API 570 Certification Practice Exam Name: Open Book - Section 1 — Multiple Choice (All Codes may be used) A total of 70 Questions. 1. Abydrotest is being conducted on an underground line as a substitute for the external inspection. The test pressure is 200 psig. At the end of the tes, the pressure must be at least a) 100 psig. b) 175 psig, 3) 190 psig. d) 195 psig. Determine the maximum allowed pressure for a Class 300 flange that has a design temperature of 950 °F. The flange material is ASTM A217 gr-C12. a) ») 9 ig d) __Notallowed - temperature is too high for this material 3. An 8NPS pipe is being replaced with A106 gr. B material. ‘The pipe retirement thickness is 0.218" and the corrosion allowance is 0.125". What is the minimum thickness of pipe that could be ordered after adjusting for mill-tolerance? 2) 021s" 0249" °) 0.343” & 0302" 4. Awelderis being qualified by RT on a 0.600" plate using the SMAW process. What is the ‘maximum atlowed length ofan individual elongated slag inclusion for this qualifying test? a) 0.125" bd) 0.200" ) 0,600" d) 1.200” 5. Daring the evaluation of radiograph the density atthe QI is 3.0. What i the minimum density allowed on this radiograph in the weld? a) 2.00 b) 2.10 3) 255 4300 MSTS 1 os/osst3 10, u 12, 13, API 570 Certification Practice Exam A liquid penetrant procedure must be qualified when performing the examination: a) om exotic materials. b) on materials over 2.0” thick, ©) on materials below 40 °F 4) with fluorescent penetrants. Ifthe “A-Number” on the PQR is an A-2, what “A-Number® must be on the WPS? a Ad by AD 2) AtorA2 4) “AcNumbers” are not required to be on the WPS. When welding pipe, peening is prohibited on: a) alll welding. b) only the root pass. ©) only the final pass, 4) only the root and final passes. ‘What is the diameter of the bolts that are used for a 6 NPS Class 600 flange? 2) 1.00inch b) 1.125 inch ©) 125:inch ) — 1375inch The size of a fillet weld refers to the fillet welds: a) leg. ) throat ) toe, dD face, ‘What is the “F-Number” for an E-7018 electrode? a) Fel b) OF? Oo Fs ad Fa For Class 2 piping systems, a location should consider performing CUI inspections on: a) 10% of suspect arcas, b) 33% of suspect areas. ©) 50% of suspect areas. 100% of suspect areas. ‘The set pressure for a relief device protecting piping systems shall be: a) set no higher than 120% of design pressure, b) set by a valve repair organization holding a “VR” stamp. ©) set imaccordance with API 920. d) _setinaccordance with ASME B&PV Section VIII. 2 osos/t3 “4, 15, 16. 1, 18, 19. MSTS API 570 Certification Practice Exam ‘When performing a WFMPT (Wet Fluorescent Magnetic Particle Testing) examination, prior to the examination, the examiner shall be in a darkened area for 8) the time period required to warm up the black light. b) minute, ©) S minutes. 15 minutes. ‘What is the maximum allowed hydrotest pressure for a piping system with Class 300 flanges that are made of ASTM A182 gr. F316 material? The system has a design temperature of 600 oF a) 450 psig b) 725 psig °) 1080 psig. d 1100 psig ‘What is the required preheat for an A106 gr. B pipe that has a wall thickness of 0.500"? 2) 50°F b) 79°F 2) 150°F 6) Preheat isnot required According to B31.3, a 1-1/2 NPS carbon steel threaded pipe that is installed in a Normal Service should have a minimum wall thickness of: a) Schedule 40. 6) Schedule 60, ©) Schedule 80, 4) Schedule 160. Which of the following is an essential variable for welder qualification using the SMAW. process? a) Addition of backing b) Deletion of backing ° ange in basemetal thickness 4) Change in groove design Without performing impact tests, what is the minimum allowed temperature for the following piping system? Material: A106 gr. B Line Size 6NPS ‘Nominal thickness: 0.750” Retirement thickness: 0.500” a) +53°F b) +30°F | +15°F eae 7a 3 ow/os/t3 API 570 Certification Practice Exam 20. A tensile test specimen breaks at 18,750 Ibs. The specimen is 3/4” wide and 1/2” thick. What is the tensile strength of the specimen? a) 18,750 psi b) 25,000 psi ©) 37,500 psi 50,000 psi 21. During the design ofa pipe alteration, it is determined that impact testing of the pipe is required, The pipe material is A106 ge. C and is considered a fully deoxidized steel. During impact testing each specimen should break at or above: a) 10 fs. b) 12 fabs. ) 1S ies J) 16 feb. 22. Joe Welder qualified using a 4G coupon that is 0.625” thick, The qualification weld was ‘made with 4 layers. What is the maximum weld metal thickness that Joe is now qualified to weld? a) 0.625" by) 1.25 ©) 2,000" Unlimited 23. Whatis the retirement thickness of the described pipe? Design Pressure: 500 psig Size: I2NPS Design Temperature: 70°F Material: A106 gr. B Original Corrosion Allowance: 0.125" a) 0.158" b) 0.164” ©) 0.180" 0189" 24, During radiography of a weld that is 1.0” thick, what is the maximum allowed geometric "unsharpness in the radiograph? a) None isallowed ») 0.010" 0.020" a 0.025 25. Aneexisting line is replaced with 9 Cr- 1 Mo (A426 gr. CP9). The design conditions are 700 °F at 250 psig. The authorized inspector determines that a hydrotest should be performed. ‘What is the minimum required hydrotest pressure? a) 248 ps b) 341p ) 375 psig d— Silpsig STS 4 onosii3, 26. 27. 28, 29. 30. 31 32. ‘MSTS API 570 Certification Practice Exam ‘What is the interval for excavating and inspecting buried piping that is not cathodically protected and has a soil resistance of 12,000 ohm-cm? a) 3 years ») 5 years ) — Wyears dS years ‘What is the P-Number of a pipefitting made of SA-234-WP9? Qa Pl bP oP PSB pipe spool made of 9 Cr-1 Mo is fabricated and stress relioved. What is the maximum acceptable temperature range for the post weld heat treatment? a) -1100- 1200°F b) 1100 1325°F ©) 1300-1375 °F d) 1300-1400 °F RT will be conducted at the completion of welding a 6 NPS pipe that has a pipe wall 0.280”. ‘The radiographer does not have access to the inside of the pipe. What size of hole-type IQI should be used for the radiograph? (Excess reinforcement is not an issue.) a «2 8 ). Set Type A ‘Impacting testing is required during a piping repair of P-SB material. The impact testing ‘must be conducted in accordance with what code? a) ASME B&PY Code Section V b) ASME B&PV Code Section VIL ©) ASNT'SNT-TC-1A 4) ASTMA370 Which of the following bolting materials should not be used for a Class 600 flange?” a) A193-B7 b) AI93-BS ) — A320-L7 d) A307-B ‘What is the Quality Factor “E” for a pipe made of A381 - ¥35?_ Spot radiography according to B31.3 has been performed, a) 0.80 b) 08s 0.90 1.00 5 osfos/i3 33. 