D)
V100R009C00
Installation Guide
Issue
03
Date
2014-08-30
Notice
The purchased products, services and features are stipulated by the contract made between Huawei and the
customer. All or part of the products, services and features described in this document may not be within the
purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information,
and recommendations in this document are provided "AS IS" without warranties, guarantees or representations
of any kind, either express or implied.
The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but all statements, information, and
recommendations in this document do not constitute a warranty of any kind, express or implied.
Website:
http://www.huawei.com
Email:
support@huawei.com
Issue 03 (2014-08-30)
BTS3900(Ver.D)
Installation Guide
Product Version
The following table lists the product versions related to this document.
Product Name
Solution Version
Product Version
BTS3900
l SRAN9.0
V100R009C00
l GBSS16.0
l RAN16.0
l eRAN7.0
Intended Audience
This document is intended for:
l
Organization
1 Changes in BTS3900 (Ver.D) Installation Guide
This chapter describes the changes in BTS3900 (Ver.D) Installation Guide.
2 Overview
Familiarize yourself with this information as well as the cabinet interior, application scenarios
of the cabinets, and relevant clearance requirements before installing the cabinets.
3 Installation Preparations
Issue 03 (2014-08-30)
ii
BTS3900(Ver.D)
Installation Guide
This chapter lists the tools and instruments that must be obtained before the installation. It also
specifies the skills that the onsite personnel must have.
4 Unpacking Check
Unpack and check the delivered equipment to ensure that all the materials are included and intact.
5 Obtaining the ESN
The electronic serial number (ESN) is a unique identifier of a NE. Record the ESN of the base
station before the installation for future commissioning.
6 Installation Process
Before the BTS3900 cabinets are delivered, boards inside the cabinets have been installed. You
only need to install the cabinet and cables onsite. Some optional components may also need to
be installed based on onsite requirements.
7 Checking Installed Modules and Cables
Modules and cables in the cabinet have been installed before delivery. You need to check whether
the modules and cables are installed securely.
8 Installing a Base
A BTS3900 cabinet can be installed on a base. The base can be installed either on a concrete
floor or ESD floor according to the equipment room conditions and customer's requirements.
9 Installing the Cabinet
A BTS3900 cabinet can be installed alone, side by side with another BTS3900 cabinet, or stacked
on another BTS3900 cabinet. This section describes the procedure for installing the BTS3900
(Ver.D) cabinets in the preceding modes. The procedures for installing the BTS3900(Ver.B),
BTS3900(Ver.C), and BTS3900(Ver.D) cabinets are the same.
10 Installing a PGND Cable and an Equipotential Cable
A PGND cable connects a PGND screw in a cabinet and a PGND bar to ensure proper grounding
of the cabinet. An equipotential cable connects PGND screws on different cabinets to ensure the
equipotential bonding between the cabinets.
11 Installing Optional Modules and Their Cables
This chapter describes procedures for installing the optional modules and their cables onsite.
12 Installing Cables
Before cabinets are delivered, the boards and cables inside the cabinets have been installed. You
must install the external cables and cables for optional components onsite.
13 Installation Checklist
After the cabinets and devices are installed, you need to check the installation items, installation
environment, and cable-related items.
14 Powering On a Base Station
This section describes how to power on a base station and handle a failure in the power supply
to the components in a cabinet.
Issue 03 (2014-08-30)
iii
BTS3900(Ver.D)
Installation Guide
Conventions
Symbol Conventions
The symbols that may be found in this document are defined as follows.
Symbol
Description
Indicates an imminently hazardous situation which, if not
avoided, will result in death or serious injury.
Indicates a potentially hazardous situation which, if not
avoided, could result in death or serious injury.
Indicates a potentially hazardous situation which, if not
avoided, may result in minor or moderate injury.
Indicates a potentially hazardous situation which, if not
avoided, could result in equipment damage, data loss,
performance deterioration, or unanticipated results.
NOTICE is used to address practices not related to personal
injury.
Calls attention to important information, best practices and
tips.
NOTE is used to address information not related to personal
injury, equipment damage, and environment deterioration.
General Conventions
The general conventions that may be found in this document are defined as follows.
Convention
Description
Boldface
Italic
Courier New
Command Conventions
The command conventions that may be found in this document are defined as follows.
Issue 03 (2014-08-30)
iv
BTS3900(Ver.D)
Installation Guide
Convention
Description
Boldface
Italic
[]
{ x | y | ... }
[ x | y | ... ]
{ x | y | ... }*
[ x | y | ... ]*
GUI Conventions
The GUI conventions that may be found in this document are defined as follows.
Convention
Description
Boldface
>
Keyboard Operations
The keyboard operations that may be found in this document are defined as follows.
Format
Description
Key
Press the key. For example, press Enter and press Tab.
Key 1+Key 2
Key 1, Key 2
Mouse Operations
The mouse operations that may be found in this document are defined as follows.
Issue 03 (2014-08-30)
BTS3900(Ver.D)
Installation Guide
Issue 03 (2014-08-30)
Action
Description
Click
Double-click
Drag
Press and hold the primary mouse button and move the
pointer to a certain position.
vi
BTS3900(Ver.D)
Installation Guide
Contents
Contents
About This Document.....................................................................................................................ii
1 Changes in BTS3900 (Ver.D) Installation Guide....................................................................1
2 Overview.........................................................................................................................................3
2.1 Components of BTS3900 Cabinets................................................................................................................................4
2.2 BTS3900 (Ver.D) Configured with RFUs but Without RRUs.....................................................................................10
2.3 BTS3900 (Ver.D) Configured with RFUs and RRUs..................................................................................................15
2.4 Installation Clearance and Layout Requirements.........................................................................................................21
3 Installation Preparations............................................................................................................25
3.1 Documents....................................................................................................................................................................26
3.2 Tools and Instruments..................................................................................................................................................26
3.3 Requirements for Onsite Personnel..............................................................................................................................27
4 Unpacking Check........................................................................................................................28
5 Obtaining the ESN......................................................................................................................30
6 Installation Process.....................................................................................................................32
7 Checking Installed Modules and Cables................................................................................34
7.1 Checking a BTS3900 DC Cabinet................................................................................................................................35
7.2 Checking a BTS3900 AC Cabinet................................................................................................................................37
8 Installing a Base...........................................................................................................................42
8.1 Installing a Base on the Concrete Floor........................................................................................................................43
8.2 Installing the Base on the ESD Floor...........................................................................................................................47
vii
BTS3900(Ver.D)
Installation Guide
Contents
12 Installing Cables......................................................................................................................109
12.1 Cabling Requirements..............................................................................................................................................110
12.2 Cable Holes...............................................................................................................................................................116
12.3 Installing Power Cables............................................................................................................................................120
12.3.1 Installing Power Cables for AC Cabinets..............................................................................................................120
12.3.2 Installing Power Cables for DC Cabinets..............................................................................................................131
12.4 Installing Transmission Cables.................................................................................................................................137
12.4.1 Installing the E1/T1 Cables...................................................................................................................................137
12.4.2 Installing the FE/GE Ethernet Cables....................................................................................................................139
12.4.3 Installing FE/GE Fiber Optic Cables.....................................................................................................................140
12.5 Installing Signal Cables............................................................................................................................................142
12.5.1 (Optional) Installing a Monitoring Signal Cable Between Cascaded FAN 03C Assemblies................................142
12.5.2 (Optional) Installing Inter-BBU Signal Cables.....................................................................................................144
12.5.3 Installing a BBU Alarm Cable...............................................................................................................................148
12.6 Installing RF Jumpers...............................................................................................................................................149
12.7 (Optional) Installing CPRI Electrical Cables...........................................................................................................151
12.8 (Optional) Installing CPRI Fiber Optic Cables........................................................................................................154
13 Installation Checklist..............................................................................................................158
14 Powering On a Base Station..................................................................................................161
Issue 03 (2014-08-30)
viii
BTS3900(Ver.D)
Installation Guide
03 (2014-08-30)
This is the third commercial release.
Compared with Issue 02 (2014-07-30), this issue includes the following changes.
Topic
Change Description
02 (2014-07-30)
This is the second commercial release.
Compared with Issue 01 (2014-04-30), this issue includes the following changes.
Topic
Change Description
01 (2014-04-30)
This is the first commercial release.
Compared with issue draft B (2014-02-28), no information is changed.
Draft B (2014-02-28)
This is a draft.
Issue 03 (2014-08-30)
BTS3900(Ver.D)
Installation Guide
Change Description
Draft A (2014-01-20)
This is a draft.
Compared with the issues for the multimode base station version V100R008C00 and the singlemode base station versions WCDMA-NodeB V200R015C00, GSM-BTS V100R015C00, and
eNodeB V100R006C00, this issue includes the following new information:
l
Compared with the issues for the multimode base station version V100R008C00 and the singlemode base station versions WCDMA-NodeB V200R015C00, GSM-BTS V100R015C00, and
eNodeB V100R006C00, this issue includes the following changes.
Topic
Change Description
Compared with the issues for the multimode base station version V100R008C00 and the singlemode base station versions WCDMA-NodeB V200R015C00, GSM-BTS V100R015C00, and
eNodeB V100R006C00, no topic is deleted from this issue.
Issue 03 (2014-08-30)
BTS3900(Ver.D)
Installation Guide
2 Overview
Overview
Issue 03 (2014-08-30)
BTS3900(Ver.D)
Installation Guide
2 Overview
Issue 03 (2014-08-30)
No.
Compo
nent
Optional/
Mandator
y
Maximum
Quantity
in a Single
Cabinet
Remarks
RFU
filler
panel
Optional
BTS3900(Ver.D)
Installation Guide
2 Overview
No.
Compo
nent
Optional/
Mandator
y
Maximum
Quantity
in a Single
Cabinet
Remarks
RFU
Mandatory
Issue 03 (2014-08-30)
FAN
Mandatory
Filler
panel for
the air
intake
vent
Mandatory
BBU
Mandatory
DCDU01
Mandatory
Transmi
ssion
equipme
nt
Optional
EPS24S
48100D
C
Mandatory
EPS489
0
Mandatory
BTS3900(Ver.D)
Installation Guide
2 Overview
NOTE
A BTS3900 -48 V DC cabinet can feed power into the customer's transmission equipment. The customer
equipment is able to work with an ambient temperature of 55oC or higher.
Issue 03 (2014-08-30)
No.
Compo
nent
Optional/
Mandator
y
Maximum
Quantity
in a Single
Cabinet
Remarks
RFU
filler
panel
Optional
BTS3900(Ver.D)
Installation Guide
2 Overview
No.
Compo
nent
Optional/
Mandator
y
Maximum
Quantity
in a Single
Cabinet
Remarks
RFU
Mandatory
FAN
03B
Mandatory
Filler
panel for
the air
intake
vent
Mandatory
BBU
Mandatory
DCDU11A
Mandatory
Transmi
ssion
equipme
nt
Optional
ETP481
50-A3
Mandatory
NOTE
A BTS3900 -48 V DC cabinet can feed power into the customer's transmission equipment. The customer
equipment is able to work with an ambient temperature of 55oC or higher.
Issue 03 (2014-08-30)
BTS3900(Ver.D)
Installation Guide
2 Overview
Issue 03 (2014-08-30)
No.
Compo
nent
Optional/
Mandator
y
Maximum
Quantity
in a Single
Cabinet
Remarks
RFU
filler
panel
Optional
BTS3900(Ver.D)
Installation Guide
2 Overview
No.
Compo
nent
Optional/
Mandator
y
Maximum
Quantity
in a Single
Cabinet
Remarks
RFU
Mandatory
FAN
03C
Mandatory
Filler
panel for
the air
intake
vent
Mandatory
BBU
Mandatory
Issue 03 (2014-08-30)
DCDU12A
Mandatory
BBU
Optional
DCDU12B
Optional
Transmi
ssion
equipme
nt
Optional
BTS3900(Ver.D)
Installation Guide
2 Overview
No.
Compo
nent
Optional/
Mandator
y
Maximum
Quantity
in a Single
Cabinet
Remarks
10
Filler
panel
Optional
11
PSU
(R4850
G2)
Mandatory
12
PMU
11A
Mandatory
13
EPU05A
-02
Subrack
Mandatory
NOTE
A BTS3900 -48 V DC cabinet can feed power into the customer's transmission equipment. The customer
equipment is able to work with an ambient temperature of 55oC or higher.
Issue 03 (2014-08-30)
10
BTS3900(Ver.D)
Installation Guide
2 Overview
Sce
nar
io
Nu
mb
er
of
BB
Us
Application
Mode
Maxim
um
Numbe
r of RF
Module
s
Illustration
Applicable Cabinet
Sin
gle
cabi
net
Single-, dual-,
quadruple-, and
triple-mode
base stations
6 RFUs
The application
scenarios are
shown by
illustrations 1 and
2 in Figure 2-4.
l One BTS3900 DC
cabinet
Triple- and
quadruplemode base
station
6 RFUs
The application
scenarios are
shown by
illustrations 3 and
4 in Figure 2-4.
Cab
inet
s
inst
alle
d
side
by
side
Single-, dual-,
quadruple-, and
triple-mode
base stations
12 RFUs
The application
scenarios are
shown by
illustrations 1 and
2 in Figure 2-5.
