GENERAL - This section will define the minimum design standards which the city
expects a developer, contractor, or homeowner to follow when they intend to build,
connect to, or maintain a section of the citys sanitary sewer distribution system.
1.02
DEFINITIONS
REFERENCES
1.05
SUBMITTALS
POLICIES
A. Design Regulations
1. All sanitary sewer systems shall be designed to exclude all storm water and
water from under drain systems, roofs, streets, and other paved areas.
2. Down spout connections, foundation and basement drains, sumps and storm
drain connections shall be prohibited from discharging into the sanitary sewer
system.
3. Each dwelling unit shall be served by an individual lateral. Stacked dwelling
units may be served by a common lateral of appropriate size.
4. There shall be no physical connection between a public or private potable water
supply system and a sewer, or other appurtenances thereto, which could permit
the passage of any wastewater or polluted water into the potable supply.
5. Sewers shall be laid at least ten feet horizontally from any existing or proposed
water main. Separation distances shall be measured pipe edge to pipe edge.
6. Where a water and sewer line must cross, the water main shall be at least 2 feet
above the sewer line measured from pipe edge to pipe edge.
7. Water mains and sewer lines shall not be installed in the same trench.
8. Sanitary sewer shall be designed to flow by gravity. Use of wastewater pumping
stations shall be avoided wherever possible and shall not be permitted within the
public sewer line.
B. Design Capacity - Design average flow shall be estimated at not less than 100
gallons per capita day, including infiltration at 200 gallons per diameter inch per mile
per day. To accommodate peak flows, sewers shall be designed, flowing full, to
City of West Jordan
**
**
A. Minimum Depth - Sewers shall be placed deep enough to serve all basements,
assuming a 2% grade on all service laterals (11 feet recommended). In areas of
shallow sewer, the following note shall be added to the subdivision plat: Shallow
Sewer Depths! Contractor to verify sewer depths before excavating for basement.
Home(s) with basement may not have sewer service available for basement.. The
City Utility Engineer may increase the proposed depth if required to meet system
requirements. 4 foot minimum depth to crown of pipe is required at all times in all
locations. The top of the sewer line shall be a minimum 2 feet lower than the bottom
of any water lines placed in the same street. Sewers at depths greater than 16 feet
shall be given special design considerations.
B. Minimum Line Size - All public sewer lines shall be 8 inches in diameter or larger.
C. Location Requirements - Sewer shall be located on the low side of streets,
preferably 5 feet from street center lines; and a minimum of 5 feet from the lip of
gutters. No other utilities shall be located parallel to sewer lines within 5 feet (either
side) of sewer main, measured pipe edge to pipe edge. Sewer mains shall be
extended to property lines as per City Utilities Engineer=s request to service future
development. Ten foot sewer stubs shall be extended beyond terminal manholes to
City of West Jordan
Minimum Slope in
Feet per 100
8"
0.40
10"
0.28
12"
0.22
15"
0.15
18"
0.12
21"
0.10
24"
0.08
E. Maximum slopes shall be 12 percent or less, and in no case shall the velocity
exceed 15 fps. All high slope, high velocity sewer lines shall be properly restrained
per state code.
F. Acceptable Pipe Materials - All Sewer lines in the City shall be constructed of either
Concrete, Plastic, or Ductile Iron pipes.
G. Pipe Transitions - At manholes, where sewer diameters change, the flow energy
gradient shall be continuous. The 0.8 depth point of the two sewers shall be placed
at the same elevation, with proper allowance for any manhole head loss or as
required to provide proper flow.
H. No plugged ends of sewer lines will be allowed. Manholes must be constructed at
the ends of sewer lines.
I. Pipe Construction - See PLAN SS-02 for pipe construction requirements.
1.08
A. Minimum Size - The following rules shall apply to all sanitary sewer manholes:
1. Manhole diameters shall be at least 48 inches in diameter.
2. Manholes on sewer lines 12 inches and greater shall be 60 inches in diameter.
City of West Jordan
LATERAL DESIGN
A. Tapping Requirements - Contractor shall not tap the existing sewer main using any
method other than core drilling with a water tight rubber seal at the nose on
connection to the City sewer main.
B. Size and Slope Requirements
1. The minimum lateral size shall be 4 inches.
2. A 6 inch sewer lateral may be constructed at a minimum slope of 1 percent.
3. A 4 inch sewer lateral shall be constructed at a minimum slope of 2 percent.
C. Location - Sewer laterals shall tie directly into manholes in cul-de-sacs and at dead
end manholes. Sewer laterals may tie directly into manholes wherever possible and
practical.
D. Responsibility - The city does not assume responsibility for sewer laterals. It is the
responsibility of the home or business owner to construct, maintain, and operate any
and all sewer lateral service connections.
E. Construction - See PLAN SS-10 for Sewer Lateral construction requirements.
1.010 CLEAN-OUT REQUIREMENTS
way, access easements shall be provided for maintenance purposes and shall
be a consistent width of 20 feet the entire length of the easement.
7. All easements shall be submitted and approved by the City Engineer, or his
designee, before Final development approval shall be granted.
D. Boring
1. Boring under canals, pipelines, water courses shall be steel encased, or other
material as approved by the Utilities Engineer.
2. Minimum clearance between casing and other utilities shall be 18 inches, unless
otherwise approved by the Utilities Engineer.
End of Section