34. 36. 36. 37 38, 39, MSTS API 570 Certification Practice Exam A pipe with a locally thin area can be repaired with a fillet-weld patch only if: a) thepipe isa PL or P3 material b) designed by a professional engineer. ©) the piping system is classified as a Class 3. d) the pipe material has a yield strength of less that 40,000 psi A pipe system has a design pressure of $25 psig at a design temperature of $00 °F. The flanges are made of ASTM A182 Gr F11 CL.2. What is the minimum flange class rating for this system? a) Class 300 b) Class 400 ©) Class 600 d) Class 900 ‘What is the retirement thickness of the describe blind (blank)? Line Size SNPS Allowable Stress at design temp: 15,800 psi Design Pressure: 300 psig Gasket ID: 8.25" a) 0.438" b) 0.458" ) 0.493" dois” An A106 Gr, C tensile specimen is tested and breaks in the base metal. What is the minimum. acceptable tensile stress for this test? a) 48,000 psi b) 57,000 psi ©) 60,000 psi d) 66,500 psi A pneumatic testis performed on an altered piping system. The pipe is made of A106 gr. C material and is designed for 300 psig at 700 °F. What is required test pressure? a) 300 psig b) 330 psig ©) 400 psig d) 450 psig ‘When a pipe is subject to extemal pressure, the required thickness for straight pipe shall be calculated using: a) ASME B&PV Code Section VIL b) ASME 16.34 ©) ASME31.1 d) APIS78 Pipe is normally made of welded rolled plate when the nominal size is greater than: a) Binch b) 12 inch ©) 16 inch 4) 24 inch 6 405/13 40, al. 42, 4B. 4s. 46. STS API 570 Certification Practice Exam For welders who weld pipe, an employer may accept the welder performance qualifications from another employer only if a) they are aceeptable to the owner's inspector, b) _ the design pressure does not exceed the 300 flange class rating. ©) the other employer not a competitor of the current employer and is in a different industry. @) it's 70 %F at Shell's Canada Jumping Pound facility on Christmas Day. Consumable inserts can be specified on a WPS that is used for piping, only if: 2) the inserts are the formed ring type. b) the inserts are the “Y" type, ©) the welder was qualified with a similar consumable insert. d) the insert is the same basic material composition as the filler metal, ‘Amine stress corrosion oracking is most aggressive with: a) ‘non-stress relieved carbon steels b) _allarbon steels, °) 300 series stainless steels that were sensitized. 4) 2-1/4 Cr- 1 Mo piping that has been in operation. A200 psig pneumatic test will be conducted on a piping system. A preliminary check of the joints should be conducted at what pressure? a) 10 psig b) 25 psig ©) 50 psig dD 100psig An alteration is performed to a Normal Service pipe that is 0.500" thick. What isthe ‘maximum allowed length of incomplete penetration in a circumferential weld? a) 0,000" b) 0.031" ©) 0,100" in any 6” of weld ¢) 1.5" in any 6” of weld Determine the position of the following groove weld. The weld is inclined 10 degrees up fiom the horizontal plane. The cap is rotated 35 degrees from the top of the weld. a) Flat b) Horizontal ©) Vertical d) Overhead Densitometers used for weld quality radiography should be calibrated every: a) week. b) month, ©) quarter, d) year. 7 ossos/t3 41. 48, 49, 50. SI sts API 570 Certification Practice Exam A.B NPS piping system is being erated. The pipe is made of A106 gr C and has a design temperature of 700 °F. The current thickness is 0.245". The pipe is corroding at 0.004 ipy. ‘The next set of thickness measurements will bein 6 years. Determine the maximum pressure that this piping system can be rerated. a) 753.7 psig b) 836 psig ©) 945.6 psig 983.9 psig A welder qualifies on a 6 NPS pipe. What is the minimum pipe size the welder is now ‘qualified to weld? a) OD b) 2-7/8" 0D ©) 4NPS d) 6NPS ‘When performing a liquid penetrant examination on a steel weld, the minimum dwell time for the penetrant shall be: a) minute, b) —-S minutes. ©) 10 minutes. d) 15 minutes, Determine the minimum design temperature for the following pipe. Material: A671 Gr. CC60 Nominal Thickness 1.000" Retirement Thickness: 0.750” Stress Ratio: as a) 33°F SF ) 36 a 2% A pipe is being replaced and upgraded. Determine the pipe schedule that should be selected. Size: 10NPS Material: A106 gr. B Design Pressure: Design Temperature: Original Corrosion Allowance: 0.170" a) Schedule 30 b) Schedule 40 ©) Schedule 60 4) Schedule 80 8 owosii3, 52, 53, 54. 55. $6. 37. 58. API 570 Certification Practice Exam During alloy welding: 8) one electrode out of each 100 electrodes should be sampled. b) two electrodes out of each 100 electrodes should be sampled. ©) one electrode from each lot should be sampled. €) two electrodes from each lot should be sampled. When flanges are connected they should parallel within: a We" be", ©) 1/16 iw ft measured across the diameter 4) WBin/ft measured across the diameter A pressure testis being conducted at 400 psig. When selecting a pressure gauge, the ‘maximum allowed pressure range on the gauge is a) 0-600 psig. b) 0-800 psig. ©) 0- 1200 psig. 01600 psig. Awelder takes a qualification test using a 4G coupon. If the coupon passes the required exams, the welder is qualified to weld fillet-welds in which position(s)? a) Only Flat b) Only Overhead ©) Flatand Overhead 6) Flat, Horizontal and Overhead During an alteration to a 10 NPS pipe, the inspector discovers a scratch on the face (gasket area) of a new flange. The scratch is deeper than the serrations and is oriented in a radial direction. What is the maximum allowed length of this scratch? a) 0.120" b) 0.180" ©) 0.250" 4 03i0" Bob the Builder is being qualified to weld with the SMAW process. During the test, Bob uses ‘4 6G coupon that is 0.500” thick. What bend tests should be used to qualify Bob the Builder? 8) One face bend & one root bend b) — Twoside bends ©) One face bend & one root bend or two side bends @) Two face bend & two root bend or four side bends A wire type IQ is used during radiography on 0.500” thick pipe. The RT tech has access to the inside of the pipe. What wire set should be used for this radiograph? a) Set b) SctB Set a) Std 9 owyos/t3 59, 60. 