Triple- and
quadruplemode base
station
12 RFUs
The application
scenarios are
shown by
illustrations 3 and
4 in Figure 2-5.
Stac
ked
cabi
nets
Single-, dual-,
quadruple-, and
triple-mode
base stations
12 RFUs
The application
scenario is shown
by illustration 1
in Figure 2-6.
Triple- and
quadruplemode base
station
12 RFUs
The application
scenario is shown
by illustration 2
in Figure 2-6.
l One BTS3900 AC
cabinet
l Two BTS3900 DC
cabinets
l 1 BTS3900 AC cabinet
+1 BTS3900 DC cabinet
NOTE
l A BTS3900 cabinet is configured with one BBU by default and can be configured with a maximum of
two BBUs whose power consumption cannot exceed 1000 W. This principle applies to new site
deployment or capacity expansion.
l When cabinets are installed side by side or stacked, it is recommended that BBU 1 and BBU 0 be
installed in the same cabinet.
l One BTS3900 AC cabinet consists of one BTS3900 DC cabinet and one IMS06.
Issue 03 (2014-08-30)
11
BTS3900(Ver.D)
Installation Guide
2 Overview
Issue 03 (2014-08-30)
12
BTS3900(Ver.D)
Installation Guide
2 Overview
Issue 03 (2014-08-30)
13
BTS3900(Ver.D)
Installation Guide
2 Overview
Issue 03 (2014-08-30)
Scenario
Num
ber of
BBUs
Applic
ation
Mode
Maximum
Number of
RF
Modules
Illustration
Description
1 BTS3900
AC cabinet+1
BTS3900 DC
cabinet+1
IMS06
Triplemode
base
station
12 RFUs
The application
scenario is
shown by
illustration 1 in
Figure 2-7.
1 BTS3900
AC cabinet+1
IMS06
Triplemode
base
station
6 RFUs
The application
scenario is
shown by
illustration 2 in
Figure 2-7.
14
BTS3900(Ver.D)
Installation Guide
2 Overview
NOTICE
The IMS06 cannot be stacked on the BTS3900 cabinet. Otherwise, the heat dissipation holes on
the top of the BTS3900 cabinet will be blocked.
NOTE
When an IMS06 is configured with storage batteries, the power consumption of a BTS3900 cannot exceed
10,000 W. If the power consumption exceeds 10,000 W, large-capacity battery packs need to be added.
15
BTS3900(Ver.D)
Installation Guide
2 Overview
Sce
nar
io
Nu
mb
er
of
BB
Us
Application
Mode
Maximum
Number of
RF Modules
Illustration
Applicable
Cabinet
Sin
gle
cabi
net
Single-,
dual-, triple-,
and
quadruplemode base
stations
6 RFUs+6
RRUs
l One BTS3900
DC cabinet
Triple- and
quadruplemode base
stations
6 RFUs+9
RRUs
Cab
inet
s
inst
alle
d
side
by
side
Single-,
dual-, triple-,
and
quadruplemode base
stations
12 RFUs+6
RRUs
Triple- and
quadruplemode base
stations
12 RFUs+9
RRUs
Stac
ked
cabi
nets
Single-,
dual-, triple-,
and
quadruplemode base
stations
12 RFUs+6
RRUs
Triple- and
quadruplemode base
stations
12 RFUs+9
RRUs
l One BTS3900
AC cabinet
Two BTS3900
DC cabinets
When a BTS3900 (Ver.D) is configured with RFUs and RRUs, a DCDU-12B is installed in the
BTS3900 cabinet to distribute power to RRUs.
Issue 03 (2014-08-30)
16
BTS3900(Ver.D)
Installation Guide
2 Overview
Issue 03 (2014-08-30)
17
BTS3900(Ver.D)
Installation Guide
2 Overview
Figure 2-11 Two BTS3900 DC cabinets installed side by side (one BBU)
Issue 03 (2014-08-30)
18
BTS3900(Ver.D)
Installation Guide
2 Overview
Figure 2-12 Two BTS3900 DC cabinets installed side by side (two BBUs)
Issue 03 (2014-08-30)
19
BTS3900(Ver.D)
Installation Guide
2 Overview
Num
ber of
BBUs
Applic
ation
Mode
Maximum
Number of
RF
Modules
Illustration
Description
1 BTS3900
AC+1 IMS06
Tripleand
quadrupl
e-mode
base
stations
6 RFUs+9
RRUs
Figure 2-13
shows the
application
scenario.
An IMS06 houses
100 Ah storage
batteries, which
provide lowcapacity backup
power.
NOTICE
The IMS06 cannot be stacked on the BTS3900 cabinet. Otherwise, the heat dissipation holes on
the top of the BTS3900 cabinet will be blocked.
Issue 03 (2014-08-30)
20
BTS3900(Ver.D)
Installation Guide
2 Overview
NOTE
When an IMS06 is configured with storage batteries, the power consumption of a BTS3900 cannot exceed
10,000 W. If the power consumption exceeds 10,000 W, large-capacity battery packs need to be added.
A BTS3900 DC cabinet can be installed with its rear flush against a wall, whereas a
minimum of 100 mm (3.94 in.) space must be reserved behind the rear of a BTS3900 AC
cabinet.
The left side of the cabinet can be against a wall. Reserve a minimum of 300 mm (11.81
in.) clearance on the right side for installing noise reduction modules later.
Retain a minimum of 800 mm (31.50 in.) in front of the cabinet for maintenance.
Retain a minimum of 200 mm (7.87 in.) between the top of the cabinet and the ceiling for
cabling.
Issue 03 (2014-08-30)
21
BTS3900(Ver.D)
Installation Guide
2 Overview
The following figure shows the clearance requirements of cabinets in the following installation
scenarios: a single cabinet is installed alone, two cabinets are installed side by side, or two
cabinets are stacked.
Figure 2-16 Clearance requirements for a BTS3900 DC cabinet
Issue 03 (2014-08-30)
22
BTS3900(Ver.D)
Installation Guide
2 Overview
Layout Requirements
Layout requirements of BTS3900 cabinets are as follows:
l
Install the cabinets at a position nearest to the feeder window to minimize the feeder length.
Install the cabinets in one row in one equipment room to facilitate cabling.
No space is required between cabinets and user equipment in the same row.
Issue 03 (2014-08-30)
23
BTS3900(Ver.D)
Installation Guide
2 Overview
Issue 03 (2014-08-30)
24
BTS3900(Ver.D)
Installation Guide
3 Installation Preparations
Installation Preparations
Issue 03 (2014-08-30)
25
BTS3900(Ver.D)
Installation Guide
3 Installation Preparations
3.1 Documents
Before the installation, obtain the following documents:
Before the installation, obtain the following documents:
l
Safety Precautions
Installation Reference
A BTS3900 (Ver.D) cabinet can be stacked on an IMS06, thereby meeting power distribution
and transmission requirements. For details, see the following document:
l
Marker
Diagonal pliers
Issue 03 (2014-08-30)
32 mm (1.26 in.)
combination wrench
Socket wrench
Torque wrench
Cable cutter
Rubber mallet
Soldering iron
Wire stripper
26
BTS3900(Ver.D)
Installation Guide
3 Installation Preparations
Heat gun
Level
Multimeter
Measuring tape
Vacuum cleaner
ESD gloves
Torque screwdriver
Gloves
Utility knife
Hydraulic pliers
Torx screwdriver
The customer's technical engineers must be trained by Huawei and be familiar with the
proper installation and operation methods.
The number of onsite personnel depends on the engineering schedule and installation
environment. Generally, three to five onsite personnel are necessary.
Issue 03 (2014-08-30)
27
BTS3900(Ver.D)
Installation Guide
4 Unpacking Check
Unpacking Check
Unpack and check the delivered equipment to ensure that all the materials are included and intact.
Context
CAUTION
The gravity center of some cabinets is in the front, for example, the BTS3900AL, IBBS700T
and IBBS300T . Therefore, avoid toppling of the cabinet when the door of the cabinet is opened,
especially when you unpack the cabinet or before it has been secured onto a base.
NOTICE
l Power on a cabinet or BBU within seven days after unpacking it.
l Power on an RRU within 24 hours after unpacking it.
NOTE
When transporting, moving, or installing the equipment, components, or parts, you must:
l
Prevent them from colliding with doors, walls, shelves, or other objects.
Wear clean gloves, and avoid touching the equipment, components, or parts with bare hands, sweatsoaked gloves, or dirty gloves.
Procedure
Step 1 Check the total number of articles in each case according to the packing list.
Issue 03 (2014-08-30)
28
BTS3900(Ver.D)
Installation Guide
4 Unpacking Check
If...
Then...
Go to Step 2.
Then...
Go to Step 3.
The outer packing is severely damaged or Find out the cause and report the situation to
soaked
the local Huawei office.
Step 3 Check the type and quantity of the equipment in the cases according to the packing list.
If...
Then...
Types and quantity of the articles tally with Sign the Packing List with the customer.
those on the packing list
There are any goods missing, incorrectly
delivered, or damaged
CAUTION
To protect the equipment and prevent damage to the equipment, you are advised to keep the
unpacked equipment and packing materials indoors, take photos of the stocking environment,
packing case or carton, packing materials, and any rusted or eroded equipment, and then file the
photos.
----End
Issue 03 (2014-08-30)
29
BTS3900(Ver.D)
Installation Guide
The electronic serial number (ESN) is a unique identifier of a NE. Record the ESN of the base
station before the installation for future commissioning.
Procedure
Step 1 Record the ESN on the BBU.
l If there is no label on the FAN unit of the BBU, the ESN is printed on a mounting ear of the
BBU, as shown in Figure 5-1. Record the ESN and base station information.
l If there is a label on the FAN unit of the BBU, the ESN is printed on the label and a mounting
ear of the BBU, as shown in Figure 5-2. Remove the label and record the base station
information on the label printed with Site.
NOTE
The base station information includes the name, ID, and location of the base station.
Issue 03 (2014-08-30)
30
BTS3900(Ver.D)
Installation Guide
Step 2 Report the ESN and base station information to the base station commissioning personnel or
remove the label and give it to the base station commissioning personnel.
NOTE
For base stations configured with multiple BBUs, record the ESNs on all BBUs and submit them to the
personnel responsible for the base station commissioning.
----End
Issue 03 (2014-08-30)
31
BTS3900(Ver.D)
Installation Guide
6 Installation Process
Installation Process
Before the BTS3900 cabinets are delivered, boards inside the cabinets have been installed. You
only need to install the cabinet and cables onsite. Some optional components may also need to
be installed based on onsite requirements.
The following figure shows the installation process.
Issue 03 (2014-08-30)
32
BTS3900(Ver.D)
Installation Guide
6 Installation Process
Issue 03 (2014-08-30)
33
BTS3900(Ver.D)
Installation Guide
Issue 03 (2014-08-30)
34
BTS3900(Ver.D)
Installation Guide
Procedure
Step 1 Verify that the modules are installed securely in the cabinet and all screws are tightened.
Step 2 Check whether the power cables in the cabinet are routed correctly and connected securely
according to the following figure and table.
Figure 7-1 Power cables installed in the cabinet
P0 to
P5
Issue 03 (2014-08-30)
Cable
RFU power
cables
One End
Connector
Installation
Position
Connector
Installation
Position
3V3 connector
PWR port on
an RFU
EPC4
connector
LOAD0 to
LOAD5 ports
on the
DCDU-12A
35
BTS3900(Ver.D)
Installation Guide
No.
Cable
One End
Connector
Installation
Position
Connector
Installation
Position
P6
FAN 03C
power cable
3V3 connector
-48V port on
the FAN 03C
EPC4
connector
LOAD6 port
on the
DCDU-12A
P7 and
P8
BBU power
cables
3V3 connector
-48V port on
the UPEU
EPC4
connector
LOAD7 and
LOAD8 ports
on the
DCDU-12A
Step 3 Check whether the signal cables in the cabinet are routed correctly and connected securely
according to the following figure and table.
Figure 7-2 Signal cables installed in the cabinet
Issue 03 (2014-08-30)
36
BTS3900(Ver.D)
Installation Guide
Cable
One End
Connector
Installation
Position
Connector
Installation
Position
S1
ELU signal
cable
RJ45
connector
SENSOR port
on the FAN
03C
RJ45
connector
ELU
S2
FMUEABBU
monitoring
signal cable
RJ45
connector
COM_IN port
on the FAN
03C
RJ45
connector
MON0 port on
the UPEU
NOTE
If no BBU is
installed in the
cabinet, this
cable should
be bound to
the right side
of the cabinet.
Step 4 Check that the CPRI cables in the cabinet are routed correctly and connected securely. For details
about how to connect and disconnect CPRI cables, see Inserting and Removing CPRI Cables.
----End
Procedure
Step 1 Check whether the modules are installed securely in the cabinet, and tighten any loose screw.
Step 2 Check that the equipotential cables are installed securely, the power cables are correctly
connected, and the screws are tightened according to the following table and figure.
