one set of consistent, coherent documents.

3.4.5 Organisation - Assessment Team

3.4.5.1 It is not the intention of this document to mandate a particular composition of the Assessment Phase
teams. Traditionally the CSMs have looked to MoD departments, agencies or consultants for independent
technical support. However, the CSM must recognise that all organisations may be competitors to other
industrial subcontractors in the commercial market place. The position of any organisation (i.e. whether
‘supplier’ or ‘customer friend’) should be made clear and any track record taken into account.

3.4.5.2 The CSM should also be well aware of potential commercial problems and possible conflicts of
interest. The guidance contained in this document may help to significantly reduce such problems.

3.4.5.3 Participation of foreign consortia members is potentially complex particularly in a joint nation
development. Lessons learned from any previous co-operative projects should be sought.

3.4.5.4 Assistance from the IPT Commercial Officer should be sought at all stages.

3.4.6 Organisation - Integrated Project Teams (IPT)

3.4.6.1 IPTs empowered to conduct system design studies and trade-offs are essential to Smart Acquisition.
The IPT approach involves the participation of all stakeholders including user, customer, and industry
representation (where competition permits) from the earliest opportunity. Whilst Def Stan 21-59
acknowledges the need for co-operative stakeholder involvement, it is the responsibility of the CSM to
ensure that organisational needs and constraints are wholly appropriate to the needs of the project within the
acquisition regime.

3.4.6.2 The IPT Leader (IPTL) shall build upon the core team assembled for the functional capability
assembled during the Concept Phase. However, as the Assessment Phase is conducted principally by
contractors, the CSM will require a larger team with a specific emphasis on contract and technical
management. Under normal circumstances this will be by using either MoD personnel or members of
companies that have as little involvement as possible with the constitution of the competing consortia.

3.4.6.3 On occasions the CSM, and the other competing consortia, may need very specialised assistance or
expertise that is vested in only one consortium. Dependent upon the type of goods and services in question
the contract for Assessment Phase work must be very carefully drawn up to ensure that:

a) The CSM identifies, any specialist goods and services required for the Assessment or D&M Phases
that are effectively ‘single source’ so that appropriate commercial negotiations can be entered into;

b) The MoD has the right to use any information that it owns for MoD procurement purposes subject to
any commercial caveats agreed with that supplier;

c) All avoidable and unavoidable Government Furnished Assets (GFA) are identified and their
associated risks managed.

Unclassified
46
DEF STAN 21-59 Issue 2

3.4.7 Organisation - Consortia

3.4.7.1 In the selection process for Assessment phase consortia, the CSM shall ensure that:

a) The consortia’s organisation contains the required functional capability in depth for the duration of
the work. The functional capability of the CSM’s own team is a good guide to the structure required
of the consortia’s organisation;

b) Key individuals, with the necessary functional skills, are nominated to work on the contract. (The
CSM’s best opportunity of ensuring that the correct capability is being offered is during the
assessment of the consortia’s proposals.)

3.5 Technology Demonstration Programmes / R & D - Technology Survey

3.5.1 As the system requirements are devised and system options are considered, a more detailed
technology survey should be considered. This should aim to clarify the extent to which
equipment/technology options satisfy the system requirements, their design maturity and the extent of any
further development required. Overall the aim of the Assessment Phase is for the equipment/technology
underlying options to be at least at TRL 4 (reference TES-SSG Maritime System Maturity Issue 3).

3.5.2 Where commercial sensitivity permits, the IPT will have also reviewed relevant industrial technology
developments including R&D programmes. These could include tools and methodologies for
system/software development, approaches to adopting modular/open systems architectures for software-
intensive systems, and the capabilities of Commercial Off-The-Shelf/Non Development Item (COTS/NDI)
software and hardware.

3.5.3 It is the responsibility of the CSM to disseminate the results of any technology surveys and inform of
relevant MOD-funded R&D to other MoD and industrial participants in the IPT where security and intellectual
property considerations permit.

3.5.4 Rapid prototyping, Simulation, Synthetic Environments and other simulation techniques can be
employed to explore and demonstrate equipment capabilities, including their man-machine interfaces.
Synthetic environments and other simulation and integration technologies (such as wide area integration)
can be used to explore and demonstrate equipment interworking and operations team teamworking issues.
Such technologies should be considered if risks are significant in these areas.

3.5.5 Modelling and simulation including synthetic environments also have a potential role to play in
system acceptance.

3.6 Key Assessment Phase Processes

3.6.1 Inheritance from the Concept Phase

3.6.1.1 The CSM must conduct the Assessment Phase work in accordance with the approval granted by
the IAB at IG. The CSM team will inherit the Shared Development Environment (SDE) and deliverables from
the Concept Phase for use as the basis of data for the Assessment phase. While the design process is
iterative, the team must not simply accept the work carried out previously without question, neither should
Concept Phase be repeated.

3.6.1.2 Inherited documents can be divided into those that will, and those that will not, be updated during
the Assessment Phase.

3.6.1.3 Documents which will not be maintained through-life shall be reviewed by the project team and
modified in the light of any new/revised information to confirm their suitability for subsequent phases. This
will lead to the applicability of key documents being confirmed.

3.6.1.4 The CSM shall make the contents of the project file visible to the competing consortia within the
constraints necessary to uphold commercial confidentiality. However, the CSM must remember that certain
documentation may well be subject to commercially confidential caveats, which may limit the MOD’s freedom
of action.

Unclassified
47
DEF STAN 21-59 Issue 2

3.6.2 Assessment phase activities

3.6.2.1 Activities are shown on a generic ‘process template’ below. This serves as a guide for
implementing the Combat SE strategy. The process is presented as a ‘seamless’ set of SE activities. The
precise split between the MoD and the competing consortia for conducting the Assessment Phase studies
must be defined by the CSM consistent with the general MoD policy to transfer risk, but not all IPR, to
industry.

3.6.2.2 The division of MoD and Supplier responsibilities is such that the MoD assumes the MC
requirement definition, system specification and acceptance roles, while the competing consortia assume the
proposal of their EC Design Authority and implementation role. Each being responsible for the
documentation and deliverables associated with their role.

3.6.2.3 SE (Technical) and Project Management is an activity split between MoD and the consortia
contractors. Planning and policy review including the monitoring and review of system designs and
documentation should be performed by the MOD. Operational assessment, Whole Life Costs (WLC),
contractor assessment and risk assessment are specialist activities which will also be performed by the MoD
and for which parallel activities will be performed by the contractor within ‘design selection and assessment’.

3.6.2.4 The overarching MC requirements engineering activities (i.e. requirements management,


acquisition, review and endorsement) must be performed by the MOD. The interface between these and
contractor responsible requirements and design activities needs to be clearly defined by the Procurement
Strategy and SEMP.

Unclassified
48
DEF STAN 21-59 Issue 2

SYSTEMS ENGINEERING Management Policies and


(TECHNICAL)
and PROJECT MANAGEMENT Systems Engineering Management
Tender Production for Development & Manufacture

LIFE CYCLE DESIGN ASSESSMENT


REQUIREMENTS
PROCESS FACTORS and SELECTION
ENGINEERING
Produceability Technical Performance
Integration and Test AR&M Assessment
SYSTEMS
ANALYSIS Acceptance and Trials Policy COEIA
Support Plans Design Selection
Disposal Plans Design Validation
SYSTEM Definition of Systems Design
DESIGN Assessment Options

SYSTEM STUDIES Prototyping and Modelling

DOCUMENTATION
System Requirements Document
ITT for Demonstration & Manufacture

SPECIALIST DISCIPLINE SUPPORT AR&M Configuration Management


Human Factors ILS Safety

Figure 3.2 Assessment Phase Process

3.6.2.5 The primary activities in the Assessment phase are to:

a) Further develop URD, SRD and all relevant data (including applicable policies, objectives and
constraints) for the proposed Combat System from all stakeholders; all requirements acquired
should be recorded in the computer-held RDB (i.e. DOORS);

b) Refine and develop the CONOPS/CONEMP and operational scenarios within which the Combat
System provides a capability and to indicate what that level of capability is required to be;

c) Gain and promote a thorough understanding of the capability gap requiring solution and the
interactions between its different issues;

d) Devise and refine potential candidate design solutions and assess their technical assessment and
suitability;

e) Rationalise the range of candidate design solutions which potentially satisfy the identified need and
shortlist the most promising options for more detailed consideration;

f) Assess the function and performance of candidate design solutions and ascertain the design drivers
and technical risks;

g) Prototype any significant enhancements required in the capability of specific subsystems (which may
lead to new development equipments being required) as part of an overall risk reduction exercise (
See DPA PDG Support Group);

h) Further develop the system specification and other documentation to support the generation of the
Invitation to Tender (ITT) for Demonstration/Manufacture;

i) ITT Response assessment criteria;

j) Project Review and Assurance (PR&A). Submission of the project’s products and processes to the
scrutiny and advice of DPA and DLO Assurance Groups. PR&A serves to clearly define tangible
progress made to the benefit of both management and Combat System design team members. It
Unclassified
49
DEF STAN 21-59 Issue 2

does not diminish the need for conventional project management and other SE management
procedures.

3.6.2.6 In order to monitor the completion and review of SE activities, and the endorsement and, where
appropriate acceptance of SE products (output products or other standardised project documents/data), it is
suggested that an Activity Check List drawn from the TLMP for the Assessment Phase, be used.

3.6.3 Sources of Combat System Engineering Information

3.6.3.1 The Combat System design process involves compliance with a wide range of engineering
standards and standard engineering practice. When specifying standards to be applied during later phases,
it should be recognised that the majority of existing/mandated equipments will have been developed in
accordance with commercial standards. Standards are frequently updated and the CSM must establish the
baseline for each standard that he wishes to contract for. The CSM should produce a Standardisation
Implementation Plan (SIP). Advice can be sought from PDG. For CIS standards the CSM must complete
the JSP 602 Checklist for which advice is available from the Integration Authority.

3.6.3.2 The imposition of specific standards on suppliers, particularly retrospectively, can cause high costs.
Some standards will be essential, for example for networking/interoperability reasons, safety, or to make the
systems suitable for Operational use. The CSM should aim to structure the project so that the costs and
benefits of standardisation are identifiable.

3.6.3.3 The IPT should have already set up a Shared Data Environment (SDE) during the Concept Phase
to serve as the central repository of, or signpost to. all relevant Combat System design information. The
SDE should provide ready and easy access information such as:

a) The AMS, BRs, CBs, Def Stans, SSPs, STGPs etc.;

b) JSPs, CESG documents, Central Staff documents, DCIs, SSIs etc.;

c) Industry publications from individual companies;

d) Technical publications etc.;

e) Relevant yearbooks, defence equipment catalogues and defence periodicals;

f) Symposia and conference proceedings etc.;

g) International and national standards (BS, EU, ISO etc.);

h) Relevant Government documentation, Acts etc.

3.6.3.4 It is essential that all this information is under configuration management and access controlled to
allow the appropriate visibility to each consortia. It must not only allow visibility of the latest information
available but also to historical versions which have been used for requirement specification or contract
action. Where a conflict arises in precedence of specific documentation, the CSM should resolve it by
consultation in a manner which must be auditable.

3.6.3.5 The extent of data to be held in an SDE should not be underestimated. Failure to obtain certain
documentation, particularly any which relates to equipments that are either in-service or under development,
can lead to project delay.

3.6.4 Systems Engineering Management Plan

3.6.4.1 Smart Acquisition has introduced Systems Engineering practice to all projects.

3.6.4.2 The Systems Engineering Management Plan (SEMP) is central to the Combat System engineering
strategy. It defines the intended conduct and implementation of SE technical and project management on a
Combat System design project:

a) Establishes the activities and goals of the Assessment Phase;

Unclassified
50
DEF STAN 21-59 Issue 2

b) Manages the conduct of all technical activities, through either direct action or subcontracts on
industry, including their integration to meet the overall technical objective;

c) Ensures that phase objectives are met in programme (timescale) and cost terms;

d) Completes the formal project documentation, which is a pre-requisite for a project to progress to the
following phase.

3.6.5 Mandatory Processes

3.6.5.1 Main Gate (MG) approval by the Investment Approvals Board is required before funding is released
to the Combat System project to move to the Demonstration and Manufacture Phases.

3.6.5.2 The precise implementation of the generic process must to be tailored to meet the needs and
priorities of the project. The SEMP is the most appropriate vehicle for detailing the SE process
implementation, which must demonstrate how the approach will effect concurrency and support the overall
project business case.

3.6.6 Combined Operational Effectiveness Investment Appraisal (COEIA)

3.6.6.1 This is the formal process by which the Combat System design solution options are compared. It
balances the operational value, (primarily performance and programme) of each option with its cost. The
approach and process of how this is to be done, should have been established in a Concept of Analysis
(CoA) produced in the previous Concept Phase.

3.6.6.2 The outcome of the COEIA is the basis on which the CSM submits to the IAB not only his
recommendation for the technical solution but also his estimate for the public funds he is proposing the MoD
should commit to spend.

3.6.6.3 The COEIA predicts the achievable MOEs of the design options against agreed scenarios which
will have been derived by a cascade process from higher level agreed scenarios through the conduct of
operational analysis.

3.6.6.4 The MOEs in terms of which system effectiveness is judged will have been documented as part of
the system specification activity, as discussed in the paragraphs on Operational Analysis in this section.

3.6.7 Development, Cost and Risk Assessment

3.6.7.1 The overall technical maturity of warship (and combat system) options should be assessed
against the AMS on System (Integration) Readiness Levels and the more domain-specific guidance from the
Technical Enabling Services – Sea Systems Group (TES-SSG).

3.6.7.2 System options should be assessed and compared in terms of their Whole Life Costs (WLC)
taking into account contributors across all Defence Lines Of Development (DLODs). Cost accounting rules
(e.g. using net present value costs, using resource accounting, ignoring sunk costs etc.) must be used.

3.6.7.3 There are always uncertainties in the capture and attribution of costs (especially indirect costs
such as those associated with reliability, maintenance and training), in performance data and effectiveness
assessment, in development and production risk, and exchange rate variation. This issue can be addressed
using a variety of means such as:

a) by employing three point estimates to represent the spread of cost confidence;

b) translating risks into the variation of programme activity schedules and/or cost;

c) employing sensitivity analysis to determine the effect of uncertainties in input data and the
robustness of a solution to any variation in assumptions.

3.6.7.4 Further details on the policy which should be employed can be found in the AMS guidance on
Business Cases.

Unclassified
51
DEF STAN 21-59 Issue 2

3.6.7.5 The COEIA implicitly involves Cost trade-off analysis to answer the questions:

a) Can the MoD afford the Combat System as presently envisaged?

b) If so, what is the most cost effective design that meets the requirements?

c) If not, what actions are required?

3.6.7.6 Balance of Investment (BoI) and Cost trade-off activities must never be done in isolation or the
absence of affected Stakeholders. Their impact particularly on interoperability must be understood and
costed. Such trade-off activities may have started in Concept but a significant difference in the Assessment
phase is that a great deal of the source information will have come from design activity carried out by the
competing consortia. Each subcontractor will require to conduct mini cost trade-off exercises at each phase
of the design. These should be co-ordinated and integrated by their prime contractors at appropriate
phases, to enable the final submissions at the end of the Assessment Phase to meet the most stringent cost
constraints.

3.6.7.7 In theory, if a particularly costly requirement or problem is identified, the consortia making this
discovery should refer this to the CSM and RM who can consider the issue of a change to all Assessment
contractors.

3.6.7.8 In practice, competition will normally restrict the willingness of any one consortium to show
evidence of problems any earlier than they are required to do so by their contract. The CSM should
therefore encourage as free an exchange as possible in this critical area. It is important to appreciate that
the cost increases or decreases may affect or be caused by decisions outside the Combat System boundary.

3.6.7.9 The IPTL and CSM are allowed to trade only within the boundaries set by the DEC in his CSA.
The RM must be involved in all trading.

3.6.8 System Costing Support

3.6.8.1 The MoD PFG can provide assistance with:

a) Selection of the project cost-trade-off database to be populated by project information so that data
can be readily exported to SPS models for cost-of-ownership calculations;

b) Advice on which elements of cost information should be collected, and the granularity and accuracy
required;

c) Detailed cost analysis at appropriate project phases when sufficient information is available;

d) ‘Quick-look’ analysis - either to address particular design decisions or to balance technical options.

3.6.8.2 Detailed cost trade-off analysis is required at certain phases of the design and when major
decisions regarding direction are required. This is particularly true of inputs to the EP and decisions on
affordability. The quality of the costing advice provided by PFG is significantly dependent upon the quality of
raw cost data available both within the project and more widely in the MoD. However, if SPS provides the
means and techniques to assess the cost trade-off analysis there must be no expectation given to any
consortia that any inaccuracies in their supplied cost are accepted by the MoD and that the associated risk is
deemed to rest with MOD.

3.6.8.3 In general, the assistance of PFG in addressing cost issues will require anticipation so that
suitable resources and appropriate data can be used. The CSM will have difficulty in ensuring that SPS
assistance is available precisely when the prime contractors/subcontractors need it. CSMs should strive to
make the service available for their projects despite the potential problems identified above.

3.6.9 Acceptance Strategy

3.6.9.1 The DEC is the Acceptance Authority and he alone is responsible for his Acceptance Strategy.
He should have identified an initial Acceptance Strategy in the CSA, prior to Gate Zero. He can of course be
assisted in its production and development by the Capability Working Group, the IPT and the CSM. The

Unclassified
52
DEF STAN 21-59 Issue 2

CSM is responsible for proposing to the DEC, usually via the RM, the IPT’s Integrated Test Evaluation &
Acceptance Plan (ITEAP) in which he will state how he will present evidence to the DEC so that the DEC is
suitably informed to make the decision whether or not to grant System Acceptance. The CSM will establish
the Acceptance criteria against which the MC, EC and project deliverables will be accepted. The will include
the overall system, documentation, equipment hardware, software or firmware, integrated system,
operability, training manning levels and skills, AR&M, support, etc. To achieve this, an Acceptance Strategy
will need to be developed during the Assessment Phase.

3.6.9.2 The ITEAP shall be produced in accordance with the AMS. The ITEAP must reflect the project
acquisition and design strategies and take into account the spend profile for the project. It should consider
the contributions of the other Defence LoDs towards System Acceptance and In-Service Date.

3.6.9.3 The ITEAP should include a funded plan to address modelling, integration, test and trials and how
the acceptance process will utilise data generated by other activities. The CSM must define the role that
modelling will play in the acceptance process. Modelling can be used in two phases:

a) To predict the system performance that the Combat System can achieve;

b) To compare that predicted performance with the product’s achieved performance.

3.6.9.4 The CSM must provide advice as to how the modelling process is linked to the acceptance
process by the test and trials plans.

3.6.10 Modelling, Integration, Test and Trials Strategies

3.6.10.1 In addition to helping system development, Modelling and Simulation (M&S) including synthetic
environments also have potential roles to play in addressing integration issues and, as mentioned above, in
supporting system acceptance.

3.6.10.2 Integration is a crucial combat systems engineering activity. The CSM should consider the
Integration Strategy in terms of:

a) Integration responsibilities;

b) The extent to which integration should be conducted ashore and onboard ship;

c) The need to use dedicated shore facilities, for initial integration and possibly through-life in support of
continuing system development - such facilities may use a combination of real and simulated
equipments together with stimulators, scenario generation, and recording, replay and analysis
capabilities;

d) The time needed for conducting combat system integration and the impact this has on equipment
procurement schedules;

e) The potential need to order an additional equipment shipset (or use a shipset intended for a later
vessel in the class) for conducting integration;

f) The potential use of virtual integration facilities using synthetic environment technologies to link
development/actual equipments, for example, located at manufacturers’ premises (i.e. ‘wide area
integration’).

3.6.10.3 M&S should be used to address equipment interworking, interface and integration issues for the
combat system options under active consideration during the Assessment Phase. The use of M&S to
consider such ‘design for integration’ issues should be reflected in the M&S Plans.

3.6.10.4 M&S, demonstration, inspection, test and trials are all methods for determining whether a combat
system performs as required. Each has its part to play and offers distinct advantages (e.g. veracity, low
cost) and disadvantages (e.g. high cost, reduced veracity). There will be certain elements of combat system
functionality which only M&S can be used to confirm system acceptability and in these cases more traditional
tests and trials can be used to verify and validate the behaviour of the models and simulations.

Unclassified
53
DEF STAN 21-59 Issue 2

3.6.10.5 The CSM should consider the scope of the system requirements and how satisfaction of each
requirement will be ascertained, individually and collectively. The CSM must define the role that M&S will
play both in the acceptance process and in predicting the system performance that the Combat System can
achieve.

3.6.10.6 The CSM shall ensure that the Combat System modelling activities are compatible with the
requirement on him to supply and maintain a model of the Combat System’s capability to the Integration
authority for inclusion in MODAR and MODAF.

3.6.11 Requirements Engineering (RE)

3.6.11.1 KURs are those Military Capability requirements or constraints identified from within the wider set
of user requirements which are assessed as key to the achievement of the mission, or which are for some
reason assessed as of particular interest to management. The CSM shall ensure that all KURS are met.

3.6.11.2 KSRs are requirements (normally restricted to EC) critical to system cost, performance, time or
risk, which provide management indicators of overall system performance. Again the CSM shall ensure that
all KSRs are met.

3.6.11.3 A purpose of RE during the Assessment Phase is to generate sufficient detail until such time as
physical solutions emerge and stabilise into a definitive set of requirements. All requirements activities will
be continue to a degree commensurate with the design activities, as determined by the RM. For guidance
on the specifics of related activities refer to Section 2 - Concept Phase.

3.6.11.4 The constituent elements of the RE process needed for the Assessment phase are documented in
the AMS .

3.6.11.5 The Requirements Database (RDB) produced by the CSM during the Concept phase will be an
important method of technical communication between organisations and will require the use of an SDE.

3.6.11.6 The CSM should regularly update the RDB to reflect any changes that have been agreed with the
DEC or RM, e.g. those resulting from related sub-system and equipment development programmes that may
be progressing in parallel. Whilst the DEC is ultimately responsible for ensuring harmonisation of URDs and
SRDs across these programmes, it is the CSM’s responsibility to bring to his attention any inconsistencies.
A comparison and reconciliation exercise is recommended to ensure commonality and compatibility of
assumptions and design goals.

3.6.11.7 DOORS is the MoD’s preferred structure, format and toolset for Requirements Databases.
Depending on its implementation during the Concept Phase, (see the CSM should mandate DOORS as the
RDB within the contract. The RDB held by the CSM’s team, must be the single repository for:

a) User and System Requirements;

b) Traces between requirements and the candidate design solutions;

c) Criteria against which the requirements will be offered for acceptance;

d) Acceptance processes to demonstrate that the acceptance criteria have been met.

3.6.11.8 The CSM shall require a soft copy of each contractors RDB to be delivered as part of the output of
the Assessment Phase and shall insist that all such deliverables are compatible with the format and structure
of the original MoD RDB. The CSM shall ensure that the contractors accept that it is their responsibility to
ensure such compatibility.

3.6.12 Requirements Management

3.6.12.1 The URD is owned by the DEC. The SRD is produced by the IPT and CSM but it is endorsed by
the DEC. The RM, as the DEC's representative within the IPT, must be involved in all requirement planning
and change management.

Unclassified
54
DEF STAN 21-59 Issue 2

3.6.12.2 Requirements Management is concerned with maintaining the integrity of User and System
requirements as they evolve over time. It involves maintaining an audit trail of requirement changes,
assessing the impact of requirements changes and identifying the inter-relationships between requirements.

3.6.12.3 Requirements Engineering Planning involves the support and maintenance of the RDB scheme,
the preparation of the information and configuration control system and the definition of the requirements
engineering procedure (and associated tools, if used).

3.6.12.4 Requirements Change Management is concerned with the formal and rigorous management of
Combat System requirements once they have been established. It is closely associated with project
change/CM procedures. During the Concept phase the RDB is placed under the project CM regime to track
the evolution of the requirement. Once the URD has been formally issued at the end of Concept Phase, the
RDB is frozen under formal configuration and change control procedure to act as the endorsed baseline for
the subsequent phases. The CSM shall establish a project change control board to process and approve all
subsequent changes to the RDB during the subsequent phases of the project.

3.6.12.5 Any modifications of the requirements definition need to be promulgated to all interested parties in
a disciplined and well-documented manner.

3.6.12.6 Requirements Change Management involves:

a) Operating the project change control board, including obtaining authorisation to change any specific
requirements statement;

b) The implementation of endorsed changes to captured requirement statements and their associated
data (such as contextual information and classification fields) in a disciplined and controlled manner;

c) Authorising the release of the updated baseline RDB. The CSM shall only authorise such a release
via the IPT Commercial Officer.

3.6.12.7 Requirements Traceability Management - this ensures that requirement statements are actioned
by the relevant systems engineering activities and disciplines, and implemented in the Combat System or its
design process, as appropriate. It involves the recording of links between the RDB and models, documents
etc. as used in relevant activities. Typically these links are expressed in the form of trace tables or additional
fields in an expanded RDB. Trace mechanisms should ideally facilitate tracing in both directions.

3.6.12.8 Effective requirements change management requires traceability links - to facilitate both the
impact analysis of changes to requirements and also the subsequent actioning of the impact of a change in
requirements (for example, by the amendment of the corresponding elements in analysis, design and
assessment models). if anomaly reports are be used to initiate changes to requirements, then these can be
linked-in to requirements change management.

3.6.12.9 As a result of the design activities certain requirements may prove to be impractical to achieve
either due to technical or cost constraints. The CSM and RM are responsible for reviewing the implication of
these results with the originator of that particular requirement and, if agreed, changing the contents of the
RDB and promulgating changes to all relevant authorities.

3.6.12.10 The CSM should, where practical, avoid re-issuing the RDB during the later stages of the
Assessment Phase. Throughout the life cycle phase and particularly in circumstances where re-issue is
unavoidable, the CSM shall implement strict configuration control through the project configuration control
board, remembering that:

a) The RDB must be authorised by the Acceptance Authority (especially where a relaxation of the
endorsed requirement is being proposed);

b) Competing consortia are most likely to have developed individual, specific instantiations of the
original RDB, which may now require amendment. Such activities may be reflected in additional
costs/risks/programme delays to MOD. (Any contractor-specific instantiation of the RDB should
conform to DOORS in terms of structure, schema and consistency).

Unclassified
55
DEF STAN 21-59 Issue 2

3.6.13 Stakeholder, Domain and Scenario Analysis

3.6.13.1 The IPTL and CSM shall produce a Stakeholder Responsibility Matrix and form funded business
agreements with those stakeholders to ensure delivery of the DLODs.

3.6.13.2 During the Concept Phase, CONEMP/CONOPS and subsequent scenario analysis will have
identified high level scenarios and associated events. These can be used to provide context and clarification
of user (and system) requirements. During the Assessment phase, further consideration and refinement of
these scenarios assists the requirements engineering and systems analysis activities (particularly
Operational Analysis (OA)).

3.6.14 Acceptance Evidence

3.6.14.1 The CSM shall require the competing consortia to provide acceptance data related to each
requirement :

a) Acceptance evidence comprising:

i) Evidence that will be offered to show that the requirements has been achieved,

ii) Supporting information,

iii) Specific test limitations;

b) Acceptance event, which will be classified as one of the following types, at which the acceptance
evidence will be presented:

i) Review,

ii) Audit,

iii) Analysis (including calculation and mathematical modelling),

iv) Inspection,

v) Demonstration,

vi) Test (including Factory Acceptance Trials),

vii) Shore Facility Trials,

viii) Harbour Acceptance Trials (HATs),

ix) Sea Acceptance Trials (SATs).

3.6.15 Systems Analysis

3.6.15.1 Systems Analysis is the application of scientific principles to the study of a problem domain or
system in order to:

a) Obtain a better understanding of it;

b) Identify the component elements, their inter-relationships and impact on key characteristics and
other system issues;

c) Systematically identify and assess alternative courses of action.

Unclassified
56
DEF STAN 21-59 Issue 2

Systems
Analysis

Logical Operational System


Modelling Analysis Specification

Decomposition Refinement Production of


Aggregation of Operational Logical Model
Abstraction Scenarios
Production of
Behavioural Refinement of System
Analysis System MOEs Specification

Consistency & Further Definition of


Completness Parametric System MoPs
Analysis Performance Analysis

Requirements
Structuring

Figure 3.3 Composition of Systems Analysis Activity

3.6.15.2 Systems Analysis during the Assessment Phase is principally concerned with developing an in-
depth understanding of the problem domain and potential solution space using modelling and analysis
techniques. The composition of the Assessment Phase systems analysis activity is illustrated in
Composition of Systems Analysis Activity. Each of the constituent activities is described in turn below.

3.6.15.3 Logical Modelling

3.6.15.3.1 Logical modelling can be performed of the functional user and/or system requirements to help
establish their consistency, (internal) completeness, structure/level and absence of ambiguity.

3.6.15.3.2 A number of techniques (methods) are suitable for the conduct of logical and functional modelling.
Up-to-date advice on all aspects of tool support should be sought from experts in the field. Computer
support environments are prone to obsolescence and the MoD is littered with models which can no longer be
supported due to the demise of particular hardware or Operating System. Consortia will always press for
models and support tools to be subject to IPR restriction. The CSM should insist that all work funded by
MoD has full MoD-user rights so that it can be used without hindrance throughout the project lifecycle.

3.6.15.4 Operational Analysis (OA)

3.6.15.4.1 Operational Scenarios - Further refinement and specialisation of vignettes taken from SAG
scenarios will be used to evaluate different system options within the levels of operational capability required
and the CONEMP. The resulting vignettes shall be used during subsequent project phases to provide a
defined framework for evaluating deliverable capability concerning the vessel’s warfare and non warfare-
related roles. These scenarios will also be used as the benchmark for the equipment and Combat System
test, trials, evaluation and acceptance programme to provide the link between Equipment and Combat
System performance and operational effectiveness as described in Measures of Effectiveness (MOEs) for
the COEIA.

3.6.15.4.2 For the purposes of warfighting effectiveness assessment, the following information relating to
vignettes will need to be defined:

a) Roles and tasks of the vessels within the scenario;

b) Tactics to be employed within the scenario together with Rules Of Engagement;

c) Geometry of the engagement;

d) The physical environment (land topography, meteorology, oceanography etc.);

Unclassified
57
DEF STAN 21-59 Issue 2

e) The characteristics of vessels, e.g.; signature: broadband, narrowband, tonals; speed and
endurance; weapons and countermeasure capability; sensors and command management
systems performance, physical operational constraints such as blind arcs.

3.6.15.5 Measures of Effectiveness/Performance

3.6.15.5.1 Initial MOEs will have been developed during the Concept Phase and shall be developed in line
with scenario definition and URD completion. The aim should be to quantify all areas of required capability
in terms of specific, verifiable MOEs.

3.6.15.5.2 Measures Of Performance (MOPs), and other quantified system requirements, shall be devised
as the SRD is developed. These should at least initially aim to satisfy the URD MOEs but may need to be
traded as the potential solution space is refined. Means of MOP verification will need to be determined.

3.6.15.5.3 Parametric performance analysis techniques can be used to define the overall solution space and
potential trade-offs between the performance characteristics of different system options. They can be a
powerful technique to use within the Assessment Phase.

3.6.15.5.4 Within the sets of individual user and system requirements, those which are assessed as key to
the achievement of the mission need, or which are important for project progression and management, will
be assessed as Key User Requirements (KURs) and Key System Requirements (KSRs) respectively.
Numbers of KURs and KSRs should be kept quite low, with the precise number depending upon the range of
operational roles the vessel performs and its range of functional capabilities. KURs and KSRs provide an
indication of critical system elements and the boundary limits to trade-offs.

3.6.15.6 Operational Analysis techniques

3.6.15.6.1 Advice on the use of Operational Analysis tools and techniques which are suitable for their
intended purposes can be obtained from Dstl Naval Systems.

3.6.16 System Design

3.6.16.1 Scope

3.6.16.1.1 System Design is the process of developing candidate design solutions, capable of meeting both
the operational and functional requirements as stated in the system specification.

3.6.16.1.2 It also involves the examination and adoption of one or more system structures/architectures,
consideration of non-functional requirements, constraints, HF issues and mandated/candidate equipments.

3.6.16.1.3 To fulfil the requirements of the IAB at MG, it is usually necessary to demonstrate that, at least
initially, the Assessment Phase (if not done previously in the Concept Phase) has considered a wide range
of system design solutions. Thereafter it is normal to concentrate on the most viable, capable, affordable
and cost-effective solutions and explore variants of the preferred design (or designs) concentrating on
progressively lower-level design issues.

Unclassified
58
DEF STAN 21-59 Issue 2

System
Design

System System Design Design


Functional Studies Verification Documentation
Design

System System Policy Paper Refinement


Variants Architecture
Coherence Specification
System Non Functional
Information Analysis Subsystem Specifications
Exchange
System
Equipment Data Interfaces
Collection
Installation
Specification Engineering
of Software

Figure 3.4 Composition of System Design Activity

3.6.16.1.4 The composition of the system design activity is illustrated in Figure 3.4. In practice, iteration
between requirements engineering, systems analysis and system design, will be required.

3.6.16.2 System Functional Design

3.6.16.2.1 By the end of the Assessment Phase, each competing consortia should provide sufficient
confidence that their solution will work and meet the KURs and KSRs within their estimated Whole Life
Costs. This should be demonstrated by a prototype of each system. However in many cases a
comprehensive series of computer models will have to be acceptable.

3.6.16.2.2 The procedures and disciplines for the Concept Phase design process should be carried through
to the Assessment Phase. However the emphasis changes from Logical Modelling of the requirement by
mapping to a Physical model of a proposed implementation. The CSM is responsible for monitoring the
process.

3.6.16.2.3 This work should be carried out using tools and techniques similar to those identified in earlier
stages. The CSM shall make available to the competing consortia computer-readable copies of the models
developed during the Concept Phase or Assessment Phase 1, but shall avoid mandating their use.

3.6.16.2.4 The final selection of tools and techniques for the Assessment Phase is a decision that the CSM
shall leave to the competing consortia. However, the CSM shall require each competing consortia to deliver
a detailed justification for the tools and techniques proposed, including information on the selection and
assessment criteria applied.

3.6.16.2.5 Functional Design is the application of functional modelling techniques supported by other SE
disciplines e.g. HF; Performance Engineering; AR&M Engineering etc. to derive one or more physical models
of system design concepts. It should be noted that specific design approaches (e.g. design for performance,
design for reliability, design for supportability, design to cost) can be applied where corresponding non-
functional requirements are particularly demanding.

3.6.16.2.6 The derivation of a physical model from a logical model together with design and implementation
requirements and constraints (as contained in the RDB) uses a mixture of two distinct but complementary
techniques:

a) Candidate equipment matching - the matching of required functionality to that of candidate and / or
mandated equipments;

Unclassified
59
DEF STAN 21-59 Issue 2

b) ‘Greenfield’ design - the application of a translation procedure to derive the functionality for man and
machine – viz: operators and new development. Translation involves the allocation of function and
must take HF considerations into account.

3.6.16.2.7 The result of functional design is a number of physical models, each of which represents the
functionality and real-time behaviour of candidate design options. Each option should be practical and
potentially capable of implementation.

3.6.16.2.8 For a new Combat System, the physical models should reflect both ‘off-the-shelf’ (possibly with
tailored interfaces) and new development equipments together with the functionality performed by specified
members of the ship’s complement who are to operate and utilise the Combat System.

3.6.16.2.9 In the case of an update to an existing Combat System, the physical model may reflect the entire
Combat System or be limited to broadly the extent of the update. The extent of the update must be
addressed as it sometimes proves to be greater than first apparent when equipment design characteristics,
performance issues etc. are taken into consideration. Elements of the Combat System, which interface with
areas covered by an update generally, require some degree of modelling.

3.6.16.3 Variants of Combat System Physical Models

3.6.16.3.1 The Assessment Phase is initially aimed at producing feasible options from which a preferred
design will emerge. The design process will generate a number of different physical models, each one
representing a different view of the functionality of the required combat system. The lowest level assembly
physical models are grouped to form equipment models, Subsystem models and ultimately the single global
system, the total Combat System model.

3.6.16.3.2 Physical models enable the tracing of requirements through to specifications. They support the
numerate translation of requirements to specifications by identifying the ‘actual' hardware, software and
human components of the overall system. Control of these models enhances the traceability of the overall
design and permits the generation of variants of the design for mixes of equipment on different platforms.

3.6.16.4 Information Exchange Requirements (IER)

3.6.16.4.1 With the completion of the physical model solutions the high-level information flow between the
candidate subsystems can be identified. The CSM shall capture the detailed system Information Exchange
Requirements (IER) and data exchange requirements (DER) to ensure that the architecture studies can be
completed.

3.6.16.4.2 Ideally IERs should initially be captured in both JIFM and iSMART and associated assumptions
captured. All terms used should be lodged with CDMA for inclusion in the Defence Data Repository (DDR).
Advice on the formal documentation of the system data / information exchange requirements by the CSM is
available from (ref to www.fdm.dii.r.mil.uk).

Unclassified
60
DEF STAN 21-59 Issue 2

3.6.16.5 Equipment Data Collation

3.6.16.5.1 For mandated or candidate equipment identified within the functional design the CSM shall assist
the competing consortia in collating the equipment data. Equipment data should not be restricted to
functionality, performance, AR&M, space, weight, required services, heat etc. The information gathered
during the Assessment Phase should build upon that previously obtained at Concept Phase.

3.6.16.5.2 Where a specific equipment (e.g. navigation radar) has been identified, a market survey should be
undertaken to identify candidate equipments. Existing project databases and defence publications
(yearbooks, defence equipment catalogues and periodicals) are useful in conducting this.

3.6.16.5.3 For each of these equipments, the following information should be collated:

a) Test and Acceptance Criteria;

b) URDs, SRDs;

c) Equipment Specifications;

d) Interface Specifications and draft Interface Control Documents (ICD);

e) Comprehensive technical documentation covering functionality, performance, AR&M, weight, space,


through life cost etc.;

f) Interface documentation;

g) Model and database data;

h) Trials Reports;

i) Alteration and Addition (A&A) details, including variants.

3.6.16.5.4 This material will be useful in conducting candidate equipment matching within the functional
design activity. The Combat System Engineering Database may be a useful source of information.

3.6.16.5.5 Based on the system studies, the CSM shall require the competing consortia to translate the
functional design into a candidate architecture, i.e. physical solution. For the proposed physical solution to
the Combat System requirement it is necessary for the competing consortia to:

a) Conduct detailed evaluations on proposed solutions in order to resolve errors of incompatibility


where the functionality offered by the recommended solution does not provide requisite system
effectiveness within the scenarios provided;

b) Optimise the proposed designs to ensure that maximum capability is provided for the minimum
investment in time, cost and areas of risk;

c) Feedback the results of the evaluations into the other areas of system design.

3.6.16.5.6 The level of detail required of the candidate architecture shall be sufficient to allow all of the
necessary design documentation to be produced without imposing unnecessary constraints on the
equipment solutions. That is, existing equipment can be characterised by its BRs and CBs as its
implementation is known and accepted. However, new development equipment should be characterised in
terms of its specific requirements. In this manner the implementation risks are flowed through the competing
consortia to equipment suppliers, who in time will become the equipment design authorities.

3.6.16.5.7 The CSM shall require that the competing consortia deliver all functional and physical models, and
any variants thereof, in both hard copy and computer-readable format complete with a description of the
operating environment required to host the models.

Unclassified
61
DEF STAN 21-59 Issue 2

3.6.17 System Studies

3.6.17.1 Systems Analysis & Modelling

3.6.17.1.1 Systems analysis and modelling techniques can be employed to address the completeness and
consistency of a set of requirements such as a logical description of a system. These techniques tend to
concentrate on functionality and leave non-functional issues to manual analysis. Checklists can be used to
ensure that non-functional issues have been addressed.

3.6.17.1.2 Systems Analysis can be described as the application of scientific principles to the study of a
problem domain or system to obtain a better understanding and identify the component elements, their inter-
relationships and impact on key characteristics and other system issues. It also helps to systematically
identify and assess alternative courses of action.

a) The complexity of modern Combat Systems makes production of prototypes extremely costly both in
time and financial terms. For many aspects of Combat Systems design, modern computer
technology and SE techniques offer a cost-effective alternative to prototyping by providing the
means to `model' the system;

b) Modelling is the process of deriving a representation of some aspect, or aspects or a real-world


entity, being representative to a particular level of fidelity, i.e. accuracy, detail etc. sufficient for the
purposes for which it was constructed.

3.6.17.1.3 Computer Modelling can be used to:

a) Structure functional requirements for analysis of consistency and completeness and;

b) Promote greater understanding of what functions the Combat System is required to perform.

3.6.17.1.4 Logical modelling provides a logical, structured, unambiguous, descriptive, complete, consistent
and correct statement of required functionality in the form of a logical model. Ideally, nothing in a logical
model states how the Combat System is to be implemented.

3.6.17.1.5 Needlines and Information Exchange Requirements (IER) should be modelled e.g. in JIFM or
iSMART (or predecessor i.e. TULIP).

3.6.17.1.6 Whatever modelling is conducted for the Combat System an output from that modelling must feed
into MODAF.

3.6.17.1.7 Advice on modelling tool-sets and techniques and their relative suitability should be sought from
established MoD sources, as some may be freely available to the project through corporate licence
agreements. Lock-in to proprietary modelling tools must be avoided.

3.6.17.2 System Requirement Specification

3.6.17.2.1 Having conducted logical modelling of the User capability required, a clear and consistent view
of what is required of the new/updated system should be obtained during the Assessment Phase. The
purpose of the system requirement specification activity is to specify this formally in a SRD.

3.6.17.3 Combat System Concept Design

3.6.17.3.1 Combat System Concept Design is the process of developing candidate high-level Combat
System design solutions, which are likely to be capable of meeting both the functional and non-functional
requirements captured in the SRD). It also involves:

a) Consideration of the non-functional/design/implementation requirements and constraints covering


both features in the Combat System and how they are to be developed or implemented;

b) Examination and adoption of one or more system structures/architectures;

Unclassified
62
DEF STAN 21-59 Issue 2

c) Consideration of HF issues and mandated/candidate equipments and all other transversal (e.g.
safety, security) issues.

3.6.17.3.2 During Assessment Phase, the aim is to generate as wide a range as possible of potentially viable
Combat System design solutions. In the later life cycle phases, the system design solutions will concentrate
on the most viable (capable, affordable and cost-effective) of these solutions and explore variants of the
preferred design (or designs) concentrating on progressively lower-level design issues.

3.6.17.3.3 In practice during the course of this work, some iteration between Assessment Phase design,
systems analysis and requirements engineering, will be inevitable.

3.6.17.4 System Structure Studies

3.6.17.4.1 Structures are the ways system components may be assembled. Currently there are three
structures in Naval Combat System data handling which are either in use or under consideration, as follows:

a) Centralised structure which comprises one (or a small number) central functional processor(s)
carrying out all data handling compilations and control functions;

b) Federated structure which comprises a number of subsystems which are autonomous in data
handling to a certain degree, but can still be controlled to a certain degree by one (or a small
number) controlling computer(s);

c) Distributed structure which divides the data processing load via the processors in the system without
using fixed or central points.

3.6.17.4.2 In practice, a continuum of hybrid structures exist.

3.6.17.4.3 There are also several initiatives on Open Systems Architectures sponsored by various DECs and
applicable to naval combat systems and their constituent equipment. Advice should be sought from DEC
CCII who has core DEC responsibility for Interoperability.

3.6.17.4.4 System Structure Studies should take into account:

a) Design and implementation requirements and constraints;

b) Mandation of specific equipments;

c) Vulnerability considerations;

d) Data management considerations;

e) Information processing considerations including load, flexibility and re-configurability.

3.6.17.4.5 Other SE considerations:

a) HF to ensure that functionality is allocated correctly between man and machine functions;

b) Performance engineering;

c) AR&M engineering - Def Stan 00-41 gives guidance on such matters.

3.6.17.5 Formulation of Design Policy

3.6.17.5.1 Formal project documentation should include:

a) Design Policy Papers and Coherence specifications - to identify issues and their constituent factors,
formulate policy and to state guidelines, rules and requirements. They adopt a management and
high-level technical perspective;

Unclassified
63
DEF STAN 21-59 Issue 2

b) All design policy papers should at least be scoped and where possible progressed to draft issues
during Assessment Phase.

3.6.17.5.2 From the above work, the CSM will have one or more candidate structures which can be used for
assembling system components in functional design.

3.6.17.5.3 The CSM shall conduct, or shall ensure that competing consortia conduct, architecture studies to:

a) Create possible physical solutions that meet the logical requirements for the Combat System;

b) Subject these possible solutions to modelling studies that resolve the question of ‘how well does
solution A meet the requirements and is it better than solution B?’.

3.6.17.5.4 Trends in design, including trends in systems architecture (e.g. open and modular architectures)
and COTS equipment, and trends in the military marketplace must also be considered. Within the design
time of the project will specific solutions, which are not achievable at present, become possible? This is
particularly critical in areas such as database techniques, processing power and display technology where
MoD and Industry can have very similar requirements.

3.6.17.5.5 The results of these studies feed into other areas of the design effort, and contribute to the other
outputs of the Assessment Phase.

3.6.17.6 Architecture Modelling

3.6.17.6.1 By the end of the Assessment Phase, the technology to be used to implement the Combat
System will be reasonably firm. The CSM shall require the competing consortia to carry out, and deliver the
results of, thorough modelling studies to demonstrate that their chosen solution will meet all the system
requirements. Architecture modelling should concentrate on the proposed physical designs and
investigation of infrastructure and software architecture issues.

3.6.17.6.2 Architecture modelling will validate the system physical models. The competing consortia, guided
by the project team, will be required to evaluate the capabilities of these designs, within the agreed
scenarios.

3.6.17.6.3 Architectural modelling should study the following to expose potential architecture difficulties,
operability requirements, and system interface, communications and computer power requirements:

a) Communication bandwidths;

b) Processor speeds and capabilities;

c) Trade-off analysis of bandwidth, data volumes and processor responses;

d) Data transfers and boundary conditions between subsystems;

e) Safety implications of system architectures;

f) AR&M implications of architecture;

g) Operability conditions at subsystem interfaces;

h) Data grouped by different security classes;

i) Real time data transfer around the system;

j) Response times;

k) Data storage requirements;

l) Human computer interactions;

Unclassified
64
DEF STAN 21-59 Issue 2

m) Data communication bandwidths;

n) Trade-off analysis of bandwidth, data volumes and processor responses.

3.6.17.6.4 The degree to which the above aspects can be considered will depend on the maturity of the
supporting data and design configuration. It is likely that the necessary detail will only become available
during the course of the Assessment Phase, and even then with voids in specific areas which will require
documented assumptions.

3.6.17.6.5 Analysis of this type permits review of potential architecture difficulties, operability requirements,
and system interface communications and computer power requirements.

3.6.17.6.6 Each physical solution must be analysed for dependencies such as processor bottlenecks,
communication delays and dataflow transfers. To understand fully a system design, it is necessary to
stimulate the architecture and monitor the various dependent elements. The design detail available is likely
to be restricted and incomplete at this stage, hence the level of firm detail for modelling studies is
correspondingly limited, requiring assumptions to be made. Such an approach is both valid and useful, as
long as the assumptions made are both realistic and fully documented, so that the modelling studies can be
refined as further design detail emerges.

3.6.17.6.7 Certain high-level requirements, principally reliability, maintainability and performance, will be
budgeted in the form of lower level targets, where satisfaction of all the lower level targets would be
equivalent to satisfaction of the high-level requirement. The CSM shall ensure that AR&M and performance
budgeting, is undertaken through the apportionment and allocation of the overall project budgets, such that
the results can be assigned to each of the candidate solutions developed. This is an iterative process.

3.6.17.6.8 While much of this work will be carried out by the competing consortia, the initial identification and
decomposition of the budgets, as well as the assessment that the subsequent apportionment and allocation
does comply with these budgets will be conducted by the CSM’s team and tracked through the RDB.

3.6.17.7 System Interfaces

3.6.17.7.1 Following the completion of the system architecture studies the CSM shall document the resultant
system interfaces. For the Assessment Phase it is sufficient to identify the system interfaces by type, i.e.
RS422, Combat System LAN, etc. Detailed interface specification should be produced at this phase in
readiness for their translation into Interface Control Documents (ICD). Assumptions should be based upon
de-facto MoD documentation schemas (e.g. Def Stan 21-13) where tools are already in place for through-life
support.

