Deliverability Tests
CONTENTS
5.1
5.2
5.3
5.4
5.5
5.6
5.7
Radius of investigation
Time to stabilization
Introduction to Deliverability Testing
Flow-after-flow tests
Isochronal tests
Modified Isochronal tests
Classifications, limitations, & use of Deliverability tests
Radius of Investigation
re = radius of reservoir boundary
ri = radius of investigation
rw = radius of wellbore
Radius of Investigation
for rinv < re.
(4.65)
(4.66)
6
Time to Stabilization
Time to stabilization can be determined by
(4.63)
Example
Calculating Radius of Investigation
10
Flow-after-flow test
Isochronal test
11
Test Schematic
12
Flow-after-Flow Test
14
Flow-after-flow tests
The test is often referred to as a four-point test, because many
tests are composed of four flow rates, as required by various
regulatory bodies.
log ( 2 2 ) = log
1
log
y = mx +C
m = 1/n
16
Empirical Method
2
log (
2)
1
1
= log log
(4.30)
18
Theoretical Methods
Deliverability equations based on theoretical methods are :
2. Pressure-squared technique
19
Example 5-1
Stabilized Flow Test Analysis
20
pR =
(pR)2
201 psia
40401 psia2
Test
qsc
(mscfd)
2,730
3,970
4,440
5,550
1
2
3
4
pwf
(psia)
196
195
193
190
(pwf)2
(psia2)
38,416
38,025
37,249
36,100
(pR)2 - (pwf)2
(psia2)
1,985
2,376
3,152
4,301
21
pwf = 0
1,000
10,000
Flow Rate, qsc (mscfd)
AOF
100,000
23
Isochronal Test
- The flow-after-flow tests are very accurate but
take a long time to run specially for tight reservoir.
24
Isochronal Test
- The flow-after-flow tests are very accurate but
take a long time to run specially for tight reservoir.
-To speed up the testing process, the isochronal
tests were developed.
-Isochronal tests faster yet fairly accurate
25
Isochronal Test
Why Isochronal Tests are Quicker?
26
Isochronal Test
Shut in periods
are different
Pressure builds
Up to Pavg
28
Isochronal Test
A deliverability test designed as a series of drawdown
29
Isochronal Test
Flow the well at a fixed rates for a set period of time t,
noting the Pwf at several fixed time intervals t1, t2, t3, t4 etc.
Shut-in the well and wait until pressure is almost stabilize.
30
Example 5-2
Isochronal Test
An isochronal test was conducted on a well located in a
reservoir that had an average pressure P R of 1952 psia. The well
was flowed on four choke sizes, and the flow rate and flowing
bottom-hole pressure were measured at 3 hr and 6 hr for each
choke size. An extended test was conducted for a period of 72 hr
at a rate of 6.0 MMscfd, at which time pwf was measured at 1151
psia. Using the data in Table 5-2.
The slopes of both the 3-hr and 6-hr lines are apparently equal.
(see Fig. 5-4). Use the first and last points on the 6-hr test to
calculate n from Eqn. gives.
31
32
33
Solution
1. Given the data in Table 4-2, the deliverability equation for qsc in
mscfd is
35
Why Needed?
In normal isochronal test, time for pressure
to build up to during shut-in may be
impractically long.
Modified isochronal test shortens test times
because well does not build up to average
reservoir pressure after each flow period
Test Procedure
Conducted like an isochronal test, except the
shut-in periods are shorter and of equal
duration.
The shut-in periods should equal or exceed the
length of the flow periods.
A final stabilized flow point usually is obtained
at the end of the test but is not required for
analyzing the test data.
Wellhead Deliverability
In practice it is sometimes more convenient to measure the
pressures at the wellhead.
Classifications, Limitations,
and Use of Deliverability Tests
This may be known directly from previous tests, such as drillstem or deliverability tests, conducted on the well or from the
production characteristics of the well.
If such information is not available, it may be assumed that
the well will behave in a manner similar to neighbouring
wells in the same pool, for which data are available.
Time to stabilization may be estimated using Equation (4.63).
46
Classifications, Limitations,
and Use of Deliverability Tests
If time to stabilization is of the order of few hours, flow-afterflow test may be conducted.
Otherwise, one of the isochronal tests is preferable.
47
49
Thank You
50
Q&A
51