6 G3 a. 68. API 570 Certification Practice Exam ‘A welded split sleeve is used to make a tempor ‘electrodes are used to make the circumferential weld. 1 ‘electrodes is to a corroded pipe. E-7018 1¢ maximum allowed diameter of the a) 8" b) 582 36. d 1B. ‘An aluminum product transfer line operates at 300 °F and is 600 feet long. During operation ‘how much will the pipe grow? a) 2 bow 4 a 80" A.0,500" thick gasoline line is being altered, What is the maximum allowed height of extemal reinforcement on these new welds? a) We” bows 5/32" dy 36" ‘When performing a liquid penetrant examination, the surface to be examined should be clean, The area that shall be clean includes the surface to be examined and the adjacent: yo. >. Qo »¥. ay 6 ‘The minimum thickness of a gate valve can be determined by using the minimum thickness: a) chart in ASME BI6.5. b) _ formula in ASME B&PV Section VIII. ©) formula in ASME B31.3, d) formula in ASME B31.3 and multiplying the answer by 1.5. A welding neck flange is used in a 6 NPS Schedule 40 piping system. What is the required bevel angle on the welded end of the flange? a) -22-1/2 degrees ) 30 degrees ©) —_-37-1/2 degrees @) 45 degrees A.QNPS piping system is being fabricated using socket weld components. The actual nominal thickness of the pipe is 0.274”. The thickness of the socket wall is 0.32”. What is the required size of the fillet welds? a) 0.274" ’) 0.320" ) 0.100" 4) 0.299 10 O/05/13 API 570 Certification Practice Exam Use the attached WPS, POR and Checklist to answer Question 66 — 70. 66, 61, 68, 69. 70, Which of the following Essential Variable Ranges is incorrect? a Base metal thickness b. Weld thickness ©. P-numbers 4. F-numbers Which of the following Essential Variable Ranges is incorrect? a. Preheat requirements b, —- PWHT requirements c. Both A and B are incorrect d— Allare correct ‘Which of the following Non-Essential Variables is not addressed? a Retainers b. Backing c Filler Metal Diameter da AWS class Which of the following Non-Essential Variables is not addressed? a. Welding Progression b. Preheat maintenance ce, Land B Range d String or Weave Technique ‘Which of the following statements is true regarding specimen testing and acceptance a, The wrong type of bend tests were conducted. b, Atleast one of the bend tests should have been rejected. ©. One of the tensile test stresses is incorrectly calculated. 4. Alltests are acceptable. u 4/053, WPS-PQR Checklist (SMAW Process) WPS #___ Turn to the list of Variable - See Purple “Variable” Tab A. Checking Essential Variables 1) On the PQR- Find the value for each essential variable and list this value in the PQR Value column of the chart. When complete, put the PQR away! 2) Start at the top of the chart. For the first essential variable, find the Section IX rules and determine the appropriate acceptance standard, List this value in the Accept Stds column, 3) On the WPS-- Find the value for each essential variable and list this value in the WPS Value column of the chart. When complete, put the WPS away! 4) Compare the WPS Value to the Accept Stds value and determine if it is acceptable, Write either Yes or No in the Ok? Column. Complete the Essential Table Below (this is for the SMAW process) Step 1 Step 2 Step 3 | Step 4 Essential Variable oe Section IX Rule Accept) me | Ok? T Qualified (ase Thickness) See purple "T” Tab + (Weld thickness) See purple “F” Tab | | #Pass > $ inch =| Only applies if weld passis># | _— | _— | Yes P-Number Qualified : | See purple "PY Tab F-Number ‘Must be the Same F # ‘Must be Same A#, but Ai & _ AZ are interchangeable Preheat Temp WPS > PQR - 100°F 2 Must be same family: Yes = Yes, None = None ‘Only applies if PWHT femp is plinits) 7" _| greater than Upper Trans. temp | 7 Ma A-Number PWHT Only applies for temper bead Use of Thermal Processes | —- = = Yes welds 8. Non-Essentials Errors C. Testing Errors (Look only on WPS - Are they Addressed?) (Specimens and Acceptance Criteria) 1) y 2) 2) 3) 3) 4) 4) MSTS: msts-training.com 1 December 2011 (QW-482 SUGGESTED FORMAT FOR WELDING PROCEDURE SPECIFICATION (WPS) (Gee QW-200.1, Section IX, ASME Boiler and Pressure Vessel Code) Company Name __STELLER FABRICATORS By __ Ray Roberrrrson ‘Welding Procedure Spee. No. _237 Date__s/19/1999 Supporting PQR Nos)_333 Revision No, _0. Date ‘Welding Processes) _SMAW. ‘Type) _ MANUAL ‘Acton, Manual, Machine oF Semi-Auto) JOINTS (QW-402) poe Join Design __All Grooves or Fills Backing (Ves) NO) Backing Material Typ) ‘Rete tctng ai anos) Root Spacing — © eta © Nootsog Met pore 18" 1-116" ©) Nowmatic —() Otter Allowed ‘Sketches, Production Drawings, Wel Symtols or WritenDesrotion sould Sow the acetal arungemet of the pats to be welded, Where applicable, the ‘uot spocing spd the etal of wel oove maybe specie. (tte option ofthe Mt, sketches may be tached asta ot design, wold yer and bead sequence *BASE. METALS (QW-403) PNo, 1 GroupNo._ fo P1No__Lor 3___Group No, oR ‘Specification type and grade _ to Specification type and grade on ‘Chem, Analysis and Mech, Prop. to Chem, Analysis and Mech. Prop. ‘Thickness Range: Base Metal Groove_ua"=3" Fillet _Same PipeDia, Range: Groove Greater than NPS Fillet __ Same Other FILLER METALS (QW-404) ‘Spec. No. (SFA) S.L AWS No, (Class) __E-6010 PNo,__E:3 ANo.__A2. 18", 5/52" or 36" ‘Weld Metal Thickness Range: Groove_1/4" to Fillet___ Same lectrode-Fiux (Clas), Flux Trade Name ‘Consumable insert Other "Bach base metal-filler metal combination should be recorded individually. MSTS (Copied from ASME B&PV Code Section IX - 4/2000 - MSTS) Bxam-1 QW-482 Back) WPS No. _237 Rev. _0 POSITIONS (QW-405) POSTWELD HEAT TREATMENT (QW-407) Position(s) of Groove _ALL ‘Temperature Range __1100°F i. 25 °F Welding Progression: Up Down ‘Time Range __LHlingh, LE Position(s) of Fillet — GAS (QW-408) PREHEAT (QW-406) Percent Composition Preheat Temp. Min, 200° Gases) (Mixture) Flow Rate Tnverpass Temp, Max. Not Conialled Prebeat Maintenance _AieCool Shielding Trailing (Continvous or special heating where applicable shouldbe recorded) Backing ELECTRICAL CHARACTERISTICS (QW-409) (Current AC or DC_DC Polavty Reverse ‘Amps (Range) _ See Below Volts (Range) _See Below (Amps and volts range shouldbe recorded for each electrode size, Position and thickness, et. This information may be listed ina {abular form similaro that shown below.) Tungsten Blectrode Size and Type - ‘ue Tungsten, 2% Thre et) Mode of Metal Transfer for GMAW a (Gray ar short Sealing ar, ee) Electrode Wire feed speed range TECHNIQUE (QW-410) String or Weave Bead _ Ether Orifice or Gas Cup Size [nil and lnterpas Cleaning (Brushing, Grinding, ee.) — Grinding, Chipping or Wire Brash Method of Beck Gouging Grinding Oscillation ~~ Contact Tube to Work Distance Multiple of Single Pas (per side) Either Multiple or Single Electrodes ‘Travel Spoed (Range) Pecning_ Okif weld ishot Other = fo single pass greater than Fillee Metal Current Other Travel| (eg. Remarks, Comments, Weld Type | Amperage | Volt Speed | Hot Wire, Addition, Tech, Layers) | Process | clase | Diameter | Potarity | Range | Range | Range ‘Torch Angle, et.) all smaw | B-6010 us perp | 90.160 | 19.25 57 All smaw | eso10 | saz” perp | 1s2%0 | 229 s1 all smaw | Eso | ane | pcre | 20030 | 2229 57 STS (Copied from ASME B&PV Code Section IX - 4/2000 - MSTS) Exam-2 (QW-483 SUGGESTED FORMAT FOR PROCEDURE QUALIFICATION RECORD (PQR) (Gee QW.200.2, Section IX, ASME Boller and Pressure Vessel Code) Record Actual Conditions Used to Weld Test Coupon, Company Name __ STELLER FABRICATORS s PQRNo. 