Issue 03 (2014-08-30)
37
BTS3900(Ver.D)
Installation Guide
Figure 7-3 Equipotential cables and power cables installed inside the cabinet
Table 7-3 Equipotential cables and power cables installed inside the cabinet
No.
Issue 03 (2014-08-30)
Cable
One End
Connector
Installation
Position
Connector
Installation
Position
P0 to
P5
RFU power
cable
3V3 connector
PWR port on
an RFU
EPC4
connector
One of the
LOAD0 to
LOAD5 ports
on the
DCDU-12A
P6
FAN 03C
power cable
3V3 connector
-48V port on
the FAN 03C
EPC4
connector
LOAD6 port
on the
DCDU-12A
38
BTS3900(Ver.D)
Installation Guide
No.
Cable
One End
Connector
Installation
Position
Connector
Installation
Position
P7 and
P8
BBU power
cable
3V3 connector
-48V port on
the UPEU
EPC4
connector
LOAD7 and
LOAD8 ports
on the
DCDU-12A
P9 and
P10
DCDU-12A
power cable
OT terminal
(M6)
RTN(+) and
NEG(-)
terminals on
the
DCDU-12A
OT terminal
(M6)
RTN(+) and
NEG(-)
terminals near
RFC_1 and
RFC_2 on the
EPU05A-02
G0
Equipotentia
l cable
between the
BTS3900
and IMS06
OT terminal
(M6)
Ground bar in
the BTS3900
cabinet
OT terminal
(M6)
Ground bar in
the IMS06
G1
Equipotentia
l cable
between the
EPU and
IMS06
OT terminal
(M6)
Ground bar in
the EPU
OT terminal
(M6)
Ground bar in
the IMS06
Step 3 Check that the signal cables are installed securely and the screws are tightened according to the
following table and figure.
Issue 03 (2014-08-30)
39
BTS3900(Ver.D)
Installation Guide
S1
Issue 03 (2014-08-30)
Cable
ELU signal
cable
One End
Connector
Installation
Position
Connector
Installation
Position
RJ45
connector
SENSOR port
on the FAN
03C
RJ45
connector
ELU
40
BTS3900(Ver.D)
Installation Guide
No.
S2
S3
Cable
One End
Connector
Installation
Position
Connector
Installation
Position
FMUEABBU
monitoring
signal cable
RJ45
connector
COM_IN port
on the FAN
03C
RJ45
connector
MON0 port on
the UPEU
PMU 11ABBU
monitoring
signal cable
RJ45
connector
MON1 port on
the UPEU in
the BBU of
the BTS3900
cabinet
RJ45
connector
NOTE
If no BBU is
installed in the
cabinet, bind
the
monitoring
signal cable
for the fan
assembly on
the right side
of the cabinet.
COM_IN port
on the PMU
11A in the
EPU05A-02
Step 4 Check whether the CPRI cables in the cabinet are routed correctly and connected securely. For
details about how to install and remove the CPRI cables, see Inserting and Removing CPRI
Cables.
----End
Issue 03 (2014-08-30)
41
BTS3900(Ver.D)
Installation Guide
8 Installing a Base
Installing a Base
Issue 03 (2014-08-30)
42
BTS3900(Ver.D)
Installation Guide
8 Installing a Base
Procedure
Step 1 Determine the holes for installing the cabinet according to the positioning holes on the markingoff template, as shown in the following figure.
Figure 8-1 Positioning the base
Step 2 Drill holes at the anchor points and insert expansion bolt assemblies in the holes, as shown in
the following figure.
Issue 03 (2014-08-30)
43
BTS3900(Ver.D)
Installation Guide
8 Installing a Base
1.
Use a hammer drill with a 16 drill bit to drill holes with a depth ranging from 55 mm
(2.17 in.) to 60 mm (2.36 in.).
CAUTION
Take proper safety measures to protect your eyes and respiratory tract against the dust
before drilling holes.
NOTE
Generally, the concrete floor is solid and smooth. Therefore, you can use the center punch to help
locate the drill bit. If the conditions of the floor allow direct drilling, skip this step.
2.
Use a vacuum cleaner to clear the dust out from inside and around the holes, and measure
the distances between holes. If any of the hole is beyond the acceptable range, mark a new
anchor point and drill a new hole.
3.
Tighten an expansion bolt slightly and place it vertically into each hole.
4.
Hit the expansion bolt with a rubber mallet until the expansion tube completely enters the
hole.
5.
Remove the M12x60 bolt, spring washer, and flat washer in sequence.
Issue 03 (2014-08-30)
44
BTS3900(Ver.D)
Installation Guide
8 Installing a Base
CAUTION
After dismantling the expansion bolt assembly, ensure that the top of the expansion tube
is level with the concrete floor. Otherwise, the cabinet cannot be installed on the concrete
floor evenly and securely.
Step 3 Install the base and level it.
1.
Place the insulation plate and the base on the floor in sequence. Align holes on the base
with those on the insulation plate and those for inserting expansion bolt assemblies on the
floor. Insert four M12x60 expansion bolts into the holes, and partially tighten them, as
shown in the following figure.
Figure 8-3 Preinstalling the base on the floor
2.
Issue 03 (2014-08-30)
45
BTS3900(Ver.D)
Installation Guide
8 Installing a Base
3.
(2) Level
Use a socket wrench to fasten the M12x60 bolts in a diagonal sequence to secure the base
on the floor, and tighten the bolts to 45 Nm (398.25 lbfin.), as shown in the following
figure.
Figure 8-5 Securing the base on the floor
Step 4 Measure the insulation between the base and expansion bolts.
1.
2.
Measure the resistance between the leveling bolt and the expansion bolt, as shown in the
following figure.
Figure 8-6 Measuring the resistance between the leveling bolt and the expansion bolt
Issue 03 (2014-08-30)
46
BTS3900(Ver.D)
Installation Guide
8 Installing a Base
l If the resistance is lower than 5 megohms, the base is not insulated from the ground.
Go to Step 4.3.
l If the resistance is higher than 5 megohms, the base is insulated from the ground.
3.
Remove the expansion bolt assemblies and check whether the insulation washers are
missing or damaged.
l If yes, reinstall the expansion bolt assemblies and re-level the base.
l If no, check whether the multimeter works properly and whether the setting is correct.
----End
Context
The following figure shows the support for installing the ESD floor.
Figure 8-7 Support for installing the ESD floor
There are three models of ESD floor supports, all of which are adjustable. The heights of ESD
floors supported by the three models are listed in the following table.
Issue 03 (2014-08-30)
47
BTS3900(Ver.D)
Installation Guide
8 Installing a Base
Applicable Height
Remark
Model I
Model II
Model III
NOTE
The height of an ESD floor is the spacing between the concrete floor and the upper surface of the ESD
floor.
Procedure
Step 1 Determine the installation position for the base on the ESD floor. For details, see Installing a
Base on the Concrete Floor stepStep 1.
Step 2 Drill holes on the ESD floor.
1.
Use a hammer drill with bit 16 to drill holes at the anchor points. The holes should penetrate
the ESD floor, as shown in the following figure.
Figure 8-8 Drilling a hole on the ESD floor
Issue 03 (2014-08-30)
48
BTS3900(Ver.D)
Installation Guide
8 Installing a Base
CAUTION
Take proper safety measures to protect your eyes and respiratory tract against the dust
before drilling holes.
2.
Use a vacuum cleaner to clear the dust inside and around the holes. If the inter-hole spacing
is too wide or too narrow, locate and drill holes again.
Place the support under the ESD floor. Use bolts to fix the support to the ESD floor
temporarily, as shown in the following figure.
Figure 8-9 Fixing the support to the ESD floor
2.
Issue 03 (2014-08-30)
(2) ESD floor (3) Mounting holes for the concrete floor
Use a ruler to measure the distance between the concrete floor and the lower surface of the
ESD floor. Adjust the support to a specified height based on the measurement result, ensure
that the top of the support is leveled with the lower surface of the ESD floor, and use a
socket wrench to tighten the nuts on the support to 45 Nm (33.19 lbfft), as shown in the
following figure.
49
BTS3900(Ver.D)
Installation Guide
8 Installing a Base
3.
Issue 03 (2014-08-30)
According to the mounting holes in the concrete floor, mark the positions for installing
expansion bolt assemblies, as shown in the following figure.
50
BTS3900(Ver.D)
Installation Guide
8 Installing a Base
Figure 8-11 Marking the positions for installing expansion bolt assemblies
4.
Use a measuring tape to measure the inter-hole spacing, and ensure that the center-to-center
distances between the holes are consistent.
Step 4 Drill holes at the anchor points on the concrete floor. Then install the expansion bolt assembly.
as shown in the following figure.
Issue 03 (2014-08-30)
51
BTS3900(Ver.D)
Installation Guide
8 Installing a Base
Issue 03 (2014-08-30)
52
BTS3900(Ver.D)
Installation Guide
8 Installing a Base
Step 6 Remove the bolts that are used to temporarily fix the support in step 3.a.
Step 7 Install the base and level it.
1.
Issue 03 (2014-08-30)
Place the insulation plate and the base on the ESD floor in sequence. Align holes on the
base with those on the insulation plate and those for inserting expansion bolt assemblies
on the ESD floor. Use a socket wrench to fasten the M12x80 bolts in a diagonal sequence
to secure the base on the ESD floor, and tighten the bolts to 45 Nm (398.25 lbfin.), as
shown in the following figure.
53
BTS3900(Ver.D)
Installation Guide
8 Installing a Base
2.
Place a level on the base and observe the position of the mercury, as shown in the following
figure. If the base is not level, use the leveling bolts to level it.
NOTE
Screwing the bolts clockwise will raise the base, and screwing the bolts counterclockwise will lower
the base.
(2) Level
Step 8 Measure the insulation between the base and expansion bolts.
Issue 03 (2014-08-30)
54
BTS3900(Ver.D)
Installation Guide
8 Installing a Base
1.
2.
Measure the resistance between the leveling bolt and the expansion bolt, as shown in the
following figure.
Figure 8-16 Measuring the resistance between the leveling bolt and the expansion bolt
l If the resistance is lower than 5 megohms, the base is not insulated from the ground.
Go to Step 8.3.
l If the resistance is higher than 5 megohms, the base is insulated from the ground.
3.
Remove the expansion bolt assemblies and check whether the insulation washers are
missing or damaged.
l If yes, reinstall the expansion bolt assemblies and re-level the base.
l If no, check whether the multimeter works properly and whether the setting is correct.
----End
Issue 03 (2014-08-30)
55
BTS3900(Ver.D)
Installation Guide
Issue 03 (2014-08-30)
56
BTS3900(Ver.D)
Installation Guide
Context
To facilitate operations, you can remove the cabinet door and then install the cabinet.
Procedure
Step 1 Take the marking-off template out from the position 3 U above the bottom of the cabinet, and
determine the holes for installing the cabinet according to the anchor points on the marking-off
template, as shown in the following figure.
Figure 9-1 Positioning the cabinet
Step 2 Drill holes at the anchor points and insert expansion bolt assemblies in the holes, as shown in
the following figure.
Issue 03 (2014-08-30)
57
BTS3900(Ver.D)
Installation Guide
1.
Use a hammer drill with a 16 drill bit to drill holes with a depth ranging from 55 mm
(2.17 in.) to 60 mm (2.36 in.).
CAUTION
Take proper safety measures to protect your eyes and respiratory tract against the dust
before drilling holes.
NOTE
Generally, the concrete floor is solid and smooth. Therefore, you can use the center punch to help
locate the drill bit. If the conditions of the floor allow direct drilling, skip this step.
2.
Use a vacuum cleaner to clear the dust out from inside and around the holes, and measure
the distances between holes. If any of the hole is beyond the acceptable range, mark a new
anchor point and drill a new hole.
3.
Tighten an expansion bolt slightly and place it vertically into each hole.
4.
Hit the expansion bolt with a rubber mallet until the expansion tube completely enters the
hole.
5.
Remove the M12x80 bolt, spring washer and flat washer in sequence.
Issue 03 (2014-08-30)
58
BTS3900(Ver.D)
Installation Guide
CAUTION
After dismantling the expansion bolt assembly, ensure that the top of the expansion tube
is level with the concrete floor. Otherwise, the cabinet cannot be installed on the concrete
floor evenly and securely.
6.
Remove and dispose of the cushion collar. Then take out the insulation washer from the
accessory bag and put it on the expansion bolt with the flat side upwards, as shown in the
following figure.
Figure 9-3 Putting the insulation washer on the expansion bolt
Step 3 Move the cabinet onto the installation holes, place the expansion bolt assemblies into the holes,
and partially tighten them, as shown in the following figure.
CAUTION
The cabinet is heavy so that two persons are required to move it.
Issue 03 (2014-08-30)
59
BTS3900(Ver.D)
Installation Guide
Step 4 Use a level to check the levelness of the cabinet, as shown in the following figure. If the cabinet
is not level, adjust the leveling bolts.
NOTE
Screwing the bolts clockwise will raise the cabinet, and screwing the bolts counterclockwise will lower the
cabinet.
Step 5 Use a socket wrench to fasten the cabinet in a diagonal sequence onto the concrete floor with a
torque of 45 Nm (398.28 lbfin.), as shown in the following figure.