3.6.17.7.2 The CSM shall map the system information exchange to the system interfaces to provide an
indication of the complexity of the data exchange across the interface. Understanding the complexity of the
data exchanges is a key factor in the risk assessment of the system architecture. A good system design
requires robust protocols which will continue to work during fault conditions and with faulty data. It is
recommended that Data Management and Tactical Data Link (TDL) expertise be sought early (e.g.
www.fdm.dii.r.mil.uk).

3.6.17.8 Installation Engineering

3.6.17.8.1 During the Assessment Phase preliminary installation engineering is limited to:

a) Developing layouts for operational spaces;

b) Developing layouts for the outboard equipment fit;

c) Collating basic equipment data and budgets to ensure that the platform systems are adequately
designed: e.g. Chilled water; Electrical power; Ventilation and Air Conditioning; Hydraulics;
Pneumatics; Weight, space, maintenance access;

d) Hydrodynamic studies for below water Combat System equipments;

e) Electromagnetic Environmental Effects (E3) studies for Electromagnetic sensors and emitters (Def
Stan 08-136 applies and guidance should be sought from DCSA E3 section);
Unclassified
65
DEF STAN 21-59 Issue 2

f) Structural studies to ensure that the equipment can be installed within the platform.

3.6.17.8.2 Various modelling tools are available for these activities; choice should take into account the
databases, models and techniques used for requirements capture, structured design, architecture design
and Human Factors.

3.6.17.9 Design Verification

3.6.17.9.1 Design Verification is the checking that the design concepts (expressed as physical models) and
resulting from the functional design activity, correctly reflect:

a) User and System requirements, including agreed trade-offs;

b) Approved documentation describing the functionality and design characteristics of mandated and
candidate equipments where adopted as part of the Combat System design;

c) Formal design decisions.

3.6.17.9.2 The verification of activities and related project documents/data should be undertaken only when
they have been completed and brought under formal CM. The execution of design verification should be
recorded.

3.6.17.9.3 A cycle of project reviews shall be used by the CSM as the mechanism for ensuring that the
competing consortia offer their Combat System design for design validation.

3.6.17.9.4 The adoption of formal mechanisms such as trace tables for linking requirements and constraints
on system designs to the designs themselves greatly facilitates the conduct of design validation. Design
validation, i.e. the process of confirming that the offered design is 'fit for purpose' in the sense that it is
capable of fulfilling the roles envisaged, is a much more complex and open-ended process than design
verification and is best addressed in an ongoing manner through formal design review mechanisms required
by the SEMP.

3.6.17.10 Design Documentation

3.6.17.10.1 In parallel with design solutions, design issues should be identified, policies formulated and
implementation rules stated. The CSM will document during assessment:

a) Policy Papers; used to identify issues and their constituent factors, formulate policy and to state
guidelines, rules and requirements. They adopt a management and high-level technical perspective;

b) Combat System Coherence Specification; (1) the possession of consistency and integrity, (2) the
adoption and maintenance of system-level rules which define key features of operating procedures
and interfaces within a system. More than one may be needed depending on the diversity of system
options. They should lead to a more uniform, integrated and complete Combat System. The
coherence specification should evolve into a formal technical specification to accompany the
subsystem specifications;

c) Combat System Subsystem Specifications; updated as part of the system analysis activity.
Following on from this, draft subsystem specifications based on the candidate architectures shall be
developed;

d) Combat System Anomaly Reports; produced as the formal mechanism for documenting and
managing the resolution of problems and issues;

e) Combat System Design Variants Record. - The process of deriving and assessing design options,
key assumptions, the conduct of system design activities (including the modelling techniques used),
the derivation, evolution, evaluation and iteration of design options and discussions held, and a
record of decisions taken and any associated studies which have affected the course or conduct of
the Assessment Phase.

Unclassified
66
DEF STAN 21-59 Issue 2

3.6.17.11 Platform Installation Studies - Budgets

3.6.17.11.1 At the start of the Assessment Phase, the CSM shall negotiate with the DEC and platform
project in respect of Combat System budgets in the following areas:

a) Space available in specific compartments;

b) Weight budgets;

c) Power budgets by type and standard, i.e. 24V, 115V 60Hz, essential supplies, non essential
supplies, etc.;

d) Chilled water budgets;

e) Hydraulic power budget;

f) Pneumatic power budget;

g) Internal and external constraints on the Combat System;

h) Heat budget;

i) Timing budgets;

j) Accuracy budgets;

k) Alignment budgets;

l) Yaw, Pitch and Roll budgets.

3.6.17.11.2 Throughout Assessment Phase, the CSM shall keep both the platform project and the
contractors appraised of the developing system budgets, with particular emphasis upon (perceived) design
compliance and acceptance of those budgets as the candidate Combat System architectures develop. The
CSM shall attempt to retain a margin between the budgets agreed with the platform authority and the
budgets made available to the competing consortia, especially if there are emerging requirements whose
budgets are not yet defined. The CSM shall require that the competing consortia complete the Combat
System design within such budgets.

3.6.17.12 Weapon Equipment Schedule (WES)

3.6.17.12.1 The CSM shall require that the competing consortia document the Combat System budgets in
a WES. Further, the CSM shall require that the WES be delivered at intermediate stages during the
Assessment Phase to facilitate negotiations with the platform project to meet the Combat System
requirements. The WES is one of the controlling documents for the Combat System.

3.6.17.13 Internal Arrangements

3.6.17.13.1 The CSM shall draw upon earlier Human Factors (HF), complementing and platform general
arrangement studies to:

a) Inform the platform project of the proposed internal arrangements for the Combat System
operational spaces (recognising DEC and RM responsibilities);

b) Agree with the platform project the interface details of the Combat System operational spaces with
respect to the platform.

3.6.17.13.2 The CSM shall provide the platform project with sufficient detail to allow conflicts between
Combat System equipments and other platform systems to be identified and resolved.

3.6.17.13.3 The CSM shall require the competing consortia to deliver draft layouts for the operational
spaces within the platform indicating the fitting arrangements for the Combat System. These layouts shall
Unclassified
67
DEF STAN 21-59 Issue 2

include sufficient detail for the CSM to have confidence that the Combat System can be fitted in to the
available space.

3.6.17.14 External Arrangements

3.6.17.14.1 The CSM shall advise the platform project of the Combat System requirements concerning its
external arrangements and shall agree the final layouts for each competing consortium’s Combat System
solution. The CSM shall provide the platform project with sufficient details to allow the resolution of conflicts
between Combat System equipments and other platform layout constraints.

3.6.17.14.2 The CSM shall require the competing consortia to deliver draft layouts for the fitting of the
Combat System equipment to other parts of the platform, e.g. flight decks on carriers, areas external to the
pressure hull on a submarine. These external arrangements shall include sufficient detail for the CSM to
have confidence in the Combat System platform interface requirements.

3.6.18 Life Cycle Process Factors

3.6.18.1 During the Assessment Phase, there is a need to build upon policy and plan documentation co-
ordinated through the TLMP and SEMP. At this phase, the following topics need to be revisited to document
policy in line with the evolving Combat System design:

a) Procurement strategy;

b) Implementation and production issues, including adoption of COTS, and approach to software-
intensive system components;

c) ITEAP;

d) ILS/Logistic Support Analysis (LSA) strategy; Further advice should be sought from the Support
Solutions Envelope / Maritime Support Strategy (DLO / TES);

e) Capability Roll-out plan;

f) Disposal plan.

3.6.19 Life Cycle Process Factors - Integration Strategy

3.6.19.1 The contractors have to formulate their integration strategy plan to the point where firm price
development of the chosen method can be undertaken. In the extreme case of a new Shore Integration
Facility (SIF) the site must have been established and evaluated as fit for purpose. All buildings and
services must have been designed to a state where they can be accurately costed. The environment for the
Combat System must have been designed to a sufficient level of detail. This detail will establish the design
of the scenario generators, the recording and analysis equipments and the simulation / stimulation
requirement for each Combat System equipment. There must also be a coherence specification and
subsystem specifications for each equipment’s respective element of the SIF. There also has to be a
programme showing that the SIF will be built, integrated, and accepted before its first usage in the Combat
System integration plan.

3.6.19.2 A Combat System integration plan has to be formulated to show the development of integration
test/trial orders and the sequence of integration tests that are to be undertaken to ensure the integrity of the
Combat System design and to prepare the Combat System for acceptance; this plan should include both
shore and ship tests/trials. It is most important that the Combat System contractor can make all equipment
suppliers aware of the extent of their obligations to support Combat System integration when negotiating
equipment contracts.

3.6.19.3 The issues in the integration strategy plan should be further explored. Whilst avoiding integration
at a SIF may appear to be the cheapest ‘ least work’ option, this also represents the highest risk to the
Platform project. New technology solutions may also have to be explored and recommendations made
regarding their adoption and their impact upon a traditional SIF-based approach. Wide-area networking at
‘slower than real time’ may offer an opportunity to test protocols and basic functionality thereby reducing the
risk of poor design.

Unclassified
68
DEF STAN 21-59 Issue 2

3.6.19.4 The intended longevity of the SIF is an important issue. It may be required for the initial
development only, or it may be required for through-life support of the class.

3.6.19.5 The SIF test environment will contain some form of scenario generator to drive simulators or
simulators interfaced to the Combat System equipments. The simulators and stimulators may be included in
the equipment contracts, and if so, there is an opportunity to use them for on-board training, maintenance
diagnostics, and system set-up. As already implied, a SIF also needs extensive data recording and analysis
facilities. The integration programme may also benefit from having several networks available in the SIF to
enable parallel testing and so shorten the trials programme.

3.6.19.6 An outline Combat System integration plan should show the sequence of integration tests to be
undertaken to ensure the integrity of the Combat System design and to prepare the Combat System for
acceptance; this plan should include both shore and ship tests/trials.

3.6.19.7 The method and plan must be taken into account in this phase's Combat System costings and risk
assessment. The form in which they are passed into the next phase will depend upon MOD's intended
relationship with the competing contractors - an integration method might be mandated, indicated as
preferred, or left to the contractor. If not mandated, any other method or plan offered will be compared with
the reports of this phase to see if there are any shortfalls in a contractor's offering.

3.6.20 Assessment and Selection

3.6.20.1 A suggestion for the assessment and selection process of the candidate design solutions is shown
in Figure 3.5. All the following factors must be taken into consideration:

a) Operational effectiveness;

b) Technical assessment and performance;

c) AR&M;

d) Development, cost;

e) Risk;

f) Affordability;

g) Supportability.

3.6.20.2 The preferred options will be subject to formal COEIA evaluation and a recommendation made to
the IAB at MG. The IAB should not being asked to select a solution development.

Design
Assessment
& Selection

Design Technical Technical ARM Refinement System Design


Selection Feasibility Performance Assessment of COEIA Specification
Assessment Assessment

Technical Risk Definition of Operational Design Development


Equipment Effectiveness Feasibility Option Record
Identification of Scientific Performance Assessment
&Technology Difficulty Characteristics Interface
Overall Documentation
Option
Assessment Outline System
Agreed Characteristics
Development,
Cost & Risk Outline System
Assessement Acceptance Questionnaire

Figure 3.5 Design Assessment and Selection


Unclassified
69
DEF STAN 21-59 Issue 2

3.6.20.3 System design, design assessment and selection are iterative processes to `close the design
loop' and identify any options which would benefit from further exploration and refinement to effect
improvements.

3.6.20.4 Formal documentation is completed to reflect the design assessment and selection process and
to document the most promising design options (i.e. the highest ranking options in the COEIA).

3.6.20.5 Design Selection

3.6.20.5.1 From the functional perspective the CSM shall compare the solutions against a defined set of
criteria, such as those identified below;

a) Duplication of functionality between subsystems;

b) Degree of Subsystem autonomy;

c) Resilience to External Failures;

d) Complexity of Interfaces;

e) Complexity of Data Exchange;

f) Inter-equipment Data Rates;

g) Data Storage Requirements;

h) Size and complexity of the Resultant Subsystems;

i) Operator numbers, workload and skill levels;

j) Interoperability.

3.6.20.6 Technical Assessment

3.6.20.6.1 In support of the recommendation to the IAB it must be shown that project and programme risk
has been reduced to a manageable level that ensure successful ISD delivery. This requires the Assessment
Phase to provide a comprehensive measurement of the technical risk through scientific and technological
assessment of the candidate design solutions in terms of Technology Readiness Levels (TRLs). Such
assessment should be thorough and captured in a ‘risk register’ relating to each design. Technological
assessment will cover hardware and software areas and shall consider if:

a) The technology is available now;

b) The technology is being developed as part of another programme;

c) The technology will be developed as part of another programme, which is yet to be approved;

d) The maturity of system-wide and integration issues should also be addressed using System
Readiness Levels (SRLs).

3.6.20.7 Performance and Effectiveness Assessment

3.6.20.7.1 The achievable performance of candidate Combat System designs against MOPs can be
determined by aggregating the lower-level performance achievable by individual equipments taking into
account interworking and interference factors as necessary. The degree of satisfaction of the user
requirement MOEs will need to be ascertained either through understanding the correlation between MOPs
and MOEs or by directly assessing the achievable MOEs using Operational Analysis tools.

3.6.20.7.2 Such performance assessment is often conducted as part of an integrated approach to


performance and effectiveness assessment whereby performance measures can be defined which if
satisfied confer a level of capability, which leads to satisfaction of the Combat System effectiveness
Unclassified
70
DEF STAN 21-59 Issue 2

requirements. This serves to facilitate the specification of required system capability in performance rather
than effectiveness terms for procurement and acceptance purposes.

3.6.20.8 AR&M Assessment

3.6.20.8.1 Each candidate design solution will be subjected to AR&M assessment. AR&M prediction
techniques should be employed.

3.6.20.8.2 Design Options - If design variants are being considered, a Design Development Assessment
Option Record documents the assessment and shortlisting of variants of one or more baseline Combat
System designs. It is therefore often known as the Combat System. This document provides a historical
record of the conduct of a study which should be appended to the design options/variants record, identifying:

a) Key assumptions made;

b) Conduct of Combat System design activities;

c) Limitations of any techniques used;

d) Development of output products and other standardised documents/data;

e) Design baselines (a system baseline is the documented, approved description of the system at a
specific time) and other relevant configuration control issues;

f) Relevant discussions held, decisions taken and associated studies which have affected the conduct
or course of the study.

3.6.20.9 Interface Documentation

3.6.20.9.1 The CSM shall develop preliminary interface documentation for the Combat System. During
the Assessment Phase, this shall be limited to:

a) Operational spaces layouts for the candidate designs. Sufficient detail to confirm that it is viable to fit
the design within the platform;

b) Information Exchange Requirements. These identify the information needs of each subsystem
without the need to complete the detailed Interface Specifications (IFS) and Data Exchange
Specifications (DES).

3.6.20.10 Acceptance Documentation

3.6.20.10.1 By the end of the Assessment Phase, the ITEA Plan should:

a) Meet the maturity level expected by PR&A;

b) Embrace all of the options being presented in the Main Gate Business Case;

c) Be sufficiently robust to underpin the WLC and schedule estimates presented in the MG Business
Case;

d) Inform the SRM and Asset Delivery Schedule;

e) Be tailored to the options remaining at MG;

f) Identify risks, cost and schedule drivers;

g) Identify demands on test resources and other Government-Furnished Assets (GFA);

h) Define any further Test & Evaluation (T&E) activity to be performed prior to supplier selection (if
applicable);

Unclassified
71
DEF STAN 21-59 Issue 2

i) Address interoperability issues;

j) Define the distinction and relationship between Contract and System Acceptance.

3.6.20.10.2 BR 4050 contains full guidance on Acceptance matters.

3.6.20.10.3 Validation Criteria relate to the user requirements, concern military capability (across all Lines
Of Development) and are expressed in terms of MOEs. Verification Criteria relate to system requirements,
concern singular DLODs such as equipment provision and are typically expressed in terms including MOPs.
It is the Verification Criteria which will form the basis for System Acceptance and associated with each of the
Verification Criteria shall be the mechanisms by which the Combat System MOPs (and other system
measures) will be offered for acceptance. Acceptance may include the use of M&S techniques and, in the
case of areas of capability for which model-based acceptance is going to be employed, the validation of
those models will need to be explicitly addressed.

3.6.21 Specialist Discipline Support

3.6.21.1 A number of specialist activities which have significant downstream implications on the cost and
effectiveness of the evolving Combat System need to be considered during the Assessment Phase as
follows:

a) Air Engineering;

b) Alignment;

c) AR&M;

d) CM;

e) Cost;

f) Documentation;

g) Electromagnetic & Environmental Effects (E3);

h) Environmental Impact Assessment (see ‘Environet’ on the MoD intranet);

i) HF/Operability;

j) ILS/Supportability;

k) Installation and Ship Services;

l) Information Management, Interface/Data Management;

m) Modelling & Simulation (M&S), including Synthetic Environments;

n) Naval Architecture;

o) Operational Performance/Effectiveness;

p) Safety;

q) Security;

r) Shock and Vibration;

s) Software Development;

t) Structural Engineering;

Unclassified
72
DEF STAN 21-59 Issue 2

u) Training.

3.6.21.2 Configuration Management

3.6.21.2.1 Configuration Management (CM) is an important theme of the AMS, essential to keep track of
requirements, specification and plans which define the Combat System baseline design and the acquisition
and support processes through which it will be realised. The emphasis of CM during Assessment activities is
to enhance and develop the framework within which trade-offs can be managed effectively, whilst
enabling/retaining the flexibility to explore options and evolve solutions. Consideration is required as to how
CM will be applied and managed across the various levels of the combat system (from system-level, through
equipments to software, hardware and firmware components) and through-life. Def Stan 05-57 mandates
high level CM requirements for all projects.

3.6.21.3 Data Management

3.6.21.3.1 The contractors have to formulate and declare their "design for integration" approach, with a
detailed explanation of how information passing between systems is to be managed. The data management
standards for the definitions of application data elements, co-ordinate systems, network interfaces, network
protocols, and application protocols have to be included in their coherence specifications.

3.6.21.3.2 Convincing supporting evidence for their choices should be supplied, demonstrating their
suitability for the Combat System real-time environment. Details of the intended tool support for application
data definition, communications profile compliance testing, and interface application data testing should also
be provided. In particular, the performance and characteristics of all chosen network profiles should be
exposed in considerable detail to minimise the risk of an inappropriate choice.

3.6.21.3.3 The contractors have to formulate and declare:

a) Their overall management of the development of the inter-equipment interface specification


documentation set;

b) The way in which an equipment's compliance with the coherence specification, Data Exchange
Specifications (DES), and Interface Specifications (IFS) will be assured during Development;

c) How they will undertake related compliance testing in factory tests, thus ensuring each equipment is
"fit for integration".

3.6.21.3.4 The contractor's stage outputs are a coherence specification and a stated method of managing
interfaces. The coherence specification must be judged on its "completeness" and the credibility of the
supporting evidence for the choices therein. The management of interfaces must judged on its credibility
and its visibility to MoD during development.

3.6.21.3.5 Current standards for the definitions of application data elements, co-ordinate systems, network
interfaces, network protocols, and application protocols can be used as benchmarks to reduce the risk of a
replacement being inappropriate to the Combat System real-time environment. The consequences of
replacement standards upon interface documentation practice and upon tool support need to be carefully
assessed (i.e. application data definition tools, communications profile compliance testing tools, and
application data testing tools). An indication of the performance required from any networks should emerge
from the various modelling processes and indication of required integrity characteristics will drive from the
Combat System AR&M and vulnerability requirements. The process for the overall management and
development of the inter-equipment interface specification documentation set and its compliance testing
needs to be established.

3.6.21.3.6 These issues will impact on the costings and the risk assessment made in this phase. The results
of these investigations will be reflected in the phase outputs. The form, which they take, will depend upon
MOD's intended relationship with the competing contractors and the prevailing MoD policy on standards.
Selected standards may appear directly in the coherence specification as being mandated or preferred. The
coherence specification may merely state the areas in which standardisation is recommended (in which case
the work of this phase would be in reports and used by MoD to assess a contractor's choice). Similarly the
consideration of the management of IFS documentation and interface compliance testing may be passed to
the Assessment contractors or it may be retained by MoD for use in assessment of the contractor's
proposals.
Unclassified
73
DEF STAN 21-59 Issue 2

3.6.21.3.7 To permit effective competition for in-service and through-life activities, the MoD should ensure
that all data exchange standards are freely available to all equipment suppliers, support agencies and other
stakeholders without IPR constraints which might limit their use. This also applies to data management
support environments, test equipment, data recording & analysis equipment, data exchange specifications
and the data / information itself.

3.6.21.4 Human Factors Integration

3.6.21.4.1 Assessment Phase HF studies should include:

a) Suitability of designs in the light of HF developments over the course of the project;

b) Optimising cost trade-off between HF (including training and skill levels) against system and
subsystem designs;

c) Carrying out subsystem operability and inter-operability evolutions.

3.6.21.4.2 Embracing HF integration into Combat Systems design provides a number of benefits, including
improved technical solutions and visibility within the DPA of through life costs.

3.6.21.4.3 The approach defined in STG Publication 11, Human Factors Guide for Management and Design
in Royal Navy Combat Systems, is intended to ensure that full account is taken of the human element in
system design. Systems which are an aggravation to their users not only require huge resources to
ameliorate them, but are also highly detrimental to morale and ultimately Naval recruitment. HFI therefore
has a large impact on overall effectiveness. Historically, Ships’ Staff have had to endure system designs
which would not be tolerated in other commercial industries.

3.6.21.4.4 The Human Factors Integration Plan (HFIP) is crucial and specifies both the planning, co-
ordination and technical design work for HF and is divided into two parts:

a) Part 1 - The Management Plan;

b) Part 2 - Technical Information and Specifications.

3.6.21.4.5 The HFIP is compiled during the Concept Phase (see Human Factors) for implementation in all
subsequent phases.

3.6.21.4.6 During Assessment, the HFIP needs to be expanded and enhanced to include:

a) Review of the applicability of tools chosen during Concept Phase;

b) Cost trade-off analysis is required to validate the location of functionality within the system. The
conclusions of the HF studies require to be integrated with those of other aspects of the design.

3.6.21.4.7 Following the STGP 11 guidelines HFIP Part 1 is to be updated and HFIP Part 2 progressively
compiled.

3.6.21.4.8 Also of particular concern to the CSM at this phase of the design process is the impact of
equipment design on the operator numbers and skill levels. This has significant external effects as well as
the internal project considerations.

3.6.21.4.9 External effects include:

a) Platform considerations on accommodation size and balance between ratings/senior ratings/officers;

b) Impact on ship size, engine power, fuel, endurance etc.;

c) Impact on training/recruitment/retention and availability of training billets; effects on sea/shore ratios


and long term branch numbers.

Unclassified
74
DEF STAN 21-59 Issue 2

3.6.21.5 Operability Analysis and Assessment - The CSM shall require that, with the system design
process carried out by the competing consortia, analytic operability assessments of the candidate designs be
carried out.

3.6.21.6 Operability analysis shall be of sufficient depth to provide the following information concerning
each of the candidate designs:

a) Platform Procedures;

• Operations Areas,

• Readiness States,

• Watchkeeping Policies,

• Manning Levels/Outline Scheme of Complement;

b) User Characteristics;

• Anthropometric Dimensions,

• User Levels,

• Cognitive Capability,

• Specific Skills,

• Naval Experience and Training;

c) User Role Definition;

• Operator Positions,

• Combat System Roles,

• Combat System Role Interaction,

• External Role Interaction,

• Training Roles;

d) User Interface Standards, (to be included within the coherence specification);

• Displays,

• Dialogue Style,

• Environmental Standards.

3.6.21.7 This analysis shall be based on the operational performance scenarios described earlier in this
Section under Performance and Effectiveness Assessment. This analysis shall be carried on into D&M.

3.6.21.8 Integrated Logistic Support (ILS)

3.6.21.8.1 ILS shall be applied to all future system/equipment procurement, major upgrades, off-the-shelf
procurement etc. in accordance with Def Stan 00-60.

3.6.21.8.2 During the Assessment Phase, ILS activities include:

a) The formation of an LSA management team (if appropriate);

Unclassified
75
DEF STAN 21-59 Issue 2

b) Updating COO and WLC estimates. These should be indicative, allowing an informed judgement on
the solution, together with its support package ensuring optimum value for money;

c) Update and further refine the ILS strategy documents started during Concept Phase;

d) Conducting LSA supportability assessment tasks and in particular trade-off analysis. This will
contribute significantly to the decision on the preferred contractor;

e) Attending the bidders conference. Producing ILS ITT/Statement Of Work (SOW) for contract award
for full development.

3.6.21.8.3 Wherever practicable, demonstrations of support capabilities should occur.

3.6.21.8.4 The availability of data suitable to populate the tailored Logistic Support Analysis Record (LSAR)
will begin to arrive, maintenance policies will be emerging and remaining support risks will be being
managed.

3.6.21.9 Availability, Reliability and Maintainability (AR&M)

3.6.21.9.1 AR&M issues identified in Concept Phase outputs form the basis of Assessment Phase activities.
During the early part of Assessment, the AR&M concept panel should agree assessment criteria for marking
the AR&M sections of the full development tenders. The AR&M project panel then takes over after formal
endorsement of the URD and has many of the same members as the concept panel, but is chaired by the
IPT Leader.

3.6.21.9.2 During Assessment the contractor must:

a) Prepare preliminary AR&M plans including component selection control procedures, initial AR&M
predictions, subsystem AR&M targets, AR&M development plans, sub-contract AR&M plans, and
identified AR&M resources and costs;

b) Carry out detailed design and related AR&M activities including listing approved and non-approved
components, applying component control procedures, devising an initial critical items list and life
limited items list, applying a component de-rating policy, refining AR&M models, refining and
updating AR&M predictions, and checking design redundancy;

c) Define the AR&M strategy for full development, including planning development phase AR&M tests.

3.6.21.9.3 The terms of reference and therefore main tasks/activities of the project panel are:

a) To assist the IPTL in defining the Reliability and Maintainability (R&M) aspects of the specification
including the assessment criteria for the tender proposals and the method of gaining sufficient
assurance that the R&M requirements have been satisfied;

b) Provide suitable input to the IAB MG submission;

c) To recommend amendment or adoption of formal R&M plans, programmes and trials, prepared by
the contractor;

d) To ensure that the relevant details from these plans and programmes are included as integral parts
of the overall development cost plans;

e) To recommend verifiable milestones to monitor progress in R&M;

f) To monitor R&M aspects of the results of development and user trials and of maintainability and
testability assessments and contractor progress against achieving R&M contract requirements;

g) To agree an assessment of achieved R&M levels for acceptance purposes;

h) To enable trade-off studies between AR&M and cost to be undertaken, with the aim of striking the
optimum balance;

Unclassified
76
DEF STAN 21-59 Issue 2

i) To provide advice to both IPTL and DEC on any proposed amendments to project timescales or
targets subject to contract and cost factors. To highlight any conflict found to exist between the
various R&M requirements and detailed performance requirements, or where significant shortfalls
become apparent, and to discuss the in-service effects of any amendments;

j) To assess the results of in-service R&M demonstrations, where these are called for as part of the
Acquisition or Procurement Strategy.

3.6.21.9.4 The costs associated with AR&M activities require to be fed into the cost trade-off analysis as
other results of the design activities.

3.6.21.9.5 The outputs from the AR&M activities form inputs into ILS. AR&M is a key input into the IAB
submission documents.

3.6.21.9.6 The Reliability and Maintainability (R&M) Panel performs the following functions:

a) Analysis of environmental and operating (mission) conditions;

b) Definition of the maintenance concept and support constraints;

c) Investigates AR&M contracting strategy and demonstration methodology;

d) Reviews AR&M assessments, predictions and trade-off studies conducted by the consortia;

e) Refines AR&M requirements and their numerical values, environmental and operating
conditions for inclusion in the SRD.

3.6.21.9.7 R&M studies are undertaken within other life cycle processes (principally in system design and
design assessment and selection) concentrating on analysis, design for R&M, and prediction/assessment
(hardware and software). Trade-offs between AR&M, performance, cost and in-service date are conducted.
The results of such investigation feed into the COEIA and then into the MG Business Case.

3.6.21.10 System Security

3.6.21.10.1 Security is normally considered as a platform-wide subject. However, only the Combat System
aspects are addressed here. Security can have a profound impact on the Combat System design, for
example concerning the adoption of COTS technology.

3.6.21.10.2 During the assessment Phase the regular liaison initiated during the Concept Phase with the
DSSO Accreditor should continue.

3.6.21.10.3 The system security issues shall be fully addressed by the CSM who shall provide the
Accreditor with a plan as to how and when the Accreditation Document Set (ADS) will be provided either by
the IPT or the competing consortia e.g. by provision of :

a) An InfoSec scoping appraisal;

b) A draft System Electronic Information Security Policy (SEISP);

c) A draft Security Operating Procedure (SyOPs).

3.6.21.11 System Safety

3.6.21.11.1 The adoption of a safety case procedure is a mandatory requirement for all future warships. It
is required to encompass both platform and Combat System aspects.

3.6.21.11.2 The safety cells within MoD offering advice on system safety and software safety is DOSG.
See JSP 430 Annex F - Specialist Authorities for Ship Hazard Areas.

Unclassified
77
DEF STAN 21-59 Issue 2

3.6.21.11.3 The “SAFETY CASE” - The adoption of a safety case management procedure is now a
mandatory and legal requirement on all IPTLs and projects. It is required to encompass both platform and
Combat System aspects.

3.6.21.11.4 For systems which will contain Ordnance, Munitions & Explosives:

a) JSP 520 Pt 1 – OME Safety Management System;

b) JSP 520 Pt 2 - Operational Procedures;

3.6.21.11.5 The Defence Ordnance Safety Group (DOSG) is now part of the TES organisation. The web
site: www.ams.dii.r.mil.uk/content/docs/dosgweb contains further guidance.

3.6.21.11.6 For issues concerning Platform safety, the DOSG Technical Support (DOSGTS) Safety
Management Office (SMO) should be consulted. Relevant standards are as follows:

a) Ships – JSP 430;

b) Air – JSP 553;

c) Land – JSP 454.

3.6.21.11.7 The procedure required to generate the ‘Safety Case’ is described in the AMS

3.6.21.11.8 The mandated procedures are contained in:

a) POSMS – Project-Oriented Safety Management System;

b) POEMS – Project-Oriented Environmental Management System.

3.6.21.11.9 The safety case serves to demonstrate that the whole warship meets agreed safety objectives.
It should ensure that a clear audit trail exists from design through procurement, operator and upkeep to
disposal. In addition, a summary of the safety case, known as the safety case report, is prepared to assist in
the reviewing of performance and the provision of authority to proceed to the next phase of the life cycle.

3.6.21.11.10 The CSM shall require each competing consortium to produce a safety case for their proposed
warship Combat System solution. This shall be produced in accordance with JSP 430.

3.6.21.11.11 After selection of the Combat System solution, but still during Assessment, the CSM shall
update and re issue the Combat System safety case in accordance with JSP 430 - Ship Safety Management
System Handbook.

3.6.21.11.12 The CSM should assure himself of the following as a minimum during the Assessment Phase:

a) No significant changes have occurred in legislation or in related documents that mandate a change
in the safety policy for the Combat System;

b) No significant additional tools or methods have become available in the interim since the start of the
Assessment Phase that would ease the task of safety validation;

c) That all the consortia are giving the correct emphasis to ensuring that the system will not do
something unsafe but also that when required it will fulfil its defined function.

3.6.21.11.13 The cost and timescale implications of the need for high integrity safety critical software, and
the standards, against which it is to be identified and developed, need to be reviewed. These standards are
available from the Director of Standardisation, www.dstan.dii.r.mil.uk.

3.6.21.12 Data Management

3.6.21.12.1 The CSM shall produce the Combat System data management policies to manage the digital
and analogue data interfaces within the Combat System. When developing these policies the CSM shall
take into account that these polices are to be applied to:
Unclassified
78
DEF STAN 21-59 Issue 2

a) New subsystems - can be applied in total;

b) Modified subsystems - can be applied if change is cost effective;

c) Un-modified subsystems - can only be applied if change is cost effective and may well define what
polices can be implemented.

3.6.21.12.2 Advice should be sought from current practitioners in this specialised field. For those with
access to the MoD Intranet, www.fdm.dii.r.mil.uk provides further reading.

3.6.22 ITT for Development and Manufacture

3.6.22.1 The CSM shall ensure that the MoD intention to issue an ITT for development and manufacture is
included in the MoD contracts bulletin in accordance with the departmental procedures.

3.6.22.2 During the Assessment Phase, the CSM team, including the commercial and finance functions,
shall prepare the ITT for development and manufacture.

3.6.22.3 The IPT Commercial Officer will issue the ITT for development and manufacture.

3.6.22.4 Tender Selection

3.6.22.4.1 The CSM’s task is to ensure that the competing consortia, and particularly the lead contractors,
have properly assessed the scope of the Combat System development and are suitable organisations to
undertake the contract. The CSM’s tasks are to effect:

a) Contractor Assessment;

b) Risk Assessment;

c) Requirements Compliance;

d) Refinement of the COEIA.

3.6.22.4.2 Further details on tender assessment can be found on the AMS.

3.6.22.5 Contractor Assessment

3.6.22.1 The CSM should undertake an assessment of the potential prime contractors to ensure that they
have the financial stability necessary to undertake the contract with all its attendant risks.

3.6.22.2 The CSM should require that the competing consortia conduct similar assessments of their
potential sub-contractors. The CSM shall require that the results of such assessments be provided to assist
in the assessment of the potential prime contractors.

3.6.22.3 Contractors who fail to convince the CSM of their suitability as a prime contractor should not be
provided with the ITT for D&M. This is a very contentious issue and the advice of director of contracts should
be sought at all times.

3.6.22.4 Down selection of competing consortia can occur at any point in the assessment process unless
this would leave a single tender situation with outstanding points of clarification. Final down selection should
not occur until the CSM has finalised all points of clarification.

3.6.22.5 In a competitive situation, the CSM shall avoid cross fertilisation of the details of the solutions
proposed by the competing consortia.

3.6.22.6 Risk Assessment

3.6.22.6.1 CSM shall produce a project risk assessment in accordance with the Contract Management Plan
(CMP) for Assessment. This assessment can draw on, but must not be limited to, the risk assessments
produced by the competing consortia.
Unclassified
79
DEF STAN 21-59 Issue 2

3.6.22.6.2 The CSM’s risk assessment shall include the risks associated with the installation and integration
of the Combat System within the platform. As a rule, the competing consortia are usually unable to address
this aspect of the risk assessment to sufficient depth.

3.6.22.7 Requirement Compliance

3.6.22.7.1 The CSM shall assess the degree of compliance offered by the competing consortia against the
RDB/acceptance database. This assessment shall include:

a) Management Proposal;

b) Technical Solution;

c) Software Architecture, Development Process, Metrics and Progress Monitoring;

d) Performance Assessment;

e) AR&M Assessment;

f) Shipfit Aspects;

g) Compliance with Standards;

h) Integration, Test and Trials Process;

i) Acceptance Philosophy;

j) External Dependencies;

k) Any other commercial factors (e.g. IPR issues).

3.6.22.7.2 If in doubt, the CSM must seek clarification from the competing consortia, rather than make an
assumption.

3.6.22.8 Problems with Lowest Cost Compliancy

3.6.22.8.1 If one system is significantly cheaper than another, then the CSM must question why.

3.6.22.8.2 Once the CSM has established this, he can then advise properly on the final choice of the Combat
System. If it is not possible to determine why a particular bid is cheaper than another is, there is may be a
significant risk to the project.

3.6.22.8.3 There may be many reasons why consortium may produce a low price for a system. Included are:

a) More efficient solution and/or better technology;

b) Lower profit margins than competitors;

c) Lower labour rates than the opposition;

d) Lower corporate overheads;

e) Willingness to accept lower contingency for risk;

f) Under-estimate of scope of task;

g) Over-estimate of scope of task by competitors;

h) Deliberate loss leader for related business and/or subsequent anticipated profitable changes to
specification. This would be common where the platform and Combat System were both being bid
for by the same consortium;
Unclassified
80
DEF STAN 21-59 Issue 2

i) Profits in other sales e.g. exports.

3.6.23 SRD Production

3.6.23.1 Initial Preparation of SRD

3.6.23.1.1 Initial drafting of the SRD may be conducted in parallel with the work of the competing
consortia during assessment Phase activities.

3.6.23.2 SRD Drafting

3.6.23.2.1 The draft SRD will pass through a number of drafts and iterations before issue. Industry should
be permitted to comment on its contents.

3.6.23.3 SRD Completion

3.6.23.3.1 The SRD is generally produced on a whole warship level, being compiled from the Combat
System and platform-related drafts. Harmonisation of material and re-drafting/answering of specific
comments can be expected as the draft passes through progressively higher level review.

3.6.24 Assessment Phase Consolidation

3.6.24.1 Introduction

3.6.24.1.1 Two competing consortia will most likely conduct the Assessment Phase. Each consortium will be
working in isolation from the other although each may be utilising common subcontractors (particularly for
mandated equipments). The IPTL and his team will work to ensure that each consortium is provided with
appropriate information and access to expertise.

3.6.24.1.2 To minimise risk and to ensure the cost of the Assessment Phase is kept to budget, the IPTL will
not be in a position to alter the scope of the task during the Assessment Phase.

3.6.24.1.3 On completion of the Assessment Phase, the IPTL will receive a complete set of the output
products from each consortium. These outputs should be a complete and very comprehensive design of the
Combat System.

3.6.24.1.4 During the consolidation period the two designs and their associated costs are assessed and then
a firm/fixed price contract is awarded to one of the two consortia to proceed to the development and
production stage with their design and programme.

3.6.24.1.5 The CSM will have estimated the resource required to complete consolidation and identified the
specialist resources necessary in the Assessment Phase MoD CMP, as part of the submission for the
Assessment Phase.

3.6.24.2 Development and Manufacture Stage Input

3.6.24.2.1 During consolidation all the documentation for a properly structured contractually binding input to
the development and production stage has to be defined. Many of these will be based upon the products of
the Assessment Phase.

3.6.24.2.2 The inputs to development and production assume that the chosen consortium will implement
their design from Assessment.

3.6.24.3 Consolidation Stage

3.6.24.3.1 The aims of the consolidation stage are as follows:

a) To assess the two consortia's offerings and to select a winner;

b) To provide a comprehensive assessment of risk (for MoD use);


Unclassified
81
DEF STAN 21-59 Issue 2

c) To develop the MG Business Case in order to get funding approval for the D&M Phase;

d) To incorporate MoD initiated changes to requirements, scenarios, contractual, financial, or


procedural aspects;

e) To incorporate impact of the platform design evolution;

f) To formally publish the User and System Requirements Documents;

g) To provide details of the scope of and the programme for the acceptance process;

h) To identify a preferred contractor;

i) To de-brief the failing consortia on the reasons for their rejection;

j) Identify the capabilities and resources required within the MoD for the succeeding D&M Phase.

3.6.24.3.2 Timescale - The consolidation stage will have a realistic minimum duration dependent on the
number of appropriately skilled personnel available and the work to be carried out. Early completion is to be
encouraged otherwise the consortia may be forced to disband their teams and assign them to other work,
thereby prejudicing the validity of their bids.

3.6.24.3.3 There is no reason why the consolidation stage cannot start before the Assessment Phase
completes. With phased deliverables from consortia there will be a large amount of data for early work to
progress.

3.6.24.3.4 Tasks - During consolidation, the CSM is to make no major adjustments to the designs but he is to
ensure that the consortia have included everything that is needed. The CSM shall also ensure that
commercially sensitive information from one consortia is not revealed to the other. The documents must
properly describe the total Combat System, contain its development and integration programme, and supply
the cost information for the design.

3.6.24.3.5 The prime task of this stage is the assessment of outputs from the consortia. Prior to the
commencement of this assessment, the CSM must have developed a comprehensive marking scheme to be
used in the process. The scheme must be fair and objective; it provides the justification for selecting the
winning consortia and for rejecting the losing consortia; it will be the main source of information for de-
briefing the losing consortia; it must withstand close scrutiny if the losing consortia challenge MOD's
decision.

3.6.24.3.6 Following the identification of the preferred consortium, all the necessary contractual
documentation for the next phases must be prepared. This will also involve some negotiations with the
chosen consortium.

3.6.24.3.7 It may be necessary for the CSM to incorporate MoD initiated changes to requirements, scenarios,
contractual, financial, or procedural aspects or to incorporate the impact of the platform design evolution. In
both cases this might involve renegotiating the price offered by the preferred consortium when they
submitted their costs for providing the Combat System.

3.6.24.3.8 Another task to be completed is preparing the submission for funding for the next two stages, the
winning consortia's cost estimates will be one of the inputs, the CSM will have to make a judgement of any
contingency required and any other costs that may be incurred which are not the consortia's responsibility.

3.6.24.3.9 The CSM must identify the programme of work, size, and make-up for the MoD team for the next
two stages along with any supporting resources (e.g. computers, accommodation). He will also have to
generate the MoD CMP to cover these stages.

3.6.24.3.10 Consolidation Stage Team –

The PM should set up a team that encompasses the following functions:

a) CSM;

Unclassified
82
DEF STAN 21-59 Issue 2

b) Technical Co-ordinator (including system modelling and acceptance expertise);

c) Project Planning;

d) Risk Specialist;

e) Requirements Manager;

f) Administrative Co-ordinator;

g) Software Specialist;

h) ARM Specialist;

i) ILS Specialist;

j) Quality Specialist;

k) Safety Specialist;

l) Security Specialist;

m) Commercial Officer;

n) Finance Officer;

o) Secretarial Assistance.

3.6.24.3.11 If any personnel are seconded or contracted from industry there must be confidentiality
agreements and suitable arrangements to ensure that there will be no conflict of interest.

3.6.24.4 Outputs from the Consolidation Stage

3.6.24.4.1 Internal Review Documents - Objective and subjective evidence should be gathered into the SDE
to provide the audit trail for prime contractor selection and MG submission. With the complexities of modern
procurement it is considered that all suitable data is collected to assist in the correct eventual decision. With
the very best contract staff in the world the selection process will still involves an element of "can we trust the
contractor to do what he has promised?".

3.6.24.4.2 With the prospect of more than one IPTL and many team members over the lifetime of the
Combat System evolution it is important that the relationship of trust is built up and documented during the
project.

Unclassified
83
DEF STAN 21-59 Issue 2

This page intentionally left blank

Unclassified
84
DEF STAN 21-59 Issue 2

Systems Engineering Guide for Naval Combat Systems –


Demonstration and Manufacture Phase

4 Demonstration and Manufacture Phase

4.1 Introduction

4.1.1 Demonstration and Manufacture phases are rarely serial activities, particularly in a complex system
acquisition where they are hugely interdependent. Therefore this document addresses D & M phases
together. In addition Integration, Test and Trials activities are supportive of Demonstration, Manufacture and
In Service phases and are covered therefore in a separate section. At the commencement of the D&M
Phases, a Combat System design will have been proposed either through the previous Assessment Phase
(AP) phase or as part of the tender for a whole warship design and build contract.

4.2 Purpose of the Demonstration and Manufacture Phase

4.2.1 The purpose of the D&M phases is to de-risk and co-ordinate the realisation of the proposed system
design. This is achieved through the acquisition of subsystem and equipment components which can be
integrated together to provide the required system functionality and performance.

4.2.2 The objective of these phases is to realise a design of the Combat System that will satisfy CONEMP
, URD and SRD and to further the arrangements necessary to meet all Lines of Development (LODs) when
in-service.

4.2.3 The Shift in Emphasis

4.2.3.1 In terms of the Combat System as a whole, the D&M Phase is typified by a shift of emphasis, from
the ‘top-down’ system design perspective, to a ‘bottom-up’ implementation perspective. This is illustrated in
Figure 4.1 which depicts the shift in emphasis compared to previous phases.

4.2.3.2 During Concept and Assessment Phases, the main thrust is to explore and define the system in
terms of its operational need, ensuring that the system-level requirements are reflected by lower level
subsystem and equipment performance. During these phases, lower level subsystem and equipment design
characteristics (such as functionality, physical implementation constraints and performance) are predicted or
quantified using representative data generated from modelling and prototyping activities.

4.2.3.3 Once the Combat System design baseline is established at the end of Assessment Phase/early in
the demonstration and manufacture phase, the acquisition process can commence in earnest. As
subsystems and equipments become available for integration, actual subsystem and equipment
characteristics will be confirmed through test and evaluation.

4.2.4 System Design and System Implementation Perspectives

4.2.4.1 The ‘top-down’ system design perspective is appropriate when considering change to the system
requirement and assessing potential impact on the system design. This perspective, through which the
requirements engineering, system analysis and system design elements remain key, applies when
considering changes to the system. During these phases, system design activities are expected to be strictly
contained. Changes to the requirement arising from operational or implementational issues must be
investigated through the formal Systems Engineering (SE) process as for previous phases.

4.2.4.2 The ‘bottom-up’ perspective becomes increasingly prominent during the implementation of the
system design. This is manifested through the need to assess, manage and co-ordinate the characteristics
of subsystem and equipment components as they are acquired, developed and produced. The
‘implemented performance’ of individual subsystems and equipments must be considered in terms of overall

Unclassified
85
DEF STAN 21-59 Issue 2

system performance and actions taken to ensure that system-level objectives and requirements can be met.
This is the prevalent perspective during this and the following/related integration, test and trials.

SYSTEM DESIGN SYSTEMS ENGINEERING PROCESS SYSTEM IMPLEMENTATION

The emphasis of System Design The SE process ‘drives’ system design and implementation The emphasis of System
SE Process Implementation is ‘bottom-up’,
is predominantly ‘top-down’, SD through Requirements Engineering (RE), Systems Analysis
considering system level issues SA (SA) and System Design (SD) activities. These define the assessing and managing the
and how these can be RE system design to progressively lower levels of detail. System characteristics of equipment
addressed by subsystem and Studies (SS) and Documentation Production (DP) support the components as they are acquired,
equipment implementation. investigation of system characteristics and documentation of developed and produced.
SS DP the design.

COMBAT SYSTEM COMBAT SYSTEM


Requirements Acceptance

SUBSYSTEMS The ‘implemented performance’ of SUBSYSTEMS


Analysis/Design Integrate/Test individual subsystems and
equipments must be considered in
terms of overall system
Acquire Equipment performance and actions taken to
ensure that system-level
EQUIPMENTS objectives and requirements can EQUIPMENTS
be met.

CONCEPT ASSESSMENT 1 ASSESSMENT 2 DEVELOPMENT and INTEGRATION TEST and


MANUFACTURE TRIALS

The emphasis of the System Design perspective dominates in the early stages of the Following contract award for D & M, there is a
Life Cycle since the design is being ‘driven’ at the system-level. Information relating to change in emphasis towards the System Implementation perspective. This
predicted performance of constituent (candidate) subsystems and equipments is used change of emphasis continues through Integration Test and Trials up to
to predict overall system characteristics. Combat System Acceptance.

Figure 4.1 Shift in Emphasis of Demonstration and Manufacture

4.2.4.3 Both perspectives can be expressed through the application of the generic SE process introduced in
Section 1. The system implementation perspective, which is the dominant view during this phase, invokes
general SE and project management activities, supported through system studies and documentation
production.

4.2.5 Demonstration and Manufacture Phase Activities

4.2.5.1 Combat Systems engineering during these phases is mostly concerned with managing the
relationship between the ‘top down’ system design perspective, driven by whole system requirements, which
is imposed on the ‘bottom-up’ system implementation, typified by the real world characteristics of subsystem
and equipment components. This is in order to achieve the optimum compromise through trade-offs
between what is required and what is actually possible under the prevailing circumstances.

4.2.5.2 The elements of the core process within its wider SE context are developed as the basis for the
demonstration and manufacture phase process as illustrated in Figure 4.2. This shows the life cycle
activities of particular importance during this phase in relation to key inputs and outputs.