333 ___ WPS No. Date_s989 - Welding Process(es)__SMAW. ‘Types (Manual, Automatic, Semi-Auto.) MANUAL. ~ JOINTS (QW-402) 1" Groove Design of Test Coupon (For combination qualifications, the deposited weld metal thickness shall be recorded fo each filler metal or process used.) BASE METALS (QW-403) POSTWELD HEAT TREATMENT (QW-407) Material Spee, _ SA-S16 0 SA-S16 ‘Temperature _None ‘Type or Grade _ 60 Time PNo._L wPNo_1 - Other ES = ‘Thickness of Test Coupon _/2" 7 aoe Diameter of Test Coupon _ PLATE. : Other = GAS (QW-408) 7 Percent Composition Gas{es) (Mixture) __Flow Rate Shielding — FILLER METALS (QW-404) Trailing Backing SFA Specification 5.1 sification E-6010 AWS PTRICAL CHARACTERISTICS (QW-408) Filler Metal F-No.__P-3 Current__DC ‘Weld Metal Analysis A-No,__A Polarity Reverse Size of Filer Metal - Amps, 125-145 Volts Other i: ‘Tungsten Electrode Size E Other ‘Weld Metal Thickness__12" - — POSITION (QW-405) TECHNIQUE (QW-410) Position of Groove _1G ‘Travel Speed __ Weld Progression (Uphill, Downhill) — String or Weave Bead Weave Other Oscillation “Multipas or Single Pass (pr side) Mulipie Single or Multiple Blctrodes__ PREHEAT (QW-406) Other = Preheat Temp __ _ Interpass Temp. Not Monitored — MSTS (Copied from ASME B&PV Code Section IX - 4/2000 - MSTS) Exam-3 QW-483 (Back) POR No. _333 Tensile Test (QW-150) SpsimenNo. | Witte Thickness Area ‘Utimate Load | timate Stress | Type ofFailure (inch) (inch) (69, inches) dbs) (si) Location 1 0750 05 0375 23,060) 61,500 | Base ~ Ductile a 0750 05 0375 24,400 58250 | Weld Ductile Guided-Bend Tests (QW-160) ‘Type and Figure No Result Side QW-462.2 No Deftsis OK 32 Side QWAG22 W532" Linear - OK B= Side- QW.462.2 [No Defects OK A Side QW-402.2 V6" Linear -OK ‘Toughness Tests (QW-170) Specimen Notch Notch Test Impact Lateral Exp, Drop Weight No. Location Type Temp. values | s¢shoor ils Break No Break Fillet-Weld Test (QW-180) Result-Satisfectoy: Yes, No Peneiraton into Parent Metal: Yes No. Macro-Results Other Tests ‘Type of Test. _ Deposit Analysis Other ‘Welders Name _Matt Webber Clock No, Stamp No. _WX “Tests conducted by: _Undereut Lab Laboratory Test No.__UL4322 ‘We centfy thatthe statements in this record are correct and that te tes welds were prepared, welded, and tested in accordance withthe requirements ‘of Section IX ofthe ASME Code Date_May 19, 1999 Manufacturer By TELLER FABRICATORS Rambs Steller (De oF reord of tes ar istrative only and way be medifed to conform the type and number of tess required bythe Code) (Copied from ASME B&PY Code Section IX - 4/2000 - MSTS) Exam-4 API 570 Certification Practice Exam Name: Closed Book - Multiple Choice (No Codes or class materials may be used) A total of 128 Questions. 1, Insovere refinery services which type of pipe is normally used? a) Cast b) Machined ©) Seamless Welded 2. Pressure applied inside a pipe creates stresses in the pipe wall. These stresses are highest on which weld orientation? a) Circumferential weld b) Longitudinal weld ©) 30 degree mitered weld 4) Alllare about the same 3. Which of the following is not an acceptable method for establishing the piping corrosion rate in anew service? 2) Owner's experience b) Inspect the piping system within 3 months of operation ©) Corrosion data from trade journal 4 Corrosion data from phone discussion with a consultant corrosion engineer. 4, Per B31.3, how much RT is conducted on circumferential welds of a pipe in Normal Service? a) 0% b) 5% 10% d) 100% 5. For welded pipe, the normal thickness undertolerance is 8) -0.00 inch, b)— -0.01 inch, ©) -0.0125 inch, ) — -12.5% of the specified wall thickness. 6. When qualifying a weld procedure the essential variables must: 8) berecorded on only the POR. b) be recorded on only the WPS, ©) _berecorded on both the WPS and POR. 4) berecorded on both the WPS and WPQ 7. Apipe has a thickness designation of 40S”, What does the “S” mean? 8) Schedule b) Seamless c) Stainless steel a) Steel MSTS 1 HSB 10. nL. 12, 13. 14 15, MSTS API 570 Certification Practice Exam Which of the following types of pipe should not be used in pressurized hydrocarbon service? a) ») °) ¢ ‘Threaded cast iron Butt welded carbon steel Rolled and welded carbon steel Socket welded stainless stect Generally socket-welded piping is not used for nominal pipe sizes above: a) ») °) ’ Linch, 2inch, 4 inch, 6 inch, A propane piping system should be classified as: a) ») °) 4d Class 1 Class 2 Class 3 Category D According to ASME/ANSIB165 flanges made from plate materials can only be used for: a) ») °) a blind flanges. Class 150 flanges. Class 150 and 300 flanges. threaded flanges. ‘The corrosiveness of soils can be determined by measuring the sol’s: a) ») ° a plasticity, resistivity. modulus of elast galvanic potential, ity. Preheat should never be substituted for a postweld heat treatment if the: a) b) °) a pipe wall thickness is greater than 1.0”. pipe is a P-3 material, ‘post weld heat treatment was designed to prevent environmental cracking, post weld heat treatment was designed to reduce stress levels in the heat affected zone. Which of the following is a required marking on ASMEVANSIB16.5 flanges? a) » ° d) Bolt material Nominal pipe size Outside diameter of flange ‘Temperature rating During welding, non-essential variables: a » ©) d) ‘must be recorded only on the WPS and must be followed by the welder. ‘ust be recorded on the WPS and are optional for the welder. ust be recorded on both the WPS and PQR. are optional on both the WPS and PQR. 2 4SH3 16, 17. 18, 19. 20. 21 22, 23, ‘MSTS API 570 Certification Practice Exam During a hydrotest, all joints should be: ) tested for 1 hour. b) eft uninsulated. ©) eft uninsulated and unpainted. soap tested. ASME/ANSI B16.5 requires flanges to be: a) made by forging. b) hydrotested. spected by RT. ) marked with the class rating, Which of the following activities is not included in the seope of API 570? a) Rerating a piping system b) Operating a piping system ©) Replacing a portion of a piping system ) Inspecting a piping system Which of the following refinery piping systems may be excluded from the specific requirements of API 570? 