Issue 03 (2014-08-30)
60
BTS3900(Ver.D)
Installation Guide
Step 6 Check the insulation between the cabinet and expansion bolt assemblies.
1.
2.
Measure the resistance between the cabinet and the expansion bolt assemblies, as shown
in the following figure.
Figure 9-7 Measuring the resistance
NOTE
Measure the resistance between the ground bar on the cabinet and the expansion bolt assemblies.
Issue 03 (2014-08-30)
61
BTS3900(Ver.D)
Installation Guide
l If the resistance is lower than 5 M, the cabinet is not insulated from the ground. Go
to 7.c.
l If the resistance is higher than 5 M, the cabinet is insulated from the ground.
3.
Remove the expansion bolt assemblies and check whether the insulation washers are
missing or damaged.
l If yes, reinstall the expansion bolt assemblies and re-level the cabinet.
l If no, check whether the multimeter works properly and whether the setting is correct.
----End
Context
To facilitate operations, you can remove the cabinet door and then install the cabinet.
Procedure
l
Stand the cabinet, place the cabinet on the base, and push the cabinet until its rear
aligns with the rear of the base.
CAUTION
The cabinet is heavy so that two persons are required to move it.
2.
Issue 03 (2014-08-30)
Use a torque wrench to secure the two M12x50 bolts in the front of the cabinet to 45
Nm (398.28 lbfin.), as shown in the following figure.
62
BTS3900(Ver.D)
Installation Guide
Hammer out the knock-out mechanical parts on both sides of the bottom of the IMS06
to install clamps later, as shown in the following figure.
Figure 9-9 Hammering out the knock-out mechanical parts
2.
Issue 03 (2014-08-30)
Stand the cabinet, place the cabinet on the base, and push the cabinet until its rear
aligns with the rear of the base.
Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
63
BTS3900(Ver.D)
Installation Guide
CAUTION
The cabinet is heavy so that two persons are required to move it.
3.
Install the fixture block with the M12x60 expansion bolt onto the front of the cabinet,
and use a socket wrench to tighten the bolt to 45 Nm (398.2 lbfin), as shown in the
following figure.
----End
Procedure
Step 1 Remove the connection plates on the top of the cabinets, as shown in the following figure.
Issue 03 (2014-08-30)
64
BTS3900(Ver.D)
Installation Guide
Step 2 Install the connection plates in the way shown in the following figure, and then use a torque
screwdriver to tighten the M5 screw to 2 Nm (17.7 lbfin.), as shown in the following figure.
Figure 9-12 Installing the connection plates
----End
Issue 03 (2014-08-30)
65
BTS3900(Ver.D)
Installation Guide
Procedure
Step 1 Remove the screws and connection plates from the top of the lower cabinet, and install the
mounting blocks on the top rear of the cabinet. Then use a socket wrench to secure the bolts to
45 Nm (398.28 lbfin.). as shown in the following figure. The mounting block is delivered with
the cabinet.
Figure 9-13 Removing the screws and connection plates
Step 2 Remove the cover plate from the top of the upper cabinet, as shown in the following figure.
Issue 03 (2014-08-30)
66
BTS3900(Ver.D)
Installation Guide
Step 3 Place one cabinet on the top of the other cabinet, and push the upper cabinet until the two cabinets
are aligned in the rear. Use a socket wrench to secure the front two M12x55 bolts to 45 Nm
(398.28 lbfin.). The following figure shows the BTS3900 cabinets installed in stacking mode.
Figure 9-15 Securing the cabinet
----End
Issue 03 (2014-08-30)
67
BTS3900(Ver.D)
Installation Guide
10
A PGND cable connects a PGND screw in a cabinet and a PGND bar to ensure proper grounding
of the cabinet. An equipotential cable connects PGND screws on different cabinets to ensure the
equipotential bonding between the cabinets.
Context
The following table lists the specifications of a PGND cable and an equipotential cable.
Table 10-1 Specifications of a PGND cable and an equipotential cable
Cable
One End
Remarks
PGND cable
OT terminal (M8)
OT terminal (M8)
Equipotential cable
OT terminal (M6)
OT terminal (M6)
Procedure
l
Issue 03 (2014-08-30)
Cut the cable to a length suitable for the actual cable route.
2.
Add OT terminals at each end of the cable according to the instructions in Assembling
the OT Terminal and the Power Cable.
3.
Connect one end of the PGND cable to the ground bar on the inner wall of the cabinet,
connect the other end of the PGND cable to the external ground copper bar outside
Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
68
BTS3900(Ver.D)
Installation Guide
the cabinet, and then use a torque screwdriver to tighten the M8 screw to 8 Nm (70.81
lbfin.). as shown in Figure 10-2.
NOTICE
Install OT terminals in the correct way, as shown in the following figure.
NOTE
The method of installing a PGND cable for a BTS3900 AC cabinet is the same as the method
of installing a PGND cable for a BTS3900 DC cabinet. This section uses a BTS3900 DC cabinet
as an example.
Issue 03 (2014-08-30)
69
BTS3900(Ver.D)
Installation Guide
4.
Lay out the cables according to the instructions in Cabling Requirements and Cable
Holes, and use cable ties to bind them.
5.
Cut the cable to a length suitable for the actual cable route.
2.
Add OT terminals at each end of the cable according to the instructions in Assembling
the OT Terminal and the Power Cable.
3.
Connect one end of the PGND cable to the ground bar on the right inner wall of the
cabinet, connect the other end of the PGND cable to the ground bar on the left inner
wall of the cabinet, and then use a torque screwdriver to tighten the M6 screw to 4.8
Nm (42.48 lbfin.). as shown in the following figure.
NOTE
The method of installing an equipotential cable between a BTS3900 AC cabinet and a BTS3900
DC cabinet is the same as the method of installing an equipotential cable between two BTS3900
DC cabinets. The following figure shows the connection of an equipotential cable between two
BTS3900 DC cabinets installed side by side.
Figure 10-3 Installing an equipotential cable between cabinets installed side by side
4.
Lay out the cables according to the instructions in Cabling Requirements and Cable
Holes, and use cable ties to bind them.
5.
Issue 03 (2014-08-30)
Cut the cable to a length suitable for the actual cable route.
Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
70
BTS3900(Ver.D)
Installation Guide
2.
Add OT terminals at each end of the cable according to the instructions in Assembling
the OT Terminal and the Power Cable.
3.
Connect one end of the PGND cable to the ground bar on the low inner wall of the
cabinet, connect the other end of the PGND cable to the ground bar on the upper inner
wall of the cabinet, and then use a torque screwdriver to tighten the M6 screw to 4.8
Nm (42.48 lbfin.). as shown in the following figure.
NOTE
Two BTS3900 AC cabinets cannot be stacked. Therefore, this step applies only to two stacked
BTS3900 DC cabinets.
4.
Issue 03 (2014-08-30)
Lay out the cables according to the instructions in Cabling Requirements and Cable
Holes, and use cable ties to bind them.
Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
71
BTS3900(Ver.D)
Installation Guide
5.
----End
Issue 03 (2014-08-30)
72
BTS3900(Ver.D)
Installation Guide
11
Issue 03 (2014-08-30)
73
BTS3900(Ver.D)
Installation Guide
If a site is configured with RFUs and RRUs, the RRUs and their cables must be installed onsite.
For details, see the related RRU installation guide.
Issue 03 (2014-08-30)
74
BTS3900(Ver.D)
Installation Guide
Context
A satellite card needs to be installed onsite only for a USCU that uses two satellite cards. To
install a satellite card, perform steps 1 to 3.
Procedure
Step 1 Optional: Loosen the two M3 screws on the panel of the USCU and pull it out, as shown in the
following figure.
Figure 11-1 Removing the USCU
Step 2 Optional: Install a satellite card on the USCU, as shown in the following figure.
1.
2.
Place the satellite card on the USCU, aligning the mounting holes on the satellite card with
the bolts on the USCU.
3.
Use the three M1.6 screws removed in step a to secure the satellite card, and tighten the
screws to 0.1 Nm (0.89 1bfin.).
4.
Connect one end of the RF jumper for the satellite card to the RF port on the satellite card,
and connect the other end to the GPS port on the USCU.
NOTICE
There are six mounting holes on the satellite card, but you need to install only three screws, as
shown in the following figure.
Issue 03 (2014-08-30)
75
BTS3900(Ver.D)
Installation Guide
Step 3 Optional: Install the USCU in the BBU, and tighten the captive screws on the USCU to 0.6 Nm
(5.31 lbfin.).
Step 4 Remove the connection plate on the top of the cabinet, and install a support for the GPS surge
protector in the position. Then use a torque screwdriver to tighten the M5 screws to 2 Nm (17.7
lbfin), as shown in the following figure.
Issue 03 (2014-08-30)
76
BTS3900(Ver.D)
Installation Guide
Step 5 Install the GPS clock signal cable, as shown in the following figure.
1.
Connect the type N female connector on one end of the GPS clock signal cable to the top
of the cabinet, and use a torque wrench to tighten the screw to 6.5 Nm (57.53 lbf in.).
2.
Connect the SMA male connector on the other end to the GPS port on the USCU, LMPT,
or UMPTa6, and use a torque wrench to tighten the connector to 0.8 Nm (7.08 lbf in.).
NOTE
If the BBU is configured with an LMPT or UMPTa6, the GPS clock signal cable is preferentially connected
to the GPS port on the LMPT or UMPTa6.
Step 6 Install the GPS surge protector and the GPS jumper, as shown in the following figure.
1.
Issue 03 (2014-08-30)
Use a torque wrench to secure the Protect port on the GPS surge protector onto the type N
female connector at one end of the GPS signal cable, and tighten the screw to 4 Nm (35.40
lbf in.).
Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
77
BTS3900(Ver.D)
Installation Guide
2.
Use a torque wrench to secure the GPS jumper to the Surge port on the GPS surge protector,
and tighten the screw to 4 Nm (35.40 lbf in.).
Step 7 Lay out the cables according to the instructions in Cabling Requirements, and use cable ties to
bind them.
Step 8 Label the installed cables according to the instructions in Attaching an L-Shaped Label.
----End
Context
A Bias-Tee couples the DC power or OOK signals into the feeder and a GATM is connected to
the antenna through the Bias-Tee. When a DRFU is configured, a GATM and a Bias-Tee must
be installed, and usually a straight DIN Bias-Tee is used.
The following figure shows the ports on a straight DIN Bias-Tee and the following table
describes the cable connections on the straight DIN Bias-Tee.
Issue 03 (2014-08-30)
78
BTS3900(Ver.D)
Installation Guide
Bias-Tee and RET control signal cable. The other end of the cable is
connected to any port from ANT0 to ANT5 on the GATM.
PGND cable
The following figure shows the connections of cables between a GATM and a straight DIN BiasTee.
Issue 03 (2014-08-30)
79
BTS3900(Ver.D)
Installation Guide
Issue 03 (2014-08-30)
80
BTS3900(Ver.D)
Installation Guide
NOTE
In the BTS3900 (Ver.D) DC and BTS3900 (Ver.D) AC cabinets, the installation are the same. The following
figure uses the BTS3900 (Ver.D) DC cabinet as an example.
Procedure
Step 1 Install the GATM, as shown in the following figure.
1.
2.
Tighten the four M6 screws on the mounting ear on both sides of the GATM to 2 Nm (17.7
lbfin.).
Cut the cables to the length suitable for the actual cable route, and add OT terminals to both
ends of the cables according to the instructions in Assembling the OT Terminal and the
Power Cable.
2.
Connect the M4 OT terminal on one end of the PGND cable to the GND port on the straight
DIN Bias-Tee, and then use a torque screwdriver to tighten the M4 screw to 1.6 Nm (14.16
lbfin.).
3.
Connect the OT terminal on the other end to the ground bar of the antenna.
4.
Lay out the cables according to the instructions in Cabling Requirements, and use cable
ties to bind them.
5.
Label the installed cables according to the instructions in Attaching a Cable-Tying Label.
Issue 03 (2014-08-30)
Connect the end with a 3V3 connector to the -48V port on the GATM and tighten the screw
on the connector using a torque screwdriver to 0.6 Nm (0.44 ftlb).
Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
81
BTS3900(Ver.D)
Installation Guide
2.
Add a connector to the other end of the cable according to the type of power equipment
and connect the end to the power equipment.
Base Station
Power
Device
Installation Position
Method of Adding a
Connector
BTS3900(Ver.B)
DCDU-01
BTS3900(Ver.C)
DCDU-11A
BTS3900(Ver.D)
DCDU-12A
Connect one end of the cable to the COM1 port on the GATM.
2.
Connect the other end of the cable to the MON0 or MON1 port on the BBU.
Step 6 Install the monitoring signal cable between the fan unit and the GATM.
1.
Connect one end of the cable to the COM2 port on the GATM.
2.
Connect the other end of the cable to the COM_IN port on the fan unit in the cabinet.
NOTE
The fan unit to be used in a cabinet varies according to the cabinet type. The fan unit types include: FAN, FAN
03B, or FAN 03C.