Unclassified
86
DEF STAN 21-59 Issue 2

Combat System
DEVELOPMENT and MANUFACTURE

SYSTEMS ENGINEERING (TECHNICAL)


and PROJECT MANAGEMENT
Equipment for Integration
in Shore Facilities
Models & Simulations DESIGN CHANGE in FOC Vessels
MANAGEMENT in Follow-on Vessels
Cost Models in Training Facilities
Effectiveness Models
Functional Models COMBAT SYSTEM
Architectural Models LIFE
CYCLE DEVELOPMENT
HCI Simulations PROCESS
AR&M Analyses FACTORS
SUBSYSTEM/
EQUIPMENT FDP

ACCEPTANCE

SYSTEM STUDIES

INTEGRATED LOGISTIC SUPPORT


Key Documents
Contract Documentation DOCUMENTATION Supporting Documentation
Management Plans Equipment Design Information
Requirements Database SPECIALIST DISCIPLINE SUPPORT Equipment Test, Trials &
System Design Acceptance Information
Documentation Equipment Operation & Support
CONFIGURATION MANAGEMENT
Information
Acceptance Documentation

Figure 4.2 Demonstration and Manufacture Phase, Overall Process

4.2.5.3 Combat System demonstration and manufacture activities are summarised as follows:

a) Systems Engineering (Technical) and Project Management - the over-arching management process
addressing contract, risk, quality, project and SE aspects throughout these phases;

b) Life Cycle Process Factors - anticipation of the needs of downstream activities, such as preparation
for the integration, test and trials activities, liaison with the platform design process and Through Life
Management;

c) Design Change Management - effective management of change and impact assessment against
Combat System design baselines;

d) Combat System Development - influence across equipment/subsystem and platform programmes to


maximise the achievement of Combat System-level objectives and requirements;

e) Subsystem Equipment Development and Manufacture - visibility of the acquisition of


subsystem/equipment components including the selection of existing equipment and demonstration
and manufacture of new or modified equipments;

f) Acceptance - progressive generation and review of acceptance evidence to predict compliance with
the requirements and provide confidence that the implementation is proceeding according to plan;

g) System Studies - modelling, simulation and related analyses supporting evaluation of the evolving
design implementation, assessment of engineering trade-offs and a basis for the investigation of
change;

h) Integrated Logistic Support - co-ordination of Integrated Logistic Support (ILS)/ Logistic Support
Analysis (LSA) activities associated with the demonstration and manufacture of Combat System
components;

Unclassified
87
DEF STAN 21-59 Issue 2

i) Documentation - maintenance of key documents used to co-ordinate the detailed design of the
Combat System, and the demonstration of lower-level documents defining the implementation;

j) Specialist Discipline Support - integration of engineering and support specialist disciplines within the
SE process;

k) Configuration Management - implementation of the regime through which all demonstration and
manufacture products are controlled and co-ordinated.

4.2.6 The Transition from Demonstration and Manufacture to Integration, Test and Trials

4.2.6.1 The early life cycle phases (Concept and Assessment) are discrete phases typified by a distinct
transition from one phase to the next. This is not the case for the latter phases where there is seldom a
distinct single boundary between what are effectively notional phases.

4.2.6.2 From the system perspective, the transition between demonstration and manufacture, and related
integration test and trials is the series of events associated with the delivery of subsystems and equipments
for integration. Though this is not necessarily a specific milestone in overall Combat System programme
terms, it is a convenient point by which to separately discuss issues associated with acquisition and
integration.

4.2.7 Platform Integration

4.2.7.1 The Combat System cannot be considered in isolation. The integration of the Combat System
components into the platform is a major facet of the system demonstration process, which has to be
considered throughout all design and integration activities. This includes:

a) The realisation of the installed Combat System components in terms of their physical characteristics
(e.g. size, shape, weight, service requirements);

b) The interactions between the Combat System and the platform which characterise the warship as a
fighting unit (e.g. blind arcs, alignment);

c) The interactions between the Combat System components themselves (e.g. mutual interference,
interfaces, physical arrangements).

4.2.7.2 The progressive integration of equipments into a coherent system, where the system comes together
as a whole, is treated as a subject in its own right in Integration, Test, Evaluation and Acceptance.

4.3 Inputs

4.3.1 Inputs from Previous Phases

4.3.1.1 Inputs to the demonstration and manufacture phase include all the output products generated from
the previous Assessment Phase or equivalent pre-contract work undertaken in support of responding to an
ITT including:

a) Systems Engineering Management Plan (SEMP);

b) User Requirements Document (URD);

c) Systems Requirement Document (SRD) possibly in the form of the contractual SRD agreed between
the IPTL and the preferred contractor; the SRD should also include associated acceptance /
verification criteria that need to be addressed in the ITEAP; the proposed Combat System Design
including Subsystem Specifications, Coherence Specifications, Interface Documentation, Design
Policy Papers;

d) Integration, Test Evaluation and Acceptance Plan (ITEAP);

e) Through Life Management Plan (TLMP);

Unclassified
88
DEF STAN 21-59 Issue 2

f) The contract;

g) Training Needs Analysis;

h) Combat System Safety Case;

i) Models supporting the Combat System definition from a number of complementary perspectives
including: functionality, Human Factors (HF), architectural performance, installation, Availability,
Reliability and Maintainability (AR&M) and operational effectiveness.

4.3.1.2 The Combat System Manager (CSM) will inherit the documentation from the previous phases (where
applied) and this can be used as the basis of the project file for the Demonstration and Manufacture Phases.
Arrangements need to be made to share and manage documentation development between MOD,
contractors and equipment sub-contractors (and if appropriate partners).

4.3.2 Inputs Associated with Contract Placement

4.3.2.1 The contractual basis for D&M is centred on the result of negotiations between the procurement
authority and the Combat System Integrator (CSI) organisation (considered later under the heading
‘Organisation’ (4.5 Organisation)) (Note: This may be part of the prime contractor’s organisation.). Advice
should be sought from the relevant contract authority.

4.3.2.2 The actual coverage, form and content of the requirements and acceptance criteria may vary
according to the contracting regime and the level of agreement between the procurement authority, the
Combat System Integrator and the supplier organisations (described under ‘organisation’).

4.3.2.3 Documentation developed as part of the Assessment Phase or earlier will have to be reviewed in
order to align the proposed design with the negotiated requirements and acceptance baseline by both the
MoD and the successful contractor. Care must be taken to both ensure commonality between MoD and
industry baseline data and identify any variation in requirements, which may impact on system performance.
Some consolidation will be necessary to ensure that the negotiated contract baseline for demonstration and
manufacture is related back to the requirements definition in terms of any technical changes agreed through
the clarification and negotiation process prior to contract award.

4.4 Outputs

4.4.1 There is a range of output products arising from the D&M Phase. The deliverables from the
equipment demonstration/acquisition process can be grouped into:

a) Equipment sets for integration and installation on vessels and in shore establishments (and trainers)
together with supporting test equipment where necessary;

b) Design, demonstration and manufacture information, including demonstration and manufacture


plans, specifications and drawings;

c) Equipment test, trials and acceptance information including test and integration documentation
(including ship fitting/services data), trials plans, specifications and schedules, and equipment
Acceptance criteria and Results;

d) Equipment operation and support information including Master Record Index (MRI) data,
Configuration Management (CM) documentation, technical publications, upkeep documentation,
Logistic Support Analysis Record (LSAR) and operator/maintainer training documentation.

4.4.2 Additionally, there are many output products, which are maintained from previous phases and
extended as a result of system demonstration. These can be grouped under the following headings:

a) Management plans;

b) Requirements and acceptance data;

Unclassified
89
DEF STAN 21-59 Issue 2

c) System functional and performance models used for tracking the Combat System design and to be
used in support of aspects of system assessment, optimisation and acceptance. These are provided
together with analysis reports detailing the results and recommendations of investigations such as
change impact, actual performance shortfalls etc.;

d) Integration test plans, schedules and specifications in preparation for the subsequent integration
activities;

e) System test, trials and acceptance information including trials plans, specifications and schedules,
and system Acceptance Criteria and results;

f) System operation and support information including MRI data, CM documentation, technical
publications, upkeep documentation and LSAR.

4.4.3 All items will be produced, maintained and controlled as an inherent element of the system baseline
design description under the appropriate CM procedures. This may be controlled and coordinated through a
central platform-oriented information infrastructure or at the Combat System level depending on the contract
regime.

4.5 Organisation

4.5.1 Organisational Roles

4.5.1.1 The division of responsibilities between MoD and industry organisations is necessarily dependent
on the outcome of negotiations for the D&M contract and is commensurate with the level of risk accepted by
industry. There is therefore no absolute model, which defines the boundary of responsibilities and illustrates
all variations.

4.5.1.2 D&M involves a number of organisations each of which have distinct roles to play in the
demonstration of the Combat System as an enterprise, as depicted in Figure 4.3 also shows various
enterprise options for allocating responsibilities between MoD and Industry.

4.5.1.3 Though the actual boundary of responsibilities is negotiable within the prevailing procurement
regime, the roles are generally well understood. They are as follows:

a) End User, or customer of the system, in this case the Royal Navy with a nominated “Customer 2”,
represented through the DCDS (EC), with a nominated “Customer 1 and his requirements manager”,
CSA, FOSM, FOSF and Dstl organisations. During the D&M Phase, end-user involvement is
managed through the procurement authority;

b) Procurement Authority, in all cases the MOD, and including Combat System (CSM’s core team),
whole warship (platform project manager), and equipment (Equipment Project Manager (EPM))
representation;

c) Warship Integrator, responsible for overall management of the whole warship programme in a prime
contract setting;

d) Combat System Integrator, responsible for the design, demonstration, manufacture and integration
of the Combat System, defining its constituent equipments and overseeing their acquisition,
installation, integration and acceptance;

e) Platform Design Authority, responsible for the design, demonstration, manufacture, integration and
acceptance of the platform structure and systems. The platform design authority is responsible for
installation and integration of Combat System equipments on board the platform;

f) Equipment Supplier, responsible for developing, modifying, producing and supplying equipment and
associated design, test and support documentation.

Unclassified
90
DEF STAN 21-59 Issue 2

COMBAT SYSTEM ACQ POLICY


END-USER
ORGANISATION Prime Design
Contract Agency Partner/Alliance
CS Integ’n Equipment
Authority Oriented

PROCUREMENT AUTHORITY
Whole Warship

Marine Combat
Engineering Propulsion Platform System MOD

Development &
Production
Contract

WHOLE WARSHIP
INTEGRATOR

MARINE
PROPULSION
PLATFORM DESIGN COMBAT SYSTEM
AUTHORITY INTEGRATOR Industry

Equipment Equipment for


Contracts Integration

PROCUREMENT EQUIPMENT
AUTHORITY SUPPLIERS

Figure 4.3 Demonstration and Manufacture Organisational Relationships

4.5.2 Contractual Arrangements

4.5.2.1 The roles above are defined to set organisational issues in perspective. Inevitably there is much
room for negotiation of roles and responsibilities given a particular contractual context and there are a variety
of possible arrangements under which the demonstration and manufacture phase can be progressed:

a) Under the auspices of a Prime Contract for a whole warship procurement (e.g. T45, LPH, LPD(R),
Astute). In this case, MoD involvement is at the highest level of project management, dealing with
an industry prime contractor through a formal contractual relationship. MoD control of SE activities is
through ‘hands off’ management of the whole warship/CSI organisations. The main MoD
responsibilities under prime contractor arrangements are monitoring and reviewing progress,
identifying and tracking risk, promulgating change, and agreeing acceptance mechanism;

b) As a Combat System Integration Authority with Industry assuming the role of CSI (e.g. as originally
proposed for the S&T Update Final Phase WSIA). This arrangement is applicable to Mid Life
Updates (MLUs) where the Combat System enhancements are significant and platform modifications
required are minimal;

c) As a Design Agency, in support of the MOD(DPA) (e.g. S&T Update Initial Phase WSA, Vanguard
CSDA). This permits MoD to control the procurement of principal equipments, which contribute to
the Combat System capability and devolve the day-to-day SE activities to industry;

d) Other Equipment-Oriented Combat System projects still in existence (e.g. T23, T42, CVSG) have
inherited organisational set-ups based on MoD equipment procurement approaches. For these
projects, MoD have generally taken full responsibility for procurement and integration of individual
equipments;

Unclassified
91
DEF STAN 21-59 Issue 2

e) MoD and Industry Partnerships, sometimes branded as an ‘Alliance’, where MoD and Industry work
together, provide an alternative approach. Involvement of MoD and industry in trade-offs throughout
the life cycle to optimise the application of SE practice although it is not clear how partnership will be
effected across contractual boundaries.

4.5.2.2 The actual contractual arrangement, which comes into place, is largely dependent on the
procurement strategy invoked and the boundary of responsibilities negotiated between the MoD and
industry. In each case, the primary responsibilities are to put in place a controlled, coherent and co
coordinated process for managing the range of SE tasks to be undertaken.

4.5.2.3 The main focus of this section from an organisational point of view is the procurement organization
where design authority has been vested to industry though an appropriate contract. Note: Organisational
considerations are subject to reporting structures, which will vary and are currently under review.

4.5.3 Whole Warship

4.5.3.1 The Warship Project Manager (WPM) is responsible for the warship project as a whole,
coordinating marine, platform and weapon system engineering activities and any foreign participation which
may be required. The CSM needs to report to the WPM on a regular basis and maintain a close liaison with
members of the WPM’s team in order to effectively manage all issues arising from the Combat System and
platform interaction.

4.5.4 Combat System

4.5.4.1 Though the primary role of MoD during this phase is as an informed customer applying ‘hands off’
project management and overall direction to the Combat System implementation project, the wide variety of
potential high-risk issues demand an appropriate level of SE capability and well directed scope in terms of a
CONEMP and URD.

4.5.4.2 The MoD Combat System core team must be capable of supporting the management functions to a
level appropriate to the size and complexity of the Combat System project, typified by the following roles:

a) CSM, responsible for the project as a whole;

b) Technical Co-ordinator, responsible for controlling and directing the multi-disciplinary team and
monitoring and reporting of the technical quality of the work;

c) Administration Co-ordinator and Planner, responsible for advising the CSM of progress against
budget and schedule and associated planning activities;

d) Quality Assurance (QA) Manager, responsible for ensuring that appropriate quality control processes
are in place both in the MoD and within the contract organisation;

e) Specialist Subcontractor/Customer ‘friend’ providing technical and administrative support throughout


the phase where needed;

f) Contracts and Finance support;

g) Customer 1, 2 and Requirements Manager.

4.5.5 Equipment Supply

4.5.5.1 The equipment supplier will enter into a contractual relationship with the Combat System integrator
in order to provide their equipment and associated deliverables according to an agreed programme. The
involvement of EPMs, responsible for particular equipment selected for inclusion in the Combat System is an
important consideration.

4.5.5.2 Whilst it is important that the CSI can exert influence over the equipment supplier to ensure visibility
of the equipment design and provide evidence of progress, there may be limitations. The precise
arrangements on the Combat System/equipment supplier contract will depend on:

Unclassified
92
DEF STAN 21-59 Issue 2

a) Whether the equipment is legacy/Non Demonstration Items (NDI), Commercial Off The Shelf
(COTS), new or modified and the extent of demonstration required to meet the
equipment/subsystem requirement;

b) The level of commercial agreement achievable between the parties;

c) The underlying requirement which led to the equipment being developed in the first instance. This
may be market-led, MOD-driven, or determined from non-UK influences such as EU initiatives or US
DoD policy;

d) The significance of the equipment in the Combat System design (i.e. the number and complexity of
its interfaces with other equipments and its contribution to overall Combat System functionality,
performance and effectiveness);

e) The Combat System programme;

f) Whether or not the item is Government Furnished Equipment (GFE).

4.6 Demonstration and Manufacture Phase Processes

4.6.1 Introduction

4.6.1.1 The division of responsibilities between the CSM and contractor organisations is dependent on the
outcome of negotiations for the demonstration and manufacture contract and is commensurate with the level
of risk accepted by the contractor. The boundary of responsibility identifying which activities are assigned to
the CSM organisation and which are assigned to the contractor organisation must be clearly established in
relation to the positions agreed by both parties. This should be documented in the suite of management
plans as discussed under the section on SE (Technical) and project management. Clearly there is much
scope for variation between contracts and the implementation of the generic process must be tailored to
reflect prevailing project circumstances.

4.6.2 Demonstration and Manufacture Phase Activities

4.6.2.1 The primary activities which are to be undertaken during the Demonstration and Manufacture phase
are depicted in Figure 4.4 and described in detail in the clauses which follow:

Unclassified
93
DEF STAN 21-59 Issue 2

SYSTEMS ENGINEERING (TECHNICAL) Contract Management Risk Management Quality Management Project Management
and PROJECT MANAGEMENT Systems Engineering Management Acceptance Reviews & Audits

LIFE CYCLE DESIGN CHANGE MANAGEMENT INTEGRATION TEST and TRIALS [Chapter 9]
PROCESS FACTORS
Requirements
Engineering ACCEPTANCE &
Review of produceability of CERTIFICATION
Subsystem/Equipment Systems
designs Analysis
Definition and acquisition of COMBAT SYSTEM
System TRIALS
Shore Integration Facilities Design
Preparation for the
progressive integration of SYSTEM INTEGRATION
subsystems and equipments COMBAT SYSTEM DEVELOPMENT & TEST
Preparation for Integration
Platform Integration and
Installation Data Management

Planning and preparation for


acceptance SUBSYSTEM/EQUIPMENT
Subsystems/
DEVELOPMENT and PRODUCTION
Support Infrastructure Equipment for
Acquisition of NDIs/COTS integration
Consideration of Disposal Acquisition of New/Modified Equipment

ACCEPTANCE
Planning for Acceptance Evidence Gathering Formal Certification

SYSTEM STUDIES Maintenance of Prototypes and Models System Change Investigation and Impact Studies
Monitoring and Assessment of Subsystem and Equipment Characteristics (Design Evaluation)

INTEGRATED Logistics Support Analysis (LSA) Life Cycle Costing (LCC) Integrated Supply Support Technical Documentation
LOGISTIC SUPPORT Maintenance Planning Support & Test Equipment Manpower & HF Training & Training Equipment

DOCUMENTATION Management Plans System Baseline Documentation Detailed Design Documentation


Test, Trials & Acceptance Documentation Operation & Support Documentation Handbooks

SPECIALIST DISCIPLINE SUPPORT Alignment AR&M Communications Cost EMC Human Factors ILS Interfaces
Operational Effectiveness Platform Integration Safety Security Shock Software Training

CONFIGURATION MANAGEMENT Configuration Definition Configuration Control Configuration Accounting

Figure 4.4 Demonstration and Manufacture Phase Activities

4.6.2.2 The process model for this phase sets out those activities, which must be conducted. The process
model reflects the primary activities introduced earlier and reflects the system/subsystem/equipment
hierarchy through which Combat System demonstration is achieved. Manufacture in the system context is
largely contained within the subsystem/equipment demonstration and manufacture processes and these
topics are addressed in sufficient detail to appreciate system-level aspects.

4.6.3 Systems Engineering (SE) (Technical) and Project Management

4.6.3.1 Objectives

4.6.3.1.1 SE (Technical) and Project Management covers:

a) The goals and activities to be conducted during the D&M Phase including acceptance;

b) The conduct of all technical activities, including their integration to meet the overall technical
objectives;

c) The processes through which the phase objectives are met in programme and cost terms;

d) The provision of all deliverables including equipment and supporting documentation required by the
contract in preparation for installation, integration, acceptance and in-service support.

Unclassified
94
DEF STAN 21-59 Issue 2

4.6.3.1.2 During earlier phases, the scope of project management and SE activities is contained since they
are necessarily oriented towards developing the design as a concept. Though previous phases consider and
investigate all manners of management and engineering issues, it is not until the demonstration and
manufacture phase that the acquisition process begins in earnest. At this point the scope of the project
expands significantly to include demonstration and/or acquisition across a wide and varied set of interacting
subsystems and equipments.

4.6.3.1.3 It is important to acknowledge that once D&M begins, all parties across the Combat System
enterprise - from MoD at the very top representing the ultimate customer, the RN, through the Combat
System integration organisation, to the subsystem and equipment suppliers and in turn to their suppliers -
have entered a set of ‘partnering’ relationships.

4.6.3.2 MoD CSM Role

4.6.3.2.1 Though the contractual boundaries delineate the actual responsibilities of each party which will vary
widely with the nature of the contractual agreement, accountability for the success or failure of the Combat
System to meet project level goals of fitness for purpose, programme and cost ultimately lie with the MOD. It
is essential to put in place appropriate management controls which provide clear lines of communication
across all levels of the enterprise and which foster a spirit of commitment and co operation.

4.6.3.2.2 The MoD CSM role throughout this phase is one of ‘hands-off/eyes-on’ management, i.e. to ensure
that the Combat System enterprise is progressing to cost and programme and that any changes are
thoroughly investigated and if agreed, implemented in the most cost-effective manner.

4.6.3.3 Activities during the Demonstration and Manufacture Phase

4.6.3.3.1 SE (Technical) and project management activities required to co-ordinate demonstration and
manufacture must be anticipated during previous phases and management plans provide the means to
document proposed policy and practice.

4.6.3.3.2 These activities need to be considered in the context of other related project-level management
disciplines (contract management, risk management and quality management) as well as whole warship
procurement and subsystem/equipment procurement issues across the hierarchy. This is illustrated in
Figure 4.5 which emphasises the inter-relationships between related activities at different levels of the
hierarchy.

4.6.3.3.3 Many of the activities are common to previous phases covered in this guide.

Unclassified
95
DEF STAN 21-59 Issue 2

MOD Project Contract


MOD need Management Plans to define
the overall objectives and controls of
Risk Quality
Combat System Development in context
with overall warship procurement and Project Management
individual equipment projects
Systems Engineering Management

Whole Warship/Combat System


Management Plans provide the link Contract
between overall MOD objectives and
Industry plans for implementation.
Systems Engineering Management Risk Quality
requires specific plans for high risk
areas such as Design & Development, Project Management
Production and Build, Integration, Trials,
Acceptance, ILS, AR&M, HFI etc. Systems Engineering Management

Subcontract Management

Subsystem/Equipment
Contractual relationships are detailed Contract
through Contract and Subcontract
Management Plans. The Contract
Management Plan calls up lower level Risk Quality
Management Plans to link overall
Combat System objectives with plans Project Management
for Subsystem/Equipment
implementation. Systems Engineering Management

Subcontract Management

Figure 4.5 Hierarchy of Project Management Activities

4.6.3.3.4 The policy of Smart Acquisition means that MoD and Industry often collaborate in the decision-
making process during D&M. This means that the MoD must closely monitor the progress of a project as an
informed customer.

4.6.3.3.5 The Contract Management Plan (CMP) is the highest level in the management plan hierarchy, and
cascades responsibility down the Combat System enterprise through subordinate industry-authored (and
MoD approved) CMPs. The CMP sets the context for the balance of responsibilities within MoD and
between MoD and industry, and thus bounds the Combat System contract.

4.6.3.3.6 Priority Project Management activities to be conducted during the demonstration and manufacture
phase are summarised in Table 4.1.

4.6.3.4 Systems Engineering Management

4.6.3.4.1 Within the scope of Combat System and lower-level SE management activities are the manufacture
of detailed plans addressing particular facets of the SE process.

Unclassified
96
DEF STAN 21-59 Issue 2

Table 4.1 Project Management Activities


PM Discipline Topic(s) Priority Activities During This Phase

Contract Contract Management Plan (CMP) The MoD CMP, which formalises the Combat
Management System Procurement Strategy, will be
formally set in place for the duration of the
Demonstration and Manufacture phase.

Any contract changes need to be reflected by


the MoD CMP and thereafter through the
subordinate CMPs where affected.

Risk Management Risk Management Plan (RMP) Continued application of Risk Analysis
Risk Register methods, update of the Risk Register and
Risk Analysis raising of RRAPs, as a result of risk
Risk Reduction Action Plan (RRAP) promulgation up through the Combat System
implementation hierarchy.

Regular liaison with the CSI and CSESs by


ongoing ‘visibility’ and formal risk review at
programmed Reviews and Audits.

Quality Quality Plan Periodic auditing of management processes


Management Software Quality Plan through the Combat System Enterprise to
Systems Engineering Management Plan ensure compliance with recognised Quality
(SEMP) [see later] Standards e.g. BS5750 ISO 9000 series
certified.

Auditing of the Systems (and Software)


Engineering processes, against a recognised
(e.g. Carnegie-Mellon) SE Capability Maturity
Model.

Project Project Management Plan (PMP) Review of the PMP to reflect any changes in
Management organisational/reporting arrangements.

Programme Control and Performance Regular scheduled review of the


programme(s) and progress. Liaison with
Reviews and Audits EPMs to review Weapon Equipment Delivery
Programmes (WEDPs) and relationship with
Combat System programme;

Liaison with CSI; Agreement and visibility of


the Project Review Cycle; Action tracking.

Review of methods/tools support and training.

Configuration Management and Change Auditing of the Configuration Management


Control Plan process for controlling the effects of change
to the system design and implementation
baseline(s).

4.6.3.4.2 The exact coverage of detailed plans is subject to variation amongst the assignment of SE activities
within organisational structures. The MoD needs to review and agree all subordinate plans generated by the
Combat System enterprise as detailed in Table 4.2.

Unclassified
97
DEF STAN 21-59 Issue 2

Table 4.2 Systems Engineering Management Activities


SE Discipline Topic(s) Priority Activities During This Phase

Systems The Systems Engineering Management Review and agreement of inter-related plans
Engineering Plan (SEMP) provides a top level plan for addressing SE issues across the Combat
Management integrating ‘best practice’ SE activities System hierarchy to ensure compatibility with
(General) across the project. overall MoD SEMP objectives.

Work Breakdown Structure (WBS) Demonstration, refinement and agreement of


the Combat System WBS; Maintenance and
review of the WBS spend profile and input of
information into project LCC analysis;
Monitoring of project deliverables; Review of
MoD resource profiles.

SE Process Performance Monitoring of key Technical Performance


Measures (TPMs) at programmed control
points identified by the CSI, to assess actuals
versus predicted performance and plans for
containment; Monitoring of design baseline
control (see CM); Visibility and review of CSI
design data.

System Security Combat System Security Policy Periodic review and audit of Combat System
project information and handling; Review of
integration of security into the Combat
System implementation; Management of
security risk through physical transmission,
espionage and intelligence gathering.

System Safety Safety Management Plan (SMP) Facilitate the achievement of safety
objectives stated in the SMP through the
demonstration and refinement of the Safety
Case through the phase.

Design & Software Management Plan Review to ensure compatibility of lower level
Demonstration Interface Management Plan plans with MoD SEMP Objectives.
Management EMC/Signatures Management Plan

Manufacture & Integration Plans


Build Management GFE/GFI Management Plan
Jigs & Tools Management Plan

Integration, Test Modelling, Test & Trials Management


Evaluation and Contract Acceptance Schedule
Acceptance Plan

ILS AR&M Management Plan


Human Factors Integration Plan
Technical Publications Plan

Through Life The MOD’s overarching Planning


Management Plan Document supported by key documents
such as the CONEMP, URD, SRD and
ITEAP.

Systems Engineering Management Activities (continuation)

Unclassified
98
DEF STAN 21-59 Issue 2

SE Discipline Topic(s) Priority Activities During This Phase

Disposal Disposal Plan

Safety Analysis Demonstrate ability to support safety case.

Integration strategy A subset of the TLMP addressing how Definition of system boundaries, interfaces,
and Plan integration and interoperability will be data structures, security etc, how they
achieved. support the User IO Requirements and how
they are tested.

4.6.3.5 Technical Performance Measures

4.6.3.5.1 Technical Performance Measures (TPMs) should be maintained for all critical performance
requirements at both the system and subsystem/equipment levels. TPMs for all configuration items should
be monitored throughout the demonstration and manufacture phase for movement outside bounds of
acceptable performance. These should be accompanied by a definition of the purpose/scope, reporting
period and details of the collection method. Considerations include:

a) Requirements;

1) Number of requirements decomposed & analysis suggested,

2) Number of requirements responded to,

3) Number of requirements agreed;

b) Design;

1) Load budget estimate,

2) Load budget given by supplier,

3) Total Combat System load budget prediction,

4) Interfaces identified;

c) Procurement;

1) Request For Quote (RFQ)/Invitation To Tenders (ITTs) prepared, reviewed, issued,

2) Tender responses received,

3) Assessment criteria produced,

4) Tender responses clarified;

d) Modelling;

1) Scenarios identified/reviewed/endorsed,

2) Measures Of Effectiveness (MOEs) identified/reviewed/endorsed,

3) Measures Of Performance (MOPs) identified/reviewed/endorsed,

4) Effectiveness/capability predictions,

5) Performance prediction,

Unclassified
99
DEF STAN 21-59 Issue 2

6) System thread analysis;

e) Safety;

1) Hazards identified,

2) Hazards with As Low As Reasonably Practicable (ALARP) assessment,

3) Safety case(s) preparation,

4) Test & integration,

5) Tests specified/issued;

f) In Service Support;

1) Faults raised/accepted/attributed,

2) Solutions proposed/implemented/accepted,

3) General (e.g. risk),

4) Problems addressed/resolved,

5) Risks identified/mitigated/resolved.

4.6.3.5.2 TPMs should be formally reviewed through the project review cycle, which identifies the major
control points of the system/subsystem/equipment programmes. The assessment of TPMs at each control
point should be conducted in addition to establishing that other technical, budget and programme
requirements are being met.

4.6.3.6 Related Information

4.6.3.6.1 Further information on project management aspects of a Combat System project is available in the
CDPIs and DPMGs.

4.6.4 Life Cycle Process Factors

4.6.4.1 Objectives

4.6.4.1.1 Life Cycle Process Factors are those aspects of the Combat System life cycle which need to be
anticipated well in advance to achieve a design optimised against a range of design issues including
through-life costs. Effectively, this means looking ahead to consider what can be done at this phase to ease
what needs to be done during subsequent phases.

4.6.4.1.2 At this phase in the life cycle, the majority of through-life aspects will have been previously
considered in some depth. The main objective at this phase is to maintain focus and ensure that
optimisation of the design is pursued through succeeding levels of the Combat System/subsystem/
equipment hierarchy.

4.6.4.1.3 In particular, preparation is needed for integration test and trials, anticipation of acceptance, support
whilst in-service and due consideration of disposal. Each of these areas needs to be addressed in relation to
the demonstration intent so that the evolving design can be optimised.

4.6.4.2 MoD CSM Role

4.6.4.2.1 The role of the MoD CSM includes ensuring that through-life aspects are planned for and
considered in sufficient depth throughout the D&M Phase. This needs to be addressed both in the
implementation of the specified requirements and specifications, and for any changes which are assessed
and applied to the system design baseline.

Unclassified
100
DEF STAN 21-59 Issue 2

4.6.4.2.2 To this end, the CSM must satisfy himself that he retains sufficient visibility of through-life issues
across subsystem/equipment D&M and platform design and build processes. Again, the vehicle for
maximising visibility of demonstration is through the project review cycle through which risk issues are
formally raised and action identified. Where the procurement boundary of the project system requires
integration with other systems, interface mechanisms must be agreed.

4.6.4.3 Activities during the Demonstration and Manufacture Phase

4.6.4.3.1 These activities during the D&M Phase are anticipated and supported by the extensive range of
through-life modelling activities (i.e. models, simulations and system representations used for change
impact/assessment, training etc.) described under systems studies (see later).

4.6.4.4 Integration Strategy

4.6.4.4.1 The contractor will have to provide the tools for Combat System integration in a timely way; be it
modifications to an existing Shore Integration Facility (SIF)/Shore Demonstration Facility (SDF), a new
SIF/SDF, or a new approach, such as synthetic environments. The tools must be installed, tested, and
accepted prior to the commencement of the Combat System integration programme.

4.6.4.4.2 During this phase the integration strategy would be updated in accordance with the equipment
delivery dates that emerge from the chosen equipment suppliers. The demonstration of the intended group
and overall Combat System tests and trials into detailed tests/trials orders would commence and the
supporting scenarios would be developed for input to the scenario generator. The First Of Class (FOC's)
installation, test and trials programme would also be developed at this time.

Unclassified
101
DEF STAN 21-59 Issue 2

Table 4.3 Summary of Life Cycle Process Factors


Life Cycle Aspect Priority Activities at this Phase

Demonstration and Review produceability of subsystem and equipment designs.


Production

Integration Anticipate integration through the refinement and implementation of the


integration strategy including:

• Strategy for testing, with due emphasis on maximum system-level


testing through FATs;

• Definition of the sequence of integration and programme liaison with


Equipment sponsors and manufacturers;

• Planning for extent/re-use of SDF/SIF facilities;

• Definition of stimulation/simulation and scenario generator functionality


required in support of the Integration Strategy;

• Appraisal of commonality of system architectures across the fleet;

Definition and development of Test Equipment and rigs to support system-aspect


testing;

Definition and development of test and trials recording and analysis equipment;

Instigation of data management practice for all data exchange across all inter-
connecting equipments, whether through direct links or via a data highway;

Advance planning for the Shore-based Integration environment (e.g. housing,


services and supplies etc);

Integration with the Platform.

Acceptance Refinement of the Acceptance strategy and preparation for acceptance, ensuring
that verification and validation activities throughout Subsystem/Equipment
Demonstration and Manufacture are adequate and in place. Including:

• Scheduling of progressive acceptance activities in Equipment FAT;

• Acceptance in the shore environment;

• Acceptance on the FOC vessel;

• Acceptance on follow-on vessels;

• Contractual acceptance across the Combat System enterprises;

• Support to Platform Acceptance.

In-Service Support Support infrastructure;


Anticipation of obsolescence of equipment components.

Disposal Ensure that identification and review of disposal issues is adopted at all
appropriate levels of the system hierarchy.

Unclassified
102
DEF STAN 21-59 Issue 2

4.6.5 Design Change Management

4.6.5.1 Objectives

4.6.5.1 The Combat System engineering process must recognise that change is inevitable. Change may
be driven by external changes to the requirement as a consequence of real world events, but more likely
through the nature of the demonstration process. The key to success is to manage change such that any
impact is first assessed before being implemented. By judicious use of CM techniques and co-ordination of
the implementation process through formal reviews, it should be possible to contain change to a manageable
level.

4.6.5.2 MoD CSM Role

4.6.5.2.1 During these phases, the MoD CSM role is one of identifying, promulgating and assessing the
impact of changes to the Combat System to meet a new or modified operational capability. This may result
from a change in threat or the definition of a new role, which demands further investigation.

4.6.5.2.2 Alternatively, change may be necessary to meet performance shortfalls of specific equipment(s). In
such cases, the impact of shortfalls will require further investigation in terms of what this means to the
capability of the warship and the consequent impact on system operational context.

REQUIREMENTS SYSTEMS SYSTEM


ENGINEERING ANALYSIS DESIGN

Implement
Change
Analyse
Change
PROCESS PROCESS
INPUTS Propose OUTPUTS
Change

Information
Base

Evaluate Document
Change & Report

SYSTEM STUDIES DOCUMENT PRODUCTION

Figure 4.6 Design Change Management Activities

4.6.5.3 Activities during the Demonstration and Manufacture Phase

4.6.5.3.1 The generic SE process illustrated in Figure 4.6 provides a suitable template for co-ordinating
design change management activities. These can be considered as:

a) Propose change and analyse change, i.e. the definition of the change within the context of previously
conducted requirements engineering and system analysis activities;

b) Evaluate change, to perform impact assessment across pertinent performance aspects such as
functionality, architectural impact, operability, AR&M, effectiveness and costs (including
consequential costs);

c) Implement change, to incorporate the change in the system design baseline for cascading through
any affected subsystem and equipment demonstration and manufacture contracts;

d) Document and report the change impact assessment, proposed modifications etc.

4.6.5.3.2 All changes will demand a controlled regime (i.e. a project review cycle) through which to revisit the
system baseline design and ensure that any impact is identified and understood.

Unclassified
103
DEF STAN 21-59 Issue 2

4.6.5.4 Requirements Engineering

The first step in assessing the change is in expressing it as new or modified requirements and adding this
information to the URD/SRD. The URD/SRD (and its electronic form held in a RDB) must continue as the
repository of all configured requirement statements and the vehicle by which progress of the acceptance
process will be documented and tracked. The requirements set will be reviewed and changes agreed for
incorporation (deletion, modification or addition). Changes to the requirements baseline will need to be
controlled through the CM regime as applied to the URD/SRD. (Typically using DOORS and Architectural
Views.)

4.6.5.5 Systems Analysis

4.6.5.5.1 The results of previous systems analysis activities will need to be revisited to ensure that the
implications of any changes are fully understood, quantified and carried through to the design. Each will be
supported by pertinent system studies, described later in this Section.

4.6.5.5.2 Any changes to functional requirements will need to be highlighted and traceability information
followed through. Changes will be reviewed and formally agreed through review to confirm that there is a
suitable basis for proceeding with system design activities.

4.6.5.6 System Design

4.6.5.6.1 In a similar way, the system design should be revisited to verify compliance with the requirements.
Shortfalls need to be investigated and contained wherever possible or changes to the system design
proposed for their resolution. This may include revisiting the following:

a) System Design, as defined by a physical model and its variants, to confirm the partitioning and
investigate the impact of any changes to the implementation and its interfaces;

b) Design Documentation, in particular ensuring that any changes are reflected in the requirements of
the coherence specification and the appropriate subsystem specifications;

c) Design Verification, to ensure that traceability between requirements and analysis and design
entities is maintained.

4.6.5.6.2 System studies should continue to be used to ensure that the design is compliant with the
requirements and represents a viable solution. In particular, architectural performance modelling and
Human Computer Interface (HCI) operability modelling should be conducted to identify and quantify the likely
performance of the integrated system. Design review is the formal route through which any major changes
to the system design are declared. This is the precursor to formally invoking changes to affected
subsystem/equipment contracts.

4.6.6 Combat System Demonstration

4.6.6.1 Objectives

4.6.6.1.1 Combat System demonstration can be considered as a major risk reduction activity - ‘bridging the
gap’ between the demonstration and/or acquisition of subsystems/equipments into which it has been
partitioned followed by the progressive integration of equipments into a complete whole to provide the
required Combat System functionality.

4.6.6.1.2 The main objectives of this activity are to oversee the acquisition process, in particular the
acceptance of system components, and prepare for integration both within a shore environment and on the
FOC vessel. The primary considerations here are:

a) Interface and data management (that is the co ordination of data flow across equipment interfaces,
and enforcement of system coherence rules/standards);

b) Preparation for integration in the shore environment (SIF/SDF), including provision of the facility;

c) Liaison with the platform design and build process;


Unclassified
104
DEF STAN 21-59 Issue 2

d) Co-ordination of the evolving equipment design and management of Combat System shortfalls.

4.6.6.2 MoD CSM Role

4.6.6.2.1 The MoD CSM role, as a minimum, is one of ‘informed customer’, monitoring progress of the
project against the programme, facilitating communications and the resolution of issues between Combat
System, equipment and platform programmes wherever there is potential conflict. Additionally, liaison will be
necessary to prepare the way for extension of use of existing shore facilities.

4.6.6.2.2 The CSM should satisfy himself that policy and strategy for integration of the Combat System is
being implemented in an effective manner, and those integration risks are identified early and appropriately
managed. This also means ensuring that the testing and acceptance of equipments meets the needs of the
Combat System and that duplication of testing is minimised.

4.6.6.3 Preparation for Integration

4.6.6.3.1 The ITEAP, prepared and refined during earlier phases will have defined the overall approach to
integration, test and Acceptance, the role of modelling, data management, and the implementation of the
strategy in terms of equipment test strategies, shore-based integration, and integration on the FOC and
follow-on vessels. During the demonstration and manufacture phase, preparation for implementation of the
strategy will become a priority task. This includes:

a) Rigorous application of data management practice for all data exchange across all inter connecting
equipments, whether through direct links or via a data highway (including ‘implied’ interfaces);

b) Further definition of one-off, repeat tests of functionality, performance, and HCI aspects through
stand-alone tests, Combat System test and residual tests;

c) Definition of the sequence of integration and programme liaison with equipment sponsors and
manufacturers;

d) Promulgation of the ITEAP strategy, with due emphasis on maximising system level interface
compatibility testing through equipment Factory Acceptance Trials (FATs);

e) Demonstration of Combat System integration test documentation;

f) Equipment design proving with particular emphasis on interface design and implementation of data
exchange and protocols across interfaces;

g) Planning for extent/re-use of SDF/SIF facilities;

h) Definition and acquisition/development of stimulation/simulation and scenario generation facilities


required in support of shore-based integration, test and trials as determined by the integration
strategy;

i) Definition and development of test equipment and rigs to support system-aspect testing;

j) Definition and development of test and trials recording and analysis equipment;

k) Advance planning for the shore-based integration environment (e.g. housing, services and supplies
etc);

l) Generation of evidence in support of higher level e.g. Platform Acceptance.

Unclassified
105
DEF STAN 21-59 Issue 2

4.6.6.4 Data Management

4.6.6.4.1 Data Management, that is the co-ordination of data exchange across separately procured Combat
System equipments, is a fundamental control mechanism of the integration policy. The implementation of
data management procedures serves to reduce the risk of interface problems during the integration process
and optimise data exchange across the Combat System design solution. This involves:

a) Definition of responsibilities for data management between platform and Combat System projects,
and support from other organisations (e.g. MCTA);

b) Interface standardisation covering documentation, network interfacing, data formats, and messages
(e.g. Def Stans 21-13, 21-24, 21-26 and 21-28);

c) Interface definition through formal issue cycle of Interface Specification (IFS) and Data Exchange
Specification (DES);

d) Documentation of interface protocols and definition of representative scenarios;

e) Definition of data highway/equipment linking tests and trials and reporting;

f) Data exchange proving, through tests and follow-up analyses;

g) CM of all interface documentation and test data.

4.6.6.4.2 The chosen contractor will implement the contracted ‘design for integration’ approach offered in the
Assessment Phase, enforcing the standards for the definitions of application data elements, co-ordinate
systems, network interfaces, network protocols, and application protocols included in their coherence
specifications. They may have to develop the coherence specification as demonstration of the Combat
System equipments are likely to raise issues which are best dealt with in that document.

4.6.6.4.3 The contractor will also apply their information and interface management method which should be
visible to MOD, policing the demonstration of detailed DES and IFS in the context of their mandated
standards, and then comprehensively checking compliance in ‘design proving’ FATs.

4.6.6.4.4 Further information concerning Integration and Data Management Policy for Surface Ships can be
found in Def Stan 21- 88.

4.6.6.5 Platform Integration

4.6.6.5.1 The integration of the Combat System into the platform is a major facet of the system
demonstration process, which has to be considered throughout all D&M activities. This includes the
realisation of the installed Combat System in terms of its physical characteristics (size, shape, weight etc.)
and the interactions between the Combat System and the platform, which characterise the platform as a
fighting unit.

4.6.6.5.2 The range of platform engineering disciplines involved with the integration of Combat Systems
equipments include:

a) Whole platform and upper deck engineering including spatial integration addressing access for
operation and maintenance, shock excursion envelopes, removal and maintenance envelopes, HF
requirements, and advising on construction;

b) Naval architecture, to monitor and control weight and stowage against assigned budgets and advise
on ballast arrangements and requirements;

c) Structural engineering, to produce and verify structural design guidance information (scantlings) and
advise on structural analyses including shock, noise and vibration;

d) Marine/mechanical engineering, to develop ship system schematics, mounting arrangements, and


manage budgets for equipment services and constraints such as heat load, ventilation, cooling etc;

Unclassified
106
DEF STAN 21-59 Issue 2

e) Electrical engineering, to develop and test electrical supply and distribution systems and
switchboards;

f) Security, Safety, Frequency Allocation and Mutual Interference studies and design constraints.

4.6.6.5.3 The relationship between Combat System and platform engineering issues becomes more complex
as each proceeds from design through demonstration and manufacture. Due consideration is required of the
life cycle process factors, in particular, installation, tests and trials, acceptance, and support.

4.6.6.5.4 As a consequence, it is essential that the platform and Combat System design, demonstration and
manufacture activities proceed in a co-ordinated manner. Naturally this requires extensive liaison to ensure
that all potential risks associated with the integration of the Combat System into the platform are identified
and effectively managed.

4.6.6.6 Platform Design and Build

4.6.6.6.1 Current initiatives within the platform integration specialism favour an integrated approach using a
concurrent engineering environment. This may include Computer Aided Design (CAD) and Electronic Data
Management (EDM) facilities wherein all engineering drawing data and associated design documentation
are held in electronic format within a configured central repository.

4.6.6.6.2 Tool support to the engineering database provides the opportunity to review 3D virtual
representations of compartments, equipment installation arrangements, allocated services, spares holding
and equipment removal routes to gain early visibility and agreement of physical platform integration issues
and solutions. This can be used in support of the acceptance process, once the relationship between model
and real world physical implementation is verified.

4.6.6.6.3 The provision of ship-fitting data to the shipbuilder and SIF/SDF are significant milestones in the
equipment demonstration and manufacture programme covering delivery of preliminary, initial and final
guidance information packs. The exchange of information in support of installation of the Combat System
equipment on board, includes:

a) Compartment general arrangements;

b) Upper deck layouts;

c) Equipment definitions and detailed drawings;

d) Analysis and calculations;

e) Cable runs;

f) Pipe/cable sizing;

g) Piping isometrics;

h) Weights and Centres of Gravity (Cs of G);

i) Seating/mounting arrangements.

4.6.7 Subsystem/Equipment Demonstration and Manufacture

4.6.7.1 Objectives

4.6.7.1.1 Subsystem/Equipment Demonstration and Manufacture comprises equipment implementation up to


the point of delivery from the factory for integration either into the SIF/SDF, FOC or follow-on vessel. This
includes both the acquisition of NDIs/COTS equipment and the demonstration, initial manufacture and repeat
manufacture of new or modified equipments.

Unclassified
107
DEF STAN 21-59 Issue 2

4.6.7.1.2 At the Combat System level, activities are generally related to the monitoring of
subsystem/equipment contracts to ensure that their contribution to the system design is progressed in a
disciplined manner. As a consequence, the main priorities are:

a) Visibility of the subsystem/equipment design, demonstration and manufacture processes for the
identification and management of equipment-level risks;

b) Acquisition of information in support of on-going system studies including performance parameters;

c) Provision of evidence in support of acceptance, both to satisfy compliance with the Subsystem
Specifications, and in support of the Combat System acceptance strategy;

d) Enforcement of CM and change control processes under an appropriate and auditable regime;

e) Acceptance Arrangements.

4.6.7.2 MoD CSM Role

4.6.7.2.1 The MoD CSM role is concerned with tracking the demonstration of high risk items through the
review cycle, gaining early visibility of potential problems, and monitoring progress towards acceptance. This
will be managed in the context of Combat System demonstration.

4.6.7.3 Activities during the Demonstration and Manufacture Phase

4.6.7.3.1 Prior to demonstration, the system will have identified/defined many components, which may be
categorised as:

a) NDIs i.e. legacy/in-service equipments and equipments to be procured without modification as well
as ‘off the shelf’ items including products developed for military application and COTS;

b) New equipments and modified variants of equipments in service. In addition, in order to integrate
NDIs into the Combat System, protocol/data conversion units may need to be developed.

4.6.7.3.2 The items selected for inclusion in the system need to be acquired and the acquisition managed
through a co-ordinated, structured and disciplined process as illustrated in Figure 4.7 and described in the
clauses which follow.

4.6.7.4 Acquisition of Non-Development Items

4.6.7.4.1 Unmodified in-service NDIs which are to be acquired and incorporated into the Combat System
without modification need to be procured in the most cost-effective manner. Acquisition will need to address
the re-qualification of existing equipment against devolved requirements using existing test data wherever
possible in support of the formal auditing process described later.

4.6.7.4.2 In-service equipments which have already achieved System Acceptance (SA) and which can be
produced and used without modification need to be acquired though the most appropriate procurement
route, determined by the CSI. Acquisition may often present problems however and obsolescence is a major
concern. There may be valid commercial or practical reasons why suppliers choose not to re-start
manufacture of existing designs, e.g. the expense of re-tooling after previous manufacture runs have long
ceased, availability of manufacturer’s drawings (through manufacturer negligence, business failure or failure
to ensure ESCROW), component obsolescence etc.