8) 3/8” OD gasotine drain line b) 6 NPS fuel gas line ©) 4 NPS crude line operating at 100 °F d) 3 NPS catalyst line Graphitization of carbon steels begins to ocour when metal temperatures exceed: a) 20°F b) 80°F ©) 1000°F. a) 1100°F During pipe fabrication, who has overall responsibility for compliance with the Code? a) API.S70 Authorized Inspection b) Designer ©) Manufacturer d) Owner ‘Who has the responsibility to determine the extent of PMI performed? a) Authorized Inspector b)— Owner/Uiser ©) Repair organization ) Engineering organization ‘Which of the following piping systems is covered by B31.3? 2) 4.NPS- 10 psi low pressure instrument air pipe at local refinery. b) 6 NPS - 300 psi fuel gas line at local utility power plant, ©) 1 NPS~45 psi gasoline line at a tank terminal. 4) 6 NPS - 900 psi high pressure crude pipeline in the Gulf of Mexico, 3 4513 24 26, 28, 29. 30. 31, MSTS API 570 Certification Practice Exam An in-service process pipe is classified as Class 1 when the percentage of H2S exceeds: a) 0.5%. b) 1%, 3) % do 3% A welder becomes unqualified when he has not welded using the: a) procedure for 6 months. b) procedure for 12 months. ©) process for 6 months. process for 12 months. APQR test coupon with a shell thickness of “T” can generally be used to qualify a wall thickness on the WPS up to: Opt b) LIT early 2upto4” A pressure testis always required: a) afterall repairs. }) afer all major repairs and alterations. ©) after all rerates. whenever the authorized inspector believes one is necessary, ‘When can radiography not be used to qualify a welder? a) When using the SAW process b) When using the GMAW process with the pulse are mode ©) When using the GMAW process with the short circuit mode d) When qualifying in the overhead position Generally, raised face flanges should have surface finish of; a) 50-250 micro-in. b) 125-250 micro-in, ©) 125-500 micro-in 4) 250-500 micro-in During a direct visual exam of a pipe weld, the minimum light intensity should be: a) 10 footcandles. b) 50 footcandles ©) 100 footcandles, 4) 1000 footeandles, Describe the “3G” welding test position. a) Horizontal groove b) Vertical groove ©) Overhead groove d) —Ackansas bellhole 4 HH3 32, 33, 34. 35, 36. 37. 38. MSTS API 570 Certification Practice Exam ‘Seal welding pipe threads: a) may be used to prevent leaks. ) is used to strengthen the threaded joint. ©) isnot allowed in B31.3, 4) isnot allowed in API 570. ‘Which of the following piping components is most likely to have a substitution with the wrong material? a) A.20" length of 6 NPS pipe Bb) Weld-neck flange ©) Expansion joint d)—_ Bolting Liquid thermal relief valves should be set ata pressure mot higher than: 8) 100% of the design pressure. b) 110% of the design pressure. ©) 120% of the design pressure. d) 150% of the design pressure. ‘When fabricating pipe, unknown materials: a) should never be used (except for door stops). b) canbe used only in Category “D” piping c) canbe used only if successful tensile tests are conducted. 4) canbe used only ifthe safety factor is increased to 4 to 1 ‘The material verification program specified by API 578 covers: a) only pressure-containing components, b) only pipe, and fittings. ©) only pipe, fittings, and welds, d) __pressure-containing and non-pressure containing components. What is the interval for thickness measurements on a Class 1 piping system? a) Syears b) 10 years ©) The lesser of 5 years or 1/2 the remaining life of the pipe 4d) The lesser of 10 years or 1/2 the remaining life of the pipe According {o B31.3, a welder’s qualification records from a previous employer can: a) never be accepted. b) be accepted if the Inspector approves. ©) be accepted only if the welding is performed on Category “D” piping. 4) be accepted only after obtaining an written recommendation from the previous employer, When welding together piping components of different thickness, the thicker part should be trimmed with a 8) 10° taper. b) 20° taper. ©) 30°taper. €) 40° taper. 5 MSN3 40, soil: 4 2. 8. 4s 46. 41, MsrS API 570 Certification Practice Exam ‘When performing soil-to-air inspections on uncoated lines, itis recommended to excavate the a) ») 12-24" ‘When performing preheat prior to pipe welding, the preheat zone must extend: a) I beyond the edge of the weld. b) 3" beyond the edge of the weld. ©) 6" beyond the edge of the weld. ) 12” beyond the edge of the weld, ‘When obtaining thickness measurements a) all CML’s on the circuit must be measured, b) the CML readings on a circuit should be averaged. ©) a CML on each type of pipe component should be recorded, 4) the CML's must be measured using the UT method, Flange bolts are unacceptable if the bolt threads do not extend: a) beyond the face of the nut by I thread. ) inside the mut within 1/2 thread of the nut face. ©) inside the nut within 1 thread of the nut face. 4) inside the nut within 2 threads of the nut face. Carbon steel materials are most likely to be incorrectly substitution in: a) achrome steel pipe system. b) stainless steel pipe system, ©) any fervitic stcl pipe system, @) any non-ferrous pipe system. Per B31.3 how much of the fabrication should be visually examined for a pipe in Severe Cyclic service? a) 5% b) 10% ) 50% 100% When calibrating a UT instrument, that has a delay line with a single element search unit, use: a) atest block of any thickness, made of the same material of that to be examined, b) atest block of any thickness, made of material with the same velocity of that to be examined. ©) at least two test blocks of any thickness. 4) at least two test blocks with thicknesses near the maximum and minimum to be examined. During an API 570 pipe repair, which welding discontinuity is always unacceptable? a) Crack b) Incomplete Penetration ©) Porosity @)— Undercut 6 4SH3 48. 49. 50. sl. 32. 83. 