Connect the DIN straight male connector on one end of the RF jumper to the BTS port on
the Bias-Tee, and use a torque wrench (size: 32 mm [1.26 in.]) to tighten the connector
with a torque between 25 Nm (221.27 lbfin.) and 35 Nm (309.78 lbfin.).
2.
Connect the DIN elbow male connector on the other end to the RF port on an RFU.
3.
Lay out the cables according to the instructions in Cabling Requirements, and use cable
ties to bind them.
4.
Attach color codings to RF jumpers according to the instructions in Color Ring for the
Antenna System and Attaching the Color Ring.
Step 8 Install the RET control signal cable, as shown by cable "c" in Figure 11-9.
Issue 03 (2014-08-30)
82
BTS3900(Ver.D)
Installation Guide
1.
Connect the SMA straight male connector on one end of the RET control signal cable to
the DC/OOK port on the DIN Bias-Tee. Use a torque wrench to tighten the connector with
a torque 0.8 Nm (7.08 lbfin.).
2.
Connect the SMA elbow male connector on the other end to any port from ANT0 to ANT5
on GATM. Use a torque wrench to tighten the connector with a torque 0.8 Nm (7.08 lbfin.).
3.
Lay out the cables according to the instructions in Cabling Requirements, and use cable
ties to bind them.
4.
Label the installed cables according to the instructions in Attaching an L-Shaped Label.
Connect the DIN straight male connector on one end of the RF feeder to the ANT port on
the straight DIN Bias-Tee, and use a torque wrench (size: 32 mm [1.26 in.]) to tighten the
connector with a torque between 25 Nm (221.27 lbfin.) and 35 Nm (309.78 lbfin.).
2.
3.
Lay out the cables according to the instructions in Cabling Requirements, and use cable
ties to bind them.
4.
Attach color codings to RF jumpers according to the instructions in Color Ring for the
Antenna System and Attaching the Color Ring.
----End
Issue 03 (2014-08-30)
83
BTS3900(Ver.D)
Installation Guide
Context
l
The following figure shows the position for installing the DCDU-12B in a cabinet.
Table 11-2 Position for installing the DCDU-12B
Base Station
Installation Position
BTS3900 (Ver.D) DC
BTS3900 (Ver.D) AC
BTS3900L (Ver.D)
Issue 03 (2014-08-30)
84
BTS3900(Ver.D)
Installation Guide
The following table lists the specifications of the DCDU-12B power cables.
Table 11-3 Specifications of the DCDU-12B power cables
Base
Station
Cable
Wire Color
BTS390
0
(Ver.D)
DC
DCDU
-12B
power
cable
RTN
(+)
DCDU
-12B
power
cable
RTN
(+)
Blac
k
Blue
(UK)
NEG
(-)
Blue
Grey
(UK)
Blac
k
Blue
(UK)
Connector
One
End
The
Other
End
l 1x160 A: 35
mm2 (0.054
in.2)
OT
termin
al (M6)
Depend
ing on
the
external
equipm
ent
OT
termin
al (M6)
OT
terminal
(M6)
l 1x160 A: 35
mm2 (0.054
in.2)
BTS390
0L
(Ver.D)
BTS390
0
(Ver.D)
AC
CrossSectional Area
35 mm2 (0.039
in.2)
Procedure
Step 1 Remove the four M6 screws on both sides of the slot for installing the DCDU-12B.
Step 2 Stick a cable claw onto the right side of the DCDU-12B, as shown in the following figure.
Figure 11-11 Sticking a cable claw onto the right side of the DCDU-12B
Hold the DCDU-12B with both hands, and slide it into the cabinet until the mounting ears
on both sides of the DCDU-12B contact the columns.
2.
Tighten the four M6 screws on both sides of the DCDU-12B to 3Nm (17.7 lbfin.).
Issue 03 (2014-08-30)
85
BTS3900(Ver.D)
Installation Guide
(1) DCDU-12B
Cut the cable to the length suitable for the actual cable route.
NOTE
In AC scenarios, the recommended length of the DCDU-12B power cable is 1.2 m (3.94 ft).
2.
Add OT (M6) terminals to one end of the power cable according to the instructions in
Assembling the OT Terminal and the Power Cable and add terminals or connectors to the
other end according to the power equipment.
DANGER
Do not expose the mental wire in the cable when adding OT terminals, as shown in the
following figure.
Issue 03 (2014-08-30)
86
BTS3900(Ver.D)
Installation Guide
Step 5 Optional: In DC scenarios, install the DCDU-12B power cable, as shown in the following figure.
Skip this step in AC scenarios.
1.
Use a Phillips screwdriver to loosen the M3 screw on the protective cover for the wiring
terminals on the DCDU-12B and remove the protective cover.
2.
Connect one end of the black or blue wire of the power cable with an OT terminal to the
RTN(+) terminal on the DCDU-12B, and one end of the blue or gray wire of the power
cable with an OT terminal to the NEG(-) terminal on the DCDU-12B. Then use a torque
screwdriver to tighten the M6 screws on the OT terminals to 4.8 Nm (42.48 lbfin).
3.
Reinstall the protective cover onto the DCDU-12B, and use a torque screwdriver to tighten
the M3 screw on the protective cover to 0.3 Nm (2.66 lbfin.).
4.
Issue 03 (2014-08-30)
87
BTS3900(Ver.D)
Installation Guide
Step 6 Optional: In DC scenarios, install the DCDU-12B power cable, as shown in the following figure.
Skip this step in AC scenarios.
1.
Use a Phillips screwdriver to loosen the M3 screw on the protective cover for the wiring
terminals on the DCDU-12B and remove the protective cover.
2.
Connect one end of the black or blue wire of the power cable with an OT terminal to the
RTN(+) terminal on the DCDU-12B, and one end of the blue or gray wire of the power
cable with an OT terminal to the NEG(-) terminal on the DCDU-12B. Then use a torque
screwdriver to tighten the M6 screws on the OT terminals to 4.8 Nm (42.48 lbfin).
3.
Use a Phillips screwdriver to loosen the M3 screw on the protective cover for the RFC_1
wiring terminal on the EPU05A-02/04 and remove the protective cover.
4.
Connect the other end of the black or blue wire of the power cable with an OT terminal to
the RTN(+) terminal near the RFC_1 silkscreen, and the other end of the blue or gray wire
of the power cable with an OT terminal to the NEG(-) terminal near the RFC_1 silkscreen.
Then use a torque screwdriver to tighten the M6 screws on the OT terminals to 4.8 Nm
(42.48 lbfin).
5.
Reinstall the protective covers on the DCDU-12B and EPU05A-02/04, and use a torque
screwdriver to tighten the M3 screws on the protective covers to 0.3 Nm (2.66 lbfin.).
Issue 03 (2014-08-30)
88
BTS3900(Ver.D)
Installation Guide
Step 7 Lay out the cables according to the instructions in Cabling Requirements, and use cable ties to
bind them.
Step 8 Label the installed cables according to the instructions in Attaching a Cable-Tying Label.
----End
Context
The following table lists the position for installing the second BBU (BBU 1 in the following
figure) in a BTS3900 or BTS3900L cabinet.
Issue 03 (2014-08-30)
89
BTS3900(Ver.D)
Installation Guide
Installation Position
BTS3900 (Ver.D)
Issue 03 (2014-08-30)
90
BTS3900(Ver.D)
Installation Guide
Issue 03 (2014-08-30)
91
BTS3900(Ver.D)
Installation Guide
Procedure
Step 1 Align a cable claw with the holes on each side of the BBU. Then use two M4 screws to secure
each cable claw to the BBU and tighten the screws to 1.2 Nm (10.62 lbfin.), as shown in the
following figure.
Figure 11-19 Installing cable claws on the BBU
Step 2 Slide the BBU into the cabinet along the guide rails, and then use a torque screwdriver to tighten
the four M6 screws on the panel to 3 Nm (26.55 lbfin.), as shown in the following figure.
Issue 03 (2014-08-30)
92
BTS3900(Ver.D)
Installation Guide
NOTICE
When installing a BBU equipped with boards, hold the bottom of the BBU with your hands and
slide it into the cabinet slowly to prevent it from falling.
Cut the power cable to a length suitable for the actual cable route.
2.
According to the cabinet type and power equipment type, add a connector to the BBU power
cable at the end connecting to the power equipment. The following table describes how to
add a connector to the BBU power cable.
Table 11-5 Method of adding a connector to the BBU power cable
Base Station
Power Equipment
Method of Adding a
Connector
BTS3900 (Ver.B)
DCDU-01
DCDU-11A
BTS3900L (Ver.B)
BTS3900 (Ver.C)
BTS3900L (Ver.C)
Issue 03 (2014-08-30)
93
BTS3900(Ver.D)
Installation Guide
Base Station
Power Equipment
Method of Adding a
Connector
BTS3900 (Ver.D)
DCDU-12A
BTS3900L (Ver.D)
Step 4 Install the BBU power cable, as shown in the following figure.
CAUTION
Ensure that the BBU power cable for a BBU added to a running base station must be connected
to the BBU first and then to the power equipment. The operations in the reverse sequence may
cause component damage or personal injury.
1.
Connect the 3V3 connector at one end of the BBU power cable to the -48V port on the
UPEU. Then tighten the screws on the connector to 0.6 Nm (5.31 lbfin.).
2.
Connect the other end of the BBU power cable to the power equipment, as listed in the
following table.
Table 11-6 Positions for installing BBU power cables
Base Station
Power Equipment
Installation Position
BTS3900 (Ver.B)
DCDU-01
BBU port
DCDU-11A
DCDU-12A
BTS3900L (Ver.B)
BTS3900 (Ver.C)
BTS3900L (Ver.C)
BTS3900 (Ver.D)
BTS3900L (Ver.D)
Issue 03 (2014-08-30)
94
BTS3900(Ver.D)
Installation Guide
Figure 11-21 Installing BBU power cables for BTS3900 cabinets when BBU 1 is installed
in the extension cabinet that is installed together with the basic cabinet or is stacked on the
basic cabinet
Figure 11-22 Installing BBU power cables for BTS3900 cabinets when BBU 1 and BBU
0 are installed in the same cabinet
Issue 03 (2014-08-30)
95
BTS3900(Ver.D)
Installation Guide
Step 5 Install the inter-BBU signal cable, as listed in the following table.
Table 11-7 Installing the inter-BBU signal cable
Base Station
Installation Method
Step 6 Lay out the cables according to the instructions in Cabling Requirements, and use cable ties to
bind them.
Step 7 Label the installed cables according to the instructions in Attaching a Cable-Tying Label.
----End
Issue 03 (2014-08-30)
96
BTS3900(Ver.D)
Installation Guide
Context
l
The boards in the BBU to be installed onsite include the WMPT, WBBP, GTMU, GBBP,
LMPT, LBBP, UTRP, UPEU, and UEIU. The actual boards to be installed depend on the
configuration requirements of a base station. The following uses the procedure for installing
the WMPT and UPEU as an example. The procedures for installing other preceding boards
are the same.
The surge protection boards to be installed include the UELP and UFLP.
Operation Rules
l
When moving a board, you must hold the board with both hands, as shown in the following
figure.
Figure 11-24 Incorrect and correct operations when moving a board
Issue 03 (2014-08-30)
When installing a board, you must hold the ejector lever side of the board with one hand
and hold another side of the board with the other hand to ensure that the board is moving
in the correct direction. Do not hold the board with only one hand and never apply lateral
forces to the board. The following figure shows incorrect and correct operations when
installing a board.
97
BTS3900(Ver.D)
Installation Guide
Figure 11-25 Incorrect and correct operations when installing a board (1)
When installing a board, ensure that your hands are level so that the board and the guide
rails are on one level. Do not apply lateral forces to the board. Otherwise, the board will
be distorted. The following figure shows incorrect and correct operations when installing
a board.
Figure 11-26 Incorrect and correct operations when installing a board (2)
CAUTION
l Handle the board with care and avoid collision. Do not pile or compress boards after they
are unpacked.
l When inserting a board into a subrack, prevent it from colliding with the subrack and push
it into the subrack until it snaps into place.
Issue 03 (2014-08-30)
98
BTS3900(Ver.D)
Installation Guide
Procedure
Step 1 Put on an ESD wrist strap or a pair of ESD gloves.
NOTICE
Take proper ESD protection measures, for example, put on an ESD wrist strap or a pair of ESD
gloves, to prevent electrostatic damage to the boards, modules, or other electronic components.
Step 2 Install the WMPT and UPEU.
1.
Remove the screws on the filler panels in the slots to be used, and gently remove the filler
panels.
2.
If there are ejector levers on the panels of the boards, raise them and remove the boards. If
there are no ejector levers, directly remove the boards.
3.
Slowly insert the board into the slot until it snaps into place. Then, lower the ejector levers.
4.
Step 3 Optional: In an outdoor base station, you need to install a UELP or UFLP. The following
describes how to install a UELP in an SLPU as an example. The procedure for installing a UELP
or UFLP in the surge protection subrack for transmission signals in a BTS3900AL (Ver.A) is
similar.
1.
Remove the screws on the filler panels in the slots to be used, and gently remove the filler
panels.
2.
Slowly insert the board into the slot until it snaps into place.
3.