Unclassified
108
DEF STAN 21-59 Issue 2

FOC Platform Design & Build FOC


Combat System Development SIF/SDF
Data Management Preparation for Integration

Acquisition of NDIs/COTS Equipment


Evaluated NDIs/COTS Equipment

Development of Pre-Production Prototype for


Acquisition of New/Modified Equipment Shore Integration/Reference set

Initial Production Unit for


FOC Integration Test & Trials

Repeat Production Units for


Follow-on Platform Integration Test & Trials
Follow-on
Platform
Integration

Requirement Reviews Design Reviews Test Reviews Audits


RE SA SD PD DD Imp Int Test Acc
Equipment Equipment-level Equipment Equipment Equipment Equipment Equipment
Requirements System Analysis and Preliminary Detailed Implement- Integration Tests & Design
Engineering Design Design Design ation Acceptance

Figure 4.7 Subsystem/Equipment Demonstration and Manufacture

4.6.7.5 COTS

4.6.7.5.1 COTS technology may be defined as ‘readily available technology developed to exploit the
requirements of the market place’. This includes both commercial products and items developed for military
application. COTS is not a panacea to demonstration problems, since it brings with it constraints which need
to be addressed in relation to the Combat System life cycle. These include:

a) Scope of COTS implementation (i.e. from single COTS component to complex interacting system of
many COTS components) directly influences the significance of COTS issues at the Combat System
level;

b) Acquisition of COTS products demands a flexible requirements engineering process through which
trade-offs between requirements and offered product characteristics can be evaluated;

c) Integration of COTS components (particularly diverse software packages developed by competing


organisations) into an operable system is a non-trivial undertaking. Incompatibilities are inevitable,
given the diverse features of available products;

d) Testing demands a definition of the requirements to which the subject equipment has been
designed. Requirements to which re-used/COTS equipment has been designed are not necessarily
available or, if they are, complete;

e) Systems and equipments built from COTS components are dependent on the COTS suppliers for
standardisation, documentation and business longevity for through-life support;

f) COTS products have their own unique upgrade paths, influenced by their trading market, which may
affect compatibility between interacting COTS components. Maintenance is potentially complicated
whether or not interfacing technology is used to contain the impact of one COTS item on another.

4.6.7.5.2 In order to be able to take advantage of the benefits, it is important that the design of the Combat
System can in some way contain the rapid evolution of COTS products. This means that the Combat
Unclassified
109
DEF STAN 21-59 Issue 2

System itself may need to evolve through a controlled regime of continuous engineering to co-ordinate
design evolutions which meet the requirements, maximising the use of state-of-the-art products whilst taking
action in anticipation of COTS obsolescence. The implementation of CM is therefore a key issue in the
control and management of hardware and software, equipment and system build configurations.

4.6.7.6 Acquisition of New/Modified Equipment

4.6.7.6.1 New equipment and modified variants of existing equipment need to be acquired through a more
rigorous process through which trade-offs between system and equipment-level issues can be more
effectively raised and resolved. Close monitoring of equipment programmes is essential to ensure that they
do not stray from the specified functionality as defined by the requirements and subsystem specifications.
Any compromises, concessions, or design clarifications must be adequately assessed for their impact upon
other subsystems and agreed changes reflected in baselined data, including models.

4.6.7.6.2 New equipments necessary to meet the Combat System requirement will have been identified
during previous phases. Often and somewhat inevitably, a Combat System design will include equipments
where the complexity and cost of the demonstration has necessitated a separate procurement programme.
This is typically the case for the command system and principal sensor e.g. integrated sonar suite or major
radar or tracker equipment. In these cases, the degree of independence of the equipment/subsystem is a
major risk to the integrity of the Combat System. This must be afforded suitable visibility within the Combat
System risk management regime.

4.6.7.6.3 Some equipment may require modification to meet the requirements of the Combat System design.
The extent of the modifications will determine the validity of available documentation, models and
performance data. Furthermore, the level of acceptance testing required proving compliance will also be an
issue of negotiation and agreement on a case-by-case basis.

4.6.7.6.4 Though each equipment project will have its own specific demonstration strategy, the generic
process can be described through the following phases:

a) Demonstration of a pre-manufacture standard prototype equipment for design acceptance testing


(design proving), environmental qualification and Electromagnetic Compatibility (EMC) testing;

b) Refurbishment of the equipment and its installation, integration test and trials in a shore based
facility (or for use as a reference set). The equipment unit used for design acceptance testing,
environmental qualification and EMC testing is most likely to be used as a reference set due to the
risk of the environmental testing seriously reducing equipment longevity below the bounds required
for the platform fit;

c) Initial manufacture of the equipment to be subject to installation, integration test and trials on the
FOC platform;

d) Full (repeat) manufacture of the equipment for installation, integration, test and trials on follow-on
platforms.

4.6.7.6.5 The underlying approach is to demonstrate compliance with the requirements by means of a
complete set of D&M tests. These are applied in full on the first set of equipment to be developed and
produced. For subsequent manufacture runs, specific subsets of tests identified from the test hierarchy will
be sufficient to demonstrate compliance thereafter.

4.6.7.7 Equipment Design

4.6.7.7.1 Design reviews provide visibility of progress (and opportunities for acceptance) of the design
detailed by subsystem/equipment design specifications, drawings and supported by calculations.

4.6.7.7.2 The equipment design needs to be progressed from an established baseline, and early activities in
the equipment demonstration process serve to formally determine the basis for subsequent demonstration.
The extent to which formal reviews are applied for reviewing the design is an issue for consideration against
the contractual milieu and what is considered most appropriate for risk management purposes. This
includes:

Unclassified
110
DEF STAN 21-59 Issue 2

a) Equipment-level requirements engineering culminating in review to ensure that the specific


requirements are appropriate and achievable;

b) Equipment analysis and design activities to consolidate the proposed design and define it in terms of
configuration items prior to embarking on further design work and committing to equipment assembly
subcontracts/purchasing of equipment components.

4.6.7.8 Equipment Implementation and Integration

4.6.7.8.1 Equipment implementation proceeds with the procurement of equipment components and sub
assemblies and the demonstration of hardware. Equipment integration involves the progressive build up of
components, sub-assemblies, hardware and software into working equipment.

4.6.7.8.2 Test reviews provide a check that the preparations for testing and the associated test
documentation is adequate as a basis for proceeding into formal testing. A test review is performed for each
configuration item and will include an inspection of test results.

4.6.7.9 Equipment Tests and Design Acceptance

4.6.7.9.1 Equipment Test activities generally use a pre-manufacture prototype as the vehicle for
demonstration and acceptance of the design and for subsequent environmental and EMC testing. At the
system level, equipment tests will support system-level studies, providing metrics on predicted equipment
performance based on low-level performance test data.

4.6.7.9.2 Design acceptance of the equipment will focus on physical performance and verify interfaces and
data exchange in a dynamic representative scenario, within the constraints of stand-alone operation.
Selected (previously run) tests will be used to confirm and formally agree test results presented for formal
acceptance. Provisional acceptance will be sought for those elements of the design, which cannot be fully
accepted until the completion of environmental qualification or later through Combat System integration test
and trials.

4.6.7.9.3 Environmental qualification testing proves that the design is capable of supporting operation of the
equipment in a representative ship or submarine environment in accordance with the equipment
environmental test specification.

4.6.7.10 Configuration Audits

4.6.7.10.1 Configuration Audits are formal checks that each configuration item is functionally consistent
and physically compliant with the requirements. Configuration audits should be conducted on all equipment
with some rigour so that manufacture can proceed without having to repeat all tests on each item for proof of
compliance.

4.6.7.10.2 Conducting configuration audits throughout the demonstration and manufacture programme on
each configuration item in an incremental fashion provides a progressive build-up of proof of compliance and
confidence in the manufacture build standard for the equipment.

Unclassified
111
DEF STAN 21-59 Issue 2

4.6.7.11 Manufacture Readiness

4.6.7.11.1 Once acceptance of the design is achieved, equipment manufacture can commence.
Manufacture readiness review determines the status of all outstanding demonstration-related issues,
manufacturing concerns and resources, which must be resolved, before manufacture can be given the go-
ahead. Unless a “Service” is being procured, an agreed stage, which may be prior to acceptance off
contract, design documentation will come under the formal configuration control of the customer as a basis
of contract. This is especially important for non-functional requirements of importance e.g. performance,
safety and security. Critical Design Reviews are normally used to mark this transition if prior to acceptance.

4.6.7.12 Equipment Factory Testing

4.6.7.12.1 Equipment Factory Testing repeats a representative set of design acceptance tests to verify
that the manufacture equipment meets the design requirements. This involves a series of tests of the
installed equipment including mechanical and cable continuity checks and a comprehensive set of function
tests to verify interface operation and quantify physical performance.

4.6.7.13 Related Information

4.6.7.13.1 Subsystem/equipment demonstration has been the subject of much standardisation and
additional guidance is available within the AMS and Def Stan documents relevant to weapon equipment
procurement, and Naval systems Upkeep.

4.6.8 Acceptance

4.6.8.1 Objectives

4.6.8.1.1 The primary vehicle for demonstrating and ensuring compliance with the requirements is the
acceptance process. This is a central theme of modern SE practice, which demands due attention at each
phase of the life cycle.

4.6.8.1.2 Acceptance is an incremental process through which evidence of compliance with the requirements
should be accumulated throughout all project phases. Adoption of such an incremental process leads to a
schedule of acceptance, which demonstrates compliance as early in the project as possible, consistent with
the need to generate definitive evidence. This approach serves to minimise risk of eventual failure, and
hence reduce overall programme costs.

4.6.8.2 Combat System Issues

4.6.8.2.1 As is the case for many aspects of this phase, acceptance of the Combat System has to be placed
in context. The basis of acceptance is determined by the requirements. In the case of the Combat System,
these are likely to comprise Combat System-level requirements (which define the required capability of the
Combat System as a whole), lower level requirements and constraints on component equipment, as well as
constraints imposed on and by the platform.

4.6.8.2.2 Acceptance of the Combat System is closely coupled with acceptance of the hierarchy of
equipment and subsystem components of which it is constituted, and the platform on which it is fitted.
Although many aspects of acceptance cannot be completed until later phases, the planning and conduct of
acceptance must be given a high priority, since it is an integral part of the demonstration, manufacture,
delivery and integration of component parts. Acceptance risk may be further contained through the adoption
of a structured modelling approach as detailed in systems studies (see later).

4.6.8.3 MoD CSM Role

4.6.8.3.1 The CSM must liaise closely with the MoD acceptance team dedicated to dealing with the
acceptance activities which fall within the remit of the MoD organisations involved. This will depend on the
contractual arrangements under which the Combat System contract is let, however the main acceptance
responsibilities of the CSM, with respect to the Combat System, are:

Unclassified
112
DEF STAN 21-59 Issue 2

a) Co-ordination of MoD resources involved in the acceptance process including Royal Navy
organisations, in particular the Acceptance Authority, and Ships’ Staff Standing By. Relevant
organisations should be recorded in the TLMP and be members of the Acceptance Community of
Interest;

b) Together with the Requirements Manager, negotiation, agreement and approval of detailed
acceptance proposals to demonstrate that contract requirements will be met;

c) Witnessing of acceptance events and presentation of acceptance evidence;

d) Signification that evidence submitted clears defects, deficiencies, and problems;

e) Processing of concessions, waivers, or changes relating to MoD requirements;

f) Conferral or recommendation of formal acceptance.

4.6.8.4 Acceptance Activities during Demonstration and Manufacture

4.6.8.4.1 The strategy for acceptance through the Combat System programme will have been explicitly
detailed by the ITEAP generated previous to this phase. The ITEAP serves to define roles and
responsibilities both of MoD and industry across the acceptance process, which is illustrated schematically in
Figure 4.8.

Requirements Management of the Acceptance Process Formal


Allocation and Visibility of progress towards Acceptance/ Cumulative
Decomposition Progressive Acceptance Acceptance

Combat System Development

Validation of System/Compliance with Requirements


RE Acc
Verification of System Design
SA Test
Lower-level Evidence of
Subsystem/Equipment Verification Compliance with
Requirements, SD Int Lower-level
partitioned by the Subsystem/ Subsystem/ Requirements for
System Design Equipment Equipment Formal Acceptance
Contracts Deliverables

Subsystem/Equipment
Development and Production

Validation of Equipment/Compliance with Requirements


RE Acc

Verification of Equipment Design


SA Test

Verification
SD Int

PD DD Imp

Figure 4.8 Combat System Acceptance Process

4.6.8.4.2 The acceptance process can be thought of as ‘closing the square’, satisfying Combat System
design requirements cascaded down the subsystem/equipment hierarchy by the accumulation of acceptance
evidence produced from lower level acceptance events.

4.6.8.4.3 At each level, verification of the transformations between requirements, analyses, design,
implementation and test activities ensures traceability of requirements to eventual products. This validation
mechanism supports certification and acceptance.

Unclassified
113
DEF STAN 21-59 Issue 2

4.6.8.4.4 Visibility of the progress towards acceptance is an important consideration. Reviews are a major
element in the acceptance process, especially in determining whether the acceptance evidence generated
satisfies requirements. The acceptance process has therefore to deal with both success and failure of
acceptance events and link in to general management processes to initiate and be involved in recovery
programmes if defects and deficiencies arise.

4.6.9 System Studies

4.6.9.1 Objectives

4.6.9.1.1 System Studies are those activities, which are continued throughout the Combat System life cycle
providing descriptive, analytical or simulation-based symbolic models of system emergent properties and
predictive indications of system performance across a number of key disciplines.

4.6.9.1.2 In support of the demonstration and manufacture phase, the primary objective of modelling is to
plan and anticipate integration across equipment interfaces, to predict system performance and to assess
the effect of introducing changes to the Combat System baseline design.

4.6.9.2 Inter-related Modelling Activities

4.6.9.2.1 The Combat System can be regarded as one level in the hierarchy of modelling activities
conducted to varying degrees during this phase. This is depicted in Figure 4.9 which shows the typical span
of inter-related modelling activities.

Unclassified
114
DEF STAN 21-59 Issue 2

OA Studies
OVERALL CAPABILITY
The capability of the Warship
(according to its Roles, Tasks,
Missions and Scenarios) need to be
evaluated in the context of other
assets

Naval
Architecture Whole Warship Effectiveness
Human Factors Studies Modelling PREDICTIVE INDICATION
Signatures Combat System Studies contribute
LSA
Vulnerability LCC/TLC to Warship performance prediction
and provides a basis for acceptance
of operation-dependent design
aspects

Compartment Platform Combat System


Arrangements Studies Weapon & Studies System
Cable Runs/Service HCI Prototyping System Physical AR&M
Sensor Arc
Schematics Service Coverage Operability Functionality Architecture
Budgets
PLATFORM INTERFACES
The interaction between Platform
Design & Build and Combat
System engineering requires EQUIPMENT MODELS
effective co-ordination Equipment Definitive ‘as-built’ Equipment
Modelling Performance data become available
as the Equipment Design proceeds
through its Life Cycle

Platform Equipment Equipment


Design and Build Evaluation Test & Trials

COTS/NDIs REAL DATA


Benchmarking Definitive ‘as-built’ Equipment
is necessary to support Performance data become
evaluation of Non available as the Equipment Design
Development Items proceeds through its Life Cycle

Figure 4.9 Combat System Studies in Context

4.6.9.2.2 The D&M phase is typified by detailed design and manufacture information becoming available
through evaluation and test of developed or acquired equipments. This can be used to refine equipment
models, which contribute to Combat System-level modelling activities. Similarly, as the platform design and
build process progresses, corresponding platform studies will further define many of the physical constraints
which need to be considered for successful installation and integration of the Combat System with the
platform.

4.6.9.2.3 Combat System and platform modelling activities need to be co-ordinated with each other where
they overlap and where they contribute to the overall ‘whole warship’ characteristics, in particular operational
effectiveness and life cycle costs. Ultimately the characteristics of the whole warship in turn contribute to a
defined level of capability assessed through Operational Analysis (OA). All the above have to be carried out
in the context of agreed concepts of operation.

4.6.9.3 MoD CSM Role

4.6.9.3.1 The modelling activities conducted across each of these areas need to be managed across the
hierarchy. It is ultimately the responsibility of the CSM to ensure that modelling activities conducted in other
areas, such as that for equipment programmes, or platform-oriented modelling, which can support the
Combat System level objectives are identified, coherent with interfacing systems, and modelling resources
made available to the Combat System project.

4.6.9.3.2 The CSM also must ensure that all Combat System-level modelling activities are progressed in a
concerted manner, and at the appropriate level commensurate with the purposes of risk reduction. To
achieve this, a decision must be made whether to maintain Combat System models (delivered from the

Unclassified
115
DEF STAN 21-59 Issue 2

previous Assessment Phase) within a MOD/Defence Science and Technology Laboratories (Dstl) controlled
reference facility, in order to independently assess and influence the system demonstration process, or
devolve responsibility and maintain close visibility of contractor modelling activities.

4.6.9.3.3 In either case, the CSM must ensure maximum compatibility between outputs of the Combat
System level modelling activities and inputs required for modelling at project and capability levels.

4.6.9.4 Modelling Activities conducted during previous Phases

4.6.9.4.1 Models assembled during previous phases, and which represent various aspects of the Combat
System design baseline, should be carried through demonstration and beyond. This is a continuing theme
consistent with the modelling strategy formulated during previous phases and identifies the use of modelling:

a) For analysis to further understanding of system behaviour and to provide confidence in the projected
system operation and performance;

b) For specification through representation of particular facets of the design and identify and specify
information flow across interfaces;

c) To consider dynamic aspects of the system in operation;

d) In support of the assessment of a proposed design or comparison of options against defined criteria
and support trade-off studies;

e) As a formalised description of the Combat System configuration baseline against which changes can
be assessed and their impact explored;

f) As required by MoD policy e.g. Views as required by the MOD’s Architectural Framework (MODAF).

4.6.9.4.2 In pursuit of these objectives, modelling outputs from previous phases are likely to include
Functional Models (including logical models of the requirements analysis, and physical models of
equipments and system design), prototypes of equipment/subsystem Man Machine Interfaces (MMIs),
Equipment AR&M analyses, and preliminary effectiveness models using agreed scenarios. Furthermore,
platform studies will have generated draft platform services’ budgets published in the Weapon Equipment
Schedule (WES) and draft spatial layouts and fitting arrangements which will provide the basis for
consideration of platform integration aspects.

4.6.9.5 Modelling Activities during the Demonstration and Manufacture Phase

4.6.9.5.1 The main objective of modelling in this phase is to use and evolve models generated from earlier
activities to:

a) Enumerate and aid the understanding of requirements, to assist in requirements analysis and
support the manufacture of system and subsystem specifications;

b) Refine model fidelity using data generated from the performance evaluation of real equipment;

c) Assess the impact of any shortfalls or improvements in system design performance;

d) Support the optimisation of the design;

e) Support investigation and problem solving associated with integration across equipment interfaces;

f) Identify under-utilised or dormant capability (in terms of functionality and architectural performance)
accompanying the incorporation of NDIs;

g) Support acceptance of design aspects which cannot be definitively or practically demonstrated (e.g.
operational effectiveness);

h) Support subsequent analysis of test and trials results e.g. pre-trials predictions and post trials
analysis;

Unclassified
116
DEF STAN 21-59 Issue 2

i) As required to support MODAF.

4.6.9.5.2 Modelling is an important technique for the investigation of system performance aspects. Many of
the objectives above require a complementary approach to modelling where the key performance
parameters addressed by one model can be used as a basis for further study in another aspect. The subject
of framework methodologies for identifying, deriving and quantifying key performance parameters, and their
relationship to MOEs, is a developing area currently pursued by both Dstl and industry.

4.6.9.6 Prototyping

4.6.9.6.1 Prototyping particular elements of the Combat System design, such as MMIs and novel signal
processing algorithms, for evaluation outside the core design process is encouraged as a risk-reduction
measure. The usefulness of prototypes however must be justified through trade-off between the cost of
developing representative prototypes to the required fidelity, and the confidence, which can be ascribed to
the results of prototypes, especially in the area of performance.

4.6.9.6.2 Prototypes developed during previous phases can be carried through system demonstration and
manufacture and maintained alongside the evolving design. Some prototyping tools now offer the facilities to
quickly prototype aspects of the system design as a means of exploring design issues. Prototypes
generated through these means can then be used to support specification and detailed designs.

4.6.9.7 Functional Modelling

4.6.9.7.1 Functional models provide a descriptive record of the baseline design against which the detailed
design can be evolved, monitored and evaluated, as a basis for predictive studies and for investigating
potential discontinuities across subsystem/equipment boundaries. A functional (physical) model can be used
as the co-ordinating baseline both as a reference of the evolving design and as a basis for further
investigations into other performance aspects such as operability, architectural performance and AR&M.

4.6.9.8 Human Factors and Operability

4.6.9.8.1 With appropriate HCI operability models and MMI demonstrators developed ahead of equipment
manufacture, potential operator performance, equipment/subsystem inter-operability and proposed drills can
be evaluated without the need for manufacture hardware and/or software.

4.6.9.8.2 These can be refined, as design performance data becomes available. Parameters, which reflect
equipment and system operability may be entered into effectiveness models to assess their impact on
system effectiveness in, agreed operational scenarios.

4.6.9.9 Architectural/Engineering Performance Studies

4.6.9.9.1 Architecture modelling serves to explore the physical characteristics of the Combat System design
to produce an objective analysis of:

a) Interface loading identifying bottlenecks and under-utilised capacity;

b) System response to interface over-loading;

c) Likelihood of data loss due to overwriting of data, on both interfaces and buffers;

d) Processor loading;

e) System response times;

f) Interaction with other sub-system components and external systems.

4.6.9.9.2 The Combat System design as defined for demonstration and manufacture provides the most
stable, detailed and thereby valid baseline for detailed architectural investigation. As subsystem and
equipment design information becomes definitive, an architectural model can be developed to represent the
evolving solution and provide a realistic model of system dynamics for evaluation of key performance
parameters.
Unclassified
117
DEF STAN 21-59 Issue 2

4.6.9.10 Availability, Reliability and Maintainability AR&M

4.6.9.10.1 AR&M are vital operational characteristics and between them have a dominant impact upon
both operational effectiveness and Life Cycle Costings (LCCs). Initial AR&M assessments in Assessment
Phase can only at best reveal indications of potential problem areas. Detailed design information (down to
component level) produced during demonstration is necessary before any meaningful AR&M statistics can
be generated. As more definitive design information becomes available (including from prototypes and pre-
production equipment), detailed AR&M analyses of equipment may be conducted and AR&M prediction may
yield results of more confidence. Impact of significance to the TLMP must be recorded.

4.6.9.11 Operational Effectiveness

4.6.9.11.1 Effectiveness may be considered as how well the Combat System performs its allotted
missions, roles and tasks in pre-determined scenarios, and is derived from an assessment of the system’s
performance expressed in terms of its functionality, architecture, operability and availability.

4.6.9.11.2 To maintain a common basis for performance assessment as a whole, it is desirable that
operability, AR&M and effectiveness be assessed against a set of common scenarios, which must be
coherent with approved operational concepts and maintained by MOD. This should give an indication of the
use of the system in a representative set of conditions, so that meaningful objective comparisons can take
place.

4.6.9.11.3 As the detailed design solution is realised and indicative performance is provided through other
modelling and evaluations, the effectiveness model developed during earlier life cycle phases can be further
refined. An effectiveness prediction can also take into account the compliancy of solutions against functional
and performance requirements and assess how effective the system as whole is as a result of the additional
capability. Results which have an impact on the requirement must be recorded and may be used to advise
trade off decision.

4.6.9.12 Model Validity

4.6.9.12.1 The validity of the modelled system is an important consideration and care should be taken to
verify and calibrate model outputs against real-world data wherever possible. Any conclusions made as a
result need to be qualified in terms of the limitations of the modelling technique and the fidelity of the model
representation. With many models, validity cannot be formally assured and, in practice, confidence must be
gained in them in part through their usage. As with other aspects, modelling must be under configuration
control.

4.6.9.13 Synthetic Environments

4.6.9.13.1 Synthetic Environments are distributed networks of interacting systems which can be used for
system demonstration and evaluation, training, mission rehearsal, strategy and tactics demonstration.
Synthetic environments can be created involving a wide variety of training simulators, war game facilities and
real equipment in live exercises all integrated through the extensive use of specialised protocols. These
techniques are currently emerging and should offer scope for reducing integration risk.

4.6.9.13.2 The concept aims to unite available and emerging technologies to gain an insight into system
functionality at the earliest opportunity. It proposes the implementation of a virtual system, using a
combination of established equipments, bespoke hardware-based simulators and model-based simulated
equipments using modelling tools.

4.6.9.13.3 System functionality can be evaluated using a library of standard acceptance scenarios, which
cover examples of the physical and operational environments. Each of the entities which form the system
need not be present at any one location but can take part in a system simulation either locally to a scenario
controller or via telecommunications.

4.6.9.13.4 This approach enables activities akin to system integration at a system level based upon
design concepts rather than implementation. As equipments become available, equipment prototypes and
the system re-examined, repeating trials performed with the simulators to investigate system compatibility
can replace simulations. The results of these trials can be fed reiteratively into the system demonstration
phase to yield a more compliant and effective system. The evolution of the system can continue through the

Unclassified
118
DEF STAN 21-59 Issue 2

life cycle to provide the basis for a shore facility in which training and other activities requiring a valid and
accurate representation of the final system can take place.

4.6.9.14 NDIs and COTS

4.6.9.14.1 For modelling to reveal its potential, detailed design data is a necessary pre-requisite for all
aspects of the assessment. The adoption of NDIs (excluding legacy systems for which performance data is
available) and widespread usage of COTS technology is likely to provide less visibility of the detailed design
since Intellectual Property Rights (IPRs) are fiercely protected. Where NDIs and COTS provide a critical
component of the Combat System design, then it will be necessary to provide an independent evaluation of
the subject equipment across a predetermined set of performance evaluation criteria.

4.6.10 Integrated Logistic Support (ILS)

4.6.10.1 Combat System-level ILS Issues

4.6.10.1.1 The demonstration and manufacture phase delivers the military capability required and
expressed in the URD – this includes the support solution. From the Combat System perspective, this phase
is typified by the acquisition of individual equipments and preparation for their integration together and with
the platform environment and through life maintenance.

4.6.10.1.2 All ILS activities need to be considered from both system and platform integration viewpoints
through extensive liaison with both EPMs and the platform design authority. In support of this objective, the
WSM will have access to appropriate ILS expertise within his team or maintain direct lines of communication
with a dedicated ILS team. The maintenance of external interfaces is also part of the support solution and
business agreements are required to back this up.

4.6.10.2 ILS Activities during the Demonstration and Manufacture Phase

4.6.10.2.1 The main thrust of ILS at this phase is the continued application of ILS and Logistic Support
Analysis (LSA) principles throughout the subsystem/equipment acquisition process, and the preparation of
optimum arrangements to satisfy the Combat System’s operational and upkeep needs when in-service. This
will be achieved through the fully tailored ILS/LSA programme with inputs to the LSAR. The range of ILS
activities to be conducted during this phase is illustrated in Figure 4.10 which also provides Def Stan 00 60
task designations where appropriate.

Unclassified
119
DEF STAN 21-59 Issue 2

EQUIPMENT ACQUISITION ILS ILS/LSA


Monitor system/equipment design process 100 PLANNING & Review (and update) ILSP and LSAP [102]
Ensure equipment efficiently supported CONTROL Programme and Design Reviews [Task 103]
Accept Contractor ILS Deliverables
200 MISSION & Update Use Study [Task 201]
SUPPORT Mission & Support System Standardisation [Task 202]
COMBAT SYSTEM SYSTEM Comparative Analysis [Task 203]
DEFINITION Review Technological Opportunities [Task 204]
Review Supportability/Design Factors [Task 205]
SUBSYSTEMS 300 PREPARATION &
EVALUATION OF Review Functional Requirements [Task 301]
SUPPORT SYSTEM Review Support System Alternatives [Task 302]
ALTERNATIVES Review Trade-off Analysis [Task 303]

EQUIPMENTS 400 LOGISTIC SUPPORT Perform Task Analysis [Task 401]


REQUIREMENTS Early Field Analysis [Task 402]
Post Production Support Analysis [Task 403]
500 SUPPORTABILITY Supportability Assessment Report [Task 501]
ASSESSMENT
PLATFORM

PLATFORM DESIGN & BUILD ILS


Ensure CM/Platform Fit Definition system LSAR Reports
set up and operated correctly
Provide the Platform Authority with Maintenance Planning
evidence of support requirements Supply Support
compliance Support & Test Equipment
Manpower and Human Factors
LSAR Training and Training Equipment
Technical Documentation
Packaging,Handling,Storage & Transportation
Facilities
Non-Operational Computer Resources Support
Life Cycle Costing
Reliability & Maintainability
Safety

Figure 4.10 ILS Activities Conducted during the Demonstration and Manufacture Phase

4.6.10.2.2 During demonstration, identification of detailed support requirements can be undertaken since
the system/equipment design should be reasonably stable. Whilst some design optimisation is still possible
it should be limited. During this phase, the support infrastructure can be identified and optimised to ensure:

a) Compliance with the overall platform support concept;

b) Limitation of the support requirements (especially unique to type support);

c) Consistency with the available support infrastructure;

d) Availability when required.

4.6.10.2.3 During manufacture, support items should be procured and delivered. The objective is to
provide a cost effective level of support when required. Care must be taken to ensure that any design
changes during manufacture are considered and reflected in the support procurement process. Issues
relating to support during acceptance and hand-over must also be anticipated.

4.6.10.2.4 Throughout this phase, the CSM needs to maintain overall visibility of ILS activities through
close liaison with the ILS manager in order to ensure that the overall strategy is being implemented in a
coherent manner. This will ensure that all deliverables, and in particular the ILS-related items (such as the
LSAR, handbooks, training and support infrastructure) continue to meet the overall Combat System support
requirements at the optimum LCC.

4.6.10.2.5 MoD needs to maintain a close ‘watching brief’ through the scheduled programme of design
reviews and audits as determined by the project review cycle. The review cycle must address and review all
ILS aspects as an integral part of the demonstration and manufacture process across all levels of the
system/subsystem/equipment hierarchy.

4.6.10.2.6 The degree to which scrutiny is necessary depends on the overall ILS strategy appropriate to
the Combat System project. The application of risk identification and management techniques from the
Unclassified
120
DEF STAN 21-59 Issue 2

support perspective across the system hierarchy should serve to identify those areas requiring close
monitoring.

4.6.10.2.7 The key activities during this phase are:

a) Develop Support Policy Statement;

b) Review ILS funding and Long Term Costing (LTC) Estimates;

c) Maintain ILS and LSA Strategies;

d) Maintain Use Study;

e) Maintain ILS and LSA Plans;

f) Review of Contractor ILS and LSA Plans;

g) Review LSA Tasks in Progress;

h) Perform Detailed Task Analysis, and Enter Results of Maintenance Task Analysis into LSAR;

i) Produce Strategy for LSAR In-service;

j) Identify Support Resource Requirements;

k) Update and Review LCC Modelling;

l) Monitor Contractor Logistic Demonstration.

4.6.10.3 Liaison with the Platform Design Authority

4.6.10.3.1 ILS activities conducted throughout the demonstration and manufacture of constituent
equipments of the Combat System cannot be conducted in isolation from the platform design and build
process. The overriding objective here is to synchronise, through the project review cycle, the ILS/LSA
programme across design, AR&M, HF and LCC areas. This is to ensure that the Combat System and the
platform together conform to the through-life support requirements and that there is commonality of purpose
across all ILS activities.

4.6.11 Documentation

4.6.11.1 Objectives

4.6.11.1.1 The D&M Phase marks the beginning of Combat System demonstration as an enterprise
across a number of co-operating organisations necessary to realise the design. The suite of documentation
generated during previous phases continues as statements of Combat System-level objectives and design
intent. These objectives are cascaded through the organisational hierarchy as contractual requirements and
give rise to a plethora of documentation of increasing detail, which refine the requirements and provide
details of their implementation.

4.6.11.1.2 Within the scope of this guide it is not possible to identify each and every deliverable document
across the hierarchy. However, a summary of the key documents is provided together with indications of
associated action required during this phase.

4.6.11.1.3 The role of the MoD CSM is to ensure that all the required documentation is produced to the
requisite content and quality, faithfully reflecting the emerging design which will satisfy all the overall Combat
System objectives.

Unclassified
121
DEF STAN 21-59 Issue 2

Table 4.4 Summary of Documentation


Activity Documentation (Output Products) Associated Activities

Systems Policy and Strategy Papers Updated to keep abreast of demonstrations


Engineering Management Plans (see Project during the phase. Updated, reviewed and
(Technical) and Management) agreed by CSM.
Project System Security Policy
Management Software Management Policy
Configuration Management Plan
Life Cycle Costings
Safety Cases

System URD, SRD Configured as baseline data, together with


Requirements CONEMP/CONUSE acceptance data Changes raised by DEC
ITEAP defined by IPT RMs and investigated by
TLMP CSM. Changes against the baseline
embodied in baseline increments when
agreed.

Change investigation and impact analysis


performed by CSI. Agreed changes
promulgated down the contractual hierarchy
as necessary.

The CONUSE is developed from the


CONEMP to reflect the actual system
solution.

System Design System (Design) Specification Maintained by CSI under direction of CSM.
Coherence Specification Configured as baseline data. Used to
Subsystem Specifications support investigation of change impact as
Interface Documentation (SIDs, IFSs, above.
DESs)

Combat System Data Management Policy Developed by the CSI under direction of
Demonstration Shore Facility Integration Strategy CSM.

Equipment Equipment FDIP Process Plans Developed by EDC under direction of CSI (or
Demonstration and Equipment Requirement/Procurement EPM dependent on Design Authority
Manufacture Specifications/SOW/STIR arrangements). Reviewed and agreed by
Equipment AR&M Reports CSI and CSM.
Equipment Interface Documentation
Equipment Manufacture Drawings
Equipment Guidance Information (IGI &
FGI)
Equipment MRI data
Equipment Test Schedules and results.

Unclassified
122
DEF STAN 21-59 Issue 2

Summary of Documentation (continuation)

Activity Documentation (Output Products) Associated Activities

Platform Design Design Baseline Definitions (Naval Developed by PDC under direction of PPM.
Architecture, External Structures, Deck Reviewed and agreed by PPM and CSM.
Structures, Bulkhead Penetrations, Chilled
Water, Ventilation, Hydraulics, Heat
Management etc.)
Design Disclosure Papers
Load Analysis Reports
Platform Design Assessment Reports
Safety Justification Report
General Arrangement (GA) Drawings
Signature Management Plan
Interface Certificates
Interim Guidance Information (IGI)
Final Guidance Information (FGI)

System Studies Operational Scenario Definitions Conducted by CSI under direction of CSM.
Effectiveness Models Reviewed by DEC and FLEET
Effectiveness Assessment Reports

Operability Demonstrators Conducted by CSI under direction of CSM.


System Operability Assessment Reports Reviewed by IPT RMs and CinCFleet.

Functional Models Developed by CSI under direction of CSM.


Architecture Assessment Reports Subsystem/Equipment-level modelling
AR&M Modelling and Reports conducted by EDC under direction of
Trade-off Study Reports CSI/CSM.
Reviewed and agreed by CSM.

Integration, Test & Integration Test Evaluation and Developed by CSI under direction of CSM.
Trials Acceptance Plan Reviewed and agreed by CSM.
Shore Integration PFA Strategy
Integration Test
Requirements/Specifications
Test Equipment Specifications
Trials Policy, Trials Requirements, Trials
Management Plan
Subsystem Integration Test Procedures
and Reports
Combat System Integration Test
Procedures and Reports

Equipment II/Trial Procedures and Developed by EDC under direction of CSI (or
Reports EPM dependent on Design Authority
Equipment PFA/STW Procedures and arrangements). Reviewed and agreed by
Reports CSI and CSM.
Equipment HAT(E) Procedures and
Reports
Equipment Integration (PINT/SINT/FINT)
Test Procedures and Reports

Unclassified
123
DEF STAN 21-59 Issue 2

Abbreviations

CSM MoD Combat System Manager


ILSM MoD ILS Manager
CSI Combat System Integrator
CSSC Combat System Support Contractor
PPM Platform Project Manager
PDC Platform Design Contractor
EDC Equipment Design Contractor

4.6.12 Specialist Discipline Support

4.6.12.1 Objectives

4.6.12.1.1 Specialist Discipline Support is a general term for the many different specialisms, which need
to be considered during the design, demonstration and build of the Combat System. The main purpose of
grouping these separate specialisms together under a single heading is to make sure that they are
individually resourced and collectively addressed.

4.6.12.1.2 The main purpose of specialist discipline support at this phase is to ensure that all design,
demonstration and manufacture issues are appropriately addressed from each specialism viewpoint. For
each specialism, the objectives are to:

a) Review the Combat System design solution and identify improvements to the design where possible;
(Note: Non-functional areas, e.g. Security, Safety and Performance, especially where certification
require specialist support);

b) Predict the performance of the design;

c) Devise and agree the tests and trials which will show that the design meets the requirements;

d) Review evidence of compliance with the requirements.

4.6.12.2 MoD CSM Role

4.6.12.2.1 The MoD CSM role is to provide guidance to the Combat System integrator, to review and
approve progressive acceptance evidence in support of the specified requirements. In support of this
objective, the CSM will require access to a pool of specialist engineering expertise either within his own
team, or temporarily assigned from elsewhere.

4.6.12.3 Concurrent Engineering

4.6.12.3.1 Concurrent engineering is a key theme for the demonstration of integrated systems. The
implementation of concurrent engineering practices must serve to apply participating specialist disciplines to
ensure that the evolving design can be efficiently produced and supported. In organisational terms, this
requires an integrated multi-disciplinary team approach to system demonstration, wherein peer participation
of all engineering disciplines is applied throughout each system life cycle activity. Concurrent engineering
places significant demands on understanding, processes and procedures to achieve overall system-level
technical coherence.

4.6.12.4 Activities during the Demonstration and Manufacture Phase

4.6.12.4.1 As with all previous phases of the life cycle, the consideration of the evolving design from a
number of engineering discipline perspectives is required to support trade-off analysis to optimise the system
design. Specialist support is needed in the areas identified in Table 4.5.

Unclassified
124
DEF STAN 21-59 Issue 2

Table 4.5 Specialist Discipline Support


Engineering Discipline Priority Activities at this Phase

Air Engineering Liaison with aircraft project(s) to refine Combat System interfaces.

Alignment Review design/implementation documentation to ensure that all equipments (in


particular Command System, sensors and effectors) are aligned to a common
platform datum.

AR&M Ensure visibility of equipment and system AR&M analyses in support of predictive
compliance with AR&M requirements.

Cost Maintain and refine Through Life Costings/LCCs as demonstration progresses.


Influence the demonstration process to optimise LCCs.

Documentation Review and approve operating documentation including handbooks, operating


instructions, test instructions, maintenance instructions and training material. See
also Def Stan 00-60, RN ILS Manual.

EMC, RADHAZ, Tempest, Identify, plan and manage signature parameters including EMC, Radiation
Magnetic and Nuclear Hazards, Tempest, Magnetic, Electromagnetic Pulse and Electrostatic Discharge.
Survivability Review predictions of system susceptibility and emissions, and proposals for
improvements. See Def Stan 08-124.

Environmental Factors Ensure that equipment is developed, tested and accepted against appropriate
and realistic environmental requirements (atmosphere, temperature and humidity,
noise, vibration, shock, watertight integrity, fire etc). See Def Stan 08-124.

HF/Operability Raise and promulgate fleet-wide HCI and ergonomics issues and assess impact
of evolving design on manpower, tasking and skills requirements. Develop HF
Log detail and conduct regular assessment of Combat System HFI. Update and
revise HF AQ and ACs. Oversee demonstration of training aids, rigs and
simulators. See Sea Technology Group Publications 10 & 11.

ILS Facilitate design for support trade-offs. LSAR population. See ‘ILS’ in this
Section, Def Stan 00-60, RN ILS Manual.

Installation and Ship Services Ensure early Guidance Information is made available to the platform projects.
See ‘Combat System Demonstration’ in this Section.

Interface Data Management Ensure Interface and data management controls are in place iaw Integration
Strategy. See ‘Combat System Demonstration’ in this Section.

Modelling Use of MoD reference sets to verify modelling outputs from Equipment-level and
Combat System-level modelling activities in particular functionality of physical
design, operability and operational effectiveness. See ‘System Studies’ in this
Section.

Specialist Discipline Support (continuation)

Engineering Discipline Priority Activities at this Phase

Mutual Interference Physical, electronic, shock, electro-magnetic.

Naval Architecture Liaison with platform/whole warship design and build projects for review of

Unclassified
125
DEF STAN 21-59 Issue 2

Engineering Discipline Priority Activities at this Phase

Combat System contributions to buoyancy, stability, Cs of G etc.

Operational Prediction of MOPs and MOEs in support of capability assessment. Refinement


Performance/Effectiveness and agreement of operational scenarios used for modelling and acceptance.

Safety Review safety issues through auspices of warship-level Safety Panel in


accordance with JSP 430, DEF STAN 00-56 and the Health and Safety at Work
Act (HASAWA). Develop Ship Safety Case.

Security Ensure compliance with the System Security Policy for identification and
authentication, control of access, security accounting and audit, TEMPEST
protection, and generation/update of pertinent Security Operating Procedures. In
accordance with JSP 440.

Shock and Vibration Ensure that new equipments are designed to withstand shock parameters as
assigned iaw DG Ships Parts 1 and 2. Further information regarding shock is
provided in the Shock Manual. See BR 3021 and Def Stan 08-107.

Software Demonstration Ensure that all software is developed according to a consistent process capable
of supporting predictive and quantifiable metrics (in accordance with an
established Software Capability Maturity Model).

Structural Engineering Review structural analysis using finite element analysis models and tools.

Training Review and agree training needs of operators, maintainers and base support,
training equipment, including shore-based and ‘on-job’ facilities. See also RN ILS
Manual.

Interoperability IO is a mandated KUR for all projects delivering CIS content, See AMS IO CIS
Topic. Requirements to support it will apply to many equipments.

4.6.12.5 AR&M

4.6.12.5.1 Throughout the D&M Phase, the Reliability and Maintainability (R&M) project panel will
continue to provide the project manager with advice and monitor the achievement of R&M requirements by
the contractor. If it becomes apparent that the R&M requirement will not be met, or achievement may be
threatened by financial or timescale constraints, the project panel should review the situation and advise the
project manager so that he may decide the best course of remedial action.

4.6.12.5.2 Hence it is important that the AR&M project panel maintains full visibility of R&M matters
throughout project demonstration and continue to function until System Acceptance (SA) has been achieved.
Evidence that R&M requirements specified in the URD have been met is required before a submission for
acceptance can be made.

4.6.13 Configuration Management (CM)

4.6.13.1 Objectives

4.6.13.1.1 CM of the emerging design is a critical activity within the D&M Phase. All information
associated with the Combat System/subsystem/equipment hierarchy and its relationship to the platform
needs to be managed under a formal regime in accordance with the CM plan.

4.6.13.1.2 The main objectives of this activity are to ensure that the design is progressed through the
contractual hierarchy though an auditable set of inter-relating processes, and that change is managed in a
controlled manner. CM therefore supports the assessment of change against incremental baselines used to
co-ordinate and communicates the evolving Combat System design solution.

Unclassified
126
DEF STAN 21-59 Issue 2

4.6.13.2 MoD CSM Role

4.6.13.2.1 The primary role of the CSM is likely to be that of ‘informed customer’ ensuring that the CM
function is adequately policed and that CM baselines are co-ordinated across all D&M processes. The MoD
activities during this phase should be thought of as the top level of the design and implementation ‘pyramid’
as depicted graphically in Figure 4.11. MoD needs to ensure that the SE process applied throughout the
Combat System demonstration and manufacture enterprise is optimised to engineer products which comply
with the requirements and support the specified level of capability.

4.6.13.2.2 The level of involvement should be determined chiefly by the contract management policy.
Clearly, it is important for the CSM to keep a close watch and actively participate in all Combat System level
reviews and audits which should highlight any lower-level activities in the subsystem/ equipment areas,
which require closer scrutiny. In parallel, the risk management process should highlight any potential areas
of concern well before actual problems arise.

4.6.13.2.3 It is important that MoD activities in support of Combat System demonstration and manufacture
activities are co-ordinated against an appropriate project review cycle. This is so that the results of any intra-
mural or independently funded system studies (such as those conducted using MoD reference models) can
be used to influence demonstration and manufacture at the earliest opportunity.

4.6.13.3 Activities during the Demonstration and Manufacture Phase

4.6.13.3.1 CM, though important during previous phases to keep track of requirements, specification and
plans, becomes a fundamentally significant issue with the proliferation of requirements, specifications,
physical deliverables, test and acceptance data during the demonstration and manufacture phases. CM
provides the means for co-ordinating the design and definition of the product and for assessing and
progressing design changes. All products and documentation must be configured within the CM regime.
The various facets of CM during these phases are illustrated in Figure 4.11, which illustrates the extent of
CM of SE activities across the Combat System hierarchy.

4.6.13.3.2 CM must be seen in the context of the overall management objectives documented by
management plans throughout the enterprise. Project management documentation must also be configured
within the Combat System CM regime.

Unclassified
127
DEF STAN 21-59 Issue 2

MOD needs to be confident that all levels of the hierarchy are audited. This is to ensure that the
SE process is optimised to engineer products which comply with the requirements and support the
specified level of capability.

Support Baselines
Acceptance Baselines

Verification Baselines

Physical Baselines

Functional Baselines

Requirements Baselines
Whole
Warship

Combat
System

Subsystem/
Equipments
The
Project
Review
Cycle imposes
formality across
Development and
Ultimately, Configuration Management is a whole-product issue, which needs to be Production, synchronising
co-ordinated across the Combat System/subsystem/equipment hierarchy. Each level Combat System-level and lower
must apply CM to an appropriate degree, supported by automated tools and procedures. level activities

Figure 4.11 Configuration Management Baseline

4.6.13.4 Baselines

4.6.13.4.1 CM provides the mechanisms through which the design can be taken through D&M in a
controlled manner. This is achieved through imposition of CM baselines across each of the SE activities.
The baselines provide a progressive scheme, which records the status of the design, demonstration,
manufacture, integration and test processes with rigour so that the design is supported by an auditable
regime.

4.6.13.4.2 The following items need to be incorporated in the configured project baselines with
appropriate mechanisms for change to be authorised, controlled, recorded and managed:

a) Management Plans;

b) Requirements hierarchy with associated visibility of constraints and acceptance information;

c) Models;

d) Build Records;

e) Design and Demonstration Documentation;

f) Manufacture information, in particular Installation Guidance Information.

4.6.13.4.3 A number of baselines across SE activities are recommended as follows:

a) Requirements Baselines - identify all operational, functional, physical and performance requirements
together with their constraints, source derivations and allocations;

Unclassified
128
DEF STAN 21-59 Issue 2

b) Functional Baselines - determines the status of functional requirements as explored and expressed
through modelling of the design and supported by traceability between requirements and model
elements;

c) Physical Baselines - record the evolving design implementation as it is progressed through design,
demonstration and manufacture activities;

d) Verification Baselines - to manage the models and analyses used to predict Combat System
performance and to refine their predictions, as more detailed performance data becomes available.
This should includes data of relevance to both performance and overall capability;

e) Acceptance Baselines - established alongside the requirements baseline to control associated


acceptance information including URD, SRD, ITEAP and TLMP, proposed evidence of compliance,
procedures, tolerances and pass/fail criteria;

f) Support Baselines - to maintain data in the LSAR alongside the evolving Combat System
implementation.

4.6.13.4.4 Each of the baselines should be reviewed at the point in the project review cycle at which they
are first instantiated and thereafter audited at each formal review. The project review cycle provides the
structure through which project baselines and change control processes are formally audited. The baselines
provide a solid foundation for the impact assessment of engineering change requests through which change
control can be effected. Each baseline represents a particular aspect of the design evolution and should be
synchronised so that the design itself moves forward through the formal process of reviews.

4.6.13.5 Maintenance of Baseline Data

4.6.13.5.1 With the increasing quantity of information to be configured, it is necessary to provide an


environment through which all data (including models and engineering information) can be effectively
managed. Some form of electronic data management with recourse to hard copy where necessary, is an
essential part of modern CM.

Unclassified
129
DEF STAN 21-59 Issue 2

This Page Intentionally Left Blank

Unclassified
130
DEF STAN 21-59 Issue 2

Systems Engineering Guide for Naval Combat Systems –


In-Service Phase

5. In-Service Phase

5.1 Introduction

5.1.1 The Acquisition Management System (AMS)

5.1.1.1 The prime source of guidance for the implementation of Smart Acquisition processes within the
DPA, DLO and DCSA for EP and STP projects is contained in the AMS at www.ams.dii.r.mil.uk or
www.ams.mod.uk. The content of this Def Stan uses the basic principles contained within the AMS and
whilst these are unlikely to change, the implementation details may. The AMS is the subject of frequent
update and should therefore be consulted for clarification of that detail.