55. MSTS API 570 Certification Practice Exam Which of the following best describes undercut of a weld?” 8) The parent material and filler material are not completely bonded, 'b) The weld root is not completely filled. ©) There isa groove in the parent material a the toe of the weld ®)_Anelongated inclusion directly under the weld cap. Which of the following is not a common location for significant external corrosion of a piping, system which operates at 125 °F? 8) Bottom side ofa pipe atthe pipe supports b) Under pipe clamps ¢) Near small connections that penetrate through the insulation d) Topside of an uncoated & uninsulated line in the unit piperack, ‘The RT procedure used for a pipe repair must conform to the requirements of: a) ASNT, SNT-TC-1A b) ASME, B&PV Code Section V ©) ASME, B&PV Code Section VIIT ) ASME, B&PV Code Section IX ‘What is the minimum holding time forall pressure tests on piping? a) 10 minutes b) — 20minutes ©) 30minutes ¢) 60-minutes ‘When a relicf device or valve is removed for repair, the inspector should: 18) inspect the inside of the inlet and outlet piping where the valve was removed. b) tag the valve, to ensure the valve is returned to the correct location, ©) provide a cost estimate for the anticipated repairs, d) ensure that the flange bolts are renewed. Thickness measurements are suggested at pipe fittings since: a) they are generally more accessible. b) many are forged or cast ©) directional changes generally create increased turbulence. 4) the nominal thickness of most fittings is generally less than that of straight pipe. An insulated line is subject to dewpoint corrosion, Which of the following parts of the pipe is, ‘most likely to experience accelerated corrosion? a) Dead Legs b) Elbows ©) Welds ) Straight pipe Flange leaks in certain fluids can cause: a) galling of bolts and nuts. b) bolt lengths to shorten, ©) bolts to crack or corrode. 4) bolting stresses to decrease. 7 MUSAB 56 51, 58. 59. 60. 61 0. 6. API 570 Certification Practice Exam Heat tracing could cause cracking in a carbon steel piping which is i: a) crude oil service, b) asphalt service ©) sulfuric acid service. d) caustic service. Excessive repairs to pump bearings may be a result of: 8) increased corrosion rates in the attached piping systems, b) excessive forces coming from thermal growth in the attached piping systems. ©) incorrect metallurgy in the attached piping systems. external pipe inspections are overdue. Loose or broken anchor bolts at pipe supports are most easily detected by: a) visual examination b) straight beam UT. ©) finger tightening. d) — bammertesting. A pneumatic pressure testis to be conducted on a normal service piping system. During pipe erection, how many of the joint assemblies should be examined? a 5% b) 10% ) 100% 4) random examination During a pipe repair, preheat is substituted for the required postweld heat treatment. What is the minimum acceptable preheat temperature? a) 150° ») 200° ©) 300°F 50°F When UT readings are taken at higher temperatures, the hot readings: a) will be greater than the actual thickness. b) will be smaller than the actual thickness. ©) maybe greater or smaller than the actual thickness depending on the material type. ) will vary from the actual thickness only because the UT instrument’s accuracy decreases. Existing valves in severe cyclic temperature services should be checked for: a) erosion. b) cracks. ©) distortion caused by liquid hammer. 4) galvanic corrosion. A primary location of deterioration in a swing check valve is the: a) flange face. ) cover gasket. ©) shaft and hinges. da disk. 8 S/S 64, 65. 66. 67. 68, 69. 70. MTS API 570 Certification Practice Exam ‘Thickness measurements on Injection Points should be conducted at least every: a) year, b) 3 years, ©) 5 years 1 years. An existing hydrocarbon line is being pressure tested at 300 psi. Which of the following test ‘mediums should not be used? (line has not been thoroughly cleaned) a) Gasoil b) Nitrogen ©) Helium Air Pressure tests should be conducted: a) after PWHT. b) before PWHT, ©) without the joints being painted or primed, d) without the joints being painted. (priming is ok) ‘What is the corrosion rate for the described CML? Reading #1. 0.331 1992 Retirement Thickness: 0.120” Reading #2: 0320” @/1998 Reading #3: 0.292” 6/2005 a) 0,002 ipy b) 0.003 ipy ©) 0.004 ipy d) 0.029 ipy What does the letier“F” on an RT indicate? ) Fast film speed b) Radiation is also coming for the far side of the radiograph ©) Penetrameter was placed on the film side d) certain wire type penetrameter was used for the RT Fatigue cracks may be difficult to find since: 8) the cracks are extremely tight b) itis difficult to predict the location of fatigue cracks ©) mosteracks occurs under insulation 4) the time period between crack initiation and failure is short What is the minimum # of RT exposures required to RT a new 2 NPS weld? (No access to the inside) a 1 b) 2 ) 3 d 4 9 Ys n n. 14, 75, 16 n. 78, MSTS API 570 Certification Practice Exam When using a hole type penetrameter on a radiograph, what hole size must be seen on the radiograph? a) IT bor ) 3t a 4T During inspection of an injection point circuit, extensive inspection should be conducted, downstream of the injection point for a distance at least: a) 12 inches, b) 25 feet ©) 3 pipe diameters 4) 10 pipe diameters Insulated austenitic stainless steel pipe is susceptible to CUI (chloride stress corrosion cracking) at a) 0-200%F b) 25-250°R. ©) 65-204. & — 150-400°F. Tack welds should be: a) made by a qualified welder or welding operator. b) removed when welding out the piping joint ©) made with a filler material that is stronger than the pipe. 4) fused with the final pass. Which of the following is not a factor contributing to creep? a) Line size b) Operation temperature ©) Length of time in operation ) Actual stress levels in pipe ‘The minimum and maximum density range in the area of interest on a radiograph using a gamma ray source is a) 13-40. by) 18-40. 2) 20-40. 4) dependent on the plate material Which of the following is not a major contributor to fatigue cracking? a) Mechanical vibration b) The number of pressure cycles c) The number of temperature cycles €) The numberof ph changes According to API 570, intemal inspection of large pipe: a) ismandatory. b) when done, should be conducted similar to API 510 internal inspections. ©) when done, should be conducted at least every 10 years. 4) isnever recommended, 10 4SN3 19, 80. 81 2. 83. 84, 85, 86, MSTS API 570 Certification Practice Exam Which of the following is not an acceptable way to qualify a welder? a) Bend tests of a coupon. b) Tension tests of a coupon. ©) RT ofa coupon. d) RT of 1 production weld, During the external inspection, spring hangers should be checked to ensure that the: a) spring is not stuck. ») spring is not bottomed out. ©) correct spring type was installed. ) correct spring metallurgy was installed. According to API $70: 8) a CML should be assigned to each fitting, >) CML’s can never be eliminated. ©) the number of CML’s should be based on the metallurgy and length of the pipe. d) thickness measurements should be taken atthe 4 pipe quadrants During a piping repair, who is specifically responsible for quality control? 