Issue 03 (2014-08-30)
99
BTS3900(Ver.D)
Installation Guide
----End
Context
l
Issue 03 (2014-08-30)
The RFU is installed in the vacant RFU subrack in the cabinet, as shown in the following
figure.
100
BTS3900(Ver.D)
Installation Guide
The colors and structures of the power cables in this document are for reference only, which
may differ from those of the cables onsite.
The colors and structures of cables vary according to countries and regions. If cables are
purchased locally, the cables must comply with local rules and regulations.
Issue 03 (2014-08-30)
The following table lists the specifications of the RFU power cable.
101
BTS3900(Ver.D)
Installation Guide
Power
Equipment
W
ir
e
Color
Mo
st
Re
gio
ns
U
K
BTS3900AL
(Ver.A)
DCDU-12C
R
T
N
(+
)
Bla
ck
B
lu
e
N
E
G
(-)
Bla
ck
G
ra
y
R
T
N
(+
)
Bla
ck
N
E
G
(-)
Blu
e
R
T
N
(+
)
Bla
ck
B
lu
e
N
E
G
(-)
Blu
e
G
ra
y
R
T
N
(+
)
Bla
ck
N
E
G
(-)
Bla
ck
l BTS3900
(Ver.B)
DCDU-01
l BTS3900A
(Ver.B)
l BTS3900L
(Ver.B)
l BTS3900
(Ver.C)
DCDU-11A
l BTS3900A
(Ver.C)
l BTS3900L
(Ver.C)
BTS3900
(Ver.D)
Issue 03 (2014-08-30)
DCDU-12A
Connector at
One End
Connector at
the Other
End
3V3 connector
EPC4
connector
3V3 connector
Parallel
terminal
3V3 connector
Tool-less
female
connector
(pressfit type)
3V3 connector
EPC4
connector
102
BTS3900(Ver.D)
Installation Guide
Base Station
Type
Power
Equipment
W
ir
e
Color
Mo
st
Re
gio
ns
U
K
l BTS3900A
(Ver.D)
DCDU-12A
R
T
N
(+
)
Bla
ck
B
lu
e
N
E
G
(-)
Bla
ck
G
ra
y
l BTS3900L
(Ver.D)
Connector at
One End
Connector at
the Other
End
3V3 connector
EPC4
connector
Procedure
Step 1 Put on an ESD wrist strap or a pair of ESD gloves.
NOTICE
Take proper ESD protection measures, for example, put on an ESD wrist strap or a pair of ESD
gloves, to prevent electrostatic damage to the boards, modules, or other electronic components.
Step 2 Remove the 3V3 connector from the lower part of the filler panel in the slot where the RFU is
to be installed.
Step 3 Remove the filler panel.
l
Issue 03 (2014-08-30)
If the base station uses the Ver.D cabinets, turn the knob on the upper part of the filler panel
in the direction indicated, lift the filler panel slightly, and then pull out the filler panel, as
shown in the following figure.
103
BTS3900(Ver.D)
Installation Guide
If the base station uses the Ver.B or Ver.C cabinets, loosen the four captive screws from
the filler panel, and then remove the filler panel.
Step 4 Place the new RFU on guide rails, and slide it along the rails until it snaps into place.
Step 5 Tighten the captive screws on the four corners of the RFU panel to secure the RFU to the subrack,
and the recommended torque is 0.6 Nm (5.31 lbfin.).
Step 6 Install the RFU power cable, as shown in the following figure.
1.
Optional: Remove the newly installed RFU connector from the DCDU-12A or
DCDU-12C.
2.
Connect the 3V3 connector removed from the filler panel to the newly installed RFU. Then
tighten the captive screws on the 3V3 connector to 0.6 Nm (5.31 lbfin.).
3.
Optional: Reinstall the newly installed RFU connector on the DCDU-12A or DCDU-12C,
as listed in the following table.
Table 11-9 Connector type of RFU power cable
Issue 03 (2014-08-30)
Power Equipment
BTS3900 (Ver.B),
BTS3900L (Ver.B), and
BTS3900A (Ver.B)
DCDU-01
Parallel terminal
BTS3900 (Ver.C),
BTS3900L (Ver.C), and
BTS3900A (Ver.C)
DCDU-11A
104
BTS3900(Ver.D)
Installation Guide
Power Equipment
BTS3900 (Ver.D),
BTS3900L (Ver.D), and
BTS3900A (Ver.D)
DCDU-12A
EPC4 connector
BTS3900AL (Ver.A)
DCDU-12C
EPC4 connector
CAUTION
Ensure that the RFU power cable for an RFU added to a running base station must be
connected to the RFU first and then to the power equipment. The operations in the reverse
sequence may cause component damage or personal injury.
Figure 11-31 Installing the RFU power cable
Issue 03 (2014-08-30)
Installation Method
Installing RF Jumpers
105
BTS3900(Ver.D)
Installation Guide
Installation Method
Installing RF Jumpers
BTS3900AL(Ver.A)
Installing RF Jumpers
Step 8 Install the CPRI electrical cables, as described in the following table.
Table 11-11 Installing CPRI electrical cables
Base Station Type
Installation Method
BTS3900AL(Ver.A)
Step 9 Lay out the cables according to the instructions in 12.1 Cabling Requirements, and use cable
ties to bind them.
Step 10 Optional: In an outdoor base station, use a PVC corrugated pipe to protect the cables outside
the cabinet, and tie the pipe to the cable hole on the cabinet.
Step 11 Label the installed cables according to the instructions in Attaching a Sign Plate Label.
----End
Procedure
Step 1 Install the EMU and its cables according to section "Installing the EMU" in EMU User Guide.
Step 2 Install the EMU monitoring signal cable, as shown in the following figure.
1.
In a DC cabinet, connect the RJ-45 connector at one end of the EMU monitoring signal
cable to the MON1 port on the UPEU in the BBU. In an AC cabinet, connect the RJ-45
connector at one end of the EMU monitoring signal cable to the COM OUT port on the
PMU.
2.
Connect the DB9 male connector at the other end of the EMU monitoring signal cable to
the RS485 port on the EMU and tighten the screws.
Issue 03 (2014-08-30)
106
BTS3900(Ver.D)
Installation Guide
Step 3 Lay out the cables according to the instructions in Cabling Requirements, and use cable ties to
bind them.
Step 4 Label the installed cables according to the instructions in Attaching an L-Shaped Label.
----End
Issue 03 (2014-08-30)
107
BTS3900(Ver.D)
Installation Guide
Issue 03 (2014-08-30)
108
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
12
Installing Cables
Issue 03 (2014-08-30)
109
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
If a cable listed below is not required, skip the cabling requirements of the cable.
The bending radius of a 7/8'' feeder must be greater than 250 mm (9.84 in.), and the bending
radius of a 5/4'' feeder must be greater than 380 mm (14.96 in.).
The bending radius of a 1/4'' jumper must be greater than 35 mm (1.38 in.). The bending
radius of a super-flexible 1/2'' jumper must be greater than 50 mm (1.97 in.), and the bending
radius of an ordinary 1/2'' jumper must be greater than 127 mm (5 in.).
The bending radius of a power cable or PGND cable must be at least three times its diameter.
The bending radius of a fiber optic cable is at least 20 times of its diameter, and the bending
radius of a breakout cable is at least 30 mm (1.18 in.).
The bending radius of an E1/T1 cable must be at least three times its diameter.
The bending radius of a signal cable must be at least five times its diameter.
Different types of cables must be separately laid out and bound, with a minimum distance
of 30 mm (1.18 in.) from each other.
The cables must be bound tightly and neatly. The sheaths of the cables must not be damaged.
The cable ties must face the same direction, and those at the same horizontal line must be
in a straight line.
The excess of the indoor cable ties is cut off. The excess of 5 mm (0.197 in.) of the outdoor
cable ties is reserved, and the cut surfaces are smooth without sharp edges.
After cables are installed, labels or nameplates must be attached to the cables at their ends,
curves, and interconnection positions.
Security requirements
l
When routing cables, avoid sharp objects, for example sharp edges on the wall. If necessary,
use tubes to protect the cables.
When routing cables, keep the cables away from heat sources and use heat insulation
materials to insulate the cables from the heat sources.
Reserve a proper distance (0.1 m or 3.937 in. is recommended) between equipment and
cables especially at the cable curves to protect the cables and equipment.
Route each cable into the room through the feeder window.
Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
110
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Reserve drip loops for all cables outside the feeder window before routing them into the
room. Ensure that the radiuses of the drip loops are greater than or equal to the minimum
bending radiuses of the cables.
When routing a cable into the room, ensure that a person is assisting you in the room.
Protect outdoor cables against potential damage. For example, put the cables through tubes.
The cables to be protected include AC power cables, transmission cables, and cables laid
out underground.
When routing cables through tubes on the ground below the cabinet, put a 30 mm to 50
mm (1.18 in. to 1.97 in.) length of the tubes into the base of the cabinet but do not put the
tubes into the cabinet. Use waterproof tape or waterproof silicon gel to block both ends of
the tubes and use sheet metal tabs to secure the tubes to the cable holes in the base.
When routing cables through tubes along a metal cable trough below the cabinet, do not
put the tubes into the base of the cabinet but cover the cable trough and connect the tubes
to the cable holes in the base.
Use clips to secure cables outdoors. For the method of installing a clip, see the installation
guide delivered with the clip.
Arrange cables neatly along the routing direction and use clips to secure the cables.
Determine the positions where the clips are installed according to the actual situation. For
example, 7/8" feeders are secured with clips at an interval of 1.5 m to 2 m (4.92 ft to 6.56
ft), CPRI fiber optic cables and power cables are secured with clips at an interval of 1 m
to 1.5 m (3.28 ft to 4.92 ft). Ensure that the clips are evenly spaced and in the same direction.
When fastening cables with a clip, ensure that the cables are aligned neatly and are routed
through the holes in the clip. Do not stretch the cables too tightly.
NOTE
There are two types of clips: 3-hole clip and 6-hole clip, which are described as follows:
l
A 3-hole clip is shown by illustration a in the following figure. It is often used to fasten feeders.
A 6-hole clip is shown by illustration b in the following figure. It is often used to fasten power cables and
CPRI fiber optic cables.
Issue 03 (2014-08-30)
111
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Issue 03 (2014-08-30)
112
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Power cables must be installed in the position specified in engineering design documents.
If the length of power cables is insufficient, replace the cables rather than adding connectors
or soldering joints to lengthen the cables.
Cables can only be laid out under well-planned instructions. The cabling activities of fiber
optic cables are allowed only when qualified personnel and communication facilities are
available.
Issue 03 (2014-08-30)
113
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
After routing a DC power cable onto the platform on a tower, route it along the shortest
path to the rails surrounding the platform, and route it along the inside of the rails.
After routing a DC power cable close to the equipment on a tower, use clips to secure the
power cable onto a pole or the rails surrounding the platform. Ensure that there is no
excessively long distance between the equipment and the position where the power cable
is secured.
PGND cables for a base station must be connected to the same group of ground bars.
The external conductor of the coaxial wire and the shield layer of the shielded cable must
have proper electrical contact with the metal surface of the equipment to which they are
connected.
PGND cables and signal cables must be installed separately. A certain distance must be
reserved between them to prevent interference from each other.
Other devices must not be used for electrical connections of the PGND cables.
All the metal parts in the housing of the equipment must be reliably connected to the ground
terminal.
Cabling of E1 cables
l
E1 cables must not cross power cables, PGND cables, or RF cables when laid out. If
transmission cables are laid out with power cables, PGND cables, or RF cables in parallel,
the spacing between them must be greater than 30 mm (1.18 in.).
E1 cables are lined up straight and bound neatly with cable ties.
E1 cables must not be pressed by the door of the cabinet when routed, as shown in the
following figure.
Figure 12-4 E1 cables routed in the cabinet
Issue 03 (2014-08-30)
At least three people are required for laying out fiber optic cables. The cabling activities
of fiber optic cables are allowed only when qualified personnel and communication
facilities are available.
Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
114
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
The operating temperature of fiber optic cables ranges from -40C to +60C (-40F to
+140F). If the actual temperature is beyond this range, take protective measures or select
another route.
Do not stretch, step on, or place heavy objects on fiber optic cables. Keep the fiber optic
cables away from sharp objects.
When fiber optic cables are routed, the excess of the fiber optic cables must be coiled around
special devices, such as a fiber coiler.
An unarmored fiber optic cable must be bound using binding straps. If a fiber optic patch
cord needs to be secured in a cabinet or a piece of equipment, use binding straps to bind it
and then use cable ties to secure the binding straps to the cabinet or equipment. Ensure that
the fiber optic cables can flexibly move in the cable ties. Do not bend the fiber optic cables
sharply. The following figure shows how to bind the fiber optic cables correctly.
Figure 12-5 Binding fiber optic cables
When coiling fiber optic cables, apply even strength. Do not bend the fiber optic cables
with force.
The fiber optic cables must not be pressed by the door of the cabinet when routed, as shown
in the following figures.
Figure 12-6 CPRI fiber optic cables routed in the cabinet (1)
Issue 03 (2014-08-30)
115
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Figure 12-7 CPRI fiber optic cables routed in the cabinet (2)
After routing a fiber optic cable onto the platform on a tower, route it along the shortest
path to the rails surrounding the platform, and route it along the inside of the rails.