5.2 Purpose of the In-Service Phase

5.2.1 The purpose of the In-Service (IS) phase is to support and maintain the capability to fulfil operational
requirements. This includes the upkeep and support of both the operational Combat System and the shore-
based development, integration and training facilities. From the Combat System perspective the IS phase is
‘phased in’, with equipments entering the stage separately as they each achieve System Acceptance.
System Acceptance of the Combat System as a whole coincides with the acceptance of all constituent
subsystems/equipments and ensures that the support infrastructure is in place.

5.2.2 Through previous phases, as the design was implemented, the characteristics of integrated
equipments will have determined the actual properties of the overall Combat System. Support
considerations will have been addressed in earlier stages through the application of Integrated Logistic
Support (ILS). In the IS phase, ILS becomes the dominant discipline as the support principles are put into
practice.

IN-SERVICE IN-SERVICE COMBAT SYSTEM


UPKEEP ASSESSMENT DESIGN MODIFICATION

SE Process
COMBAT SYSTEM COMBAT SYSTEM SD
SA
RE
SUBSYSTEMS SUBSYSTEMS
SS DP

EQUIPMENTS EQUIPMENTS Requirements Acceptance

SPARES DATA RECORDING & ANALYSIS


FIXES DEFECTS & DEFICIENCY REPORTS
ENHANCEMENTS OPERATIONAL DEFICIENCY Analysis/Design Integrate/Test
REPORTS

Modelling, Analysis and Acquire Equipment


Assessment
Support Infrastructure

The In-Service Support stage is characterised by the maintenance and repair of the operational Combat System through upkeep support.
Data gathered from operational usage of the Combat System provides the basis for continued assessment of system performance. The
generic SE process provides a framework for the investigation of system characteristics, shortfalls and potential solutions. This may lead to
improvement or enhancement of the Combat System implementation so that it continues to meet its operational requirement.

Figure 5.1 Combat System In-Service Phase

5.2.3 The baseline Combat System capability which has achieved System Acceptance must be not be
allowed to degrade whilst IS. To this end, the Combat System must be supported through upkeep, by the
provision of spares, fixes and enhancements, as necessary. IS assessment of the warship and Combat

Unclassified
131
DEF STAN 21-59 Issue 2

System serves to identify shortfalls which may require remedial action, and even modification to the design.
These themes are illustrated in Figure 5.1, which identifies the central IS activities as IS upkeep and IS
assessment. These give rise to Combat System design modification depicted by the familiar ‘V’
development model of system implementation.

5.2.4 Pre-planned capability upgrade may be effected as part of an Incremental acquisition approach. In
this approach, staged upgrades to the combat system are made as budgetary constraints allow, or military
demand or threat evolution requires, and/or technology maturity permits. Design and Acceptance of the
successive increments should be conducted in a manner which keeps the amount of system re-testing to a
minimum.

5.2.5 In-Service Support (ISS) Activities

5.2.5.1 The realisation of ILS which manifests itself through the central ISS activities of IS upkeep, IS
assessment and Combat System design modification is shown in the context of other Systems Engineering
(SE) related activities, together with the operational IS Combat System in Figure 5.2.

5.2.5.2 Once the Combat System has entered service, the maintenance and assessment of the IS Combat
System becomes the driving force for any potential enhancements. This means that the assessment of the
implemented system is the reference from which other activities will be proposed and conducted. The basis
for this assessment will be the suite of performance models and supporting documentation assembled within
a through-life support infrastructure.

MAINTENANCE/ DATA TRIALS and


ENHANCEMENT ACQUISITION ACCEPTANCE
COMBAT SYSTEM

In-Service Combat System REMOVAL and


SUBSYSTEMS OPERATION DISPOSAL
Disposal by Sale
Salvage For Spares
EQUIPMENTS
Destruction

Integrated
Combat Systems IN-SERVICE SUPPORT
Shore Facilities, Trainers
FOC, Follow-on Vessels
SYSTEMS ENGINEERING (TECHNICAL)
and PROJECT MANAGEMENT

INTEGRATED LOGISTIC SUPPORT

IN-SERVICE IN-SERVICE TRIALS and


UPKEEP ASSESSMENT ACCEPTANCE

SYSTEM
Through-Life DESIGN
Support Infrastructure MODIFICATION

Training Through-Life
Facilities Support System SYSTEM STUDIES
Key Outputs
Shore Performance
Case for future capability
Facilities Models DOCUMENTATION
Proposals for
Test Design MLU/Enhancements
Equipment Documentation SPECIALIST DISCIPLINE SUPPORT Learning From Experience
Reports
Spares Through-Life
Data
CONFIGURATION MANAGEMENT Project Archive

Figure 5.2 In-Service Support Phase, Overall Process

5.2.5.3 Overarching the central ISS activities are the project management and SE (Technical) management
functions. In keeping with previous sections, activities which support the central activities throughout the
stage are depicted separately. These address the conduct of system-level studies, the production of
documentation, specialist engineering discipline support and Configuration Management (CM).

5.2.5.4 The infrastructure and mechanisms required for support will have been considered during earlier
stages and will already exist when the ISS stage is reached. It is this fact which is inherent within the ILS
strategy which enables analysis of supportability throughout the Combat System’s life.
Unclassified
132
DEF STAN 21-59 Issue 2

5.2.5.5 A Combat System’s component parts will usually consist of complex equipments, which are the
subject of separate procurement programs as well as Commercial Off The Shelf (COTS) items, and items,
which are already in service. Supportability of the complete system therefore demands a co-ordinated and
structured approach with an infrastructure designed to minimise the cost of ownership of the system and
ensure that it continues to meet its design intent.

5.2.6 System Acceptance, Support Handover and Operational Handover

5.2.6.1 There are two aspects of ISS: the initial support of the Combat System and equipments prior to
ultimate acceptance of the Combat System; and the support of the Combat System after this point through
the operational lifetime of the warship. How these are to be managed should be stated in the TLMP and
ITEAP. Combat System Acceptance represents the point of transfer of responsibility of support from the
Combat System procurement authority to the Combat System support authority and this can be a phased
handover as illustrated in Figure 5.3.

COMBAT SYSTEM Combat System Combat System


NWHTs/FWA NWSTs/FWA FWA ISS
Trials Trials

IN-SERVICE EQUIPMENT

Equipment HATs Equipment SATs ISS


Equipment HATs Equipment SATs ISS
Equipment HATs Equipment SATs ISS

NEW-TO-SERVICE EQUIPMENT

Equipment NWHTs/FWA Trials Equipment NWSTs/FWA Trials FWA ISS


Equipment NWHTs/FWA Trials Equipment NWSTs/FWA Trials FWA ISS
Equipment NWHTs/FWA Trials Equipment NWSTs/FWA Trials FWA ISS

The Combat System will comprise both new/modified (New-to-Service) equipments for which FWA is sought and equipments
which have already achieved FWA (In-Service). Combat System FWA can only follow FWA for each of the constituent
equipments and handover from the Equipment Design Authority to the Equipment Support Authority therefore will be phased
over a period of time as each equipment achieves FWA.
Please note : for FWA, read System Acceptance

Figure 5.3 Staged Handover of Support Responsibilities

5.2.6.2 In order to promote the application of SE principles throughout these latter stages, it is desirable that
the System Acceptance of systems and equipments coincide with the delivery of all DLODs and the
handover of the Combat System for operational use (e.g. under a Certificate of Clearance for Use (CCU)).
This however is unrealistic for projects other than a new class of platform with predominantly new
equipments. Nevertheless the CSM, in conjunction with Customer 2 should produce a capability roll-out plan
to first deliver the capability required at ISD and then the remaining capability to achieve Full System
Acceptance.

5.2.6.3 A pragmatic view must be taken in the light of the procurement regime and the relative priority of
equipment and system programmes. For equipment developed as a fleet-wide fit, there is a balance to be
sought between the needs of the Combat System programme and that of the equipment in its wider context.

5.2.6.4 Equipment programmes are often asynchronous with warship programmes and have to meet their
own contractual milestones (including System Acceptance) which do not necessarily align with the Combat
System Acceptance programme. Equipments may be fitted to different platform classes, the Combat
Systems of which have conflicting System Acceptance programmes. Furthermore, Combat Systems are
subject to ongoing development even when IS and the new equipment may be supplied by DPA and DLO.

Unclassified
133
DEF STAN 21-59 Issue 2

5.3 Inputs

5.3.1 Inputs from the Previous Phase

5.3.1.1 The installed Combat System equipment is handed over to CINCFLEET at ISD with a CCU defining
the limitations of operation, following System Acceptance. Responsibility for the support of the IS Combat
System is also normally handed over at this time from the DPA to the DLO along with financial accounting
responsibilities.

5.3.1.2 System Acceptance includes acceptance of all the separate DLODs against the URD and SRD in
the manner previously established by the CSM and IPTL (in the ITEAP) and agreed with both Customers 1
and 2.

5.3.1.3 Supply support mechanisms developed with the involvement of the support authority during previous
stages will be administered by the DLO. CM of Combat System equipment configurations and associated
items listed above will be administered within the CM process of the whole warship. Additionally the
Logistics Support Analysis Record (LSAR) developed during earlier stages, will be maintained to reflect
actual support performance.

5.3.2 Relationship with the In-Service Combat System

5.3.2.1 Documentation raised as a result of the operation of the IS Combat System also serves as input to
the activities performed within the IS stage. These include:

a) Defect and deficiency reports identifying deficiencies or failures considered to have resulted from
defective design;

b) Operational defect reports identifying operational performance deficiencies which require urgent
action.

5.3.2.2 Information exchange between onboard engineering databases and the support infrastructure also
needs to be considered. This includes configuration data and statistical equipment performance data
gathered on board which needs to be transferred into the UPKEEP system.

5.4 Outputs

5.4.1 Outputs in Support of In-Service Operation of the Combat System

5.4.1.1 Amongst the many output products of the IS stage, the single and most significant of these is the
equipment modifications (hardware and/or software) and associated documentation provided to CINCFLEET
to maintain the required level of operational capability.

5.4.2 IS Phase Outputs - to Removal and Disposal

5.4.2.1 Removal and Disposal will apply to all Combat System equipment and related items which have
reached the end of their IS life whether due to declared obsolescence (including equipment removed from
platforms undergoing refit) or through sale to another nation.

5.4.2.2 Depending upon whether the Combat System remains in use in other assets, disposal may also
apply to hardware within the IS infrastructure particularly training facilities, SDF, test equipment and spares.

5.4.3 Key Outputs to Future Programmes

5.4.3.1 Additionally, there are the overall life cycle outputs, which will feed forward into future programmes.
These include:

a) Case for future capability/proposals for Mid-Life Update (MLU)/enhancements, based on the ongoing
evaluation of IS Combat System performance and effectiveness;

Unclassified
134
DEF STAN 21-59 Issue 2

b) Learning from experience reports, identifying business areas and aspects of current engineering
practice, which may benefit from future improvement.

5.4.3.2 As an invaluable source of design, implementation and operational data for future projects, the
project archive and through-life support infrastructure needed to manage support data (i.e. Information
Technology (IT) system equipment) must also be considered for retention/archiving (or disposal). Potential
areas for consideration include:

a) Through-Life Support System(s) including LSAR, spares management systems, handbook


information, electronic documentation;

b) Performance Models/analysis data and design documentation created during the design activities
and maintained/augmented through the operational life of the Combat System in support of Post
Design Support/Services (PDS) activities;

c) Through-Life Test and Trials Data defining the operating characteristics of the IS Combat System.

5.5 Organisation

5.5.1 Organisational Roles

The IS phase involves a number of organisations, which collectively fulfil the roles depicted in Figure 5.4.
As before, the precise set of responsibilities and boundaries within the organisational structure depends on
the prevailing interface between the DPA and DLO, and the level of responsibility devolved to industry.

5.5.2 Contractor Logistic Support

5.5.2.1 Contractor Logistic Support (CLS) is the concept of divesting responsibility for support of
equipments to industry. This will provide incentive to the contractor to concentrate on supportability during
the design stage and to achieve lower spares costs to the MoD by delaying the initial spares provision until a
usage rate has been established. Some contractors may not have the experience to fully understand all the
elements of supportability required by the RN and therefore care should be exercised when a CLS contract
is being considered to ensure that the contractor is completely aware of its implications and of his
responsibilities.

5.5.2.2 CLS has many implications for the organisational boundaries between DLO, (DPA) and industry
during the IS stage. This accompanies a shift of MoD emphasis from direct involvement in IS activities
(‘support provider’) towards a pro-active management role (‘support decider’). As a result, the activities
conducted by the support organisation will move into the industry subcontract domain.

5.5.2.3 Nevertheless, the underlying process through which the IS phase is conducted remains largely
unaffected such that boundaries of responsibility can be overlaid onto the process detailed in Part B.

5.6 In-Service Phase Process

5.6.1 Introduction

5.6.1.1 The ISS phase comprises a set of activities the prime objective of which is to support and maintain
the system’s operational effectiveness. The process demonstrates that the Combat System continues to
meet its design requirements through IS system assessment and monitoring in terms of material and
operational performance; maintenance and defect repair activities; and identifies and plans the
implementation of agreed changes.

5.6.2 In-Service Process

5.6.2.1 The activities undertaken during the IS Phase are depicted in Figure 5.4 which shows the core IS
activities introduced in Part A in the context of related SE activities. Each of these areas is explored in detail
in the clauses, which follow.

Unclassified
135
DEF STAN 21-59 Issue 2

PROJECT MANAGEMENT and Contract Management Risk Management Quality Management Project Management
Systems Engineering Management Acceptance Reviews & Audits

INTEGRATED LOGISTIC SUPPORT

IN-SERVICE IN-SERVICE SYSTEM COMBAT SYSTEM TRIALS and


UPKEEP ASSESSMENT DESIGN MODIFICATION ACCEPTANCE

Test Equipment Data Recording and MODIFICATION ACCEPTANCE/


Analysis REQUIREMENTS CERTIFICATION
Shore Facilities
Defect and Deficiency
Spares Provisioning
Reporting IMPACT COMBAT SYSTEM
Maintenance and Repair ANALYSIS TRIALS
Performance Assessment
Training Co-ordination
AR&M Monitoring RE-INTEGRATION
Supply Support MODIFICATION
EMC DEFINITION AND TEST
Waterfront Support
Signatures
Safety MODIFICATION/A&A
IMPLEMENTATION

SYSTEM STUDIES Maintenance of Prototypes and Models System Change Investigation and Impact Studies
Emergent Requirement Evaluation System AR&M Analysis System Operational Performance

DOCUMENTATION A&A Installation Guidance Information Design Change Safety Case Handbooks
Engineering Databases and Information Systems Records Archive and Library

SPECIALIST DISCIPLINE SUPPORT AR&M EMC Operational Effectiveness Safety Security


Signatures

CONFIGURATION MANAGEMENT Configuration Definition Configuration Control Configuration Accounting

Figure 5.4 In-Service Support (ISS) Phase Activities

5.6.2.2 Feedback from IS operation to the support process is a vital factor in ensuring that any shortfalls
identified from monitoring Combat System performance are fully addressed. System studies provide the
modelling and analysis capability to support this aim.

5.6.3 Systems Engineering (Technical) and Project Management

5.6.3.1 MoD Role

5.6.3.1.1 Prior to embarking on IS activities, the Combat System Manager (CSM) should ensure that, for the
duration of the IS Phase, there will be:

a) A clear statement of the division of responsibilities between the different MoD authorities involved in
IS (e.g. CSM, CINCFLEET (PM and CL), Equipment Project Managers (EPMs) (DPA and DLO),
MCTA, Acceptance Authority et al);

b) A clear statement of where contractor support is to be employed, their responsibilities, the rules
under which the contractors will communicate with other parties involved (both MoD and other
contractors).

5.6.3.2 Management Plans

5.6.3.2.1 There is a need to define the organisational interfaces both within MoD (DPA/DLO) and between
MoD and industry where IS activities are contracted out. The management plan hierarchy described in
Annex B provides the necessary controls. The adoption of suitable plans provides the required visibility of
the management process throughout the organisational structure and need to accompany the project (i.e.
transferred from DPA to DLO at an agreed point). The plans listed in Table 5.1 must reflect the fact that the
scope of activities within the IS stage are significantly less-development oriented.

Unclassified
136
DEF STAN 21-59 Issue 2

Table 5.1 Project Through Life Management Plan (TLMP)


PM Discipline Topic(s) Priority Activities During the IS Phase

Contract Contract Management A CMP should be produced and maintained by the CSM. This
Management Plan (CMP) may call up a Task Specification listing Task Areas and
Task Specification deliverables. The CMP and Task Specification should be
reviewed annually and amended if appropriate.

Risk Management Risk Management Plan Continued application of Risk Analysis methods, update of the
(RMP), Risk Register, Risk Register and raising of RRAPs.
Risk Analysis, Risk
Reduction Action Plan
(RRAP)

Quality Quality Plan The quality plans address the requirements of Def Stan 05-91
Management Software Quality Plan and Def Stan 05-95 and First Level requirements of Def Stan
08-207.

Project Through Life The TLMP should extend over the duration of the IS period and
Management Management Plan address all those issue in the SSE and relating to all aspects of
(TLMP) IS Support.

Assurance Programme Control Development of interfaces with other planning systems to


and Performance exchange planning information as necessary to ensure
Reviews and Audits consistency between the plans.
Project Review and
Regular scheduled review of the programme(s) and progress.
Assurance
Agreement and visibility of the Project Review Cycle; Action
tracking.
Review of methods/tools support and training.
Configuration Auditing of the Configuration Management process for
Management and controlling the effects of change to the system design and
Change Control Plan implementation baseline(s).

5.6.3.2.2 All MoD-specific plans will have been developed during previous stages and need to be revisited
and amended where necessary to reflect the IS stage policy and constraints. Where major elements of the
IS programme is contracted out to industry, appropriate management plans will need to be developed by the
successful contractor.

Unclassified
137
DEF STAN 21-59 Issue 2

5.6.3.3 Systems Engineering (SE) Management

5.6.3.3.1 Although the IS stage accompanies a significant reduction in the level and complexity of tasks
associated with development and integration, there remains a need to co-ordinate and maintain ‘through life’
SE activities. The SEMP inherited from the previous stage should provide an adequate basis for co
ordination of the SE process, tailored to reflect the reduced scope of activities to be conducted during the IS
stage. The SEMP for the IS stage must address (either within itself or through lower-level plans as deemed
appropriate):

a) AR&M analysis;

b) CM;

c) COTS support and upgrade strategy;

d) Defect analysis;

e) EMC;

f) ILS/LSA and continued population of the LSAR (subject to the ILS Plan);

g) Installation engineering;

h) Performance assessment;

i) Safety management (subject to a separate plan);

j) Signature management (subject to a separate plan co-ordinated through the platform project);

k) System modelling;

l) System modifications and documentation (including A&As);

m) Use and maintenance of shore-based facilities.

5.6.4 Integrated Logistic Support

5.6.4.1 Objectives of ILS during the IS Stage

5.6.4.1.1 ILS activity during the IS stage will be aimed at ensuring that:

a) The supportability recommendations are translated into support products, i.e. spares, manuals,
training etc.;

b) The recommended support system is adequate to support the operational system, and is available in
a timely manner;

c) The support system is optimised by using feedback from the field to fine tune the support
infrastructure;

d) The identification of any deficiencies to allow the initiation of corrective action.

5.6.4.2 ILS/LSA Acceptance

5.6.4.2.1 Acceptance and validation of support aspects should be an integral part of the overall ship
acceptance procedures. Evidence will be required to show that the support package is in place and to
provide confidence that the Combat System and component equipments can be supported through life.
Final acceptance may require demonstration of the effectiveness of the support measures.

Unclassified
138
DEF STAN 21-59 Issue 2

5.6.4.3 LSAR Management

5.6.4.3.1 The policy for the management and maintenance of the LSAR will depend on the complexity of the
project and the probability of changes in the future. The LSAR will be transferred to DLO as part of the
transfer of responsibility for the Combat System equipment/platform. This will form part of the formal hand-
over and validation process between DPA and DLO.

5.6.4.3.2 LSAR management also includes development of LSAR interfaces with other organisations and IT
systems, with the collective objective of tracking WLCs.

5.6.4.4 In-service Failure Reporting and Analysis

5.6.4.4.1 A strategy for the level of IS failure reporting and analysis to be carried out will have been
developed which take into consideration:

a) Complexity and/or novelty of the system;

b) Operational significance;

c) Safety significance;

d) Experience with other similar systems;

e) The need to prove reliability or other predictions.

5.6.4.4.2 Defect reporting supports trend analysis used to evaluate the success of the original upkeep policy,
and any corrective measures taken. Upkeep policy should be reviewed regularly to ensure that the
assumptions are still valid.

5.6.4.5 Availability, Reliability and Maintainability (AR&M)

5.6.4.5.1 The AR&M of equipment are a major consideration of the use of support resources and hence IS
costs. The AR&M activities during the IS stage of the Combat Systems life cycle consist of monitoring the
AR&M achieved in real field usage, taking corrective actions for problems identified and considering the
effects of design or usage modifications on AR&M. Data reporting from the field usage can be used for:

a) Feedback to designers to identify and cure AR&M problems;

b) Provide data for IS AR&M trials or for the contractors warranty clause and for System Acceptance;

c) Provide feedback to, or, for support decisions (e.g. spares holdings) and for setting targets for future
equipments.

5.6.4.6 Obsolescence and Disposal

5.6.4.6.1 The Combat System, equipments and platform will have been procured against a predicted, or
required, IS life. This may be extended, or shortened, as overall defence policy dictates. Obsolescence
must be anticipated and activities initiated in response to find a suitable replacement, or extend the life of
equipments and component items.

5.6.5 In-service Upkeep

5.6.5.1 Upkeep Policy and Plans

5.6.5.1.1 Upkeep is the set of related activities, instigated by the support authority, necessary to sustain an
IS system or equipment in a specified material state and/or at a specified level of operational performance.
In the Combat System context, upkeep is defined by Combat System Upkeep Policy and Plans, which co-
ordinate upkeep policy for component subsystems/equipments, by defining common system-level objectives
as summarised in Table 5.2:

Unclassified
139
DEF STAN 21-59 Issue 2

Table 5.2 Upkeep Policy


Policy Area Topics

Overall Upkeep Policy Equipment fault diagnosis including Built-In Test Equipment (BITE).
Overall repair policy: Upkeep by Exchange versus Upkeep by Repair.
Onboard repair.
Onboard maintenance conducted through Planned Maintenance Schedules (PMS).
Base repair/overhaul and requirements for removal whilst de-perming.
Refitting dockyard support for repair, refurbishment, system proving and STW.
Support of shore facilities.
Support of shore-based training equipment including Command Team Trainer (CTT)
and Maintainer trainers.

Upkeep Periods Definition of requirements for upkeep cycles of maintenance periods:

• Self-Maintenance Periods (SMPs) and Maintenance Periods 1,


• Docking Assisted Maintenance Periods (DAMPS), Assisted Maintenance
Periods (AMPs) and Maintenance Periods 2,
• Docking Periods, Capability Update Periods (CUPS) and Refits and
Maintenance Periods 3/4.

Test equipment and tools Common Range Electrical Test Equipment (CRETE).
Calibration.
Test Equipment for shore facilities.

Defects Defect/deficiency reporting and corrective action.

Configuration management Configuration management of IS Combat System configurations and modifications.

Software and firmware Software and firmware issue and control.

Logistic Support Spares provision, built-in spares, initial replenishment stocks and stowages.
Packaging, handling and transportation.

5.6.5.1.2 Upkeep policy is developed and defined during the early stages of the life cycle to the point at
which specific upkeep requirements supporting the policy can be mandated through contractual
arrangements invoked for the development and production stage. Upkeep plans should be maintained
during the IS stage, as a baseline of upkeep and support.

5.6.5.2 MoD Responsibilities

5.6.5.2.1 The DPA and DLO operate many joint working procedures to ensure the seamless transfer of
projects from one organisation to the other and back again when required. These measures include the
‘dual-hatting’ of IPTs. The DLO usually has prime responsibility for ensuring the upkeep and support of
platforms and their systems. Fleet operating patterns directly impact on the maintenance and repair periods
available to Ships and Submarines. Under CSAs between the DLO and CINCFLEET the DLO, tailors its
upkeep and support practices to the needs of the warships.

5.6.5.2.2 Combat System IS matters should be resolved by an upkeep support working party.

5.6.5.3 Upkeep Activities

5.6.5.3.1 The primary objective of upkeep is the planning and provision of manpower, material and facilities
to support the Combat System through its life. This is administered through:

a) Combat System Upkeep Policy and Plans (as above);

b) Combat System Ship Weapons Upkeep Planning Information (SWUPI);

Unclassified
140
DEF STAN 21-59 Issue 2

c) Test Equipment, Hand Tools and Stowages;

d) Spares ranging and scaling, evaluating the implications of introducing changes to the spares
allowance and stock holdings for the Combat System identified from shortfalls in existing
provisioning and allowances;

e) Maintenance Schedules, ensuring their suitability to maintain the declared Upkeep Policy;

f) Training Co-ordination;

g) Handbooks;

h) Master Record Index (MRI);

i) Establishment Lists reviewed and updated to ensure that they reflect all Combat System changes
and contain the necessary information to support maintenance and defect rectification;

j) Defect Management (see also paragraphs on IS assessment);

k) Modification Control (see also paragraphs of Combat System design change management);

l) Ship Fit Configuration definition and control;

m) Software status control;

n) A&A sponsorship and support;

o) Design Authority Refit Requirements (DARR);

p) Weapon Equipment Delivery Programme (WEDP);

q) Post Maintenance Trials Planning;

r) Shore facilities supported both at system-level and for any equipment, which is unique to each
facility including design support, so that each facility can be kept up-to-date and fully operational.

5.6.5.4 Supply Support

5.6.5.4.1 Integrated Supply Support Procedures (ISSP) are an integral part of the ILS process and are
covered by Def Stan 00-60 Part 20-25. They cover the procedures for Initial Provisions (IP), Codification,
Procurement Planning (PP), Order Administration (OA) and Invoicing, based upon the functional standard of
AECMA 2000M and harmonised to integrate with the LSA and electronic documentation standards.

5.6.5.4.2 Current and future supply support will make use of UPKEEP, a major IT system which when
complete will replace many of the current systems such as OASIS, CRISP, PROFILE 77 etc. The purpose of
UPKEEP is to provide IT supports to the DLO with respect to upkeep and stores supply to the Royal Navy. It
allows data to be shared, which means that information is recorded once only on UPKEEP. This information
is then available throughout the MoD.

5.6.5.4.3 Configuration data provides the basis for most activities within the UPKEEP system. It will be used
in maintenance, supply, provisioning and planning activities associated with building, refitting, maintaining
and repairing vessels and weapons systems. In the configuration data control area, UPKEEP will hold
configuration data for surface warships, submarines, Royal Fleet Auxiliaries (RFAs) and other support
vessels, and for systems and equipment fitted at engineering and shore training establishments.

5.6.5.4.4 The provision of accurate configuration data, which is readily available in the DLO, enables
maintenance work to be planned more accurately. This results in the more effective and efficient conduct of
maintenance and upkeep. This may entail configuration of shore facilities to reflect the planned Combat
System configuration and the proving of the update before being effected onboard.

Unclassified
141
DEF STAN 21-59 Issue 2

5.6.5.5 Commercial Off The Shelf (COTS) Support

5.6.5.5.1 The major impact of COTS on the through-life support philosophy is the relatively short life
expectancy of COTS products (between 1 and 5 years maximum), compared to the 25+ years IS life
expectancy of the warship. The MoD must implement a shorter replacement cycle, which will significantly
impact equipment turnover, training of personnel and the provision of spares.

5.6.5.5.2 Research in the US on the implications of introducing COTS hardware and software into military
systems is being monitored by UK MoD through information exchange programmes such as MIEA 5929 (UK-
RN-N-5929). Furthermore, a NATO/industry advisory group has already produced guidance as ANEP 54
‘Guidance for COTS Insertion’ and which includes implications for life cycle support.

5.6.5.5.3 In the future, it is forecast that engineering change will be caused more by supportability issues
excluding AR&M (i.e. items becoming obsolete), than by changing requirements. With commercial
components:

a) Inter-operability is a particular problem - there is no guarantee that the replacement part or parts
supplied from different vendors will work together;

b) Change is likely to occur without notice or notification. Upgrades are driven by commercial factors
alone;

c) Manufacturers performance claims are not always accurate.

5.6.5.6 Waterfront Support

5.6.5.6.1 Support to ships and submarines at the waterfront by a competent, experienced and broadly based
engineer is a key feature of improving availability. The provision of waterfront support is primarily intended to
ensure that ships and submarines achieve and maintain the required degree of operational readiness and
availability.

5.6.5.6.2 Of particular importance is the timely resolution of engineering problems encountered onboard.
These problems can be either maintenance or design-related. The technical response to any such problems
must include a method of ensuring that all of the class is informed of the problems. This will give maximum
exposure within the operating community of problems arising that might affect other vessels, either currently
or at some point in the future.

5.6.5.7 Further Information

5.6.5.7.1 Compatibility with the existing publications for upkeep should be maintained although the impact of
ILS and accompanying tools may require tailoring of existing methods. Guidance should be sought from the
AMS and any other sources of expertise within or outside the MoD.

5.6.6 In-service Assessment

5.6.6.1 Objectives

5.6.6.1.1 IS Assessment is the continuous assessment of the IS capability, performance, effectiveness and
AR&M of the Combat System against the URD and SRD. This assessment process applies to both the
warship(s) and shore facilities and may identify the need for improvements to the Combat System design in
order to maintain or enhance the system design.

5.6.6.1.2 The baseline design of the Combat System will have previously been demonstrated during System
Acceptance. Further assessment is necessary to evaluate performance through life and detect any
degradation.

5.6.6.1.3 IS Assessment requires a close liaison with many MoD, RN and contractor IS support
authorities/agencies with whom it exchanges the necessary data, and whose facilities and expertise are
used for analysis and recording of data, including:

a) The ship or submarines for Combat System performance and effectiveness data;
Unclassified
142
DEF STAN 21-59 Issue 2

b) CINCFLEET for equipment defect reports and data relating to availability, reliability and
maintainability of Combat System equipments;

c) DPA whose facilities are used for the custody and amendment of system interface documentation,
and for the custody, maintenance and operation of specialist Combat System models;

d) Acceptance and Accreditation Authorities and Advisors.

5.6.7 In-service Assessment –

5.6.7.1 MoD Role

5.6.7.1.1 The Combat System design authority should, via the Combat System management group, develop
and maintain a register of Combat System problem areas which should contain:

a) A brief description of the problem;

b) Combat System implication statement in terms of consequent impact on other equipments and/or
operational capability;

c) Actions taken to date including previous review and next review dates;

d) Possible further risk reduction actions;

e) Possible fall back options.

5.6.7.1.2 IS performance monitoring should continuously analyse equipment and system performance,
defect and AR&M reports and other capability and performance data from sea, and reports and analysis from
other facilities. This analysis should enable achieved performance to be established, compared with agreed
performance characteristics and recommendations to be made to rectify under performance.

5.6.7.1.3 The Combat System design authority should keep under review developments in defect and
performance reporting to ensure compatibility with the Combat System philosophy and requirements for
support with the aim of minimising demands on ship’s staff for gathering performance data.

5.6.7.2 Defect and Deficiency Reporting

5.6.7.2.1 Defect Analysis is required to review Combat System and equipment defect reports and identifies
remedial action. This demands liaison with all relevant authorities to ensure that work is progressed
satisfactorily or, when system-level issues arise, conduct the management activities leading to the initiation
of remedial action and the clearance of the defect.

5.6.7.2.2 A Defect and Deficiency Report (Form ERC/S2022) may be raised at any time during the life of a
platform by parties operating, maintaining or supporting the Combat System to report a deficiency or failure
of the Combat System equipment that is considered to have resulted from defective design.

5.6.7.2.3 When action in response to a Defect Report has implications or remedy beyond an equipment
boundary and affects Combat System capability, or raises system level issues the remedial activity may
include the introduction of an authorised design change by modification or As&As.

5.6.7.3 Operational Defect Reports (OPDEFS)

5.6.7.3.1 OPDEFS are defect reports of operational performance deficiencies. OPDEFs require an urgent
response and take priority over S2022s and other technical queries. In due course, an S2022 to support the
OPDEF will be required to be raised by the originator of the OPDEF. This will often occur after the OPDEF
has received a response.

5.6.7.4 Performance Assessment

5.6.7.4.1 Performance Assessment establishes the baseline performance of the Combat System, building on
the evaluations leading to System Acceptance. Data from operational ships, submarines, shore facilities and
Unclassified
143
DEF STAN 21-59 Issue 2

operational/tactical analysis facilities, should be analysed to assess Combat System performance against
the designed capability. The purpose of this assessment is to identify:

a) Shortcomings in achievement due to the design, upkeep or support;

b) Limitations of the design;

c) Changes in the operational requirement requiring changes to the designed capability.

5.6.7.4.2 Combat System IS performance assessment should be reported at regular intervals, drawing
together evidence supporting the case for change. This should be provided against an identified shortfall
and include practical proposals for design change.

5.6.7.4.3 Combat System performance data useful for operational performance analysis includes:

a) OPDEFs;

b) ERC/S2022s;

c) Fleet Trial reports;

d) Minor Trial reports;

e) MCTA reports;

f) Index reports;

g) Acoustic Signature reports;

h) Magnetic Signature reports;

i) Analysis of SAT results;

j) Certification and Re-certification trials;

k) Patrol Analysis reports;

l) Infra-red signature reports.

5.6.7.5 Availability, Reliability and Maintainability Monitoring

5.6.7.5.1 During the IS phase there will be a requirement to form an IS AR&M panel to quantify IS reliability,
identify factors inhibiting reliability and recommend appropriate measures to improve AR&M.

5.6.7.6 Electromagnetic Environmental Effects (E3)

5.6.7.6.1 There is a through-life requirement to identify all EMC problems (including the potential effects of
Electromagnetic Pulse (EMP)/Ionising Nuclear Radiation (INR), and TEMPEST) which adversely affect the
capability of the Combat System. This involves management of the Combat System electromagnetic
environment, investigation of reported deficiencies in design or practice as they affect Combat System
performance, and the proposal and implementation of change where justified. Further advice is available
from the MoD Technical Authority for all E3 issues: DCSA Test & Reference Branch, Blandford, Dorset.

5.6.7.7 Signature Management

5.6.7.7.1 Liaison is required with the operational authority in the co-ordination of all aspects of the
management of the warship signature. This will include:

a) Ensuring that changes do not adversely affect the warship signature;

Unclassified
144
DEF STAN 21-59 Issue 2

b) Use of data from signature ranging reports and patrol reports for signature reduction or removal of
defects;

c) Set up of a magnetic safety clearance register for the Combat System to support a (submarine) de-
perm when requested;

d) Management of approved signature measurement or ranging activities, utilising existing MoD


sponsored facilities and authorities wherever possible.

5.6.7.8 Safety Management

5.6.7.8.1 All safety issues affecting the IS Combat System, must be addressed through the MoD Ship Safety
Management System (SSMS) through the following activities:

a) Review and update the Safety Management Handbook (SMH);

b) Maintain the Combat System safety live file and hazard log, and provide updates to the baseline
safety case, and platform safety certificate;

c) Assess the safety aspects of all proposed A&As, and equipment modifications for identification of
potential hazards;

d) Assess the safety status of each platform by monitoring S2022s, OPDEFs etc including proposals for
rectifying identified safety shortcomings.

5.6.7.8.2 Any limitations necessary to ensure safe operations of the Combat Systems must be specified and
promulgated in Certificates of Clearance for Use (CCU), and trials or operations which could be outside the
design standard must be identified and appropriate formal safety advice provided.

5.6.7.9 Obsolescence

5.6.7.9.1 Obsolescence, be it that of an engineering component or an equipment is a through life issue which
the Combat System design authority is responsible for addressing. The equipment sponsor (i.e. EPM) will
be responsible for overcoming the obsolescence of a component part of his equipment responsibility. This
will usually be a function of a support contract with the equipment supplier.

5.6.7.9.2 Often it will be possible to effect component replacement which will not affect the function, form or
fit of an item. In some cases, these problems may be overcome by ‘life-time buys’ of components. Some
equipment will be an amalgam of COTS and MoD-developed items where the intellectual property rights are
owned jointly and sometimes where an item is wholly MoD developed. In each case the design authority will
be in the forefront of addressing any obsolescence aspects.

5.6.7.10 Combat System Design Modification - Objectives

5.6.7.10.1 There will be many cases where, as a result of defects or deficiencies identified, a change to
the Combat System equipment is required. These may result in modifications necessary to address design
shortfalls or assuage the effects of obsolescence. Modifications may also be required to apply
improvements to designs instigated by the equipment supplier (e.g. COTS upgrades). Modifications must
not be used to be upgrade or modify capability required by the URD without DEC approval.

5.6.7.10.2 Proposed modifications to an individual Combat System equipment or sub-system will need to
be reviewed in the context of the Combat System requirement to assess feasibility, impact and justify the
benefits. This will result in the proposal being managed as a Combat System modification or A&A. Other
circumstances, where mission-specific (e.g. submarine special fits) and area-specific equipment are
required, should also be addressed in a comparable manner.

Unclassified
145
DEF STAN 21-59 Issue 2

In-Service Existing Equipment


Assessments Design

SDF/SIF HATs SATs

SE Process MODIFICATION COMBAT SYSTEM


REQUIREMENTS RE-TEST & TRIALS
SD
SA
IMPACT SYSTEM
RE ANALYSIS RE-INTEGRATION

MODIFICATION EQUIPMENT
SS DP DEFINITION RE-TEST & TRIALS

CCB Approval

MODIFICATION/A&A
IMPLEMENTATION

Figure 5.5 Combat System Design Modification

5.6.7.10.3 Modification to the Combat System baseline should be co-ordinated using a structured
approach, as illustrated in Figure 5.5, addressing pertinent issues through the following sequence:

a) Definition of the proposed modification including requirement, design impact supported by


analysis/investigation, proposed implementation, risk and funding issues;

b) Review and approval to proceed through the Change Control Board (CCB);

c) Initiation of procurement action for any hardware, software and firmware required to implement a
system modification once it has received approval;

d) Arrangements for the implementation, integration, trials and acceptance of Combat System
modifications and A&As;

e) Co-ordination of modification and A&A guidance information packages.

5.6.7.10.4 Modifications and A&As will be tracked by means of a register of all proposed changes to the
Combat System to be reviewed and published at regular intervals. This should be supported by a plan
identifying the progress of Combat System modifications and A&As.

Unclassified
146
DEF STAN 21-59 Issue 2

5.6.7.11 Combat System Design Modification Activities

5.6.7.11.1 Combat System modification typified by component equipment changes need to be managed
by the design authority through the Combat System Management Group according to a disciplined systems
engineering process as illustrated in Figure 5.5 and described in detail in previous paragraphs. The focus of
activities during the IS Phase is to define the modification, assess its impact and once agreed, oversee its
implementation, integration, testing and trials. This is achieved through the following activities:

a) Analysis and design activities defining Modification Requirements, performing Impact Analysis and
Modification Definition to investigate the effects of fitting and integrating modified equipments, the
interaction between them and the effect on the overall Combat System. This will involve
investigation of AR&M, operability, performance, vulnerability, environmental factors, mutual
interference, RADHAZ, and TEMPEST/EMC. Overall Combat System alignment, blind arcs,
personnel safety, and firing arcs will also be addressed. The activities include identifying: the total
cost of the changes to all affected equipments; the cost of their integration; and a programme to
ensure the orderly introduction of the modification to the fleet;

b) Following CCB approval for Modification Implementation, the modification will be implemented by the
Equipment Supplier, under the direction of the EPM;

c) Integration, test and trials will follow through Equipment Re-test and Trials, System Re-integration
and Combat System Re-test and Trials to confirm correct operation in Shore facilities (SDF/SIF) and
onboard the warship, under the direction of the CSM.

5.6.7.12 Support Services

5.6.7.12.1 Combat System and equipment modification is achieved through support contracts placed on
industry, typically the System and Equipment Suppliers. Support contracts should cover the activities
necessary to implement modifications needed to rectify design shortfalls, following equipment System
Acceptance. Support activities serve to maintain the Combat System design in support of the overall
operational requirement and are not intended to aid the development of future enhancements.

5.6.7.12.2 The provision of Post Design Services (PDS) services must cover all aspects of weapon
system installation engineering. For platforms that are having new equipments fitted, the PDS contractor
(i.e. equipment supplier) will assume responsibility for the following:

a) Attendance at line-out inspections;

b) Resolution of discrepancies between Level 3 guidance information and ‘as fitted’ state of warship
with subsequent approval of deviations from design intent;

c) Attendance at Installations Inspections (II);

d) Resolution of MCTA Part ‘B’ II pick-up items;

e) Liaison with EPMs to resolve any shortfall/problems with Government Furnished Equipment (GFE).

5.6.7.12.3 For platforms in service, the PDS contractor will assume the following responsibilities:

a) Response to defects raised through S2022s requiring platform attention;

b) Maintenance of the warship/Combat System configuration including equipment fit/datum pack,


drawings and updates to handbooks;

c) Response to non-programmed works necessitating the production of Statements Of Work (SOW) or


Level 4 drawings.

Unclassified
147
DEF STAN 21-59 Issue 2

5.6.7.13 Guidance Information

5.6.7.13.1 Guidance information accompanying the modification must address the following aspects:

a) Interdependencies on other equipments being fitted;

b) Equipment availability against planned fitting opportunity;

c) Provision of ship-fitting aspects of the Installation Guidance Package (IGP);

d) Availability of ships services;

e) Mutual interference aspects;

f) EMC and EMP;

g) TEMPEST;

h) Siting of equipment to provide optimum possible firing or transmission/reception arcs, shock


clearance, maintenance access space taking into account other existing and any other known new
equipment being fitted concurrently or in the future;

i) Safety requirements of JSP 430 covering design and installation.

5.6.7.14 Planning and Financial Aspects

a) In parallel with the above technical aspects of PDS, the following planning and financial aspects also
need to be addressed to ensure that the equipments can be fitted during update periods:

b) Timescales for installation, Setting To Work (STW), linking of respective equipments, HAT(E),
SAT(E) for equipments;

c) Estimated costs of installation together with contractor supplied items;

d) Approval of A&As (i.a.w. BR 8593(17));

e) Programme of Level 3 guidance information must be agreed with the platform upkeep manager to
enable:

1) The refit specification to be produced,

2) Issue of ITT for the production of Level 4 drawings (where required),

3) Delivery to selected contractor for the production of Level 4, full installation drawings,

4) Procurement of any long lead items of equipment to be addressed.

5.6.7.15 Handbooks

5.6.7.15.1 System, User and Maintainer Handbooks must be updated on completion of a refit.

5.6.7.15.2 Trials and Acceptance.

Unclassified
148
DEF STAN 21-59 Issue 2

5.6.7.16 System Design Change Validation

5.6.7.16.1 Following implementation of a design change, validation will comprise integration, tests, trials,
and acceptance certification. Test and trials provide the means to establish the capability of the Combat
System and the analysis of trial results will provide evidence for acceptance/certification as well as
indications of potential shortfalls requiring attention.

5.6.7.16.2 The conduct and presentation of system trials is co-ordinated by the Combat System
Management.

5.6.7.17 Trials Co-ordination and Management

5.6.7.17.1 Maintenance of HAT and SAT policy may be assigned to the Combat System Manager who will
co-ordinate working groups to review policy and co-ordinate technical support. Trials-related tasks include:

a) Management and supervision of system integration tasks and trials, acceptance trials, operability
assessment trials;

b) Co-ordination of fleet, minor or other trials, and examination of their content for impact on the
Combat System;

c) Preparation and distribution of trials schedules;

d) Pre-trial briefings to ships staff;

e) Provision of trials equipment;

f) Analysis and issue of trials reports;

g) Preparation and presentation of acceptance information;

h) Compilation of a trials register identifying proposed trials, trials in progress and those awaiting a final
report;

i) Assessment of Combat System trials reports to determine requirements for equipment or system
improvements;

j) Initiation of the improvement action as a result of identified shortfalls.

5.6.7.18 Documentation

5.6.7.18.1 Table 5.3 details the Combat System design and upkeep documentation required for IS.
Design and upkeep documentation needs to be maintained throughout the stage, reflecting any changes
made to the baseline Combat Systems IS and their support arrangements.

Unclassified
149
DEF STAN 21-59 Issue 2

Table 5.3 Summary of Documentation


Activity Documentation (Output Products) Associated Activities

Design TLMP and SEMP Developed by Combat System Management


System Master Record Index Group (with support from Equipment
Test Evaluation and Acceptance Criteria Suppliers)
Design Platform Contents List
Design System Interface Diagram
Design Interface Reference List
System Integration Specification
System Trials Specification
Equipment List
Acceptance Policy Paper
Acceptance Management Plan
System Integration & Trials Requirements
Platform Contents List
System Interface Diagram
Interface Reference List
System Link Diagrams

Upkeep Upkeep Planning Information Maintained by Combat System Management


Combat System Handbook Group
Weapon Equipment Schedule
Weapon Equipment Delivery Programme
Weapon Equipment Schedule
SDF/SIF Weapon Upkeep Plan
SDF/SIF Operating Procedures

5.6.8 Specialist Discipline Support

5.6.8.1 Specialist Discipline Support necessary for the IS phase centres upon the major areas of activity:

a) Support-specific activities relating to upkeep. This is traditionally the ‘core business’ of DLO and the
necessary skills should be readily available;

b) IS assessment activities require additional expertise in support of AR&M, effectiveness/operational


performance assessment, EMC, signatures and safety;

c) Modification activities necessitating recourse to analysis/design activities. These should be


conducted to the scope determined appropriate to the project needs;

d) Integration, Test and Trials activities in support of verification and validation. These should be
conducted to the scope determined appropriate to the project needs.

5.6.9 System Studies

5.6.9.1 Objectives

5.6.9.1.1 System Studies continue throughout the Combat System life cycle refining models and validating
their predictions by comparison with real operational data. This is an essential aspect of IS Combat Systems
engineering conducted by the Combat System design authority, with responsibility for specific study tasks
devolved to the Combat System management group.

5.6.9.1.2 During the IS stage, it is important that the through-life models are consulted to investigate impact
of potential change and maintained thereafter to reflect modifications to the baseline Combat System. The
main objectives of modelling in the IS Phase is to use and evolve models generated from earlier activities to:

a) Refine model fidelity using data generated from operational usage;


Unclassified
150
DEF STAN 21-59 Issue 2

b) Assess the impact of any shortfalls or improvements in system design performance;

c) Support investigation and problem solving to remedy defects and deficiencies;

d) Support analysis of test and trials results;

e) Investigate the impact of emergent requirements on the Combat System implementation.

5.6.9.2 Model Maintenance and Validation

Voluminous data recorded during operational use needs to be subject to data reduction and analysis (as
described in Section 7) to evaluate key performance parameters i.e. Measures Of Performance (MOPs) and
Measures Of Effectiveness (MOEs). Data should be compared with modelling predictions to validate or
improve the fidelity of models for through-life use.

5.6.9.3 Change Impact Investigation

5.6.9.3.1 Where specific design modifications options are required, technical investigations using modelling
techniques should be used to examine the impact on the baseline Combat System. The Combat System
design authority should determine scope of investigations to assess the impact of the change on:

a) AR&M;

b) Combat System architecture;

c) Functional compatibility;

d) Effectiveness;

e) Human Factors (HF)/operability;

f) Performance;

g) Platform installation;

h) Support;

i) WLCs.

5.6.9.3.2 The studies will assist in specification of the change and in the production of any A&A guidance
information that is required as a result.

5.6.9.3.3 The CSM should ensure that existing MoD modelling facilities should be kept under review and
developed or added to as necessary to satisfy the Combat System requirement.

5.6.9.4 Emergent Requirements

5.6.9.4.1 During the IS lifetime of a Combat System, new or additional requirements may emerge. The
respective DECs must put in place the tasking arrangements to ensure that the impact of their new
capabilities requirements are fully evaluated and costed for all the potentially affected projects. In this event,
the Combat System manager and/or his IS contractor should consult with EPMs to provide assurance that
an equipment or subsystem may be added without degradation to the Combat System. The procedures laid
down in SSP 38 (being re-issued as a ‘Maritime Acquisition Publication) (and Def Stan 21-88 for Surface
Ships) should be consulted.