8) Authorized Inspector b) Examiner ©) Owner/User @) Repair Organization Ifa hydrostatic pressure testis maintained for a lengthy period of time; a) _aspare hydrotest pump should be provided. b) the inspector should remain at the test site for the total time of the hydrotest. ©) precautions shall be taken to avoid excessive pressure. ) the test pressures should be recorded every 10 minutes. According to API 570, who should conduct the external inspection? a) The Authorized Inspector b) The Authorized Inspector or a Level II NDE examiner ©) The Authorized Inspector or qualified operation or maintenance personne! ) Anyone designated by the Owner-User ‘What NDE technique is useful for finding plugging in piping? a) Acoustic emission b) Eddy Current ) RT d UT Marking pens used to mark piping components should not contain: a) Carbon. b) Chrome. ©) Oxides. d) Sulfur ul USH3 87. 88, 89. 90. 91 92. 93, MSTS API 570 Certification Practice Exam Which of the following is not an important step when performing a hydrotest on a 300 sories stainless steel? a) Use potable water or condensate for the test medium, b) Raise pressure in small pressure steps ©) Thoroughly drain piping, 4) Thoroughly dry by blowing air through pipe. Per API.570, during repairs and alterations, the inspector shall verify thatthe new materials being used are correct. What isthe minimum amount of verification tha the inspector shall perform? a) 100% ofall piping metallurgy’s b) 100% ofall alloy piping ©) 100% ofall high alloy piping 4) Assampling of al alloy piping During weld quality radiography, when possible IQIs should be placed on the: a) film side. b) source side. ©) outside of the component. weld. Which valve type generally tends to create the most turbulence in the fluid flow? a) Ball valve b) Butterfly valve ©) — Gate valve Globe valve ‘During an in-service inspection, an old fabrication imperfection was discovered in a weld, ‘This imperfection must be: a) evaluated to the acceptance standards of the original construction code. b) evaluated to the acceptance standards of the current edition of B31.3. ©) evaluated to the acceptance standards of either the original construction code or the current odition of B31.3 d) evaluated by an engineer or inspector. ‘What is the hardness limits for pipe made from 9% Cr - 1% Mo? a) 200 Brinnel b) 225 Brinnel ©) 241 Brinnel d) 256 Brinnel A locally thinned area on a pipe: a) maybe evaluated using API 579. b) may be evaluated using API 598, ©) must be evaluated by a piping engineer. d) must never result in a thickness lower than allowed by the B31.3 thickness calculations. R W5/13 API 570 Certification Practice Exam 94, In which of the following activities must the name of the individual performing the activity be permanently recorded in the piping records? a) Creating the CML’s on a piping circuit ) Establishing the inspection intervals ©) Taking the thickness readings at the CML’s 4) Establishing the Pipe Class for the piping circuit 95, Prior to performing a pipe repair the work must be authorized by the: a) authorized inspector. ») piping engineer. ©) authorized inspector and the piping engineer. 4) jurisdiction. 96, ‘Temporary non-welded repairs of thinned piping: 8) cannever be made. b) can be made only if they are fully welded tothe pipe ©) must always us leak sealing fluids &) must be designed to account for axial forees. 97. Whats the Quality Factor “E” for a seamless pipe made from A106 gr. B? a) 0.80 b) 08s, ) 0.90 1.00 98. When the maximum weld hardness is specified in the Code, how many welds should be hardness tested? a) 10% of all heat treated welds b) 50% of all heat treated welds ©) 100% of all heat treated welds 10% of furnace heat treated welds and 100% of local heat treated welds 99. When qualifying a WPS, a bend test is considered acceptable if there is no open defect greater than: a) 0.00" b) 1/16" °) Ue” dae" 100, What is the minimum radius for a flush repair patch on a large diameter pipe? a) Linch b) inch ©) 6inch ) Flush patches are not allowed. STS B 45113 101 102. 103. 104. 105. 106 MSIS API 570 Certification Practice Exam What code covers the safety aspects of performing weld-overlay on a hydrocarbon line that is a) APIS79 b)API2015 ©) API2201 4) AWSDIA Ifa weld map is not used, the welder must stamp 2) each weld personally made, b) every 6” of weld personally made. ©) every3* of weld personally made. 4) S%of the welds personally made Welded temporary repairs on pipe 8) may remain past the next maintenance opportunity only if approved & documented by the engineer, 'b) may remain past the next maintenance opportunity only if approved by the engineer and inspector. ©) must always be replace atthe next maintenance opportunity regardless of Pipe Class. <6) must always be replace atthe next maintenance opportunity only if the pipe is a Class 1 system. Ifa welder qualifies using RT on a coupon, the total ength of weld RT’ ed must be atleast. a 6. 1 Oo 1s a) 36" Determine the Remaining Life at a specific CML. Data for the CML is as follows: Thicknesses: Corrosion Rates: Nominal thickness 0375” Short-term Rate: 0.002 ipy Current thickness. 0.295" Long-term Rate: 0.004 ipy Minimum thickness: 0.223" a) 18 years b) —20years ©) 36 years 6) 38 years During fabrication, how many welds should be visually examined? Pipe is classified as Normal Service. ay 5% b) 10% ) 100% 4d) depends on API 570 piping classification i 453 107, 108. 109. 110, UL. 112. 113. 14, MSTS API 570 Certification Practice Exam ‘What is the total number of tests that must be conducted to qualify a WPS? a) 2bend tests b) 2 bend tests ora radiograph of the tested weld ©) 2 tension tests and 2 bend tests €) 2 tension tests and 4 bend tests Which of the following is not included within the scope of B31.37 a) Engineering requirements that are necessary for safe design of a piping system, b) Engineering requirements that are necessary for safe construction of a piping system. ©) Specifying temperature limitations based on pipe materials 4d) Provide guidance for selection of pipe materials based on process chemistry. UT readings are generally accurate of pipe sizes greater than: a) 1 NPS. b) 1-12. NPS. ©) .2NPS. dS NPS. During @ pipe alteration, a defective weld is discovered on a radiograph. How many more ‘welds from the same welder should now be radiographed? ere yew 2 Cena 4 Ollie, a welding operator, takes a SAW qualification test on his first production weld. How much weld should be radiographed? a 6" hy 36" 4) Radiography is not allowed when qualifying SAW During radiography, whenever a shim is placed under a hole-type IQI: a) atleast 3 sides of the IQ] image should be visible in the RT b) all 4 sides of the IQI image should be visible in the RT. ©) the shim should be made of stainless steel d) the shim should be the same thickness as the IQI. If alloy element(s) are contained in the flux of a welding electrode, PMI testing: a) isnot necessary. b) is not necessary provided appropriate documentation is provided by the supplier. ©) could be conducted on any of the production welds, 4) could be conducted on a weld button prior to production welds The external inspection on a Class 2 line should be conducted: a) every 5 years. D) every 10 years. ©) lesser of 1/2 remaining life or 5 years. d) lesser of 1/2 remaining life or 10 years. 