After routing a fiber optic cable close to the equipment on a tower, use clips to secure the
fiber optic cable onto a pole or the rails surrounding the platform. Ensure that there is no
excessively long distance between the equipment and the position where the cable is
secured.
Coil the excess of the fiber optic cables near the equipment on the tower before securing
the cables on the tower.
Route the PGND cables along the left side of the cabinet interior.
Route six jumpers along the left side of the cabinet interior.
Route the input power cables along the left side of the cabinet interior.
Issue 03 (2014-08-30)
116
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Route six jumpers along the right side of the cabinet interior.
Route the transmission cables along the right side of the cabinet interior.
Route the monitoring signal cables close to the CPRI electrical cables.
(a) PGND cables and Input (b) Jumpers on the left side (c) DCDU power cables in (d) CPRI fiber optic cables
power cables for BTS3900
the capacity expansion
cabinet
scenario
(e) Reserved(1)
(h) Reserved(2)
NOTE
l (1) When RRUs are added to the BTS3900 (Ver.D) cabinet that is originally configured only with
RFUs, the RRUs are powered by the DCDU-12B in the cabinet and this area is used for routing
DCDU-12B power cables. In a BTS3900 (Ver.B) or BTS3900 (Ver.C) cabinet configured with RFUs
and RRUs, RRUs are powered by the DCDU-03B or DCDU-11B on a wall and this area is reserved.
l (2) When RRUs are added to the BTS3900 (Ver.D) cabinet that is originally configured only with
RFUs, the RRUs are powered by the DCDU-12B in the cabinet and this area is used for routing RRU
power cables. In a BTS3900 (Ver.B) or BTS3900 (Ver.C) cabinet configured with RFUs and RRUs,
RRUs are powered by the DCDU-03B or DCDU-11B on a wall and this area is reserved.
Route and bind cables according to the instructions for "Routing Cables in a Single
Cabinet."
Issue 03 (2014-08-30)
117
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
(a) Input power cables for the lower (b) Jumpers on the left side of the
cabinet and PGND cables
lower cabinet
(e) Reserved(1)
NOTE
l (1) When RRUs are added to the BTS3900 (Ver.D) cabinet that is originally configured only with
RFUs, the RRUs are powered by the DCDU-12B in the cabinet and this area is used for routing
DCDU-12B power cables. In a BTS3900 (Ver.B) or BTS3900 (Ver.C) cabinet configured with RFUs
and RRUs, RRUs are powered by the DCDU-03B or DCDU-11B on a wall and this area is reserved.
l (2) When RRUs are added to the BTS3900 (Ver.D) cabinet that is originally configured only with
RFUs, the RRUs are powered by the DCDU-12B in the cabinet and this area is used for routing RRU
power cables. In a BTS3900 (Ver.B) or BTS3900 (Ver.C) cabinet configured with RFUs and RRUs,
RRUs are powered by the DCDU-03B or DCDU-11B on a wall and this area is reserved.
Binding Cables
Route cables according to the routes in Figure 12-9 and Figure 12-10. Then, bind the cables to
the nearest points on the binding plate according to Figure 12-11 and Figure 12-12.
Issue 03 (2014-08-30)
118
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
NOTE
(1) When RRUs are added to the BTS3900 (Ver.D) cabinet that is originally configured only with RFUs,
the RRUs are powered by the DCDU-12B in the cabinet and this area is used for routing DCDU-12B power
cables.
Issue 03 (2014-08-30)
119
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
(4) Reserved(1)
NOTE
(1) When RRUs are added to the BTS3900 (Ver.D) cabinet that is originally configured only with RFUs,
the RRUs are powered by the DCDU-12B in the cabinet and this area is used for routing RRU power cables.
In a BTS3900 (Ver.B) or BTS3900 (Ver.C) cabinet configured with RFUs and RRUs, RRUs are powered
by the DCDU-03B or DCDU-11B on a wall and this area is reserved.
Issue 03 (2014-08-30)
120
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Prerequisites
l
The following tools are available: a Phillips screwdriver, a torque screwdriver, a cable
cutter, and a multi-purpose crimping tool.
The colors and structures of the power cables may vary from the following table.
The colors and structures of cables vary according to countries and areas. If cables are
purchased at local markets, the cables must comply with local rules and regulations.
Context
EPU05A-02
power cable
(220 V AC
singlephase)
Issue 03 (2014-08-30)
L1
Color
One End
The Other
End
Remarks
Brown
OT terminal (M6, 6
mm2 or 0.009 in.2)
Depending
on the
external
equipment
L2
Black
OT terminal (M6, 6
mm2 or 0.009 in.2)
Depending
on the
external
equipment
L3
Gray
OT terminal (M6, 6
mm2 or 0.009 in.2)
Depending
on the
external
equipment
Blue
OT terminal (M6, 6
mm2 or 0.009 in.2)
Depending
on the
external
equipment
PE
Green
and
yellow
OT terminal (M6, 6
mm2 or 0.009 in.2)
Depending
on the
external
equipment
Brown
OT terminal (M6, 25
mm2 or 0.039 in.2)
Depending
on the
external
equipment
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Cable
Color
One End
The Other
End
Blue
OT terminal (M6, 25
mm2 or 0.039 in.2)
Depending
on the
external
equipment
PE
Green
and
yellow
OT terminal (M6,
25mm2 or 0.039 in.2)
Depending
on the
external
equipment
Remarks
with a single
core and two
insulation layers
Procedure
Step 1 Prepare an EPU05A-02 power cable.
1.
Measure the distance between the EPU05A-02 and the external power equipment based on
the actual cable route, and cut the cable to a length suitable for the actual cable route.
2.
Add M6 OT terminals to one end of the power cable according to the instructions in
Assembling the OT Terminal and the Power Cable, and add a connector to the other end
of the power cable depending on the external power equipment.
DANGER
Do not expose the mental wire in the cable when adding OT terminals, as shown in the
following figure.
Step 2 Install the EPU05A-02 power cable, as shown in Figure 12-14 and Figure 12-15.
1.
Issue 03 (2014-08-30)
Use a Phillips screwdriver to loosen the M3 screw on the protective cover for the AC input
terminals, and open the protective cover.
Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
122
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
2.
When 220 V AC single-phase power is supplied, do not remove the short-circuiting bars.
3.
Route the EPU05A-02 power cable into the cabinet through the cable outlet at the bottom
of the cabinet, and connect each wire to the corresponding terminal. Then, use a torque
screwdriver to tighten the M6 screws to 4.8 Nm (42.48 lbfin.).
4.
Reinstall the protective cover for the AC input terminals, and tighten the screws on the
protective cover to 0.3 Nm (2.66 lbfin.).
Issue 03 (2014-08-30)
123
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Step 3 Lay out the cables according to the instructions in Cabling Requirements, and use cable ties to
bind them.
NOTICE
l When the EPU05A-02 or EPU05A-04 power cable and DCDU power cable are routed
together, the distance between the two cables must be greater than or equal to 30 mm (1.18
in.). In addition, the EPU05A-02 or EPU05A-04 power cables and DCDU power cables must
be bound separately.
l Route the EPU05A-02/04 power cable through the inner side (close to the RFU subrack) of
the binding bracket, as shown in the following figure.
Issue 03 (2014-08-30)
124
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Step 4 Use a PVC corrugated pipe to protect the cables outside the cabinet, and tie the pipe to the cable
hole on the cabinet.
Step 5 Label the installed cables according to the instructions in Attaching a Sign Plate Label.
----End
Context
NOTE
l LOAD0 to LOAD5 ports on the DCDU-12B feed power into RRUs with a maximum of 560 W power
consumption and require EPC5 connectors.
l LOAD6 to LOAD8 ports on the DCDU-12B feed power into RRUs with a maximum of 400 W power
consumption and require EPC4 connectors.
l The colors and structures of cables vary according to countries and regions. If cables are purchased
locally, the cables must comply with local rules and regulations.
Issue 03 (2014-08-30)
125
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Power
Equipment
One End
RRU power
cable
DCDU-12B
EPC4 or
EPC5
connector
Procedure
Step 1 Prepare an RRU power cable.
1.
Cut the power cable to a length suitable for the actual cable route.
2.
Strip the jacket off the RRU power cable to a length of 20 mm (0.79 in.) from the cable
outlet module.
3.
Route the cable into the cabinet through the cable hole.
4.
Add an EPC4 or EPC5 connector to the RRU power cable on the DCDU-12B side. For
details, see Assembling the EPC4 Connector and the Power Cable or Assembling the EPC5
Connector and the Power Cable.
Step 2 Stick temporary labels onto the RRU power cables to be installed.
Step 3 Add a correct connector to the RRU power cable on the RRU side and connect the connector to
the power port on the RRU. For details, see the related RRU installation guide.
CAUTION
Ensure that the RRU power cable for an RRU added to a running base station must be connected
to the RRU first and then to the power equipment. The operations in the reverse sequence may
cause component damage or personal injury.
NOTE
When installing RRUs outdoors, use a ground clip to ground RRU power cables near the feeder window
before routing them into the equipment room. However, this grounding measure is not required for RRUs
installed indoors. As an example, the following figure shows the procedure for installing power cables for
RRUs installed outdoors.
Step 4 Optional: Route the RRU power cable from the RRU side to the DCDU side through the feeder
window. Install a ground clip near the feeder window outside the equipment room, and connect
the PGND cable on the ground clip to the external ground bar. The installation procedure of
ground clip is as follows:
1.
Issue 03 (2014-08-30)
Use a utility knife to strip 63 mm (2.48 in.) long jacket off the power cable to expose the
shield layer.
126
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
2.
Wrap the copper sheet of the ground clip around the shield layer of the power cable, and
use cable ties to bind them tightly. Then trim off surplus part from the heads of the cable
ties without leaving any sharp edge.
Figure 12-18 Wrapping and tying the copper sheet of the ground clip
(1) Hole for a cable tie (12AWG/4 mm2 or 0.006 in.2) (2) Hole for a cable tie ( 6 mm2 or 0.009 in.2)
3.
Issue 03 (2014-08-30)
Wrap three layers of waterproof tape and three layers of insulation tape around the ground
clip.
127
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
NOTICE
Trim off surplus part of the cable ties at the position 3 mm (0.12 in.) to 5 mm (0.20 in.)
away from the head of the cable tie.
Step 5 Connect the EPC5 connector at the other end of the RRU power cable to one of the LOAD0 to
LOAD5 ports and EPC4 connector to one of the LOAD6 to LOAD8 ports on the DCDU-12B,
as shown in Figure 12-20 and Figure 12-21.
Issue 03 (2014-08-30)
128
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Figure 12-20 Installing an RRU power cable for an RRU with a maximum of 560 W power
consumption
Issue 03 (2014-08-30)
129
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Figure 12-21 Installing an RRU power cable for an RRU with a maximum of 400 W power
consumption
Step 6 Lay out the cables according to the instructions in 12.1 Cabling Requirements, and use cable
ties to bind them.
NOTICE
RRU power cables are bound along the door of the IMS06 to avoid disturbing the open and close
of the door of the cabinet stacked on the IMS06.
Step 7 Remove the temporary labels from the RRU power cables and stick permanent labels onto them.
For detailed operations, see Attaching a Cable-Tying Label.
----End
Issue 03 (2014-08-30)
130
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Prerequisites
l
Ensure the external power supply to the BTS3900 has been shut off.
CAUTION
All tools used for installation must be insulated to ensure personal safety.
Context
NOTE
When two -48 V cabinets are stacked, both the upper cabinet and the lower cabinet are powered by the
external power equipment.
The colors and structures of cables vary according to countries and regions. If cables are purchased locally,
the cables must comply with local rules and regulations.
Wire
Wire
Color in
Most
Regions
Wire
Color in
UK
CrossSectional
Area
Size of the OT
Terminal
DCDU-12A
power cable
NEG(-)
Blue
Gray
M6
RTN(+)
Black
Blue
1x160 A: 35
mm2 (0.054 in.
2)
2x80 A: 16
mm2 (0.025 in.
2)
Issue 03 (2014-08-30)
131
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Procedure
Step 1 Install DCDU-12A power cables.
1.
Measure the distance between the DCDU-12A and the external power equipment based on
the actual cable route, and cut the cables to the length suitable for the actual cable route.
NOTE
When cutting an input power cable, reserve a slack of 300 mm (11.81 in.) for cable layout over the
cable trough on the upper cabinet for future capacity expansion.
2.
Add OT terminals to one end of the power cable according to the instructions in Assembling
the OT Terminal and the Power Cable, and add a connector to the other end of the power
cable depending on the external power equipment.
Step 2 Install the DCDU-12 A power cables, as shown in the following figure.
1.
Remove the protective cover for the wiring terminals from the DCDU-12A.
2.
Connect the OT terminal on the blue DCDU-12A power cable to the NEG(-) terminal on
the DCDU-12A and the OT terminal on the black cable to the RTN(+) terminal on the
DCDU-12A, and use a torque screwdriver to tighten the M6 screws on the OT terminals
to 4.8 Nm (42.48 lbfin).