5.6.9.5 Combat System Trials Support

The data derived from Combat System trials can enable the Combat System design authority to establish or
improve the designed capability of the system. Combat System trials schedules should be monitored
against emergent requirements and Combat System modifications to ensure that the system trial remains a
valid demonstration of Combat System suitability for use at sea, and adequately tests any new functions or
Unclassified
151
DEF STAN 21-59 Issue 2

modifications. The results from trials including HATs and SATs should be assessed against design
statements and the results obtained from other platforms and the SDF to confirm system performance.

5.6.10 Configuration Management (CM)

5.6.10.1 Objectives

5.6.10.1.1 CM is the process through which the design standard of each system, sub-system and
equipment is defined, recorded, and related to the Combat System and ship fit definition/build standard of
each platform or facility. CM ensures that, throughout the life of a system or equipment, all aspects of design
change are monitored, recorded, and controlled. The primary objectives are as follows:

a) Define the baseline configuration of the system and its constituent equipments;

b) Apply technical and administrative direction to the control of changes to the configuration of the
system throughout its life;

c) Maintain the configuration definition and undertake periodic audits to verify its accuracy.

5.6.10.1.2 Combat System CM is a pan-organisation operation involving both the DPA and DLO and,
increasingly, Industry. Responsibility for implementing and conducting CM falls to the Combat System
Management Group.

5.6.10.1.3 The process includes the auditing of the Combat System configuration throughout its
operational life. This supports tracking of the latest status of Combat System design changes from initial
identification through approval to their embodiment on the warship.

5.6.11 System Studies

5.6.11.1 Configuration Management Activities

5.6.11.1.1 During the IS stage, CM activities include:

a) Maintenance of a register of all Combat System modifications (and waivers);

b) Control of the ship fit definition of the Combat System as installed in each platform and shore facility
reflecting all authorised changes to equipment hardware, software or firmware;

c) Maintenance of Combat System design and upkeep documentation;

d) Maintenance of Combat System link, interface and test documentation;

e) Demonstration through audits that the Combat System CM system is operating satisfactorily to
maintain stringent control of the configuration of the Combat System in each platform or shore
facility.

Unclassified
152
DEF STAN 21-59 Issue 2

Systems Engineering Guide for Naval Combat Systems -


Termination or Disposal Phase

6 Termination Or Disposal Phase

6.1 Introduction

6.1.1 The Acquisition Management System (AMS)

6.1.1.1 The prime source of guidance for the implementation of Smart Acquisition processes within the
DPA, DLO and DCSA for EP and STP projects is contained in the AMS at www.ams.dii.r.mil.uk or
www.ams.mod.uk. The content of this Def Stan uses the basic principles contained within the AMS and
whilst these are unlikely to change, the implementation details may. The AMS is the subject of frequent
update and should therefore be consulted for clarification of that detail.

6.2 Purpose of the Termination or Disposal Phase

6.2.1 Overall Objectives

6.2.1.1 The AMS states that the objective of this project phase is to “dispose of the capability cost
effectively, safely and in accordance with the best practicable environmental option”. This Def Stan
considers this final stage of the Combat System life cycle i.e. Combat System’s removal from RN service and
subsequent disposal. The overall process is illustrated in Figure 6.1 which shows the possible options: sale
to another nation (whole warship disposal by sale) or ‘paying off’ (i.e. decommissioning and de-storing)
followed by the dismantling and disposal of salvaged items. Both the operational platform and the support
infrastructure maintained during its in-service lifetime will be subject to either or both of these processes.

Integrated W HO LE W ARSHIP
Com bat S ystem s
DISPO S AL b y S ALE O peration B y
FOC and FO N W arships Foreign Navy
Through-Life SYST EMS ENG IN EER IN G (T EC HN IC AL)
Support Infrastructure and PR O JEC T M AN AG E MEN T
T raining Facilities,
C O M B AT FA ST TR AC K
Shore Facilities, T est SYST EM
T R IALS and
SYSTEM S AC C EPT AN CE
Equipm ent, S pares, D EFIN IT IO N EN G IN EER ING Foreign Support
Through-Life
Support S ystem , C O M B AT
O rganisation
C apability/P erform ance SYST EM
RE-ENG IN EER IN G
M odels, D esign
D ocum entation, Through-
Life D ata AND /O R

PAYIN G -O FF, DISM AN TLING ,


RE-USE and DISPO SAL Item Disposal
Integrated b y Sale
SYST EMS ENG IN EER IN G (T ECH NIC AL)
Com bat S ystem s and PRO JEC T MAN AG E M EN T
Item Salvage
Through-Life FIN AL REMO V AL &
for Spares
Support Infrastructure AS SE SS M EN T EV ALU AT IO N
Item Recycling/
M A IN T AIN a nd AR C H IVE R E C O R DS D estruction

Key O utputs
Learning From E xperience R eports
Project A rchive

Figure 6.1 Removal and Disposal, Overall Process

6.2.1.2 The major objectives of this final stage in the Combat System life cycle are to:

Unclassified
153
DEF STAN 21-59 Issue 2

a) Remove the warship from service in a cost-effective manner which preserves all relevant
information for use in other and future Combat System projects;

b) Dispose of physical assets at whole warship, major system or component level through sale,
salvaging (component re-use following dismantling) or scrapping (for re-cycling where practical, and
by destruction or discarding otherwise) as economically as possible whilst meeting safety, security
and environmental requirements.

6.2.1.3 Whole Warship Disposal by Sale

6.2.1.3.1 The drive to realise the export potential of decommissioned RN vessels, means that whole warship
disposal by sale is the most common route for redeployment of Combat System equipment. It is likely that
this route will bring with it many additional requirements (e.g. for improved customer-specified equipment fits,
removal/sanitisation of sensitive data/equipment etc.) and these must be fully defined, the consequent
modifications implemented, trialled and accepted before transfer of ownership can occur.

6.2.1.3.2 It is usually the preferred option with major warship sales, to achieve a government-to-government
‘hot’ sale with uniform-to-uniform handover. However, a contractor may be used by MoD to assist in the
preparation of warships for overseas sales. Given the typically condensed time-scales which sales of this
nature generally demand, the re-engineering process must be accomplished through a set of ‘fast track’
System Engineering (SE) activities as agreed by the customer. The re-engineering task is seldom trivial and
the adoption of a formal SE process is strongly advised in order to maintain and optimise the performance of
the modified Combat System and its support infrastructure. The process, which should be explicitly defined
by the project Systems Engineering Management Plan (SEMP), must strike an appropriate balance of
Combat Systems engineering activities (as defined in previous sections) within the constraints of the project.

6.2.1.4 Removal and Re-use or Disposal

6.2.1.4.1 Items removed through re-engineering as a result of whole warship disposal by sale will be subject
to re-use and/or disposal. Disposal also follows the platform or installed equipment reaching the end of its
operational life to be dismantled into components for sale, salvage for spares or destruction. It is not unusual
for warship and Combat System disposals to take place whilst the Combat System remains in active service
elsewhere in the fleet. Other notable circumstances which result in disposal are:

a) Major upgrade of capability (i.e. refit) as typified by a Mid Life Update (MLU) in response to changes
in perceived threat;

b) Replacement of the Combat System;

c) Modifications to reduce or improve capability as a result of political decisions;

d) Commercial Off The Shelf (COTS) hardware updates;

e) Modifications initiated to address component obsolescence;

f) Removal from service due to high cost of ownership.

6.2.1.4.2 Where the cost of refit or refurbishment is prohibitive, a platform will be subjected to ‘paying off’
which involves decommissioning and de-storing. De-storing is where all stores, victuals, expendable
weapons and other consumables are removed from the warship and returned to naval stores (as is also the
case with major refits).

6.2.1.4.3 This is followed by the removal of all equipment and associated fixtures and fittings and the
evaluation of items for sale, salvage for spares or destruction. Evaluation is conducted through the
parameters of environmental issues, safety and security which together influence the practical route for
disposal. This provides a mechanism for characterising and certifying all items and ensuring that disposal is
conducted in an appropriate and accountable manner.

Unclassified
154
DEF STAN 21-59 Issue 2

6.2.1.5 In-service Records

6.2.1.5.1 All relevant in-service data, historical log data and final system assessment data (relating to the
system capability at service exit) should be recorded, analysed and archived. This data will provide a
baseline against which characteristics of future systems can be compared. Known system strengths and
weaknesses together with summaries of key data should be recorded to provide a mechanism for feeding
back service experience to current and future Combat System projects.

6.3 Inputs

6.3.1 Removal and disposal applies to all Combat System equipment and related items which have
reached the end of their in-service life whether due to declared obsolescence (including equipment removed
from platforms undergoing refit) or through sale to another nation.

6.3.2 Disposal may also apply, depending on prevailing circumstances (accounting for whether or not the
Combat System equipment remains in use in other assets), to hardware within the through-life support
infrastructure particularly training facilities, Shore Development/Shore Integration Facilities (SDF/SIF),
reference equipment sets, test equipment and spares. Supporting information and the support infrastructure
needed to manage support data (e.g. Information Technology (IT) system equipment) must also be
considered for retention/archiving. Potential areas for consideration include:

a) Support system(s) including Logistic Support Analysis Record (LSAR), spares management
systems, handbook information, electronic documentation;

b) Performance models/analysis data and design documentation created during the design activities
and maintained/augmented through the operational life of the Combat System in support of in-
services support activities;

c) Through-life test and trials data defining the operating characteristics of the in-service Combat
System.

6.4 Outputs

6.4.1 Outputs from the removal and disposal stage comprise the items for re-use or destruction and
associated certification:

a) Final system assessments including Availability, Reliability and Maintainability (AR&M) evaluation,
final LSAR, final Life Cycle Costing (WLC) and concluding operational performance studies and
safety case;

b) General, electrical and mechanical equipment items and associated operating/maintenance


documentation where available (i.e. salvaged items);

c) Software;

d) Consumable items such as magnetic media and paper;

e) Ammunition and explosives;

f) Certificates for re-use, salvage as spares or destruction.

6.4.2 Additionally, there are the overall life cycle outputs collected together in the project archive which will
feed forward into future programmes. These include:

a) Learning from experience reports, identifying business areas and aspects of current engineering
practice which may benefit from future improvement;

b) Requirements and acceptance data;

c) Design specifications and performance analysis models and data;

Unclassified
155
DEF STAN 21-59 Issue 2

d) Test and trials data defining the operating characteristics of the in-service Combat System.

6.5 Organisation

6.5.1 In cases where the decision for whole warship disposal by sale is taken, the platform will be formally
handed over by the operating authority to the Defence Export Sales Organisation (DESO) and their agents
for disposal. The actual arrangements for disposal will depend on the precise circumstances and scope of
the disposal activities. The general roles for this and other cases, where equipments are to be removed and
disposed of, are illustrated in Figure 6.2.

CUSTOMER
ORGANISATION

OPERATING SUPPORT DISPOSAL SALES


AUTHORITY AUTHORITY ORGANISATION

DESIGN
AUTHORITY

COMBAT SYSTEM
INTEGRATOR
SALVAGE
CONTRACTOR

EQUIPMENT
SUPPLIER

COMBAT SYSTEM RE- DISMANTLING, RE-USE


ENGINEERING and DISPOSAL

Figure 6.2 Removal and Disposal Organisation Relationships

6.5.2 The following organisations will generally be involved:

a) Operating Authority (CINCFLEET) responsible for defined state of repair and co-ordinating the
handover of the platform to DESO;

b) Support Authority, responsible for co-ordinating preparatory work (excluding normal maintenance
and upkeep) in support of the sale. This includes defining the content of the package, exclusions
and removals. Post their final non-operational date, warships are considered to be DLO assets and
management responsibility rests with DLO. Additionally, the DLO will control handover of in-service
support information and systems;

c) Design Authority, usually the Equipment supplier engaged by the DPA during procurement phases.
The removal activities will be conducted by an industrial salvage contractor. Modification will
generally be handled through a ‘prime contract’ arrangement, with the lead contractor liasing with
subcontractors tasked with provision of items for integration, test and trials. DPA will also be
responsible for certification of items for disposal for sale, salvage for spares or destruction.
Furthermore DPA will be responsible for the collation and maintenance of appropriate life cycle
records of the Combat System;

d) Combat System Integrator, typically industry responsible for managing the risk associated with
modifications acquired via Equipment Suppliers, and bringing together equipment components into a
working Combat System through integration, test and trials activities;

e) Disposal Sales Organisation, that is the DESO, Disposal Sales Agency (DSA) and its UK industry
contractors for co-ordinating the disposal and sale of naval spares. For whole warship disposal,
DESO will act on behalf of the UK government, interfacing with the foreign government Customer
Organisation;

Unclassified
156
DEF STAN 21-59 Issue 2

f) Salvage Contractor for disassembling equipment and identifying disposal routes (elements of this
activity may be performed by naval bases/dockyards).

6.5.3 There may be exceptional cases where the intended transfer of responsibilities and information i.e.
between industry, DPA and DLO has not been completed prior to the decision to initiate whole warship
disposal by sale. In such cases, co-ordination of the maintenance and care tasks should be retained within
DPA under the responsibility of the designated warship project manager.

6.5.4 Whole Warship Disposal by Sale - Background

6.5.4.1 Decommissioning and Disposal By Sale

6.5.4.1.1 The decision to dispose of a whole warship as a working entity ultimately rests with Secretary of
State for Defence in consultation with the Cabinet. Options to refit, refurbish or sell on will be presented by
Consultative Defence Committees as part of the wider UK Defence Policy. Naturally there are restrictions on
the export of defence materiel. Sales are limited to NATO allies and other ‘friendly’ countries dependent on
the nature of the equipment, its classification, the end-use nation intended usage, political
situation/background and industrial factors.

6.5.4.1.2 There may be cases where a formal decision on the sale of a warship is deferred. Such cases
would result in decommissioning of the warship and placing in a reserve/standby (‘moth-balled’) state from
which it may be brought back to an operational state at some future date. Return to an operational state for
RN use would have to be managed in the same way as preparing a warship for sale. This would demand a
formal process to determine the material state of the system/equipment and identify any repair/replacement
work which may be required. Subsequent re-engineering of the Combat System would culminate in formal
acceptance trials.

6.5.4.2 Custody Care and Maintenance

6.5.4.2.1 In exceptional cases (e.g. Upholder class submarines), whole warship disposal by sale may require
custody, care and maintenance contracts placed on industry to maintain the platform and support
infrastructure (in particular the shore facilities) whilst DESO follows up sales opportunities. It is likely that
such contracts will be administered through the DPA who will be responsible for ensuring that the complete
package is maintained in a defined and configured state.

6.5.5 Systems Engineering (Technical) and Project Management

6.5.5.1 The nature and scope of the sales agreement negotiated by DESO will determine the extent of the
project and thereby the level to which management plans are necessary. Each area of the management
plan hierarchy should be addressed to a level appropriate to the project scope:

a) Contract;

b) Risk;

c) Quality;

d) Project Management;

e) SE Management and lower-level plan topics where deemed necessary;

f) Subcontract Management.

6.5.6 Combat System Definition

6.5.6.1 Sanitisation

6.5.6.1.1 Sanitisation of the Combat System is inevitably a major issue. All items of a sensitive nature
(whether due to UK policy or policy covering items acquired from other nations) must be identified and
appraised against regulations constraining their sale to potential customers. In cases where regulated items

Unclassified
157
DEF STAN 21-59 Issue 2

make a significant contribution to the capability of the platform (e.g. primary sensor equipment), replacement
items will need to be incorporated and/or modifications applied to existing designs.

6.5.6.2 Specification

6.5.6.2.1 The sales agreement negotiated by DESO must call up a suite of documents defining requirements,
functionality and performance of the Combat System as a basis for acceptance. These should include as a
minimum:

a) Combat System Requirements baseline and acceptance criteria;

b) Combat System Specification;

c) Subsystem Specifications;

d) Coherence Specification;

e) Interface Documentation;

f) Integration, Test and Trials Documentation;

g) Safety Case.

6.5.7 Combat Systems Re-Engineering

6.5.7.1 Modifications

6.5.7.1.1 Where modified, replacement or new equipment is required to be fitted, it is suggested that a formal
SE process, documented by a SEMP, is followed to manage what may be regarded as a further iteration of
the system development and integration processes. As a minimum, the SEMP must define the overall SE
process to be used to specify and co-ordinate the following:

a) Combat System functional and performance requirements;

b) System Design Modification(s) including equipments, interfaces and installation aspects;

c) Integration, test and trials coverage;

d) Operational documentation;

e) Support infrastructure.

6.5.7.1.2 The level to which formal development is invoked must be at the discretion of the project manager
in order to realise the overall requirement and ensure that the impact of changing equipment items (both in
terms of the Combat System and the platform) is fully appreciated by the customer. Further information on
system development can be found in Demonstration and Manufacture and Integration, Test. Evaluation and
Acceptance.

6.5.7.1.3 The suite of information accompanying through-life system studies (evolved models, prototypes,
data and analyses) should be used as a basis for the ‘fast track’ SE activities, in support of impact analysis,
design specification and implementation. Consideration should be given for the inclusion of through-life
system study data with the sale.

6.5.7.2 Support Infrastructure

6.4.7.1 It is also emphasised that the In-Service Support (ISS) infrastructure must be considered as an
integral part of the whole warship disposal for sale process. Provision of spares is a particularly important
issue which should not be overlooked. For further information on the disposal by sale of whole warships,
refer to JSP 336 Defence Supply Manual Part 9 - Disposal By Sale.

Unclassified
158
DEF STAN 21-59 Issue 2

6.5.8 Trials and Acceptance

6.5.8.1 The resulting ‘export variant’ must be subject to trials culminating in acceptance. The extent to
which trials are conducted is again a subject for negotiation between the design authority, disposal sales
organisation and the customer. See Section 7 for further information on trials.

6.5.9 Paying Off, Dismantling, Re-Use And Disposal

6.5.9.1 With the increasing emphasis placed on through-life issues due partly to recent Integrated Logistic
Support (ILS) initiatives, disposal has become a topic of consideration within wider environmental, safety and
security issues during early system activities.

6.5.9.2 By identifying removal and disposal as a formal Combat System life cycle stage, a framework of
assessment and review activities can be set out. This will encourage early action to ensure that this stage is
adequately planned for and appropriate measures taken to ensure that disposal of the Combat System is
conducted in an environmentally responsible, safe manner without prejudicing security. Envisaging eventual
system disposal is a feature of design approaches such as ‘design for disposal’ and the adoption of
measures such as ‘Green Passports’.

6.5.10 Systems Engineering (SE) (Technical) and Project Management

6.5.10.1 The role of SE (Technical) and Project Management during the final stage of the life cycle is to
ensure that the Combat System project is completed in a controlled and co-ordinated manner. In particular,
from a SE perspective, the project manager must be satisfied that all pertinent information is archived to
support analysis for future studies.

6.5.10.2 The central vehicle for promulgating disposal activities is the removal and disposal plan (a
subordinate plan to the SEMP). This will have been generated as a draft during earlier stages to identify
policy and practice for labelling equipment and components during their fabrication with material composition
data to facilitate recycling. Towards the end of in-service life, the removal and disposal plan should be
developed to provide the focus to:

a) Establish the goals and relevant activities necessary to perform removal and disposal;

b) Manage the conduct of final system assessments, removal and evaluation through appropriate
subcontract arrangements;

c) Manage the disposal, salvage and destruction activities through appropriate subcontract
arrangements;

d) Identify the processes through which all environmental, safety and security aspects will be
addressed;

e) Ensure that the disposal objectives are met according to programme and cost;

f) Ensure that all relevant information is suitably archived and made available to future programmes.

6.5.11 Final System Assessments

6.5.11.1 An important aspect of disposal is to complete a series of final system assessments and provide
information as an archive of the operational life of the Combat System. This will serve as a unique and
useful information base for future Combat System studies.

6.5.11.2 The purpose of the final system assessments is to complete and/or terminate ongoing studies
which have accompanied the Combat System implementation during its operational life. These should
include:

a) Availability, Reliability and Maintainability (AR&M) evaluation, concluding with final gathering of non-
obsolescent equipment and system availability and reliability data from on-board records and data
collection systems;

Unclassified
159
DEF STAN 21-59 Issue 2

b) LSAR to bring the Logistic Support Analysis (LSA) up-to-date and perform comparisons on predicted
and actual support performance in accordance with Def Stan 00-60;

c) Final life cycle costing to compare estimates and validate models used to analyse WLCs in tandem
with the LSAR. This should include the recording and analysis of all costs incurred during removal
and disposal;

d) Operational performance studies assessing the continuing capability/performance of the Combat


System over its operational life time (recognising any potential changes to the operational context
e.g. threat and environment);

e) Safety case report, used to identify aspects of the design and its operational usage which impact on
safety. This will have been updated throughout the operational life of the Combat System to address
any newly identified hazards;

f) Security evaluation of classified equipment, documents and data for sanitisation.

6.5.11.3 Each will be formally closed over a period of time during which requested information is made
available by other parties. Closure of these final system assessments is not a pre-condition to the disposal,
salvaging or destruction activities.

6.5.12 Maintain and Archive Records

6.5.12.1 From a SE perspective, it is essential that records are kept so that future applications have
comparative performance metrics on which to gauge meaningful estimates. Current innovations in large
scale data archiving such as data warehousing provide a practical means for managing the archive of
Combat System information generated throughout the life cycle. This information should be made available
to new projects through an appropriate archiving facility provided within the IT infrastructure. Access to the
archive must be assured so that the data is made available to future programmes for re-use, improved
management, contract definition, costing and performance.

6.5.12.2 A core set of information from the Combat System life cycle would include:

a) TLMP including the SEMP;

b) Requirements/Acceptance Database holding the URD and SRD;

c) Design Documentation including System Specification, Coherence Specification, Subsystem


Specifications and Interface Documentation;

d) Test and Trials Documentation including Trials Schedules and Test Forms;

e) Combat System Safety Case;

f) LSAR and WLC providing the appropriate ILS Documentation;

g) System Studies including capability/performance models and supporting data;

h) In-service data, historical log data and final system assessment data (relating to the system
capability at service exit) identifying system strengths and weaknesses.

6.5.13 Removal and Evaluation

6.5.13.1 Removal

6.5.13.1.1 Items removed which have the potential for sale or salvage as spares are evaluated during
removal. Many items will have a resale value which can be exploited through surplus sale outlets. Particular
items may be worth salvaging as spares where the associated in-service equipment or variants thereof is still
operational and existing spares are limited.

6.5.13.1.2 Removed items may include the following:


Unclassified
160
DEF STAN 21-59 Issue 2

a) Ammunition and explosives including torpedoes, mines, pyrotechnics and countermeasures;

b) Cabling;

c) Computer hardware and peripherals;

d) Consumable items including paper and other media (e.g. tapes and disks etc);

e) Documentation;

f) Electrical equipment and electronics including Printed Electronic Circuits (PECs) and Power Supply
Units (PSUs);

g) Fixtures and fittings;

h) Mechanical assemblies such as racks, shelving etc;

i) Outboard fittings;

j) Software (resident in non-volatile memory) and firmware;

k) Test equipment (e.g. oscilloscopes, multimeters, cable test equipment etc).

6.5.13.1.3 All items must be evaluated against a number of criteria as listed below to ensure the
appropriate disposal route is followed and that any certification necessary to support disposal is generated
and maintained.

6.5.13.2 Environmental Considerations

6.5.13.2.1 All items considered for disposal should be reviewed through a BS EN ISO 14001-accredited
Environmental Management System. This provides planning, control, monitoring, auditing and review
mechanisms to ensure compliance with prevailing environmental policy reflecting UK Health, Safety and
Environment legislation.

6.5.13.2.2 Relevant Acts of Parliament and related regulations include:

a) Control Of Pollution Act (COPA) 1974 - emissions to air and discharge to water, solid waste and
noise pollution;

b) Environmental Protection Act (EPA) 1990 - regulations with respect to solid waste, control emissions
to air;

c) Montreal Protocol - restrictions on CFC and related compounds;

d) UNECE (United Nations Economic Commission for Europe) Protocol - to secure a reduction in
annual emissions of Volatile Organic Compounds.

6.5.13.2.3 Hazardous items must be identified and disposal conducted in accordance with BS EN ISO
14001. Where items suitable for resale do not comply with current legislation due to age or condition,
appropriate notices should be attached.

6.5.13.3 Security

6.5.13.3.1 Evaluation of security risks associated with the handling of computer hardware and software
(application software and data), and any electronic, electrical, mechanical or physical items or arrangements
accorded sensitive status is a pre-requisite to disposal.

6.5.13.3.2 The removal of all information, both in electronic and hardcopy format, which has been stored
or processed by the system must be in accordance with the specified security procedures as invoked by the
removal and disposal plan. Computer media with a classification lower than confidential will need to be

Unclassified
161
DEF STAN 21-59 Issue 2

subjected to downgrade and sanitisation procedures. Other items accorded sensitive status will be
catalogued, certified and destroyed.

6.5.13.4 Safety

6.5.13.4.1 Safety issues, including safety of personnel, boat and decommissioning site, nuclear safety in
relation to hull integrity and containment, hazardous materials and safe removal of weapons and
pyrotechnics, need to be considered within the safety management framework mandated by JSP 430.

6.5.13.4.2 Any certification of safety critical software applications within the system is void once the
software is removed from the target hardware. Re-use of such software would require the re-application of
Def Stan 00-55 requirements. It is the responsibility of the project manager to ensure that suitable
disclaimers are provided and retained with the application.

6.5.13.5 Software

6.5.13.5.1 Removal of computer software shall be conducted in accordance with Def Stan 02-620,
covering safety and security considerations (as above), future responsibilities and conditions for re-use.

6.5.14 Equipment/Component Disposal By Sale

6.5.14.1 Items identified for disposal by sale need to be certified for re-use through certification as detailed
above. All items shall be administered and catalogued by DESO, DSA or their resale agents in industry.

6.5.15 Salvage For Spares

6.5.15.1 Items identified as potential salvage for spares need to be recovered and passed onto the spares
provisioning authority. It is unlikely that many items will be in a condition suitable for use as spares.
Exceptionally, for items in short supply, refurbishment may be considered.

6.5.16 Recycling/Destruction

6.5.16.1 Items which cannot be re-used, and do not present a security or safety risk, should be considered
for recycling for recovery and re-use of the raw material.

6.5.16.2 Items which cannot be practically re-used or recycled due to security considerations should be
destroyed. Certification of destruction in accordance with current regulations and prevailing legislation
provides a check on disposal through this route.

Unclassified
162
DEF STAN 21-59 Issue 2

6.5.16.3 Certificates for destruction will be raised by the project manager for items the destruction of which
needs to be witnessed. These will include:

a) Computer hard disks and media;

b) Documentation;

c) Weapons and explosives.

Unclassified
163
DEF STAN 21-59 Issue 2

This Page Intentionally Left Blank

Unclassified
164
DEF STAN 21-59 Issue 2

Systems Engineering Guide for Naval Combat Systems -


Integration, Test, Evaluation and Acceptance Process

7 Integration, Test, Evaluation and Acceptance Process

7.1 Introduction

7.1.1 The integration process must ensure that the Combat System is brought together under a controlled
and configured regime, through which it can be demonstrated, by means of tests and trials, that the
developed system meets its requirements, will therefore deliver the military capability required, and can be
accepted into service.

7.2 Purpose of the Integration, Test, Evaluation and Acceptance Process

7.2.1 The primary purpose of the integration, test and trials process is to bring the Combat System
together from its constituent stand-alone equipments and integrate it as a functional system within its
platform environment. Integration, Test, Evaluation and Acceptance is not always recognised as a formal
stage in its own right since it may be considered as the set of system-level development and manufacture
activities through which the Combat System is brought together as a complete system. The scope of
activities, which need to be, considered however merits a separate section.

DESIGN FOR INTEGRATION/ PROGRESSIVE


MODEL-BASED INTEGRATION PHYSICAL INTEGRATION

Design for Integration is a Integration can be thought of as a matrix of ‘bottom-up’


central theme of earlier stages activities, from equipment installation, testing equipment
dealing with System Partitioning. SE Process working together in groups, through to the fully integrated
Models and SD system. These activities are conducted for the shore-
SA
Synthetic Environments provide RE based (SDF/SIF) proving of high risk items, followed by
a means to identify and integration on the First Of Class (FOC) and subsequent
investigate integration issues. SS DP Follow-On vessels.

Requirements Acceptance
SYSTEM TEST
COMBAT SYSTEM
& TRIALS

SYSTEM
Analysis/Design Integrate/Test INTEGRATION
SUBSYSTEMS

EQUIPMENT TEST
& TRIALS
Acquire Equipment
INSTALLATION
EQUIPMENTS AND STW

SDF/SIF FOC FOLLOW-ON

Figure 7.1 Combat System Integration, Test, Evaluation and Acceptance

7.2.2 Integration will have been considered from the onset of design activities, from partitioning of the
system onwards. Risk analysis activities conducted during previous stages will have shaped the integration
strategy. This will determine the required mix of design-oriented and model-based activities, and
approaches to physical integration through shore-based and in-situ Integration, Test, Evaluation and
Acceptance as illustrated in Figure 7.1. The width of the arrows depict the relative extent of testing in each
situation, with the shore-based proving and First Of Class (FOC) trials providing the greater coverage of
testing required.

Unclassified
165
DEF STAN 21-59 Issue 2

7.2.3 Design For Integration

7.2.3.1 The concept of design for integration is a continuing thread of the strategy and is explored in some
depth in previous sections. It is the far-sightedness, considering integration as a central ‘life cycle process
factor’ during previous design activities, which seeks to assist the physical integration of procured
equipment, avoiding major incompatibilities and improving inter-operability.

7.2.3.2 In support of this goal, modelling techniques may be used to identify potential integration problems
and issues well ahead of actual physical integration at a point where costs associated with
subsystem/equipment change can be more effectively contained. The continuation of modelling during this
stage, augmented by real data acquired from equipment testing, serves to verify and refine early indications
of overall performance. The development of this approach may be witnessed by the ascendancy of
Synthetic Environments (briefly discussed in 1.5.7.2, 3.5.4 and 4.6.9.13 Synthetic Environments) where
prototypes and models of design components may be brought together for a dynamic simulation of aspects
of system operation in a representative scenario.

7.2.4 Progressive Physical Integration

7.2.4.1 The main focus of this section is the progressive physical integration of the Combat System, from the
installation and setting to work of individual equipments to the fully functional Combat System. Whilst there
are variations in the precise nomenclature adopted by submarine and surface ship Combat System
implementation, the underlying approach to integration is comparable.

7.2.4.2 The accepted practice is to first prove high-risk items associated with the integration of novel items
such as new technologies, new-to service equipments, and new interfaces in a shore-based environment
(e.g. Shore Development Facility (SDF)/Shore Integration Facility (SIF)). This provides the opportunity to
extensively exercise subject equipment integrated as a partial system and to perform tests and trials, which
cannot be practically conducted on the platform. With the advent of fast WAN connections these facilities
may be geographically distributed but conceptually form a single facility.

7.2.4.3 The shore-based environment is a cornerstone of the Combat System integration strategy as an
essential risk mitigation exercise. The extent of the equipment fit may vary with the complexity and novelty
of the Combat System, however the underlying principles remain. The aim is to prove system design
concepts and identify/resolve equipment integration problems in a benign and controllable environment
ashore before the equipment is integrated onboard and to provide this facility through life to support the In
Service phase.

7.2.4.4 Upon satisfactory completion of tests and trials in the shore-based environment, a similar set of
progressive integration activities is conducted for the FOC to prove integration with the platform. These are
conducted first through harbour trials, which are followed by sea trials. Subsequent integration activities for
follow-on platforms follow the same progressive pattern, but the depth of testing is much reduced.

7.2.5 System Change Management

7.2.5.1 System Change Management during integration, test, evaluation and acceptance is applied in a
comparable way to change management activities conducted during demonstration and manufacture, as
identified in Section 4. The main thrust here is to first investigate the potential impact of change and co-
ordinate the implementation of the change through the analysis and design process.

7.2.5.2 Approved changes will need to be implemented and integrated through the progressive sequence of
activities as before. Any shortfalls in performance of the overall Combat System against the requirement
determined from impact study and as a result of verifying models against real test data should be ‘fed
forward’ into subsequent Combat System programmes.

7.2.6 Integration, Test, Evaluation and Acceptance

7.2.6.1 The above themes are expanded in Figure 7.2 which identifies the major activities conducted during
this stage. The main emphasis of this section is the progressive physical integration of the Combat System
from the point of equipment acquisition through to the fully trialled Combat System, up to and including
System Acceptance (SA). This is achieved through a staged regime of integration, test and trials activities

Unclassified
166
DEF STAN 21-59 Issue 2

conducted in the shore environment (SDF/SIF) and, through harbour and sea trials on the FOC platform (and
to a lesser extent, follow-on platforms).

7.2.6.2 This progressive, configuration managed regime provides a basis for demonstrating Combat System
physical installation, functionality, performance, operability, Availability, Reliability and Maintainability
(AR&M) and operational effectiveness though an incremental sequence of repeatable tests, each followed by
formal acceptance. This is co-ordinated through Systems Engineering (SE) and project management
(technical) activities which run throughout all life cycle stages.

Combat System
INTEGRATION TEST and TRIALS COMBAT SYSTEM

SYSTEMS ENGINEERING (TECHNICAL)


and PROJECT MANAGEMENT SUBSYSTEMS
Key Documents
Management Plans
Requirements Database SDF/SIF HATs SATs
Design Documentation COMBAT SYSTEM EQUIPMENTS
Acceptance Documentation TEST & TRIALS
Integrated
SYSTEM Combat Systems
INTEGRATION Shore Facilities, Trainers
FOC, Follow-on Vessels
EQUIPMENT
TEST & TRIALS
Equipment for Integration Support Infrastructure
Facilities, FOC and Follow-on
ACCEPTANCE ACCEPTANCE
Vessels, Training Facilities,
Supporting Documentation
SYSTEM STUDIES SYSTEM STUDIES

INTEGRATED LOGISTIC SUPPORT ILS

DOCUMENTATION DOCUMENTATION
Models & Simulations
Cost, Effectiveness, SPECIALIST DISCIPLINE SUPPORT SPECIALIST SUPPORT
Functionality, Architecture,
HCI, AR&M CONFIGURATION MANAGEMENT CM

Figure 7.2 Integration, Test, Evaluation and Acceptance, overall Process

7.2.6.3 Both shore-based and platform-based test and trials provide evidence for acceptance of the Combat
System through the generation and presentation of acceptance evidence to demonstrate compliance with
the requirements. In the interest of improving the cost-effectiveness of the shore-based environment and
containing risk, it is desirable to demonstrate compliance with as many requirements as possible ashore.
Through the use of scenario generators, simulators and stimulators, it is possible to provide a representative
environment for the dynamic test and trials of major aspects of the Combat System.

7.2.6.4 Activities, which support the central integration, test and trials activities throughout the stage, are
depicted separately. These address the conduct of system-level studies, Integrated Logistic Support (ILS),
the production of documentation, specialist engineering discipline support and Configuration Management
(CM). CM is particularly important at this stage as the vehicle for co-ordinating the wide diversity of
system/subsystem/equipment configurations and accompanying test documentation.

7.3 Inputs

7.3.1 Integration, Test and Trials commence with the delivery of Combat System equipments, following
satisfactory completion of equipment Factory Acceptance Tests (FATs). There is a plethora of output
products arising from the previous development and production stage. These are the deliverables from the
equipment development process which can be grouped into:

a) Equipment sets for integration and installation in shore establishments (and trainers) and on vessels,
together with supporting test equipment where necessary;

b) Design, development and production information, including development and production plans,
specifications and drawings;

Unclassified
167
DEF STAN 21-59 Issue 2

c) Equipment test, trials and acceptance information including test and integration documentation, trials
plans, specifications and schedules, SRDs, ITEAPs and TLMPs.);

d) Equipment operation and support information including Master Record Index (MRI) data,
configuration management documentation, technical publications, upkeep documentation, Logistic
Support Analysis Record (LSAR) data and operator/maintainer training documentation.

7.3.2 Additionally, there are many output products, which are maintained from previous stages and
extended as a result of Combat System development. These can be grouped under the following headings:

a) Management plans;

b) Requirements and acceptance data;

c) System functional and performance models used for tracking the Combat System design and to be
used in support of aspects of system optimisation and acceptance;

d) Integration test plans, schedules and specifications in preparation for the subsequent integration
activities;

e) Combat System test, trials and acceptance information including trials plans, specifications and
schedules, and Combat System SRD, ITEAP and TLMP;

f) Combat System operation and support information.

7.3.3 All items will be produced, maintained and controlled as an inherent element of the system baseline
design description under the appropriate CM procedures. This may be controlled and coordinated through a
central platform-oriented information infrastructure or at the Combat System level depending on the contract
regime.

7.4 Outputs

7.4.1 Handover includes the physical delivery of the Combat System and the transfer of the Combat
System Design Authority to DLO (if appropriate). Handover of design authority may not necessarily
correspond with acceptance into service. Note that DLO may support platforms before they take on design
responsibility. The following items are subject to a transfer of responsibility and ownership:

a) Combat System subsystems and equipments - SA provides the point of handover of the
responsibility for individual equipments (and associated test equipment, tools and supporting
documentation) to CINCFLEET;

b) Combat System software-intensive subsystems and equipments - maturing of software for handover
to DLO needs to be considered against the equipment procurement strategy. Certain items where a
continuous development strategy is being employed (e.g. for Command Systems or systems with
significant Commercial Off The Shelf (COTS)-components) may be retained by MoD(DPA). Transfer
to DLO will occur as direct by prevailing policy;

c) SDF/SIF - these facilities are essential for investigating and replicating problems, defects and
deficiencies and for assessing and proving system/equipment modifications. The commitment to
supporting and maintaining the shore facilities needs to be considered within the prevailing
contractual and procurement policy environment. Handover may follow SA depending on the
procurement and acceptance policies;

d) Training facilities – if equipment trainers are procured through equipment contracts they will be
subject to the same procurement policies and contractual arrangement as for the parent equipment
but may have a separate ITEAP. Composite training systems (e.g. Command Team Trainer (CTTs))
procured under the Combat System URD) will be subject to an equivalent acceptance route to the
Combat System. Handover to DLO will therefore follow formal acceptance as described in the
ITEAP;

e) Engineering data - includes system design documentation provided as design drawings,


specifications and associated information in the datum pack consistent with the MRI system as well
Unclassified
168
DEF STAN 21-59 Issue 2

as system integration, test and trials documentation retained by DPA (including test form
documentation). Engineering data will accompany the Combat System at SA;

f) Models, prototypes and system study information - models and prototypes for evaluating and
assessing system functionality, performance, operability, AR&M, effectiveness and Through Life
Costs (TLCs) will become an increasingly important route for assessing emergent requirements and
performing change impact analysis on key aspects of the design. Models and prototypes will be held
in a central reference facility and made available to support both formal acceptance and
maintenance through life, the mechanism for which will be described in the ITEAP and TLMP.

7.4.2 Supply support mechanisms developed with the involvement of the DLO during previous stages will
be administered through a whole warship support infrastructure. CM of Combat System equipment
configurations and associated items listed above will likewise be administered within the CM process of the
whole warship. Additionally, the LSAR developed during earlier stages, will be brought forward and
maintained to reflect actual support performance.

7.5 Organisation

7.5.1 Contract Regime

7.5.1.1 The organisation of the integration and test teams for naval projects follows similar lines across a
wide range of projects, since all of them, inevitably, have to bring together a set of components of a system
and test them as an overall assembly. The major feature affecting the organisation of the work is the
contract regime, which will be consistent with that set up for the demonstration and manufacturing phases,
described in Section 4.

7.5.1.2 Regardless of who is running the project, or what size it is, the important feature is that the
implementation of strong project management disciplines are essential for success. The integration and
testing of a Naval Combat System involves many different organisations in industry, MoD and the RN and,
increasingly, some of the players may be based overseas. This means that the need for communications,
planning, and clearly defined responsibilities come to the fore. All of the parties involved will have to work
together at some time in the confines of the shore facilities or the vessels.

7.5.2 Organisational Roles

7.5.2.1 Integration Test and Trials involves a number of organisations each of which has distinct roles to
play as depicted in Figure 7.3. Though the actual boundary of responsibilities is negotiable to some extent
within the prevailing procurement regime, the roles are generally well defined. They are as follows:

a) End-User organisation, the RN represented by the nominated Customer 2;

b) Support Authority, the DLO, charged with the In-Service Support (ISS) of the Combat System;

c) Equipment Supplier organisations provide the products and service which has been procured as
subsystems and equipments and supporting services. It is important that these organisations are
available to support integration, test and trials activities, assist in resolving integration problems and
correct deficiencies up to and including full acceptance;

d) Conducting Authority, a role associated with Maritime Commissioning, Trials and Assessment
(MCTA), the unit

e) responsible for the conduct of tests and trials and recommendation to the Capability Acceptance
Working Group (CAWG) who are responsible for recommending acceptance of the system against
the URD. Acceptance off-contract the is a DPA responsibility whilst overall acceptance against the
URD is a Customer 1 responsibility as advised by the CWG(A), on completion of SA carried out on
behalf of CINCFLEET;

f) Combat System Integrator, responsible for bringing all of the equipment components together into a
working Combat System. Within this organisation is the Test and Trials Organisation, typically
provided by the platform design authority, who is dedicated to organising and conducting tests and
trials and producing the test documentation.
Unclassified
169
DEF STAN 21-59 Issue 2
SUPPORT
AUTHORITY

END-USER
ORGANISATION

Accepted Products Support Products


and Services and Information

COMBAT SYSTEM
INTEGRATOR

CONDUCTING TEST and TRIALS


ACCEPTANCE
AUTHORITY ORGANISATION
AUTHORITY
Acceptance
Evidence
Test
Programme/
Test Products and WEAPON/SYSTEM
Documentation Services ACCEPTANCE
COMMITTEE
EQUIPMENT
SUPPLIERS

Figure 7.3 Integration Test and Trials Organisational Relationships

7.5.2.2 The interaction of these organisations is formalised through the formation of the CWG(A), which
serves to influence all integration test and trials activities which lead to acceptance, and for the rectification
of identified defects and deficiencies.

7.6 Integration, Test, Evaluation and Acceptance Process

7.6.1 The scope of the Integration, Test, Evaluation and Acceptance process depends upon the nature of
the prevailing procurement policy and contract. The extent of a prime contract to design, build, introduce into
service, and support a new class of vessel is different in scope to that for dealing with a new variant of an in-
service weapon or command system introduced as part of a refit package. However the underlying
principles and building blocks of the process are essentially the same.

7.6.2 Responsibility for integration, test and trials activities will be identified in the ITEAP. Increasingly the
traditional role of the MoD project team is devolved to industry in the prime contract setting. In other cases,
the MoD may retain the integration authority but contract the integration role to a contractor who will act as
an ‘agency’ rather than an ‘authority’.

7.6.3 The main focus of integration, test and trials may be considered as a matrix of ‘bottom up’ activities,
from installation of equipments through to the fully integrated system as illustrated in Figure 7.4.

Unclassified
170
DEF STAN 21-59 Issue 2

Combat OVERALL INTEGRATION


System Overall Integration covers those functional and
Trials C D
performance tests that involve more than one
A B C F warfare area, together with the concurrent
B operation of Group Integration tests to check for
any degrading mutual interaction.
A E
System D E F
These culminate in tests of the whole Combat
Trials System operating under a high load and over
an extended period.

GROUP INTEGRATION
Group Integration comprises further functional
B C and performance tests of functional warfare
D areas involving more than two equipments.
A B
D B It tests the resilience of the group to concurrent
A operation, high loads, changes in configuration,
D and system ‘threads’ through the equipments
integrated in the group.

ONE-TO-ONE EQUIPMENT INTEGRATION


One-to-One/Member Integration comprises
B C Interface, data exchange, functional and
Interface performance trials between an equipment and
Trials A E (separately) each of the other equipments with
B which it interfaces.
A B
A
A reduced set of these trials may contribute to
an Interface NWHT.

STAND-ALONE EQUIPMENT TESTING


Following extensive factory testing including
FII A B C Interface and Data Exchange Proving,
HAT(E) equipments are delivered to the integration
site.
II D E F A Equipments are installed and subject to repeat
tests to confirm correct operation during STW.
FAT These culminate and contribute to the
acceptance of the equipment through HAT(E).

Figure 7.4 Stages of Combat System Integration

7.6.4 This is the system integration dimension, which is considered in detail in this section dealing with the
integration, test and trials process.

7.6.5 In practice, integration must be conducted through a sequence of tests and trials, which provide the
assurance that the Combat System is operationally acceptable prior to entering service. To limit exposure to
risk associated with integration shortfalls or failure, the accepted practice is to anticipate integration through
modelling, and then prove the system in a benign environment ashore before committing to installation and
integration on the target platform. The sequence is illustrated in Figure 7.5 and described in detail in para
7.7 Practical Integration, Test, Evaluation and Acceptance

Unclassified
171
DEF STAN 21-59 Issue 2

MODEL-BASED INTEGRATION SHORE-BASED TESTING SHIP-BASED TEST & TRIALS

Modelling SDF/SIF HATs SATs

Scenario
Generator

Sim Sim Sim Em Sim Sim Sens Sens Effect Effect


C D Stim Stim
Rec Rec
F
B A B C
C D E F
A B C
C E F
A E

MODELLING and SIMULATION SHORE FACILITIES (SDF/SIF) HARBOUR TRIALS ( HATs)


Modelling techniques may be used to The shore-based environment (e.g. SDF/SIF) is Upon satisfactory completion of tests and trials
identify potential integration problems and a cornerstone of the Combat System integration in the shore-based environment, a similar set of
issues well ahead of actual physical strategy as an essential risk mitigation exercise. progressive integration activities is conducted
integration at a point where costs This provides the opportunity to exercise for the First Of Class (FOC) to prove integration
associated with subsystem/equipment subject equipment (through simulation, with the platform. These are conducted first
change can be more effectively contained. stimulation and emulation within a dynamic through Harbour Trials in which the simulated
The continuation of modelling during this scenario representative of the operational elements (such as external sensors) are
stage, augmented by real data acquired environment) to perform tests and trials which replaced by actual equipment fit. peripherals
from equipment testing, serves to verify cannot be practically conducted on the platform. and tests repeated.
and refine early indications of overall The aim is to prove system design concepts
performance. and identify/resolve equipment integration SEA TRIALS ( SATs)
Modelling and Simulation is addressed in problems in a benign and controllable
Harbour Trials are followed by full Sea Trials,
Clauses 2 through 3. environment ashore before the equipment is
which seek to confirm correct Combat System
integrated onboard.
operation in the operational context.
Subsequent integration activities for follow-on
platforms follow the same pattern.
Sea trials form the basis for acquiring data in
support of longer-term goals such as AR&M
performance, data for which will be gathered
through-life.

Figure 7.5 Practical Sequence of Integration, Test and Trials

7.6.6 The primary activities undertaken during integration, test and trials are depicted in Figure 7.5 which
shows the underlying process against the backdrop of the practical modelling/shore/harbour/sea integration
sequence typical of Combat System integration projects. The process is described in detail in the remainder
of this part, whilst practical aspects of integration are addressed at para 7.7 Practical Integration, Test,
Evaluation and Acceptance.

7.6.7 The process elaborated here details the activities, which need to be collectively, addressed by the
Combat System organisations as an enterprise. Clearly there is much scope for variation between contracts
and the implementation of the generic process, as depicted in Figure 7.5 must be tailored to reflect prevailing
project circumstances.