15 A513 us. 116. 117. 118. 119, 120, MSTS API 570 Certification Practice Exam Cold spring generally refers to: 8) spring support in its cold position, b) a spring support in its “chocked” position ©) purposely shortening a line during fabrication to offset thermal growth 6) the installation practice of rigging a large line into a congested piperack. ‘The suggested upstream limit of an injection point circuit i: a 6 b) 12, ©) 3 pipe diameters. d) greater of 12” or 3 pipe diameters, ‘When impact testing is required each test should consist of how many test bars? eal 2 Qo 3 d) Depends on the material Identification of materials by visual stamps or markings: 4) isnot an important part of the material verification program. b) isnot substitute for PMI testing ©) is important only with high alloy materials 4) should be done only by inspectors. According to API 570, who should conduct the thickness measurement examinations? a) The Authorized Inspector b) The NDE Examiner ©) The Authorized Inspector or the NDE Examiner ) Anyone designated by the Owner-User The nominal size (NPS) ofa pipe genorally refers tothe pipes a) inside diameter. >) outside diameter. ©) inside diameter, ifthe pipe size is less 24 NPS. @) outside diameter, if the pipe size is greater than or equal to 14 NPS. Creep begins to occur in 1-1/4 Chrome steels at temperatures above: a) 450°F, b) 00°F. ©) 90°F. d— 1100°F, 16 49/3 122. 123. 124, 128. 126. 127. 128. STS API 570 Certification Practice Exam ‘A.welder who passes a groove weld qualification test using SMAW, is qualified to weld: a) onsome fillets. b) — onall fillets, ©) using a few other welding processes, d) _ onall pipe diameters. er API 578, what is the appropriate action to take when an incorrect material is located during, a PMI sampling of new materials. ) Inspect 2 more items from the inspection lot. b) Inspect 50% of the items from the inspection lot, ©) Inspect 100% of the items from the inspection lot. d) Inspection all items supplied by that manufacturer. Piping stresses are generally higher at which of the following pipe connections? 8) Flanged connections above the 300 class rating. b) —_Non-reinforved branched connections ©) Socketweld connections 4d) Weld-o-let connections All owner/users that use API 570 should: a) directly hire authorized inspectors. b) directly hire authorized inspectors and engineers, ©) have a quality assurance inspection manual. 4d) specify that all inspectors at their site get 12 weeks of vacation per year! ‘When welding is performed, which of the following NDE methods is the most extensively used? a) Liquid penetrant b) Radiography ©) Ultrasonics Visual ‘The structure of weld metal is most similar to that formed from: a) casting, b) extruding, ©) forging 4) postweld heat treatment. How many shell welds are required to be radiographed per API S77? a) Number based on authorized inspector's judgment b) Zero ) 3% d) Ginches every 50 feet ” U3 % Points & Open Closed Total API 570 Test — Answers Sheet API 570 Open Book — Answers Sheet Name: 170 Percentage Correct Number Correct: Please shade your answer, OBOE6 BOBO OEOEEEEHEO G8OEO BEEBE OEBEO 0000 GOEOE 0HEGOEOOO GO00O HOOOO GOOOO BGOB6 BOEOE OGOEGEEEES GO080 BO08E OOE8E GEE GEEEE GE8GG860G8 88009 BEEE8 BEEEO Seas geses es FSsitdad sass cdg ss esses 86006 GEEO6 08088 GO8OE HEOEOEEEOO BOEER G008H COERE OOORG GOEOR OOOROREORO OOOOR BGOB8 GEEEE OBOEE BEREE OEOROEEEEE BEER 86088 BEBEE BEEEE GEEEE BEOEEEEEEE BEEEE Hanes Cowes S SHAHN SOKA Rg SAN SHKK KAS SAAT % Points 3 3 Ope 3 s s API 570 Test — Answer Sheet API 570 Open Book — Answers Name: 170 Percentage Correct Number Correct: Please shade your answer. 08060 C6606 O6068OCCOO 00005 00068 GEE0O 90006 OEEEOH €E0OG08ONH COOOO 60080 O8008 80066 BCOGO 000696000 00085 BGGC0 66000 BEOGO GOGEE GEQEEGEEEE BGG8 GOG0G GEGed 4 6 7. 8 9 0. Seseeddddes sedag ddsss esses 80006 06008 06000 66006 66 6 00006 00008 06000 0OOOE 00000 HG0EOOOBOR 00008 60008 BEEEO 6O0OE BG0EO OG6H0EEE0008 BOE8O BGOGE BEERS EERE GEOEH BGOEEE8GOE BEGEG Sieve sess PF SHHSN ESHA KR ASAHKH ENA SR SA API 570 Closed Book — Answers Sheet Name: 1128 Percentage Correct Number Correct: Please shade your answer, GEOG 8 68688 0666866006 86606 86606 00600 08000 0OLOO HOOOEOLHEH OOEOO BOOED OOH OO 6EOEO BOBO OBOEEEEHGH O8000 66608 00008 GEEB8 BOEEE BEEEEEEHEG BEEEE GEEEE BEG88 SRRAS FUSES SSF SR AAg ss GaAs Sdsss esses 80068 BEE86 66066 66666 6G088EEE8O BOGE 89088 0BOEE 0GOEO 00000 H0OOOROEOO BOGOR GOOB8 CBEEE BBOBE BEEOE BOOROEOEEE OOBEE 8908 BEEBE GHEE BEBO BEEBE BEGEG aiden eee FS SNAAA odes SAK AN MN NR SHA Please shade your answer, (Continued) 66666 68600 O8668 06606 600 80GO8 GOGO OEORE 00008 800 80608 6880 OBO68 60006 000 868868 66686 86068 860 8O6G6 68668 C660 66000 HOOEOOOROR 00008 08088 BOERS BEER 0O0OO HOOOOGOOOR OOOO GGEG8 OBEEE OBOE BBOEO HOOEEEEEOE 00088 B8G8 BBGEE BEERE BEEEE BOCEEEEEEE BEGEE Feed SEK RS od ses See ss eee ee eee as SLESE API 570 Closed Book — Answers Name: / 128 Percentage Correct Number Correct: Please shade your answer. 88666 06668 6660680008 00008 60608 60600 00086 0OOOE COORGHOOOO COOBE OOOO 00800 BOOGO BEEEG BG0EO 68000 00069 COGOE BOE08 00666 06006 0O66680080 66000 00006 86000 Seeae ooo es ¢ees adidas seeds sddes esdse 80068 O6OEO BGOOE BOE OG0OO0EEOO 80006 00006 08000 00008 00000 0000080808 HQ0E0 BO0O8 OECBG FO0OE O6O68 FOGEEEEEOE B0G00 BO8GE GEOGO OBECO GE98O BEEEEEEG06 GEG08 adadenaeae saddad Please shade your answer. (Continued) 8EG6 O8GE 0B00060006 666 8E008 GOECO 0000080808 000 BO0EO GBE80 OBOEBE00OS O68 06606 0600 BBGEGGEEEE 660 60660 08680 0066 OEOEO 0600000858 G0G08 88808 G00CO 0O8OO 00000 0008000080 80000 60660 06008 66006 6 OBEGOEOEEE 80088 68606 GEGGE GEEEE BEGGS GEOGEGEECE SC EAeee Sooke codes odes SHR eae Ree E SITES

Anda mungkin juga menyukai