All Electrical Installation work shall be carried out in accordance with the latest issues of the
relevant SPs, DEPs and PDO Standard Drawings along with Project Drawings as a minimum
requirement.
8.2 OHL (willow conductor) poles as per electrical drawing MUKH-02/15-003.This includes 1No.
D5A type pole as per PDO standard drawings STD-4-1326-001.
8.3 OHL pole number plates and OHL identification plate shall be supplied, inscribed and installed,
liaising with PDO electrical engineer required.
8.4 Install 2Nos. Transformers and one no. VSD panel foundations.
8.5
Install Step-down/up (step-down TX + step-up TX) transformer 33kV/415V & 415V/1100V
3300V on standard foundations.
8.6 Install VSD panel on standard foundation. Secure and grout the VSD panel. The panel opening
should face north to protect from sun light. Bolts to be supplied by contractor.
8.7 Install utility panel on the standard stand. Supply, fabricate and painting of the stand for utility
panel to be done by contractor.
8.8
Installation of cable protection tiles, back filling of the trench after cable laying, and
supply/installation of cable route markers is included in the scope.
8.9 Lay and terminate electrical cables and earth cables as per approved drawing MUKH-02/15-002.
8.10
Make use of existing rig earth nest to give a maximum resistance of 4 ohm. In case of more
4ohm resistance then additional pits MUST be drilled in consultation with OQE/32B.
8.11
Pre-rig-on activity on-pad hook-up: Cables shall be left insulated, coiled and buried safely at
ES-PCP end.
8.12 Trenches shall be well compacted after backfilling using a roller compacter.
8.13 Cable markers shall be in place to indicate cable routing.
8.14 Install earth nest to give maximum of 7ohms at D5A-type pole On first day after rig moves off
location and after location clean up, hand excavate for exposing buried cables.
9.

INSTRUMENTATION.

9.1 The instrumentation scope includes BS&W probe, D/P transmitter, RTU, pressure switch, pressure
gauges, wellhead JB, pressure transmitter, coriolis sensors, and RFTs. The work has to be
carried out as per PDO Standards, Specifications and Drawings.
9.2 Calibrate and install one 0-6000 kpa pressure gauge, three 0-6000 kpa pressure gauges, and 0-6000
kpa pressure gauge on the sonolog connection. Total Nos. of pressure gauges is 4. (0-6000 kpa).
9.3 Calibrate and install one pressure transmitter, one pressure switch, and one DP transmitter. Pressure
transmitter range shall be 0-4750 kpa, pressure switch setting shall be 4750 kpa and PDI range
shall be 0-50 kpa.
Note: All pressure settings to be confirmed with OQE/33B prior to commissioning.
9.4 Install two coriolis sensors and two RFTs at both diluent and production lines. Install one BS&W
meter at production line.
9.5 Use 2 PVC conduit for RTU RS-232 cables. Use flexible conduit between VSD and RTU. The
flexible conduit shall be supplied by contractor.
9.6 Use existing electrical cable trench from the VSD panel to venting box. Make sure electrical and
instrument cables are at least 750mm apart. Sand padding, cable protection tiles, back filling of
the trench after cable laying, and supply/installation of cable route markers is included in the
scope.

Page 2 of 2

Galfar Engineering & Contracting LLC

DESIGN FLOW LINE & H/UP FOR


ES-PCP WELL MUKHAIZNA-02/15

9.7 Excavate an instrument cable trench approx. 50m long from the coriolis up to wellhead. Sand
padding, cable protection tiles, back filling of the trench after cable laying and
supply/installation of cable route markers is included in the scope.
9.8 Lay and terminate instrument cable as per approved drawing MUKH-02/15-002.
9.9 Supply, fabricate and install junction box support for new junction box.
9.10

Collect new RTU Model EXS 1000-162-00 from stores and handover to SCADA Marmul for
configuration.

9.11

Install new RTU mounting support, foundation with sunshade.


NOTE: It shall be verified that there is no stress put upon the coriolis sensors from the pipe
spools. Sensors must be installed completely stress free in the piping. Cable ends shall be
insulated, coiled and buried at ES-PCP side. Trenches shall be properly compacted after
backfilling using a roller compacter. Cable markers shall be in place to indicate cable routing.
On first day after rig moves off location and after location clean up, expose buried instrument
cables.