Unclassified
172
DEF STAN 21-59 Issue 2

SYSTEMS ENGINEERING (TECHNICAL) Risk Management System Change Management Acceptance Management Audits
and PROJECT MANAGEMENT Progress Monitoring and Reporting Cost Control QA

SHORE-BASED TESTING SHIP-BASED TESTING ACCEPTANCE

SHORE FACILITIES HARBOUR TRIALS SEA TRIALS

COMBAT Combat System SAT(F)


Contract Acceptance
SYSTEM AR&M Trials
Combat System FWA
TRIALS Operational Effectiveness
Trials Operability Trials
WEMIT Ranging Trials
Combat System HAT(F) Combat System HAT(F) RADHAZ

COMBAT System NWHT/HAT System NWHT/HAT System NWST/SAT


SYSTEM
INTEGRATION Note : For FWA
Full System Integration/Overall Integration
Staged System Integration (SYSINT)/Group Integration read SA
Data Exchange Proving [e.g. Secondary Integration (SINT) and Functional Integration (FINT)]
and Interface Proving [e.g. Primary Integration (PINT)]/One-to-One/Member Integration

EQUIPMENT Equipment HAT(F) Equipment HAT(F) Equipment SAT(F) Equipment FWA


ACCEPTANCE

EQUIPMENT Equipment Equipment Equipment


TEST & TRIALS NWHT/HAT(E) NWHT/HAT(E) NWHT/SAT(E)
Interface Proving
Data Exchange Proving
Final Installation Final Installation
Inspection Inspection
Setting To Work Setting To Work
Installation Inspection Installation Inspection

EQUIPMENT Equipment FAT Equipment FAT


ACQUISITION Interface Proving
Data Exchange Proving

DEFECT MANAGEMENT

SYSTEM STUDIES Validation and Refinement of Prototypes and Models Data Recording and Analysis Compliance
Prediction System Performance Prediction System Change Investigation and Impact Studies

INTEGRATED Logistics Support Analysis (LSA) Life Cycle Costing (LCC) Integrated Supply Support Technical Documentation
LOGISTIC SUPPORT Maintenance Planning Support & Test Equipment Manpower & HF Training & Training Equipment

DOCUMENTATION Test and Trials Documentation Trouble Reports Analysis Reports


Engineering Databases and Information Systems Records Archive and Library

SPECIALIST DISCIPLINE SUPPORT Alignment Communications EMC Procurement Handbooks AR&M Human Factors ILS
Operational Effectiveness Platform Integration Safety Security Training

CONFIGURATION MANAGEMENT Configuration Definition Configuration Control Configuration Accounting

Figure 7.6 Integration, Test, Evaluation and Acceptance Activities

7.6.8 Systems Engineering (Technical) and Project Management

7.6.8.1 Objectives

7.6.8.1.1 Managing the integration task requires a wide range of co-ordinated activities to ensure that the
Combat System is efficiently brought together from its constituent interfacing equipment and platform
components. Project management activities during this stage serve to continue the regime (i.e. the
management of contracts, risk, quality, programme, Work Breakdown Structure (WBS), organisation,
progress, change etc.) put in place at the beginning of the previous development and production stage.

Unclassified
173
DEF STAN 21-59 Issue 2

7.6.8.1.2 SE activities during this stage follow on from those initiated earlier in the life cycle, with the
emphasis on supporting the integration process. SE activities are therefore primarily concerned with:

a) Scheduled demonstration of compliance with functional, non-functional and performance


requirements, ultimately determining ‘fitness for purpose’;

b) Identifying and resolving problems arising from installation, physical integration, testing and trials;

c) Co-ordination and collation of information to support the Combat System in-service.

7.6.9 Systems Engineering (Technical) and Project Management

7.6.9.1 MoD Weapon System Manager (CSM) Role

7.6.9.1.1 The MoD CSM role is one of overseeing the Combat System enterprise, ensuring that Combat
System integration, tests and trials proceed to cost and programme. NOTE: If the Combat system is
procured by a Platform Prime Contractor, the MoD still requires to monitor and have visibility of activities in
order to support Whole Ship Acceptance. The activities to be overseen include:

a) Management of system requirements, particularly with regard to change and the assessment of
change impact;

b) Maintenance of the overall design through refining the fidelity of through-life models to represent
achieved performance;

c) Assessment of achieved performance against baseline definition for identification of potential change
for current or future Combat System implementations;

d) Addressing Combat System-wide (coherence) issues, updating the coherence, system, subsystem
and Interface Specifications (IFS) when necessary;

e) Managing integration in the SIF or FOC, monitoring the progress of test and trials;

f) Monitoring conformance of the Combat System equipments with platform policies;

g) Monitoring the equipment development programmes and ensure that SDF/SIF plans can
accommodate changes in equipment delivery dates;

h) Witnessing a representative set of equipment, integration and Combat System-level acceptance


events to confer acceptance of contract articles/deliverables;

i) Assessing during the Integration Test and Trials integration against project metrics and Technical
Performance Measures (TPMs).

7.6.9.2 Activities during the Integration Test and Trials Stage

7.6.9.2.1 SE management and project management activities required to co-ordinate integration, test and
trials must be planned for and arranged during previous stages and management plans (chiefly the ITEAP
which must reach the maturity required in time) and provide the means to document proposed policy and
practice. Many of the activities are common to previous stages covered in this guide and are addressed in
detail in para 1.6.3.2 Systems Engineering (SE) (Technical) and Project Management. Priority life cycle-
related activities to be conducted during the integration, test and trials stage are as summarised there.

Unclassified
174
DEF STAN 21-59 Issue 2

7.6.9.3 Control Points and Reviews

7.6.9.3.1 The major control points in the integration, test and trials phases that come from the structured
approach to the conduct of inspections, tests and trials, are enforced by the adoption of a BR 4050
compatible approach. Entry into each step is controlled by ‘readiness’ reviews and by ‘pre-trial’ meetings.
Exit is controlled by post-trial ‘wash-ups’.

7.6.9.3.2 The occurrence of these ‘control points’ in the overall integration, test and trials programme is
further structured by the integration strategy and the process which emerges from that. There may be some
significant ‘ready for integration reviews’ where the status of major development items and their readiness for
a major trial is to be assured.

7.6.9.4 Programme Management

7.6.9.4.1 The programme management of integration, test and trials activities, including the development and
use of a SIF should be done as a normal part of the overall project programme management. The formal
trials process (from installation inspections through to System Sea Acceptance Trials (SAT(S))) will provide
the basic logic for a draft programme. The realities of equipment deliveries, the shipbuilding programme,
and the availability of trials ranges, areas, and assets will require very careful planning and a measure of
flexibility.

7.6.9.4.2 Once the integration programme has commenced, a pragmatic approach must be taken with
regular re-planning. This is necessary to take account of the impact of equipments missing their delivery
dates and the temporary loss of equipments that cannot participate in integration until corrective fixes have
been implemented and tested.

7.6.9.4.3 For reporting purposes, a sound set of ‘process metrics’ is recommended as best practice. These
have to be meaningful, sensitive, and useful for all parties involved in the programme. Metrics must reflect
the impact of known delays and the existence of problems being faced (since these may well bring about
further delays). In recent times, programme-related metrics tends to be identified by Risk Management
techniques. Project management teams will normally agree the metrics to be used as part of the project or
programme management plan. Typical examples of these process metrics may include:

a) Project cost, variance, time to completion, cost to completion;

b) Milestones achieved, days variance on milestone;

c) TPM achievement, variance;

d) Requirements compliance (especially User Requirement satisfied), overall programme coverage.

7.6.9.5 System Readiness Levels

7.6.9.5.1 SRLs are indicators of the maturity of equipment and system design, which are selected from
actual, measurable performance parameters. These are monitored throughout the design, development,
production, build, integration, test, and trials process as a management aid to identify potential performance
problems in key areas of the design.

7.6.9.5.2 Modelling provides the initial predictions of SRL value. Later on, more detailed modelling may
provide a SRL based on calculations. Development testing may provide the first physical measurements of
SRLs but, finally, it is integration, test and trials activities that provide the ultimate data used to assess
whether the required SRL growth has occurred, along with the required increase in the SRL confidence level.

7.6.10 Design Change Management

7.6.10.1 Objectives

7.6.10.1.1 The Combat System engineering process must recognise that change is an inevitable
consequence of the integration activities. The key to success is to manage change such that any impact is
first assessed before being implemented and re-tested.

Unclassified
175
DEF STAN 21-59 Issue 2

7.6.10.2 MoD CSM Role

7.6.10.2.1 During this stage, the MoD CSM role is one of identifying, promulgating and assessing the
impact of changes to the Combat System as a result of performance shortfalls of specific equipment(s). In
such cases, the impact of shortfalls will require further investigation with respect to the capability of the
warship.

7.6.10.3 Activities during the Integration, Test, Evaluation and Acceptance Stage

7.6.10.3.1 The need to assess the impact of change remains throughout this stage, to provide feedback to
subsequent programmes and to confirm the functionality and performance of the baseline Combat System
implementation. During this stage, change is likely to arise from the sequence:

a) Identification of integration problem;

b) Proposals for a corrective change;

c) Assessment of best course of action;

d) Implementation and re-test.

7.6.10.3.2 Design Change Management activities must follow the generic process invoking a controlled
regime (i.e. a project review cycle) as described in para 1.6 and 4.6. This provides a template for revisiting
the requirements engineering, systems analysis and system design activities to ensure that any impact is
identified, reviewed and approved.

7.6.10.3.3 System studies should again be used to ensure that the design remains compliant with the
requirements and represents a viable solution. Approved changes need to be introduced following the
integration, test and trials process outlined here through the controlled environment of the SIF/SDF before
installation and testing onboard.

7.6.11 Equipment Acquisition

7.6.11.1 Objectives

7.6.11.1.1 Although it is not specifically a part of Combat System integration, successful completion of the
equipment/subsystem Factory Acceptance Test (FAT) is a pre-requisite of equipment delivery to the SIF,
FOC and Follow-on (FON) vessels. It is advisable to ensure that equipment/subsystem FAT specifications
include tests which de-risk Combat System integration, whilst the equipment remains under the direct control
of the equipment supplier.

7.6.11.1.2 No equipment should be allowed to participate in the SDF or FOC integration until it has
successfully completed its FAT. Equipment contracts should ensure that the equipment is subject to design
proving at the factory within the constraints of the stand-alone environment.

7.6.11.2 MoD CSM Role

7.6.11.2.1 Acceptance of equipment and agreement and demonstration of conformance of interfaces is an


important activity, which, in the case of high profile interfaces (e.g. command system/principal sensor), may
demand MoD CSM representation. Where individual equipments are procured through the MOD, the
Equipment Project Manager (EPM) will retain responsibility for satisfactory completion of the FAT.

7.6.11.3 Factory Acceptance Test (FAT)

7.6.11.3.1 The test results from previous testing in particular prototype testing will be presented at the
FAT for formal acceptance of the requirements and initial confirmation of Equipment Specification and that
the ITEAP is being adhered to. This will include the demonstration of selected tests to confirm and formally
agree test results. Provisional acceptance will also be sought for those elements of the design, which can
not be fully accepted until the completion of environmental testing or later, in the SIF or through HATs/Sea
Acceptance Trials (SATs).

Unclassified
176
DEF STAN 21-59 Issue 2

7.6.11.3.2 Acceptance will address the functional, physical and performance characteristics of the
equipment and the correct functioning of its interfaces within the constraints of stand-alone operation. The
FAT will include a review of the evidence presented and formal signing off. Any failures will need to be
reworked and re-tested.

7.6.11.4 Interface and Data Exchange Proving

7.6.11.4.1 It is particularly important to test and verify the physical and logical operation of external
interfaces to ensure that they conform to a recognised networking / interface standard (as defined by the IFS
e.g. Def Stans 00-19, 21-24, 21-26 and 21-28 for data transmission) and comply with their Data Exchange
Specifications (DES). For equipments which communicate across a data highway, the integration strategy
must determine not only the optimum sequence of integration but also the strategy for validating physical
and logical operation of stand-alone equipments prior to connection. Test equipment may be required to
demonstrate:

a) Compliance with the relevant interface standard;

b) Interface design proving through data highway simulation;

c) Emulated equipment-to-equipment data exchange in a limited system configuration.

7.6.11.4.2 The use of test equipment is encouraged as a risk reduction measure, though it is
acknowledged that the authenticity and fidelity of highway simulation potentially limits proof of the data
exchange and associated test scenarios.

7.6.12 Equipment Test and Trials

7.6.12.1 Objectives

7.6.12.1.1 The objective of equipment test and trials (alternatively known as equipment Preparation for
Acceptance (PFA)) is to demonstrate that the subject equipment meets its requirements in stand-alone
operation. This is to contribute to the assessment of ‘fitness for purpose’ and to determine that, when
installed, the equipment will function reliably, safely and to specification at sea in the military environment.
Equipment Test and Trials, as summarised in Table 7.1 are the necessary pre-cursor to the staged
integration of the Combat System and the test results obtained may contribute to overall acceptance.
Further details are contained in BR 4050.

Unclassified
177
DEF STAN 21-59 Issue 2

Table 7.1 Equipment Test and Trials Activities


Activity Applicability Purpose

Installation SIF/FOC/FON Installation of the equipment in the SIF, or on the FOC or FON vessel.

Installation SIF/FOC/FON Carried out after completion of installation work to give clearance to
Inspection (II) begin Setting To Work (STW) of the equipment. II may be completed
subject to defects and deficiencies, which will need to be satisfied before
FII. The II serves to confirm that:

• Equipment has been fitted in accordance with approved installation


specifications and drawings. Any departure or conflict with the
contracted or approved installation specifications or other relevant fitting
out information must be reported;
• All other installation work, connection to services (e.g. power,
chilled water etc), tests and checks required as pre-requisites for the
commencement of STW have been satisfactorily completed;
• Accompanying test equipment, special tools, documentation
(Installation Specification, STW procedures, Maintenance Schedules,
Equipment Handbook/Operating Instructions, Build State Records) and
services have been provided.

7.6.12.1.2 There is a considerable difference in the level and intention of testing of SA i.e. HAT(F) and
SAT(F) and follow-on acceptance. SA is extensive to probe the design and evidence for acceptance; follow-
on HAT and SAT is less extensive, sufficient to demonstrate that the equipment is functioning correctly.

7.6.12.2 MoD CSM Role

7.6.12.2.1 The MoD CSM needs to keep a close watch of progress towards integration and will benefit
from visibility of the equipment test and trials programme including regular liaison with the nominated EPM
for new and modified equipments, which fall within the remit of MOD.

7.6.12.3 Subsystem/Equipment Implications

7.6.12.3.1 The integration strategy must determine the optimum route for integration of equipments/
subsystems which best addresses risk to the development of the Combat System itself. There is therefore a
need to test new/modified equipment fully and rigorously as stand-alone items prior to commencing
integration in the SIF. In-service items, which have previously achieved SA and are required in an un-
modified form, need to be subject to a HAT to confirm their correct operation. The following table
summarises the implications of development status on the integration process.

Unclassified
178
DEF STAN 21-59 Issue 2

Table 7.2 Subsystem/Equipment Integration


Category Integration, Test, Evaluation and Acceptance Implications

New Equipment - solely Modelling Functional and architectural performance models of new/modified
developed, integrated and equipments can be used to assess functional compatibility and
accepted under the Combat verify data exchange across equipment interfaces. Models should
System requirement be validated by test data generated in support of FAT.

Modified Equipment - defined SIF Each new/modified equipment must pass its FAT before delivery
by an independent requirement to the SIF. The SIF equipment set must be identical to the FOC &
but functionally or physically FON sets. Where the Equipment Development and SIF
changed to support integration programmes run in parallel, interim equipments may be delivered.
into the Combat System In these cases, rigorous testing is required in the SIF.

New/Modified Interfaces - FOC All tests from Installation Inspection to System HAT need to be
separate development of conducted. New/modified equipment installed on the FOC is to
interfaces required to integrate be subjected to Equipment HAT(F)/SAT(F) trials in support of SA.
NDIs (see below)

FON FON equipment sets will require only a subset of the tests
performed on the FOC to confirm correct installation and
operation. As a minimum, FON equipment requires IIs and
HAT(E), followed by sufficient integration testing to de-risk the
Combat System HAT as determined by the Integration
Strategy/Acceptance Management Plan.

NDI In-Service Equipment - SIF/FOC/ Auditing/re-validation of test data generated from previous SIF
typically equipment which has FON and FOC testing for major equipments (central to Combat System
achieved SA to be integrated as core functions).
is without modification
Integration and repeat test of FOC equipment as determined by
the Integration Strategy/Acceptance Management Plan.

NDI Non-COTS - bespoke SIF/FOC/ Independent evaluation needed to determine functionality and
equipment in-service with a FON performance.
foreign navy which has never
been subject to UK MoD
acceptance

NDI COTS - commercial Modelling Independent evaluation needed to determine functionality and
products and items developed for /SIF/FOC performance.
military application to be /FON
integrated without modification Integration of COTS components (particularly diverse software
packages developed by competing organisations) into an
operable system is a non-trivial undertaking. Incompatibilities are
inevitable, given the diverse features of available products.

Testing demands a definition of the requirements to which the


subject equipment has been designed. Requirements to which
re-used/COTS equipment has been designed are not necessarily
available or, if they are, complete.

Unclassified
179
DEF STAN 21-59 Issue 2

7.6.13 Combat System Integration

7.6.13.1 Objectives

7.6.13.1.1 The integration of a Combat System is a complex ‘bottom-up’ process, bringing together
component equipments in an ordered sequence of repeatable steps to realise a fully operational system.
There are no absolute rules for the sequence of integration and each case must be planned according to its
needs. The vehicle for defining the optimum integration process is the previously developed integration plan,
which must establish the sequence, which represents the least risk. However, there are acknowledged
activities, which although defined as distinct steps, may in practice be combined according to the needs of
the project.

7.6.13.2 MoD CSM Role

7.6.13.2.1 The MoD CSM role is primarily one of ‘informed customer’, monitoring progress of the project
against the integration programme, facilitating communications and the resolution of issues between Combat
System, equipment and platform programmes wherever there is potential conflict. NOTE: If the Combat
system is procured by a Platform Prime Contractor, the MoD still requires to monitor and have visibility of
activities in order to support Whole Ship Acceptance. Additionally, liaison will be necessary to ensure the
smooth transition and clear responsibility for liability, from factory to shore facilities where these are under
MoD ownership (e.g. Land Based Test Sites (LBTS)/SIF at Portsdown).

7.6.13.2.2 The CSM should satisfy himself that policy and strategy for integration of the Combat System is
being implemented in an effective manner, and those integration risks are identified early and appropriately
managed. This also means ensuring that testing of equipments meets the needs of the Combat System and
that duplication of testing is minimised.

7.6.13.3 Combat System Integration Activities

7.6.13.3.1 Although the principles of Combat System integration are well founded there is some difference
in nomenclature between submarine and surface ship application. The following table summarises the
integration activities, which are to be conducted.

Table 7.3 Combat System Integration Activities


Submarine Nomenclature Surface Ship Nomenclature

Primary Integration (PINT) Member/One-To-One Integration


Testing of the electrical interface between two equipments as Interface, data exchange, functional and performance
defined by the associated and approved IFS. This tests the trials between equipment and (separately) each of the
physical and electrical characteristics of the interface together other equipments with which it interfaces. Surface ship
with its basic communications protocol, which supports the policy is to exhaustively check data content and range
data exchange. values in the stand-alone roving of equipments where
possible.

Secondary Integration (SINT) A reduced set of these trials may contribute to an


Interface NWHT.
Testing of the data exchange between two equipments for
data content and the range of values as defined in the DES.
This involves tests of message transfer in isolation.
Secondary Integration may be combined with PINT.

Combat System Integration Activities (continuation)

Unclassified
180
DEF STAN 21-59 Issue 2

Submarine Nomenclature Surface Ship Nomenclature

Functional Integration Test (FINT)


Testing of the data exchange between two equipments to
prove the functionality as defined in the DES. Typically, this
will involve a sequence of message exchanges between
subsystems in line with expected behaviour in the context of
a scenario. This is also to ensure that the separate
functions of equipment are not impaired through their
interfacing.

(Staged) System Integration Test (SYSINT) Group Integration

Staged series of individual tests to prove the functional Integration of communicating equipments which support
interaction of logical groups of equipment to show that one or more functions covered by a functional warfare
equipments can successfully operate in an integrated area (e.g. Above Water Picture Compilation or Anti-
manner. A gradual build-up of groups of equipment will Submarine Warfare). Group Integration covers further
culminate in full Combat System tests. functional and performance tests where the function
involves more than two equipments. It tests the resilience
of the group to concurrent operation, high loads, changes
in configuration, and system ‘threads’ through the
equipments integrated in the Group.

Overall Integration

Overall Integration covers those functional and


performance tests that involve more than one warfare
area, together with the concurrent operation of Group
Integration tests to check for any degrading mutual
interaction. These culminate in tests of the whole Combat
System operating under a high load and over an extended
period. Agreed scenarios are used to create heavy
though realistic track loadings for the scenarios used for
high load and volume tests.

7.6.13.4 Regression Testing

7.6.13.4.1 Regression testing serves to prove that the addition of new functionality does not detract from
the previously proven operation of an existing capability. Regression testing repeats earlier testing under a
wider variety of carefully controlled conditions to isolate and correct latent problems. Particular attention
needs to be paid to build states including software issue status in order to maintain traceability and control
between integration configurations.

7.6.13.5 Further Information

Further information can be found in:

a) BR 4050 Instructions for the Conduct of Naval Weapons Inspections and Trials;

b) The AMS, which has copious advice under ‘Acceptance’;

c) Def Stan 21- 88 Policies and Procedures for Combat System Integration in Surface Ships.

Unclassified
181
DEF STAN 21-59 Issue 2

7.6.14 Combat System Trials

7.6.14.1 Objectives

7.6.14.1.1 By the time the Combat System equipments are installed in the FOC platform, a
comprehensive programme of integration testing in the SIF will have been completed. Although the SIF is a
cornerstone of the integration and acceptance programme, it has the limitation that the Combat System
environment is simulated and the Combat System may not be fully representative of the ship fit.

7.6.14.1.2 Integration on the FOC and HATs seek to confirm the system behaviour, established in the
SIF, on-board the FOC. Subsequent SATs extend the test/trials programme to exercise functionality and
performance which cannot be adequately demonstrated in a SIF or on the warship when alongside.

7.6.14.1.3 Combat System Trials are intended to demonstrate that the integrated Combat System meets
the SRD as amplified by the ITEAP and TLMP and support the MoD CSM in presenting the Combat System
for SA.

7.6.14.2 MoD CSM Role

7.6.14.2.1 Combat System trials need to be co-ordinated as an integral part of whole warship trials as
identified in the whole warship trials plan. NOTE: If the Combat system is procured by a Platform Prime
Contractor, the MoD still requires to monitor and have visibility of activities in order to support Whole Ship
Acceptance. The plan should be consistent with BR 4050, the needs of individual equipments and
subsystems, and the requirements of the Combat System acceptance plan. It is the responsibility of the
Combat System Integrator (CSI) organisation, in coordination with the CSM to:

a) Identify appropriate trials and ensure that all relevant trials are included;

b) Determine the conduct of trials;

c) Ensure that all trials results are adequately analysed, recorded and reported;

d) Check the completeness of the trials documentation supplied;

e) Ensure that any additional trials are reported, and agree the appropriate actions required conducting
any additional trials.

7.6.14.2.2 The conduct of individual trials is the responsibility of:

a) Individual EPMs for equipments/sub-system specific trials;

b) CSI for installation, operational spaces, safety, and alignment aspects of the whole warship and for
Combat System integration and performance aspects.

7.6.14.2.3 The CSM is responsible for ensuring that all parties are aware of their individual responsibilities
and that trials produced reflect the current agreed status of the Combat System design.

7.6.14.3 Harbour Integration

7.6.14.3.1 Integration on-board the warship follows the general pattern defined in BR 4050 for inspection
and trials. Equipment is installed in accordance with the Installation Specification and then subjected to an
Installation Inspection (II). The equipment suppliers are then responsible for equipment Setting to Work
(STW).

7.6.14.3.2 Integration in the FOC may be developmental: all new/modified equipments must have reached
Naval Weapon Harbour Trial (NWHT) standard before consideration can be given to them being connected
to a ship-wide Combat System data transmission system. Experimental connection to other equipments via
the highway must be approved by the WSM.

7.6.14.3.3 Where physically separate items of equipment together form a subsystem, which is the
responsibility of a single EPM, these equipments will be linked prior to seeking harbour acceptance for the
Unclassified
182
DEF STAN 21-59 Issue 2

equipments/subsystem through the HAT(E). Equipment acceptance is the responsibility of the EPM,
although the CSI may provide assistance if required.

7.6.14.3.4 Following Contractor Sea Trials (CSTs), subsystems are linked on a group by group basis as
for the previously conducted SIF integration. Stimulation of most sensors is still required at this point and
hence trials support facilities (e.g. scenario generator and recording/analysis) will be required on-board.

7.6.14.3.5 Integration testing onboard should follow the same sequence as for the SIF, with the emphasis
on confidence building. If confirmatory results are obtained from key tests, then it is not necessary to repeat
the full range of testing, in particular to the extensive range of performance testing, carried out in the SIF.
Shortcomings or anomalies require reporting, leading to regression testing or impact analysis studies.
Completion of harbour testing will enable the Combat System HAT to proceed.

7.6.14.4 Combat System HAT

7.6.14.4.1 The Combat System HAT serves to prove the functional interaction of the full Combat System
with equipment being stimulated to simulate operation in a complex test scenario. Individual and combined
equipment functions are checked as for previous integration activities.

7.6.14.4.2 The Combat System HAT is conducted following completion of integration activities to confirm,
as far as possible in harbour, that the Combat System is free from defects, working in accordance with
approved schedules and will be supportable in-service.

7.6.14.5 Sea Trials

7.6.14.5.1 Following the harbour testing, sea trials allow the Combat System to be tested in the
operational environment. The sea trials phase includes both Combat System integration proving as well as
performance demonstration of those aspects of the design that cannot be conducted in the SIF or alongside.
Where the SIF/SDF has been used to prove both trials orders and the equipments in order to de-risk the sea
trial, previously run shore trials may be repeated. Equipment stimulators and simulations are removed to
make way for connection to actual sensors at the appropriate point in the integration/trials programme.

7.6.14.5.2 It is important that trials include a range of tests designed to exercise and prove those aspects
of system operation only demonstrable in at-sea conditions. They are intended to establish benchmarks for
comparison purposes but not necessarily to duplicate previous SIF or harbour tests.

7.6.14.6 Sea Trials Programming

7.6.14.6.1 The extent of sea trials needs to be kept to the absolute minimum to contain the cost
associated with safely operating resources, ranges and assets in the execution of specific trials. A schedule
of trials best representing the phased demonstration of the Combat System must be produced which seeks
to achieve the optimum balance, taking into account:

a) Safety aspects, including collision avoidance, navigation and communications, will always take
priority;

b) Individual EPMs seeking to achieve SATs & SA for their equipments where these are new to service;

c) Availability of assets and ranges together with clearances for firings where necessary;

d) Common use of scenario conditions modelled during earlier integration activities (e.g. effectiveness
modelling, scenario generation in the SIF);

e) Availability of operational skills through use of the ships staff in the conduct of SATs and effective
control of associated assets;

f) Operator familiarisation with the facilities;

g) Opportunities for ship staff training, maintenance, and leave;

h) Grouping of similar resources to be used for a range of trials;


Unclassified
183
DEF STAN 21-59 Issue 2

i) Contingency to allow for weather, asset non-availability e.g. defective aircraft.

7.6.14.6.2 Control of the sea trials programme should be exercised through regular (daily if required)
meeting of all the decision makers involved, the authority, the contractor, the commanding officer, and the
inspection staff, or their respective representatives empowered to make decisions.

7.6.14.7 Trials Data Recording

7.6.14.7.1 Recording and analysis support facilities are required for both for ‘quick-look’ (i.e. on-board)
purposes and subsequent, more detailed, shore analysis. Individual trial orders will clearly identify the data
to be recorded as proof of individual system attributes. ‘Quick-look’ analysis of complex trials recordings
should be used to confirm the validity of recorded data before the ship departs the ranges or releases
assets. This will serve to reduce the risk of needing to repeat trials due to faulty recording, conduct or
procedures. A guide to appropriate data types is provided in Def Stan 21-43. A DR&A ‘Needs Analysis is
required by MCTA Policy. Further advice should be sought from MCTA-W1.

7.6.14.8 Repeat Trials

7.6.14.8.1 Results required either, as supporting integration proving or acceptance will be formally
presented to the acceptance authority at the earliest opportunity after completion of the trial. Trials assessed
as standards ‘not-achieved’ will be carefully reviewed and repeat arrangements agreed between the
authority, contractor, the ship’s operational control (OPCON) authority for the warship, range authorities, and
the other asset controllers as required.

7.6.14.9 RADHAZ

7.6.14.9.1 Radiation Hazard (RADHAZ) trials are normally conducted during the later stages of vessel
construction, after the commissioning of all of the radio frequency emitters, particularly the communications
and radar equipment. These trial results are a significant input to the safety case for the vessel. There are
two basic sets of RADHAZ trials relating to personnel safety and weapon fuse safety. The objectives are:

a) To provide evidence that the safe areas defined by calculation during design are actually safe on the
vessels;

b) To demonstrate that the electro-magnetic (EM) field levels affecting weapon embarkation, stowage
or transit routes will not cause inadvertent fuse activity.

7.6.14.9.2 Further advice is available from DCSA EI&IS Test & Reference Branch, Blandford who have
specialists in all areas of Electromagnetic Environmental Effects (E3).

7.6.14.10 Ranging Trials

7.6.14.10.1 Ranging trials are undertaken after the construction and commissioning of systems on the
vessels, where ‘open water’ conditions are needed to characterise various performance parameters of the
installed Combat System and other systems. In particular, characterisation of the vessel’s signatures is
undertaken to provide information vital to the survival of the ship in wartime operations. The types of ranging
trials performed are summarised in Table 7.4.

Unclassified
184
DEF STAN 21-59 Issue 2

Table 7.4 Ranging Trials


Trial Performance Parameters or Signatures

Noise Ranging Acoustic Signatures

Magnetic Ranging Magnetic Signatures


Degaussing System Performance

Radar/Radio Frequency Radar Cross Section


Ranging Radar (Glint) Signatures
EW Calibration
Aerial ‘Polar Diagrams’ and ‘Wooding’ assessments to
determine sensor and comms receiver/transmitter blind arcs
and coverage
EW Signature

7.6.14.10.2 The objective of these trials is two-fold:

a) To characterise the signatures of the platform to enable the vulnerability to threat weapon systems to
be assessed;

b) To gather information for use in threat evaluation libraries.

7.6.14.11 Weapons Electrical Mutual Interference Trial (WEMIT)

7.6.14.11.1 WEMIT is an assessment of the weapons equipment operation on the performance of the
communications systems - both internal and external - and vice-versa. The trial comprises a methodical
progression through each subsystem/equipment to assess the effects of operating weapon equipment whilst
the communications system is operated in a ‘typical’ operational mode. As a consequence, WEMIT
demands a high level of manning to monitor the communications system performance and to detect
interference in any of the external or internal communications ‘circuits’ established.

7.6.14.11.2 The objective of the trial is to ensure those interference characteristics, if they exist, are known
and that any interference detected is operationally acceptable. A significant feature of this trial is that it
should only occur after all equipments have achieved SAT standards. Part WEMITs can be conducted at
earlier points to reduce risk in programmes with a high equipment or system development content.

7.6.14.12 Operability Trials

7.6.14.12.1 Operability trials are conducted to ensure that the expected operator performance can be
achieved. This work forms part of the Human Factors (HF) proving exercises. Operability trials can be used
at any point in the development or integration/acceptance flow. They effectively form the demonstration
point for showing that the ‘man’ forms an effective part of the system.

7.6.14.12.2 Operability trials can cover many parts of the HF spectrum, from proving the ergonomics of a
console - field of view, ability to reach controls - through to assessment of operator workload in high
stress/high load conditions. These trials are a significant feature of the overall trials programme and are
used to demonstrate the successful implementation of the HF (management) plan and the achievement of
HF requirements.

7.6.14.13 Operational Effectiveness

7.6.14.13.1 Operational effectiveness is a function of ‘performance’ and ‘availability’ of the vessel and its
weapon systems in a specific scenario. Test and trials data will be collected during the early phases of in
service life when the relevant operational and tactical development authorities control the vessels. This will
provide initial evidence in support of the validation of the modelled operational effectiveness performance,
allowing any advantages or shortfalls in performance to be characterised.

Unclassified
185
DEF STAN 21-59 Issue 2

7.6.14.14 AR&M Trials

7.6.14.14.1 In 1981, AR&M performance was given equal significance with operational performance, and
AR&M trials have become increasingly important. This is especially so when the responsibility for achieving
system or ship-level AR&M performance is allocated to a system or warship project manager or even to a
prime contractor.

7.6.14.14.2 Obviously, AR&M trials are long term activities during which AR&M data is gathered to allow
comparison of predicted and actual AR&M performance in support of contractual acceptance. This
performance depends upon many factors, including:

a) Reliability of the delivered products;

b) Maintainability of the delivered products;

c) Adequacy of logistic (stores/spares provisions and the turnaround time (logistic services));

d) Adequacy of training services to provide competent maintainers.

7.6.14.14.3 These trials provide information to show that ILS requirements have been satisfied or point to
areas where rectification effort needs to be applied.

7.6.15 Acceptance

7.6.15.1 Introduction

7.6.15.1.1 Integration and acceptance of the Combat System must be planned in concert through the co-
ordination of the integration and acceptance strategy developed during earlier stages. The integration
process must achieve a fully functioning Combat System, whilst the acceptance process is an ongoing
activity to gather evidence to gain contractual acceptance and support SA. The tests necessary for
integration purposes will generally provide evidence for acceptance. This is illustrated in Figure 7.7.

Requirements
Allocation and
Decomposition SIF FOC Follow On

Combat System
Validation of System/Compliance Formal
Reqs with Requirements Acceptance Trials Cumulative
Acceptance

Analysis Test

Lower-level Design Integrate


Subsystem/Equipmet
Requirements,
partitioned by the Acquire
System Design

Subsystem/
Equipment Subsystem/Equipment
Contracts Deliverables
Subsystem/Equipment
Evidence of
Validation of Equipment /Compliance Compliance with
Reqs Acceptance Trials Lower-level
with Requirements
Requirements for
Formal Acceptance

Analysis Test

Design Integrate

Manufacture

Figure 7.7 Combat System Acceptance


Unclassified
186
DEF STAN 21-59 Issue 2

7.6.15.1.2 The traditional approach to SA for weapon equipment uses Acceptance Criteria (ACs) as the
definition of what is to be delivered, and an AQ to ensure that the ‘end user’ is getting what the ACs defined.
This has been extended to the Combat System level progressively since 1980 and provides a keystone in
the naval project management process. In Smart Acquisition the ACs and AQs are replaced by a
combination of the SRD and associated verification criteria traced to the URD and the ITEAP.

7.6.15.3.3 The scope of the contracts being placed at present has significantly extended the scope of
supply from industry and the methods of specifying requirements has become more structured. Modern
contract regimes demand, at the contract outset, detailed definition of how the contract deliverables will be
accepted by the customer and the end user. NOTE: The URD reflects the Military Capability required and
therefore requires demonstration that the Interoperability and other Defence Lines of Development (DLoDs)
can support the Military Capability required. This cannot be solely within the contractor’s and IPT’s remit but
nevertheless must be arranged and included in the ITEAP.

7.6.15.3.4 A major feature of acceptance is that it enables the progressive gathering of acceptance
evidence, from all phases of the project. Although acceptance evidence is collected throughout the project,
and thereby reduces the risks to achievement of final acceptance, it should be noted that final acceptance is
targeted at acceptance of the system installed in the vessel after demonstration in-service, at sea. The steps
along the way to introducing a vessel into service with the RN provide a means for defining a staged
acceptance scheme, in which Integration, Test, Evaluation and Acceptance plays a significant part.

7.6.15.4 Acceptance Points - Transfer of Ownership and Responsibility

7.6.15.4.1 For contracts that involve the large scale integration of complex equipment into a complex
system as part of an even more complex product, whether ship, submarine, tank or aircraft, one aspect
which needs to be considered is: the definition of who owns what at any one time, and who is responsible for
what.

7.6.15.4.2 From a contractual viewpoint, ownership (transfer of title) should be transferred at the point of
acceptance. Ideally, this should be the point of delivery – but rarely is. So, in a contract where items come
from a number of different sources, deliverables may be provided by a number of different supplier
organisations, and are integrated progressively into the Combat System – it becomes obvious that there is a
need for great care in defining:

a) Who is to supply what;

b) Who is to provide what support services, to whom, and for how long;

c) Who is responsible for care, maintenance, and safe operation of delivered items;

d) When the point of delivery occurs – or how it is split in to phased deliveries;

e) When the point of acceptance occurs;

f) When the transfer of title takes place and who assumes ownership;

g) What the responsibilities of the new owner are.

7.6.15.4.3 There are the traditional approaches, used in MoD contracts where MoD are the prime
contractor, where the ship’s staff standing by take over ownership of equipment and systems as they
progressively reach a HAT ‘standard’. Where Industry is acting as the prime contractor, the rules are
different with ownership and responsibility being maintained on industry, rather than transferring to MOD,
until some defined acceptance point in the programme. There are also differences between surface ship
and submarine programmes, where staged acceptance may be invoked or where the MoD takes over a
surface vessel and its combat system for Part IV trials.

7.6.15.4.4 Progressive Acceptance is becoming an increasing feature of Smart Acquisition – although this
is still being formulated within official policy.

Unclassified
187
DEF STAN 21-59 Issue 2

7.6.15.5 Equipment Acceptance

7.6.15.5.1 Equipment Acceptance is a significant feature of the progress towards Combat System
acceptance. Typically equipment is developed to support use across the fleet or the submarine flotilla as
part of several Combat Systems. The fitness for acceptance into RN service is nowadays assessed at the
equipment level and the system level.

7.6.15.5.2 SA cannot be granted until equipment functionality and performance has been satisfactorily
demonstrated as part of the system trials. Similarly, it must be demonstrated that all equipment-related Line
of Development can support the needs of the Combat System.

7.6.15.5.3 The need for separate equipment acceptance depends on many factors of which the most
important are when:

a) An equipment is procured against a stand-alone URD rather than as part of a URD;

b) An in-service equipment requires modifications which affect the URD/SRD;

c) An equipment contains a significant proportion of COTS items and needs to be introduced into
service. Note that the acceptance of COTS is likely to raise many new issues, particularly with
regard to acceptance.

7.6.15.5.4 Equipment Acceptance is the responsibility of the EPM and the MOD(DPA) directorate holding
responsibility for discharging the URD/SRD. The EPM may only be able to achieve partial or provisional
acceptance until SA is achieved. (BR 4050).

7.6.15.6 Combat System SAT(F)/Combat System SA

7.6.15.6.1 Currently, with the adoption of a progressive approach to acceptance, the trials used to achieve
SA are more likely to be the Combat System SAT on the second (or a later) vessel in the class. Effectively
these trials make a point at which SA can be granted. SA depends on much more than trials and
achievement of standards at trials. Particularly, ILS provisions and AR&M performance are a significant part
of SA, which is signified by the IPT RM supported by the CAWG completing the Acceptance Questionnaire
(see BR4050) rather than a single trial.

7.6.15.6.2 SA and SAT(F) trials make the point at which the Combat System’s introduction into RN
service is completed and, operational capability is available. It also represents the acceptance by the naval
staff that the URDs have been met and the system is ‘delivered’ to the RN’s user branches -
operators/maintainers.

7.6.15.7 Contract Acceptance

7.6.15.7.1 All trials contribute evidence to demonstrate that contract requirements have been satisfied.
Traditionally, a ‘Final Acceptance Trial’ is conducted before MCTA and the shipbuilders or prime contractor
representative in the wardroom sign off the final acceptance certificates. Contract acceptance however is
the formal review of the programmed deliverables and the Defect and Deficiency Database (D3B).

7.6.16 System Studies

7.6.16.1 System Studies initiated during development and production continue during integration, test and
trials with the emphasis on using and evolving models to:

a) Refine model fidelity using data generated from the performance evaluation of real equipment;

b) Assess the impact of any shortfalls or improvements in system design performance;

c) Support investigation and problem solving of integration across equipment interfaces;

d) Support acceptance of design aspects which cannot be definitively or practically demonstrated (e.g.
operational effectiveness);

Unclassified
188
DEF STAN 21-59 Issue 2

e) Support subsequent analysis of test and trials results e.g. pre-trials predictions and post trials
analysis.

7.6.17 Defect and Deficiency Management

7.6.17.1 Objectives

7.6.17.1.1 Throughout the life span of a project, the Quality Assurance (QA) system has to ensure that
there is an adequate method for dealing with problems of non-conformances and customer complaints.
Defects and deficiencies are the terms traditionally used for problems experienced during ship-based
integration, tests, and trials phases.

7.6.17.1.2 Defects and deficiencies used to be recorded and tracked using either MOD-sponsored or
Shipbuilder-sponsored mainframe databases. Currently, the vogue is to strive for a ‘problem/action reporting
and tracking process’ which is used throughout the full project term. Essentially, problems are identified and
resolutions actioned which need to be appropriately programmed and resourced.

7.6.17.2 MoD CSM Role

7.6.17.2.1 The test and trials organisation (test groups) will be primarily responsible for managing the
resolution of defects and deficiencies during the programme up to vessel acceptance. The resolution of
defects and deficiencies is a team activity-requiring liaison between all parties.

7.6.17.2.2 The project team needs to understand whether it will be possible to solve problems within the
stated timescale. They need to be prepared for use of more resources or programme slippage. The project
(management) team to ensure it is in control should regularly review problem-solving progress.

7.6.17.3 D3B Process

7.6.17.3.1 The D3B process replaces the D448 activities for vessel acceptance.

7.6.17.3.2 The purpose of the D3B process is to agree the defect and deficiency list and, more
importantly, who is responsible for fixing the defect or remedying the deficiency and when it will be done.
Actions are allocated to the shipbuilder, MoD project organisations, ships staff, or MoD support
organisations, to be completed pre- or post-handover of the vessel to the RN.

7.6.17.3.3 With the formalisation of shore-based system integration, tests, and trials as part of the Combat
System and ship system acceptance, there has been a move to record and manage defects and deficiencies
which are not related to ship-fitted equipment. A variety of approaches exist across different projects, all of
which have some basis in the procedure used for ships during build or for equipment and systems in service
(e.g. the S2022 procedures). The recording and resolution of defects and deficiencies supports the cycle of
formal reviews of requirements, design, product tests readiness, configuration definition, and requirement
compliance.

7.6.17.4 Problem/Action Tracking Process

7.6.17.4.1 The essential features of a problem and action tracking process and toolsets used to support it
are:

a) Application of a rigorous process and dedication to managing the process is the main point. The tool
used (e.g. D3B) to support the process is only a tool. There is no easy alternative to the painstaking
exercise of vigorously addressing each and every problem and recording it with the tool in such a
way that there is no danger that the data can be misinterpreted;

b) Support of data analysis to give meaningful data, from which conclusions can be drawn and
progress assessed, including identification of bottlenecks;

c) Only collect metrics that give meaningful pointers and use the information;

d) Ensure that every problem has an owner and a solution date;

Unclassified
189
DEF STAN 21-59 Issue 2

e) Follow detail to the level where there is sufficient visibility to manage the project by making the right
decisions;

f) Focus attention on areas that will result in the biggest real impact on progress; identify the show-
stoppers and remedy them;

g) Use problem recording as a means of identifying risks - those problems that have no apparent
straightforward solution should be transferred to the risk register. It should be recognised that one
person’s problem can initiate another person’s risk.

7.6.18 Integrated Logistic Support

7.6.18.1 Introduction

7.6.18.1.1 The introduction of the practices, which make up the ILS discipline, took place over a period of
several years. Support is now viewed as a ‘full life cycle’ activity, rather than ‘what happens after
introduction into service and SA’. The level of planning which now goes in to setting up and populating the
LSAR, along with the concept and practice of ‘progressive upkeep’ means that the early stage of equipment
and system life cycle and their usage in the integration, test and trials activities now becomes an integrated
part of the logistic support life cycle.

7.6.18.2 MoD CSM Role

7.6.18.2.1 There is still the split in responsibilities across the equipment and system life cycle, between
the DPA and DLO, who fund ILS activities separately in the periods before and after transfer of responsibility
from the DPA to DLO. Handover to the DLO occurs when equipments and systems are declared ‘mature’.
Maturity needs to be demonstrated by all those things which have always been associated with SA,
particularly:

a) Compliance with the documented operational, functional, and performance requirements;

b) Demonstration of AR&M performance in service, in the hands of the RN operators and maintainers,
backed up by the logistic support organisations in MoD and in industry;

c) Evidence of a ‘stable product design’, through the lack of changes needed to make the hardware
and software of the system components work as required to meet the specified functionality and
performance;

d) The satisfaction of the ‘end user’ with the installed systems from the operator and maintainer
viewpoint, once they are considered ‘in service’;

e) The provision of all of the support facilities and services needed to train RN staff; to provide stores
facilities and services, to provide maintenance and repair facilities; and so on.

7.6.18.3 ILS Activities during Integration, Test, Evaluation and Acceptance

7.6.18.3.1 The Integration, Test, Evaluation and Acceptance activities play a significant part in the
demonstration that the planned ILS aspects meet the requirements. The value of the Integration, Test,
Evaluation and Acceptance phase of the programme to the ILS community depends on it being treated as an
integral part of the ‘product life cycle’ and a source of valuable, early, real-life information on the
implementation of products designed to optimise AR&M performance and achieve specified AR&M levels.

7.6.18.3.2 Over recent years, the move towards Combat System projects, with the improving level of SE
has helped with rationalising ILS aspects. The current vogue for concurrent engineering, often implemented
by ‘integrated’ design, build, and support teams, must be used as a significant opportunity to further improve
ILS planning, implementation, and assessment across the whole of the life cycle.

7.6.18.3.3 The MoD and industry Integration, Test, Evaluation and Acceptance teams need to ensure that
there is good interaction with the ILS teams. Each needs to involve themselves in the generation and
approval of the integration, test and trials management plan and the ILS management plan - and the ensuing

Unclassified
190
DEF STAN 21-59 Issue 2

processes throughout the project programme - to make sure that best value is derived from this part of the
programme.

7.6.18.3.4 From the time that equipment is first developed, representative AR&M data can be gathered.
Even though the information gathered at this stage needs to be used judiciously, it begins to provide
evidence that the required or predicted AR&M performance is being achieved (or not, in unfortunate cases).
For developing equipment, this will be the first ‘real life’ information for other equipments that it will add to the
existing information.

7.6.18.3.5 The maintenance regime can also be brought into play after HAT(E) is achieved and all that is
needed to support this can begin to be used and assessed. It is important that these activities are identified
as evaluations, in their own right, in the acceptance management plan and the integration, test and trials
management plan. The evaluation methods and assessment criteria need to be spelled out here too, just as
they would for the functional and performance tests and trials.

7.6.18.3.6 In these early stages, especially with developing equipment, there can be a significant level of
‘disturbance’ as items are accessed for inspection or connection to test equipment. Problems occurring
because of the level of disturbance in this phase detract from the expected AR&M growth. This is
particularly true of the shore integration facilities and the FOC. It is also important in these early phases to
recognize that “100% reporting” of defects and deficiencies does not occur in practice. A common
understanding and code of practice is needed across the whole Combat System project, so that ‘like for like’
comparisons can be made. This should be a key part of the CM plan.

7.6.18.3.7 Once installed in the vessels, the population under assessment increases, leading to more
complete information, allowing fuller assessment. Again, it is only after HAT(E) that equipment level
information would be more reliable. Equipments still get disturbed during system level testing, so both
equipment and system level information can be treated with more confidence following system HAT
[HAT(S)]. The support information from the second vessel should be one of the best indicators of reliability
growth, since there is less disturbance of the systems and, normally, more confidence all round in the
installation, functionality, and performance of the equipment.

7.6.18.3.8 Assessment of ‘turn-round’ time on spares provision and repair loops needs to be done with
care in these early stages, since these are affected by several factors. For ‘development items’, where the
support services/infrastructure are also ‘developing’, special provisions will probably be made within the
industrial base rather than through the MoD ILS organisations. For ‘in service’ items, shore facilities can find
themselves, correctly, lower down the service priorities than operational vessels or training facilities.

7.6.19 Configuration Management (CM)

7.6.19.1 CM is fundamental to the integration, test and trials programme and is set to become an
increasingly important issue as evolutionary equipment development and greater use of COTS components
becomes the norm. CM during this stage ensures:

a) Compatibility between test environments;

b) Repeatability of test conditions;

c) Consistent and compatible build states of items under test/review/assessment;

d) Delivered build state is compatible with specifications and deliverable documentation (user and
support);

e) Ability to return to previous build states and test environments in case of catastrophic failures or
problems.

7.6.19.2 It is worthless undertaking Integration, Test, Evaluation and Acceptance activities without knowing
the exact state of the ‘items under test’. When developing equipment is involved in the testing process, it is
important to understand what changes are anticipated and the implications of those changes across the
system and the supporting systems. After a development test, the equipments of the Combat System must
be restored to their previous states or the configuration record updated to a new state. The CM process in
place must be able to handle the tracking of change and the assessment, forward planning, and then
implementation of co-ordinated changes to the system.
Unclassified
191
DEF STAN 21-59 Issue 2

7.6.19.3 Declaration of the configuration of the system under test, and all-ancillary equipment and
documentation, is a key feature of the pre-trial and post-trial meetings.

7.6.19.4 It is important to anticipate the major issues such as the alignment of the ‘design state’, the design
team’s definition of the system configuration, with the ‘build state’ of the systems installed in the SIF and in
the vessels and shore training facilities. An essential feature is the early adoption of a master record
database and a soundly workable integration mechanism for aligning information between the ‘system level’
database and the equipment suppliers’ databases. As time goes on, and more systems are being
commissioned or introduced into service, the methods of dealing with spares in store and items in the repair
loops becomes increasingly important.

7.6.19.5 It is vital that the integration, test and trials team has input into the CM plan and is closely involved
in its maintenance and update. This task is not to be left to the ILS Team. They may provide the service,
but the integration, test and trials team is a major customer for that service. The CM plan is likely to contain
details of:

a) Combat System configuration in the SIF including simulators and stimulators;

b) Combat System configuration in the platform;

c) Hardware and software build state records (for SIF and platforms);

d) Hardware and software design state records (for SIF and platforms);

e) Combat System documentation including test and acceptance plans.

7.7 Practical Integration, Test, Evaluation and Acceptance

7.7.1 Shore Facilities - Objectives

7.7.1.1 The SDF/SIF provide a unique test-bed for the controlled testing and integration of individual
equipments and subsystems (without weapons items such as missiles, guns, sonar transducers etc). They
provide the following benefits:

a) Identification, exploration and resolution of problems by providing a representative environment with


easier access and greater resources availability;

b) Evaluation of the functional and physical characteristics of the whole Combat System prior to
installation, setting to work and integration onboard ship or submarine;

c) Simulation of Combat System operation in repeatable scenarios which it would be impossible to


exercise in an operational environment;

d) Support role for the Contract and SA process.

7.7.1.2 The use of a SIF is an important risk reduction measure which serves to reduce the time required
onboard to integrate, test and accept Combat Systems. It also provides a hardware and software support
facility, which enables new equipment and retrospective changes/modifications to be developed and proved
ashore, thereby consuming less operational ship time. This role is likely to become more important as
equipment development becomes more evolutionary in nature and more COTS components are utilised.
Additionally, shore facilities provide a useful training site during periods where they are not being used for
integration, test and trials. The present SDF/SIF is also networked via the Joint and Multi-national
Interoperability Assessment Network (JMNIAN), which facilitates secure “end to end” communications to
various UK facilities including the Joint Command and Battlespace Management Applied Research
Technology Demonstrator (JCBM ARTD), RAF Waddington and LSRC Blandford test facilities. The JCBM
ARTD connection allows onward connectivity to the other International test facilities via Combined Federated
Battle Laboratories (CFBL) Net.

Unclassified
192
DEF STAN 21-59 Issue 2

7.7.2 Shore Facilities

7.7.2.1 MoD CSM Role

7.7.2.1.1 The precise role and responsibilities of the MoD CSM are dependent on the role of MoD SIF
facilities in the Combat System programme which are determined by the integration and acceptance
strategy. Where facilities (e.g. Portsdown) are required, the CSM must prepare the way, setting up and
facilitating communications between SIF administration, CSI and equipment supplier organisations.

7.7.2.1.2 Throughout the shore integration process, the CSM must keep close watch over all high-risk
activities, to ensure that progress towards acceptance is achieved, and any significant problems are raised
and resolved at the earliest opportunity. In pursuit of these objectives, the CSM needs to maintain an
informed view on technical issues particular to the shore environment, which may qualify acceptance in any
way. These technical issues are summarised below.

7.7.2.2 Scenario Definition

7.7.2.2.1 The definition of scenarios is a cornerstone of the system integration process, which provides a
common basis for all dynamic modelling, and test activities, including the HAT(S). Overall policy encourages
the use of a co-ordinated and consistent set of scenarios throughout the Combat System life cycle derived
from the roles and tasks of the warship.

7.7.2.2.2 The scenarios required to demonstrate Military Capability, operability, effectiveness evaluation and
integration should be based on agreed high level scenarios derived during concept and refined though
subsequent stages through to development and production. Scenarios are developed with the objective of
faithfully representing the requirements of the operational context, elements of which will determine the
scope of real trials. This is to maximise compatibility, so that modelling, shore trials and sea trials have a
common basis which will aid verification between the modelling, integration and testing processes.

7.7.2.2.3 The scenarios chosen should be used to the maximum extent in the SIF before undertaking the real
trial to reduce the risk of a failed trial using expensive assets. Furthermore, the shore environment may be
able to provide scenarios, which would be too expensive to recreate in an actual sea trial. This however is
subject to how representative the SIF-fit is compared to the ship-fit Combat System and the fidelity of the
real-world scenario simulation.

7.7.2.3 Scenario Generation

7.7.2.3.1 The provision of a scenario generator supports the progressive programme of integration testing
with a varying mix of real equipments and emulations against a representative set of scenario conditions. A
scenario generation enables the coherent exercising of equipments and emulations comprising the SIF/SDF
for realistic system proving, by co-ordinating:

a) Simulations of Combat System equipments/functions (e.g. provision of own ships data);

b) Emulations (including the ‘stimulator’ as an inherent part of its interface functionality);

c) Real equipments with associated stimulators;

d) Stimulation consistent with generated scenario events (e.g. appearance of a new platform in the
scenario);

e) Scenario events arising from Combat System equipment actions (e.g. firing chaff);

f) Simulation highway operation in support of the above, including data recording and playback.

7.7.2.3.2 Equipment stimulation and scenario generation will typically be controlled from some form of
Centralised Computing Facility (CCF) in order to facilitate comprehensive, consistent and repeatable system
wide tests.

Unclassified
193
DEF STAN 21-59 Issue 2

7.7.2.4 Simulation

7.7.2.4.1 Simulation is the imitation or partial replication of a real or potential system involving the use of
emulation, stimulation and/or modelling. Simulation is the representation of an equipment in the form of a
‘black box’ transfer function with outputs based on pre-prepared data, or derived from input values via a
readily-definable relationship. Equipment simulations augment real equipments so that a full representation
of the Combat System can be provided within the SIF. This is applicable for situations where the use of real
equipment is either not required or not practical due to cost or other criteria.

7.7.2.5 Emulation

7.7.2.5.1 Emulation is a type of simulation, which involves the representation of equipment by its input/output
transfer function, internal functionality to a specified level of fidelity, together with interface related
components of the real equipment. Emulation may also include representative facilities for operator
input/display where appropriate. The hardware/software interface (e.g. to a data highway) should be
identical to the real equipment, and hence the real equipment (with associated stimulator, where appropriate)
and its emulation are interchangeable in the context of the SIF.

7.7.2.6 Stimulation

7.7.2.6.1 Stimulation is the exercising of sensor-dependent equipment without the sensor. The stimulator
(co-ordinated by a scenario generator) replaces the functions that would be provided by a sensor (e.g. radar
dish) operating in the real-world environment. The stimulator comprises hardware and software, and may be
equipment-specific, or generic (i.e. designed for use in conjunction with a range of radar types via software
and/or cabling changes for example). The nature of the stimulator will influence the potential procurement
route, with equipment-specific stimulators generally, though not necessarily, being provided by the
equipment supplier.

7.7.2.6.2 To achieve a co-ordinated approach to stimulation and maintain maximum control over the
integration process, a number of equipments will provide their own means of stimulation, which can be
controlled externally (e.g. from a central facility). Stimulation may be implemented as an in-built function
provided for other purposes (e.g. onboard training), or by some external equipment (e.g. dedicated PC).

7.7.2.7 Recording and Analysis

7.7.2.7.1 The main objectives of data recording is to collect evidence of the Combat System operation during
tests and trials to determine compliance to specification by subsequent analysis and for fault identification.
The key activity is to identify the data to be recorded to support the analysis.

7.7.2.7.2 Since recording and analysis is required both in the SIF and on-board, there are benefits to be
gained by using the same equipment(s)/facility for both applications. Wherever possible, ‘in-service’ or
standard recording and analysis facilities should be utilised. Data recording, data reduction and time
synchronisation requirements need to be addressed through complementary use of facilities provided by:

a) Combat System equipments which are capable of recording data as part of their normal mode of
operation;

b) Additional recording and analysis equipment e.g. highway recorders, trials/range test recorders.

7.7.2.7.3 Extensive on-line monitoring and comprehensive analysis is required during testing to confirm that
the basic operation of the equipments under test is proceeding to plan. On-line monitoring of tests during
scenario execution should be provided by the scenario generator together with the communications status of
all connected simulations/emulations/equipments.

7.7.2.8 Data Reduction

7.7.2.8.1 Data reduction is required where the volume of data collected is large and needs to be reduced to
manageable proportions by the rejection/removal of superfluous data. Techniques for data reduction can be
applied in two ways:

Unclassified
194
DEF STAN 21-59 Issue 2

a) Pre-filtering (selection) at the recorder to limit the data recorded to within user-specified parameters
(e.g. within time bands, only specified message type(s), etc.) or in accordance with a selected
default recording configuration. This is of particular relevance to data highway recording;

b) Post-recording selection to enable the analyst to only select data of current interest.

7.7.2.9 Data Analysis, Reporting and Action

7.7.2.9.1 Data analysis is required for the compilation of evidence demonstrating successful system
operation and investigation of anomalous behaviour of one or more system components. Confirmation from
each test is sought that the system configuration under test has behaved as specified in the test specification
and related documentation. The data acquired through this activity should be used to verify and refine the
through-life models, to support investigation and maintain the configured baseline definition of Combat
System behaviour.

7.7.2.9.2 Where anomalies are discovered, action is required following issue of an analysis report. This
action will generally take one (or more) of the following forms:

a) Reference back to the subsystem project, requiring the equipment to be modified to comply with the
appropriate specification (e.g. a DES);

b) Regression testing;

c) Impact analysis, possibly leading to generation of an Engineering Change Proposal (ECP);

d) Concession application, the procedure for raising and approval/rejection of concessions relating to
integration will be specified in the Combat System integration plan.

7.8 Integration, Test and Trials Stage Documentation

7.8.1 In the integration, test and trials phase of the programme, the main documentation activity is the
generation, approval and use of the test documents needed to support the integration, test and trials
activities in the shore facilities and on the vessels, in harbour and at sea. Equipment test documentation
must be prepared in parallel with hardware/software development so that both equipment and
documentation are available for testing to begin. Similarly, integration tests must be prepared in advance of
the integration stage so that integration can commence as soon as equipments become available.

7.8.2 For vessels, especially the first of class vessel, there are stringent timescales laid down in the
relevant sections of SSP 23 and BR 3018. Once the main milestones for the integration, test and trials
programme are known, and the structure of the tests and trials documentation is defined in the draft test form
index then the documentation generation programme can be developed. Because the test form index is
generic, this can be done early in the programme to assist with resource planning in the later phases of the
programme.

7.8.3 Table 5 summarises the requirements for the integration, test and trials documentation for the
vessels. The documentation for use in the shore facility needs to feed in to the vessel programme and
therefore forms a lead in to this vessel programme. The linking of the shore facility and vessel programmes
is essential, despite the different ownership (respectively, CSM and warship manager in the MoD
organisation; and technical directorate and production directorate in the shipbuilding or prime contract
organisations).

7.8.4 Documentation also needs to be split into groups which will support the four ‘building blocks’: design
verification and qualification; first off production; first off installation and build, and routine (in service) system
testing. This should be identified in the documentation requirements relating to the integration, test and trials
management plan and correlate with the list of integration, test and trials events in the various phases of the
overall programme.

7.8.5 Other Documentation

7.8.5.1 The increasing use of the installed system in the shore facility and the vessels means that the
information, which forms the whole of the handbook series, is used and assessed from an early stage. This
Unclassified
195
DEF STAN 21-59 Issue 2

provides a valuable input into the ‘handbook verification’ process. The use by ships staff standing-by of the
BR/CB documentation in draft form also provides an RN operator and maintainer view on the adequacy and
correctness of the information provided at equipment, system and ship level. However, there is a continuing
shift away from BRs/CBs to more commercial user/maintainer handbooks especially for OTS equipments.

7.8.5.2 The other main set of documentation, which is involved in this phase, is the acceptance
documentation. The Integration, Test, Evaluation and Acceptance documentation must always support the
evaluation of the system requirements, logged in the SRD. The results from the integration, test and trials
activities must provide the acceptance evidence needed to show that requirements have been fully satisfied,
this evidence being logged in the acceptance check lists, or a supporting database, the Acceptance
Database (ADB).

Table 7.5 Summary of Documentation


Activity Documentation (Output Products) Associated Activities

Systems General and Specific Policy and Strategy Updated to keep abreast of developments
Engineering Papers (including Data Management during the stage. Updated, reviewed and
(Technical) and Policy, ITEAP, COTS Policy) agreed by CSM.
Project
Management Management Plans (CMP, RMP, Risk
Register, Risk Analysis, RRAP, Quality
Plans, SEMP, PMP)

Lower tier Management Plans (Integration


Management Plan, Test and Trials Plan,
Acceptance Management Plan, Support
Plan, Disposal Plan)

Configuration Management Plan


Life Cycle Costings

Design Change URD, SRD, ITEAP and TLMP Requirements configured as baseline data,
Management System (Design) Specification together with acceptance data) in a combined
Coherence Specification database
Subsystem Specifications
Interface Documentation (SIDs, IFSs, Change investigation and impact analysis
DESs) performed by CSI. Agreed changes
Verification Cross Reference promulgated down the contractual hierarchy
Index/Acceptance Database (ADB) as necessary.

Unclassified
196
DEF STAN 21-59 Issue 2

Summary of Documentation (continuation)

Activity Documentation (Output Products) Associated Activities

Combat System Trials Policy, Trials Requirements, Trials


Integration Management Plan
Integration, Test, Evaluation and
Acceptance Plan
Shore Integration Plan
Integration, Test and Trials Programme
Test Documentation Preparation
Programme

Integration, Test, Evaluation and Developed by CSI under direction of CSM.


Acceptance Requirements/ Specifications Reviewed and agreed by CSM.
Test Equipment Specifications
Subsystem Integration Test Procedures
and Reports
Combat System Integration Test
Procedures and Reports

Equipment II/Trial Procedures and Developed by EDC under direction of CSI (or
Reports EPM dependent on Design Authority
Equipment PFA/STW Procedures and arrangements). Reviewed and agreed by
Reports CSI and CSM.
Equipment HAT(E) Procedures and
Reports
Equipment Integration (PINT/SINT/FINT)
Test Procedures and Reports

Combat System Test Form Index (TFI) Working Issues of Test Form Index. Final
Test and Trials Issue to Datum Pack for each Vessel.

Test Forms Development from Draft to Design Authority


and Test Group Approved Issues.

Test Schedules (Detailed Operating Development from Draft to Design Authority


Instructions for Functional and and Test Group Approved Issues.
Performance Tests & Trials)

Certified Test Forms Gathered and Maintained as Acceptance


Evidence from Integration, Test and Trials
activities. Final Issue to Datum Pack for each
Vessel.

Trouble Reports/Defect Reports Records of problems experience with conduct


of test or trial, or with system. Register of
recorded problems and defects still requiring
action to clear them, as part of the D3B
(Defects and Deficiencies Database).

Unclassified
197
DEF STAN 21-59 Issue 2

Summary of Documentation (continuation)

Activity Documentation (Output Products) Associated Activities

Design Queries (for those issues which Raised during Integration, Test and Trials
cannot be understood from available activities where issue is ‘not trouble’ and ‘not
documentation) a defect’. May lead to Defect Reports,
Trouble Reports, or Change Requests.

Trials Plans (Requirements for Use of RN Documents worked up from Draft responding
and Other Assets, often known as the to Trials Requirements to Authorised Issue
‘Form ALPHA’) with appropriate Operating and Project
Authorities. Delivered as part of Datum Pack
or appendices to the Acceptance Database
(ADB).

Trials Orders (Trials Schedules for vessel- Documents worked up from Draft (in
based activities) response to Trials Requirements) to
Authorised Issue with appropriate Operating
and Project Authorities.

Trials Operation Plans (for range facility Documents worked up from Draft (in
usage, especially NATO Ranges or response to Trials Requirements) to
AUTEC) Authorised Issue with appropriate Operating
and Project Authorities.

Trials Reports (Records of trials outcome Part of Project Acceptance records


produced by Conducting Authority) (appendices to ADB).

Trials Analysis Reports (Records of trials Part of Project Acceptance records


outcome produced by Presenting (Design) (appendices to ADB).
Authority)

Acceptance URD, SRD with Traceability to results Completed by CSI under direction of CSM.
from ITEAP Reviewed and agreed by CSM/CWG(A).
Acceptance Check List

System Studies Operational Scenario Definitions Conducted by CSI under direction of CSM.
Effectiveness Models Reviewed by DEC
Effectiveness Assessment Reports

Operability Demonstrators Conducted by CSI under direction of CSM.


System Operability Assessment Reports Reviewed by DEC, FLEET and FOSM/FOSF.

Functional Models Developed by CSI under direction of CSM.


Architecture Assessment Reports Subsystem/Equipment-level modelling
AR&M Modelling and Reports conducted by EDC under direction of
Trade-off Study Reports CSI/CSM.
Reviewed and agreed by CSM.

Unclassified
198
DEF STAN 21-59 Issue 2

Summary of Documentation (continuation)

Activity Documentation (Output Products) Associated Activities

Integrated Logistic Upkeep Policy and Plan Developed by CSI (or CSSC dependent on
Support Ship Weapon Upkeep Planning support arrangements) under direction of
Information ILSM/CSM. Reviewed and agreed by
Weapon Upkeep Disclosure Documents ILSM/CSM.
STTE (Special To Type Equipment)
Report
CRETE (Common Range Electrical Test
Equipment) Report
Handtools Reports
Stowage Requirements and Reports
Spares Reports
Planned Maintenance Reports
Defect Reporting Procedure
Ship Fit Configuration
MRI (Master Record Index )
WEDP (Weapon Equipment Development
Programme)
A&A Proposal Forms
Software Issue Control Report

Training Plan and Reports Developed by CSI (or CSSC dependent on


Training Course Material support arrangements) under direction of
Combat System Handbooks (CBs/BRs) ILSM/CSM. Reviewed and agreed by
Planned Maintenance Schedule (PMS) ILSM/CSM and FOSM/FOSF.
Weapon Repair Facility Statements
(WRFS)

Equipment Upkeep Plans and Policy Developed by EDC under direction of CSI (or
Equipment Training Plans and Course EPM dependent on Design Authority
Material arrangements) under direction of ILSM/CSM.
Equipment Spares Reports Reviewed and agreed by ILSM/CSM.
Equipment Handbooks
Establishment Lists (E Lists)

Configuration Configuration Definitions Established in Design Phases. Maintained as


Management Design States. Approved Design State at
Acceptance.

Configuration Accounts Established during earlier phases leading up


to Installation. Maintained as Build state
throughout the Integration, Test and Trials
programme as baseline definition for all tests
and trials. Delivered as Build State Definition
at Acceptance.

Configuration Audit Reports Maintained as part of Project/ Configuration


Management Files.

Unclassified
199
DEF STAN 21-59 Issue 2

Summary of Documentation (continuation)

Activity Documentation (Output Products) Associated Activities

Change Control Documentation Register of items which will affect Integration,


Test and Trials aspects, Change Note Files.
Register of Outstanding Changes forms part
of D3B Records.

Relevant Change Note Files handed over to


ILS Design Group at Acceptance.

7.9 Integration, Test and Trials Stage Specialist Discipline Support

7.9.1 Objectives

7.9.1.1 In the integration, test and trials phase of the programme, many of the specialists are able to gather
real-life information on the implementation of their designs. The following table provides a view of the level
of specialist support required by the integration, test and trials team for activities in the shore facilities, for
vessels in harbour, and vessels at sea.

Table 7.6 Specialist Discipline Support


Engineering Specialist Discipline Support through
Discipline
Shore Facility Activities Harbour Activities At Sea Activities

Air Engineering TBD - if applicable Aircraft Handling and Flying Trials for all types of
Movement Trials, rotary and fixed wing aircraft
Aircraft Fuelling/Defuelling embarked.
Trials
Air Weapons Handling
Aircraft Arming Trials.

Alignment Assessment of the use of Measurement of real-life Measurement of real-life


Alignment Data by all values for insertion into values for insertion into
relevant system components. Operational and Test Operational and Test
Software for static testing. Software for dynamic testing.

AR&M Initial assessment of AR&M Initial assessment of AR&M Assessment of AR&M


performance based on the performance based on the full performance growth based
partial system fit in the shore system fit in the vessel. on the full system fit in the
facility. Assessment of Removal vessel.
Initial assessment of Routes and maintainability. Assessment of maintainability
maintainability of installed at sea. In-service R&M data
equipment. collection.

Cost Maintain and Refine Through Life Costings/LCCs as Integration, Test & Trials progresses.

Influence the Integration, Test and Trials process to optimise LCCs.

Unclassified
200
DEF STAN 21-59 Issue 2

Specialist Discipline Support (continuation)

Engineering Specialist Discipline Support through


Discipline
Shore Facility Activities Harbour Activities At Sea Activities

Documentation Delivery of Handbooks and other documentation in time to support the Integration, Test &
Trials programme.

Turning round amendments to handbooks and other user documentation arising from use in
the facility.

Electro- Assessment of problem areas RADHAZ Trials Degaussing Trials


Magnetic which are realistically Transient Trials (EMI) EMC Part 2
Engineering represented in the shore EMC Part 1 WEMIT
facilities Tempest Trials

Environmental Probably Not Applicable here. Assessment of problem areas Assessment of problem areas
Factors Shore facilities are benign and assistance with and assistance with
environments. Environmental rectification. rectification.
testing usually done in
development phase.

HF/Operability Assessment of areas which Assessment of HF/Operability Assessment of HF/Operability


are realistically represented Performance issues in the Performance issues in the
in the shore facilities, real vessel environment. real operating environment.
especially after RN Training,
using RN Operator and Crew Certification for Sea Crew Certification for
Warfare Teams. Trials. Operations.

ILS Operation of interim ILS Operation of Commissioning/ Operation of ‘Commissioning/


facilities for Maintenance, Test & Tuning’ ILS facilities Test & Tuning’ ILS facilities
replacement items, and repair for Maintenance, replacement for Maintenance, replacement
loops. items, and repair loops. items, and repair loops.

Initial assessment of ILS Assessment of ILS Provisions Assessment of ILS Provisions


Provisions based on support based on support of full based on support of full
of partial system fitted in the system fitted in vessel, system fitted in vessel,
shore facility. operated by contractor. operated by RN Staff.

Installation & Resolution of Trouble Support to proving of Ships Support to proving of Ships
Ship Services Reports. Services Interfaces under Services Interfaces under
static conditions. dynamic conditions.
Initial assessment of
measured ‘Demands’ and Resolution of Trouble Resolution of Trouble
‘Loads’ vs the predicted loads Reports. Reports.
developed in the Design
Phases using the partial Assessment of measured Assessment of measured
system fitted in the shore static ‘Demands’ and ‘Loads’ dynamic ‘Demands’ and
facility. vs the predicted loads ‘Loads’ vs the predicted loads
developed in the Design developed in the Design
Phases. Phases.

Unclassified
201
DEF STAN 21-59 Issue 2

Specialist Discipline Support (continuation)

Engineering Specialist Discipline Support through


Discipline
Shore Facility Activities Harbour Activities At Sea Activities

Interface Data Design Verification of the Design Verification of all Design Verification of all
Management Interfaces available in the Interfaces available in full Interfaces available in full
partial system fitted in the system fitted in the vessel, system fitted in the vessel,
shore facility. under static and stimulated under typical dynamic
dynamic conditions. conditions.

System Network loading System Network loading System Network loading


assessment. assessment. assessment.

Resolution of Trouble Resolution of Trouble Resolution of Trouble


Reports and Defect Reports. Reports and Defect Reports. Reports and Defect Reports.

Modelling and Assistance with development Assistance with development Assistance with development
Analysis of trials scenarios for the of trials scenarios appropriate of trials scenarios appropriate
scenario-based sub-system to the nominated trials ranges to the nominated trials ranges
and system level trials. [At this stage, all trials are [At this stage, all trials are
scenario-based sub-system scenario-based sub-system
Prediction of expected results and system level trials]. and system level trials].
for trials.
Prediction of expected results Prediction of expected results
Assistance with investigation for trials. for trials.
into anomalous system
behaviour and analysis of Assistance with investigation Assistance with investigation
trials data. into anomalous system into anomalous system
behaviour and analysis of behaviour and analysis of
trials data. trials data.

Naval The Naval Architects are unlikely to have any input into this phase. Naval Architects will be
Architecture collecting ‘measured data’ on weights and C’s of G to balance the vessel in inclining and trim
experiments.

Operational Assessment of the As for the Shore facility, using Assessment of the
Performance Operational Performance system data from the full Operational Performance
against earlier predictions, if system installed in the vessel. against earlier predictions,
information which is using ‘macro level’ data
significant in determining which is available through
system performance is testing the system in the
available from the facility, e.g. vessel at sea or on ranges,
system data transfer e.g. actual signal to noise
latencies and accuracies. ratios, beam patterns,
tracking accuracies, etc.

Unclassified
202
DEF STAN 21-59 Issue 2

Specialist Discipline Support (continuation)

Engineering Specialist Discipline Support through


Discipline
Shore Facility Activities Harbour Activities At Sea Activities

Safety Independent Safety Independent Safety Independent Safety


Assessment of the Hazard Assessment of the Hazard Assessment of the Hazard
Log and the Safety Operating Log and the Safety Operating Log and the Safety Operating
Procedures for the system in Procedures for the system in Procedures for the system in
the facility and any the Vessel in harbour and the Vessel at sea and any
contributions to the Pre- any contributions to the Pre- contributions to the Pre-
Construction Safety Report. Operations Safety Report. Operations Safety Report.

Particular attention to any Particular attention to any Particular attention to any


Safety-Critical features. Safety-Critical features. Safety-Critical features.

Security Initial Assessment of Security Intermediate Assessment of Final Assessment of the


policy implementation using Security policy security Policy
system components implementation for the implementation for the
available. system installed in the vessel system in the vessel operated
operated in harbour. at sea within the RN
Operating and Support
environments.

Noise, Shock & Assessment of problem areas Assessment of installed Assessment of installed
Vibration which are realistically Noise and Vibration Noise and Vibration
represented in the shore performance in the vessel. performance in the vessel.
facilities.
Assistance with resolving any Assistance with resolving any
Shock aspects are usually issues arising. issues arising.
dealt with as part of the
design and development
activities.

Software Assessment of the Quality of delivered software. Resolution of technology and infrastructure
Development problems arising. Independent audit of software functionality. Independent assessment of any
safety critical features.

Structural Not applicable in this phase. Structural aspects are usually


Engineering dealt with as part of the
design and development
activities. There may be
problems to resolve in the
installation phase or following
sea trials.

Unclassified
203
DEF STAN 21-59 Issue 2

Specialist Discipline Support (continuation)

Engineering Specialist Discipline Support through


Discipline
Shore Facility Activities Harbour Activities At Sea Activities

Training Use of shore facility system Training of Ship’s Staff and


for preparation of training MCTA to support equipment
course material for operator and system level trials.
and team level training, and
for ‘training the Trainers’.

Use of shore facility for


training ships staff, if
Operator, Maintainer, and
Command Team Trainers are
not available for the early
courses.

Unclassified
204
DEF STAN 21-59 Issue 2

Annex A
Normative References

A.1 Reference Information

A.1.1 The publications shown below are referred to in the text of this standard. Publications are grouped
and listed in alpha-numeric order.

AECMA 2000M International Specification for Technical Publications Utilising a Common Source
Database – Initial Provisioning

ANEP 54 ‘Guidelines for COTS Insertion’

BR 3018 Nuclear Safety Management of Naval Reactor Plant (Formerly TOANS)

BR 3021 Shock Manual (Metric) Vol 1 & Shock Manual (Metric) Vol 2

BR 4050 Instructions for the Conduct of Naval Weapons Inspections and Trials

BR 8593(17) Alterations and Additions (A&As) Procedures for Surface Ships and Submarines
(Supersedes Oct 98 Edition)

BS ISO/IEC 15288 Systems Engineering – System Life Cycle Processes

BS EN ISO 14001 Environmental management systems. Requirements with guidance for use

BS 5750 ISO 9000 Quality Management and Quality Assurance

COPA Control Of Pollution Act (COPA) 1974

D448 Report of Material and Trials State of New Construction and Post LOP(R)

Def Stan 00-19 The ASWE Serial Highway

Def Stan 00-41 Reliability and Maintainability, MoD Guide Practices and Procedures

Def Stan 00-55 Requirement for Safety Related Software in Defence Systems (Obsolescent 04-2005)

Def Stan 00-60 Integrated Logistic Support:


Part 0 – Application of Integrated logistic Support (ILS)
Part 1 – Logistic Support Analysis (LSA) and Logistic Support Analysis Record (LSAR)
Part 3 – Guidance for Application of Software Support
Part 10 – Electronic Documentation
Part 20 – Application of Supply Support Procedures
Part 21 – Procedures for Initial Provisioning
Part 22 – Procedures for Codification
Def Stan 05-57 Configuration Management of Defence Material.

Def Stan 05-91 Quality Systems Requirements for Design, Development, Production, Installation and
Servicing (Obsolescent 03-2004)

Def Stan 05-95 Quality System Requirements for Design, Development, Supply and Maintenance of

Unclassified
205
DEF STAN 21-59 Issue 2

Software

Def Stan 08-107 General Requirements For The Design of Electrotechnical and Naval Weapon Equipment
(Cat 2)

Def Stan 08-124 Radio Frequency Environment and Acceptance Criteria for Naval Stores Containing
Electro-explosive Devices (Cat 1)

Def Stan 08-136 Requirements for Electromagnetic Engineering:


Part 1 - Electromagnetic Engineering Management (Cat 2)
Part 2 – Guide to the Application of Electromagnetic Engineering (Cat 2)

Def Stan 21-13 Combat System Interface and Link Documentation:


Part 1 – Management Guide (Cat 3)
Part 2 – Interface Documentation (Cat 3)
Part 3 – Link Document Guide (Cat 3)

Def Stan 21-24 Data Transmission – Direct Memory Access Interface Standards:
Part 1 – The Software Interface (Cat 1)
Part 2 – The Electrical Interface (Cat 1)
Part 3 – The Enhanced Software Interface (Cat 1)
Part 4 – The Enhanced Electrical Interface (Cat 1)

Def Stan 21-26 Requirements for the Digital Representation of Shipboard Data Parameters:
Part 1 – Standard Units, Parameter representations and Element Formatting (Cat !)
Part 2 – Guide to the Use of NES 1026 Part 1 (Cat 1)

Def Stan 21-28 Standard for Inter-system Communications Protocols:


Part 1 – High Level Language of Message Construction (Cat 1)
Part 2 – Rules and Protocols for Intercommunication Across Digital Highways (Cat 1)
Part 4 – Rules and Protocols for the Passing of Large Blocks of Data Across Digital
Highways (Cat 1)

Def Stan 21-43 Data Recording and Analysis for Maritime Platforms, Systems and Equipments, Guidance
for User Requirement Capture (Cat 3)

Def Stan 21-88 Policies and Procedures for Combat System Integration in Surface Ships

DOORS Requirements Database

E Lists (Establishment Lists)

EIA 632 Electronics Industries Alliance (EIA) Standard: Processes for Engineering a System

EPA Environmental Protection Act 1990

Form ERC/S2022 Defect and Deficiency Form

Health and Safety at Work Act 1974

IEEE 1220 IEEE Standard for Application and Management of the Systems Engineering Process,
Institute of Electrical and Electronics Engineers. Revision to align IEEE 1220 with
ISO/IEC 15288 and provide a lower level of detail than 15288 is underway and due out
December 2004. After that it will be fast tracked as an ISO standard

Unclassified
206
DEF STAN 21-59 Issue 2

Joint Customer 2 Handbook

JSP 336 Defence Supply Manual Part 9 – Disposal by Sale

JSP 430 Ship Safety Management System Parts 1 to 4

JSP 440 The Defence Manual of Security

JSP 454 Procedures for Land Systems Equipment Safety Assurance

JSP 520 Ordnance Munitions Explosives Safety


Part 1 – Management System
Part 2 – Operational Procedures

JSP 553 Military Airworthiness Regulations (formerly JSP 318B)

JSP 600 Information Coherence Directions

JSP 602 The Data Imperative

MIEA 5929 (UK-RN-N-5929) Information Exchange Programme

MILSTD 499B Systems Engineering

MoD AMS Acquisition Management System – Human Factors Integration – Practical Guidance for
Integrated Project Teams

Montreal Protocol

S2022 Ship Report of Shortcomings In Material Design Or Support

Smart Approvals Guidance Version 9.1

STG Maritime System Maturity

SSP 23 Design of Surface Ship Structures (Vols. 1 & 2)

SSP 38 Technical Procedural Requirements for the Procurement & Upkeep of Naval Weapon
Systems

STG Publication 10 HFI Management Guide

STG Publication 11 HFI Technical Guide

UNECE United Nations Economic Commission for Europe Protocol

WSAF 129 Shore Support Arrangements for Warships (formerly known as 'Form Alpha)

A.1.2 Reference in this Standard to any normative references means in any Invitation to Tender or
contract the edition and all amendments current at the date of such tender or contract unless a specific
edition is indicated.

A.1.3 In consideration of clause A.1.2 above, users shall be fully aware of the issue and amendment
status of all normative references, particularly when forming part of an Invitation to Tender or contract.
Responsibility for the correct application of standards rests with users.

Unclassified
207
DEF STAN 21-59 Issue 2

A.1.4 DStan can advise regarding where normative references documents are obtained from. Requests
for such information can be made to the DStan Helpdesk. How to contact the helpdesk is shown on the
outside rear cover of Def Stans.

Unclassified
208
DEF STAN 21-59 Issue 2

Annex B
Abbreviations

A&A Alteration and Addition

ACs Acceptance Criteria (formerly Acceptance Characteristics)

ADB Acceptance Database

ADS Accreditation Documentation Set

AKA Also Known As

ALARP As Low As Reasonable Practicable

ALSP Aggregate Level Simulation Protocol/Process

AMP Acceptance Management Plan; Assisted Maintenance Period

AMS Acquisition Management System

ANEP Allied Naval Engineering Publication

AP Assessment Phase

AQ Acceptance Questionnaire

AR&M Availability, Reliability and Maintainability

ARP Applied Research Programme

AUSCANZUKUS Australia, Canada, New Zealand, United Kingdom, United States

AUTEC Atlantic Undersea Test and Evaluation Centre

BITE Built-In Test Equipment

BoI Balance of Investment

BR Book of Reference

BS British Standard

C2W Command and Control Warfare

C4I Command, Control, Communications, Computers and Intelligence

CAD Computer Aided Design

CADMID Concept, Assessment, Demonstration, Manufacture, In-Service, Disposal

CALS Continuous Acquisition and Life-cycle Support

CAWG Capability Acceptance Working Group

CB Confidential Book

Unclassified
209
DEF STAN 21-59 Issue 2

CCB Change/Configuration Control Book

CCF Centralised Computing Facility

CCU Certificate of Clearance for Use

CDMA Central Data Management Authority

CDP Cardinal Date Programme; Chief of Defence Procurement

CDPIs Chief of Defence Procurement Instructions

CESG Communications Electronics Security Group

CFBL Combined Federated Battle Laboratories

CFC Chlorofluorocarbons

CINCFLEET Commander in Chief Fleet

CIS Communications and Information Systems; CIS Integration Strategy

CL Core Leadership

CLS Contractor Logistic Support

CM Configuration Management

CMM Capability Maturity Model

CMP Contract Management Plan

CMS Command Management System

COA Concept of Analysis

CofG Centre of Gravity

COEIA Combine Operational Effectiveness and Investment Appraisal

CONEMP Concept of Employment

CONOPS Concept of Operations

CONUSE Concept of Use

COO Cost of Ownership

COPA Control of Pollution Act

COTS Commercial Off The Shelf

CRETE Common Range Electrical Test Equipment

CSA Customer Supplier Agreement

CSDA Combat System Design Authority

CSED Combat System Engineering Database

Unclassified
210
DEF STAN 21-59 Issue 2

CSI Combat System Integrator

CSM Combat Systems Manager

CSSC Combat System Support Contractor

CSTs Contractor Sea Trials

CTT Command/Combat Team Trainer

CUPs Capability Update Periods

CVSG Carrier Vertical Strike Guide

CWG Capability Working Group

CWTA Captain Weapons Trials Assessment

D&M Demonstration & Manufacture

D3B Defect and Deficiency Database

DA Design Authority

DAMPs Docking Assisted Maintenance Periods

DARR Design Authority Refit Requirements

DCDS Deputy Chief of Defence Staff

DCIs Defence Council Instructions

DCSA Defence Communication Services Agency

DD Detailed Design

DDR Defence Data Repository

DEC Director Equipment Capability

Def Stan Defence Standard

DER Data Exchange Requirement

DES Data Exchange Specifications

DESO Defence Export Sales Organisation

DIS Distributed Interactive Simulation

DLO Defence Logistics Organisation

DLOD Defence Lines Of Development

DoD Department of Defense (US)

DOSG Defence Ordnance Safety Group

DOSGTS Defence Ordnance Safety Group Technical Support

Unclassified
211
DEF STAN 21-59 Issue 2

DP Documentation Production

DPA Defence Procurement Agency

DPMGs Defence Procurement Management Guide

DR&A Data Recording, Reduction, Assessment and Analysis

DSA Disposal Sales Agency

DSSO Defence Security Standards Organisation

DStan Defence Standards Organisation

DSTL Defence Science & Technology Laboratories

E3 Electro-Magnetic Environmental Effects

EAC Equipment Approval Committee

EC Equipment Capability

ECC Equipment Capability Customer

ECP Engineering Change Proposal

EDC Equipment Design Contractor

EDI Electronic Data Interchange

EDM Electronic Data Management

EIA Electronics Industry Association

EI&IS Engineering, Interoperability & Information Services

EMC Electromagnetic Compatibility

EMI Electromagnetic Interference

EMP Electromagnetic Pulse

EP Equipment Programme

EPA Environmental Protection Act

EPM Equipment Project Manager

ERC Equipment Reference Code; Event Record Card

ESCROW n. Law. A deed held by a third party until certain conditions are fulfilled.

EU European union

EW Electronic Warfare

FAT Factory Acceptance Trials/Test

FBG Future Business Group

Unclassified
212
DEF STAN 21-59 Issue 2

FDIP Full Development and Initial Production

FDP Full Development & Production; Flight Data Processing; Full Development
Programme; Final Design Phase etc.

FGI Final Guidance Information

FII Final Installation Inspection

FINT Final/Functional Integration Test

FMECA Failure Modes Effects and Criticality Analysis

FOC First Of Class/Full Operational Capability

FON Follow On (Vessels)

FOSF Flag Officer Surface Flotilla

FOSM Flag Officer Submarines

FWA Fleet Weapon Acceptance – (obsolete term) now know as System Acceptance

GA General Arrangement (Drawings)

GFA Government Furnished Assets

GFE Government Furnished Equipment

GFI Guideline For Industry

HASAWA Health and Safety at Work Act

HATs Harbour Acceptance Trials

HCI Human Computer Interface

HF Human Factors

HFI Human Factors Integration

HFIP Human Factors Integration Plan

HLA High Level Architecture

IAB Investment Appraisal Board

ICD Interface Control Documents

IEEE Institute of Electrical and Electronic Engineers

IER Information Exchange Requirements

IFS Interface Specification

IG Initial Gate

IGI Initial/Interim Guidance Information; Installation Guidance Information

Unclassified
213
DEF STAN 21-59 Issue 2

IGP Installation Guidance Package

II Installation Inspection

ILS Integrated Logistic Support

ILSM Integrated Logistic Support Manager (MoD)

ILSP Integrated Logistic Support Plan

INFOSEC Information System Security

INR Initial/Ionising Nuclear Radiation

IOR Interoperability Requirements

IP Initial Provisions

IPR Intellectual Property Rights

IPT Integrated Project Team

IPTL Integrated Project Team Leader

IRC International Research Collaboration

IS In-Service

ISD In-Service Date

ISMART Interoperable Systems Management and Requirements Transformation

ISO International Standards Organisation

ISP Integrated Support Plan

ISS In-Service Support

ISSP Integrated Supply Support Procedures, Initial System security Policy

ISTAR Intelligence, Surveillance, Target Acquisition and Reconnaissance Equipment

ISTD In-Service Target Date

IT Information Technology

ITEAP Integrated Test Evaluation and Acceptance Plan

ITT Invitation To Tender

JCBM ARTD Joint Command Battlespace Management Applied Research Technology


Demonstrator

JDCC Joint Doctrine & Concepts Centre

JETL Joint Essential Task List

JIFM Joint Information Flow Model

Unclassified
214
DEF STAN 21-59 Issue 2

JMNIAN Joint and Multi-national Interoperability Assessment Network

JSPs Joint Service Publications

KSRs Key System Requirements

KURs Key User Requirements

LAN Local Area Network

LBTS Land Based Test Sites

LCC Life Cycle Costing

LDs Liquidated Damages

LODs Lines of Development

LORA Level Of Repair Analysis

LPD(R) Landing Platform Dock (Replacement)

LPH Landing Platform Helicopter

LSA Logistics Support Analysis

LSAR Logistics Support Analysis Record

LSRC Land Systems Reference Centre

LTC Long Term Costing

M&S Modelling and Simulation

MC Military Capability

MCTA Maritime Commissioning, Trials & Assessment

MDAL Master Data and Assumptions List

METL Maritime Essential Task List

MG Main Gate

Mil Std Military Standard (US)

MILCAP Military Capability

MLU Mid Life Update

MMI Man Machine Interface

MoD Ministry of Defence

MODAF MoD Architectural Framework

MODAR MoD Architectures Repository

MOE Measures of Effectiveness

Unclassified
215
DEF STAN 21-59 Issue 2

MOP Measures of Performance

MRI Master Records Index

MTA Maintenance Task Analysis

NATO North Atlantic Treaty Organisation

NDIs Non-Development Items

NEC Network Enabled Capability

NSC Naval Support Command

NWHT Naval Weapon Harbour Trial

NWST Naval Weapon Sea Trial

OA Operational Analysis; Order Administration

OME Ordnance, Munitions, Explosives

OPCON Operation Control

OPDEF Operational Defect

ORBAT Organisation for Battle

OSD Out of Service Date

OTS Off The Shelf

PC Personal Computer

PCT Performance, Cost, Time

PD Project Definition; Preliminary Design

PDC Platform Design Contractor

PDG Procurement Development Group

PDS Post Design Services

PECs Printed Electronic Circuits

PFA Preparation For Acceptance

PFG Procurement Finance Group

PINT Primary Integration Test

PM Pivotal Management; Project Manager

PMP Project Management Plan

PMS Planned Maintenance Schedule

POEMS Project-Oriented Environmental Management System

Unclassified
216
DEF STAN 21-59 Issue 2

POSMS Project-Oriented Safety Management System

PP Procurement Planning

PPM Platform Project Manager

PR&A Project Review and Assurance

PSU Power Supply Unit

QA Quality Assurance

QAR Quality Assurance Representative

R&D Research and Development

RADHAZ Radiation Hazard

RAF Royal Air Force

RAMP Requirements and Acceptance Management Plan

RAO Research Acquisition Organisation

RCM Reliability Centred Maintenance

RDB Requirements Database

RE Requirement Engineering

RFA Royal Fleet Auxiliaries

RFQ Request For Quote

RM Requirement Manager

RMP Risk Management Plan

RN Royal Navy

RRAP Risk Reduction Action Plan

S&TE Support and Test Equipment

S+T Science and Technology; Swiftsure and Trafalgar (Class Submarines)

SA Systems Analysis, System Acceptance

SAG Studies Assumption Group; Standardisation Advisory Group

SATs Sea Acceptance Trials

SD Systems Design

SDE Shared Data Environment; Shared Development Environment

SDF Shore Development Facility

SE Systems Engineering

Unclassified
217
DEF STAN 21-59 Issue 2

SEISP System Electronic Information Security Policy

SEMP Systems Engineering Management Plan

SID System Interface Diagram

SIF Shore Integration Facility

SINT Secondary Integration Test

SIP Standardisation Implementation Plan

SMH Safety Management Handbook

SMO Safety Management Office

SMP Standardisation Management Plan; Self Maintenance Period; Safety Management


Plan

SOW Statement Of Work

SPS Special Procurement Services

SRD Systems Requirements Document

SRL System Readiness Level

SRM Supplier Relationship Management; Stakeholder Responsibility Matrix

SS System Studies

SSE Support Solutions Envelope

SSIs Shipbuilder Supplies Item

SSMS Ship Safety Management System

SSON Single Statement of (User) Need

SSP Sea Systems Publication

STG Sea Technology Group

STGP Sea Technology Group Publications

STIR Statement of Technical Information Required

STP Short Term Programme

STTE Special To Type Equipment

STW Setting To Work

SWUPI Ship Weapons Upkeep Planning Information

SyOPs Security Operating Procedure

SYSINT (Staged) System Integration Test

Unclassified
218
DEF STAN 21-59 Issue 2

T23 Type 23 Frigate

T42 Type 42 Destroyer

T45 Type 45 Destroyer

T&E Test and Evaluation

TDL Tactical Data Link

TDP Technology Demonstrator Programmes

TES Technical Enabling Service

TES-SSG Technical Enabling Services – Sea Systems Group

TFI Test Form Index

TLC Through-Life Cost

TLMP Through-Life Management Plan

TPMs Technical Performance Measures

TRL Technology Readiness Level

TS Technical Support

TTCP The Technical Co-operation Program

TULIP Through Life Interoperability Planning (Predecessor of ISMART)

UK United Kingdom

UNECE United Nations Economic Commission for Europe

URD User Requirement Document

URS User Requirement Specification

US United States

VCDS Vice Chief of the Defence Staff

VCRI Verification Cross Reference Index

VFM Value for Money

WAN Wide Area Network

WBS Work Breakdown Structure

WEDP Weapon Equipment Demonstration Programme; Weapon Equipment Delivery


Programme

WEMIT Weapons Electrical Mutual Interference Trial

WES Weapon Equipment Schedule

Unclassified
219
DEF STAN 21-59 Issue 2

WLC Whole Life Costs

WPM Warship Project Manager

WRFS Weapon Repair Facility Statements

WSA Warship Support Agency

WSAC Weapon System Acceptance Committee

WSAF Warship Support Agency Form

WSIA Weapon System Integration Authority

WSM Weapon System Manager

Unclassified
220
DEF STAN 21-59 Issue 2

Inside rear cover

Unclassified
221
©Crown Copyright 2006

Copying Only as Agreed with DStan

Defence Standards are Published by and Obtainable from:

Defence Procurement Agency

An Executive Agency of The Ministry of Defence

UK Defence Standardization

Kentigern House

65 Brown Street

GLASGOW G2 8EX

DStan Helpdesk

Tel 0141 224 2531/2

Fax 0141 224 2503

Internet e-mail enquiries@dstan.mod.uk

File Reference

The DStan file reference relating to work on this standard is .

Contract Requirements

When Defence Standards are incorporated into contracts users are responsible for their correct
application and for complying with contractual and statutory requirements. Compliance with a Defence
Standard does not in itself confer immunity from legal obligations.

Revision of Defence Standards

Defence Standards are revised as necessary by an up issue or amendment. It is important that users
of Defence Standards should ascertain that they are in possession of the latest issue or amendment.
Information on all Defence Standards can be found on the DStan Website www.dstan.mod.uk,
updated weekly and supplemented regularly by Standards in Defence News (SID News). Any person
who, when making use of a Defence Standard encounters an inaccuracy or ambiguity is requested to
notify UK Defence Standardization (DStan) without delay in order that the matter may be investigated
and appropriate action taken.

Anda mungkin juga menyukai