3.
Reinstall the protective cover, and use a torque screwdriver to tighten the M3 screw on the
protective cover to 0.3 Nm (2.66 lbfin.).
Step 3 Route the other end of the DCDU-12A power cables out of the cabinet from the cable hole on
the top of the cabinet, and connect the cables to the external power equipment.
Issue 03 (2014-08-30)
132
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Step 4 Lay out the cables according to the instructions in Cabling Requirements and Cable Holes, and
use cable ties to bind them.
Step 5 Label the installed cables according to the instructions in Attaching a Cable-Tying Label.
----End
Context
RRU power cables feed power from the DCDU-12B into RRUs.
l
The EPC5 connectors connected to the LOAD0 to LOAD5 ports on the DCDU-12B feed
power into the RRUs (power consumption of each RRU is less than or equal to 560 W).
The EPC4 connectors connected to the LOAD6 to LOAD8 ports on the DCDU-12B feed
power into the RRUs (power consumption of each RRU is less than or equal to 400 W).
NOTE
l The colors and structures of cables vary according to countries and regions. If cables are purchased
locally, the cables must comply with local rules and regulations.
l The type of connector connecting to the power port on the RRU depends on the type of the RRU. For
details about how to add a connector to an RRU power cable, see the related RRU installation guide.
Procedure
Step 1 Prepare an RRU power cable.
1.
Cut the power cable to a length suitable for the actual cable route.
2.
Strip the jacket off the RRU power cable to a length of 20 mm (0.79 in.) from the cable
outlet module.
3.
Route the cable into the cabinet through the cable hole.
4.
Add an EPC4 or EPC5 connector to the RRU power cable on the DCDU-12B side. For
details, see Assembling the EPC4 Connector and the Power Cable or Assembling the EPC5
Connector and the Power Cable.
Step 2 Add a correct connector to the RRU power cable on the RRU side and connect the connector to
the power port on the RRU. For details, see the related RRU installation guide.
CAUTION
Ensure that the RRU power cable for an RRU added to a running base station must be connected
to the RRU first and then to the power equipment. The operations in the reverse sequence may
cause component damage or personal injury.
Issue 03 (2014-08-30)
133
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
NOTE
When installing RRUs outdoors, use a ground clip to ground RRU power cables near the feeder window
before routing them into the equipment room. However, this grounding measure is not required for RRUs
installed indoors. As an example, the following figure shows the procedure for installing power cables for
RRUs installed outdoors.
Step 3 Optional: Route the RRU power cable from the RRU side to the DCDU side through the feeder
window. Install a ground clip near the feeder window outside the equipment room, and connect
the PGND cable on the ground clip to the external ground bar. The installation procedure of
ground clip is as follows:
1.
Use a utility knife to strip 63 mm (2.48 in.) long jacket off the power cable to expose the
shield layer.
Figure 12-23 Stripping the jacket off the power cable
2.
Wrap the copper sheet of the ground clip around the shield layer of the power cable, and
use cable ties to bind them tightly. Then trim off surplus part from the heads of the cable
ties without leaving any sharp edge.
Figure 12-24 Wrapping and tying the copper sheet of the ground clip
(1) Hole for a cable tie (12AWG/4 mm2 or 0.006 in.2) (2) Hole for a cable tie ( 6 mm2 or 0.009 in.2)
3.
Issue 03 (2014-08-30)
Wrap three layers of waterproof tape and three layers of insulation tape around the ground
clip.
Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
134
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
NOTICE
Trim off surplus part of the cable ties at the position 3 mm (0.12 in.) to 5 mm (0.20 in.)
away from the head of the cable tie.
Step 4 Connect the EPC5 or EPC4 connector at the other end of the RRU power cable to one of the
LOAD0 to LOAD5 ports or one of the LOAD6 to LOAD8 ports, respectively, on the
DCDU-12B, as shown in Figure 12-26 and Figure 12-27.
Issue 03 (2014-08-30)
135
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Issue 03 (2014-08-30)
136
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Step 5 Lay out the cables according to the instructions in Cabling Requirements and Cable Holes, and
use cable ties to bind them.
Step 6 Label the installed cables according to the instructions in Attaching a Sign Plate Label.
----End
137
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Prerequisites
NOTICE
Ensure that both ends of the E1/T1 cable are disconnected from any equipment. Then, solder a
connector to each E1/T1 cable during the same session.
Context
l
This section describes the connections and routing of E1/T1 cables for the BTS3900
(Ver.D) DC. The connections and routing of E1/T1 cables for BTS3900 (Ver.B), BTS3900
(Ver.C), and BTS3900 (Ver.D) are the same.
This section describes how to install E1/T1 cables in a GU base station using independent
transmission. For details about E1/T1 cable connections in other scenarios, see section
"Transmission Cable Connections" in the related 3900 Series Base Station Cables.
Procedure
Step 1 Connect one end of the E1/T1 cables to the E1/T1 ports on the GTMU/WMPT/UMPT/UTRP,
and tighten the two captive screws on each board to 0.25 Nm (2.21 lbfin.).
Step 2 Route the other end of the E1/T1 cables out of the cabinet through the cable hole on the top right
side of the cabinet, and then connect the E1/T1 cables to the external transmission equipment,
as shown in the following figure.
Figure 12-28 Installing the E1/T1 cables
Step 3 Lay out the cables according to the instructions in Cabling Requirements and Cable Holes, and
use cable ties to bind them.
Issue 03 (2014-08-30)
138
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Step 4 Label the installed cables according to the instructions in Attaching an L-Shaped Label.
----End
Context
l
This section describes the procedure for installing the FE/GE Ethernet cables for a BTS3900
(Ver.D) DC. The procedures for installing the FE/GE Ethernet cables for the BTS3900
(Ver.B), BTS3900 (Ver.C), and BTS3900 (Ver.D) are the same.
This section describes how to install FE/GE Ethernet cables in a GU base station using
independent transmission. For details about FE/GE Ethernet cable connections in other
scenarios, see section "Transmission Cable Connections" in the related 3900 Series Base
Station Cables.
Procedure
Step 1 Connect one end of the FE/GE Ethernet cables to the FE0 ports on the GTMU, WMPT, UMPT,
LMPT, or UTRP.
Step 2 Route the other end of the FE/GE Ethernet cables out of the cabinet through the cable hole on
the top right side of the cabinet, and then connect the E1/T1 cables to the external transmission
equipment, as shown in the following figure.
Figure 12-29 Installing the FE/GE Ethernet cables
Step 3 Lay out the cables according to the instructions in Cabling Requirements and Cable Holes, and
use cable ties to bind them.
Issue 03 (2014-08-30)
139
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Step 4 Label the installed cables according to the instructions in Attaching an L-Shaped Label.
----End
Prerequisites
NOTICE
l Wear an ESD wrist strap or a pair of ESD gloves to prevent damage to any module.
l The performance of an optical module may deteriorate if it is exposed to the air for more
than 20 minutes. Therefore, insert a fiber optic cable into an unpacked optical module within
20 minutes.
Context
l
Single-mode optical modules are labeled as SM and multimode optical modules are labeled
as MM.
The puller of a single-mode optical module is blue. The puller of a multimode optical
module is black or gray.
The optical modules to be installed must match the rates of their corresponding ports.
An FE/GE fiber optic cable has an LC connector at one end and an FC connector, SC
connector, or LC connector at the other end.
The SFP0 and FE/GE0 ports on the LMPT are used for one GE input. Therefore, the two
ports cannot be used simultaneously.
The SFP1 and FE/GE1 ports on the LMPT are used for another GE input. Therefore, the
two ports cannot be used simultaneously.
This section describes the procedure for installing the FE/GE fiber optic cables for a
BTS3900 (Ver.D) DC. The procedures for installing the FE/GE fiber optic cables for the
BTS3900 (Ver.B), BTS3900 (Ver.C), and BTS3900 (Ver.D) are the same.
This section describes how to install FE/GE fiber optic cables in a GU base station using
independent transmission. For details about FE/GE fiber optic cable connections in other
scenarios, see section "Transmission Cable Connections" in the related 3900 Series Base
Station Cables.
Procedure
Step 1 Install an optical module, as shown in Figure 12-30 and Figure 12-31.
1.
Remove the dustproof cap from the corresponding FE/GE optical port on the corresponding
board in the BBU.
2.
Issue 03 (2014-08-30)
140
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
3.
4.
5.
Step 2 Install the fiber optic cables, as shown in Figure 12-32 and Figure 12-33.
1.
Remove the dust-proof caps from the connectors at the end labeled 2A and 2B on the fiber
optic cables, and insert the connectors into the optical modules in the BBU.
2.
Route the fiber optic cables out from the cable hole on the top right side of the cabinet.
3.
Connect the other end of the fiber optic cables to a routing device.
Figure 12-32 Removing the dust-proof caps from the fiber optic cable
Issue 03 (2014-08-30)
141
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
NOTICE
The TX and RX ports on the BBU boards must be connected to the RX and TX ports on the
transmission equipment, respectively.
Step 3 Lay out the cables according to the instructions in Cabling Requirements and Cable Holes, and
use cable ties to bind them.
Step 4 Label the installed cables according to the instructions in Attaching an L-Shaped Label.
----End
Prerequisites
Cabinets have been installed side by side or stacked.
Issue 03 (2014-08-30)
142
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Procedure
Step 1 Connect one end of the monitoring signal cable between two cascaded FAN 03C assemblies to
the COM OUT port on the fan assembly in the basic cabinet, and the other end to the COM IN
port on the fan assembly in the extension cabinet, as shown in Figure 12-35 and Figure
12-34.
Figure 12-34 Installing the monitoring signal cable between cascaded FAN 03C assemblies (for
cabinets installed side by side)
Issue 03 (2014-08-30)
143
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Figure 12-35 Installing the monitoring signal cable between cascaded FAN 03C assemblies (for
stacked cabinets)
Step 2 Lay out the cable according to the instructions in Cabling Requirements and Cable Holes, and
use cable ties to bind it.
Step 3 Label the installed cable according to the instructions in Attaching an L-Shaped Label.
----End
Issue 03 (2014-08-30)
144
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Prerequisites
l
Optical modules, fiber optic cables, and electrical cables meeting the following
requirements are available:
The optical modules and fiber optic cables are of the multimode type.
The rate of optical modules installed in the UMPT and UCIU is 5 Gbit/s or 2.5 Gbit/s.
The inter-WBBPf signal cable is a QSFP electrical cable.
NOTE
l The single-mode optical module is labeled as SM and the multimode optical module is labeled
as MM.
l The puller of a single-mode optical module is blue and the puller of a multimode optical module
is black or gray.
l Figure 12-36 shows the label on an optical module.
(2) Wavelength
Context
The following table lists BBU interconnection modes and the positions to which inter-BBU
signal cables are connected. For details about BBU interconnection modes, see Inter-BBU Signal
Cable Connections.
Table 12-4 Positions to which inter-BBU signal cables are connected
Interconnection
Mode
Installation Position
BBU 0
BBU 1
UCIU+UMPT
UMPT+UMPT
Issue 03 (2014-08-30)
145
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
NOTICE
A color-coding tape marked Master is attached to one end of an inter-BBU cable that connects
two UMPTs in different BBUs. When installing the cable, connect the end marked Master to
the CI port on the UMPT in BBU 0 and the other end to the CI port on the UMPT in BBU 1.
NOTE
NOTICE
The performance of an optical module may deteriorate if it is exposed to the air for more than
20 minutes. Therefore, insert a fiber optic cable into an unpacked optical module within 20
minutes.
Procedure
Step 1 Remove the dustproof cap from the corresponding port on the BBU and install the optical
modules in BBU 0 and BBU 1, as shown in the following figure.
1.
2.
3.
Step 2 Remove dustproof caps from both ends of the fiber optic cable, as shown in Figure 12-38.
Issue 03 (2014-08-30)
146
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Figure 12-38 Removing the dustproof caps from the fiber optic cable
Step 3 Install one or two inter-BBU signal cables connecting the UCIU to the UMPT. The following
figure shows the installation of two inter-BBU signal cables.
NOTE
l You need to install two inter-BBU signal cables connecting the UCIU to the UMPT in GU+UL mode.
l You need to install only one inter-BBU signal cable connecting the UCIU to the UMPT in GU+L or GL+U
mode.
1.
Connect one end of the cables to the M0 and M1 ports on the UCIU in BBU 0.
2.
Connect the other end of the cables to the CI ports on the UMPT_U and UMPT_L in BBU
1.
Step 4 Optional: Install an inter-BBU signal cable between the WBBPf boards in the two BBUs, as
shown in the following figure. This cable is required only when baseband interconnection is
supported.
1.
Connect one end of the cable to the HEI port on the WBBPf in BBU 0.
2.
Connect the other end of the cable to the HEI port on the WBBPf in BBU 1.
NOTE
l Optical modules with the same labels are of the same type. On BBU 1, install optical modules of the same
type as those on BBU 0.
l You need to connect the end labeled 2A and 2B on the fiber optic cable to BBU 0, and the end labeled 1A
and 1B on the fiber optical cable to BBU 1.
l The TX and RX ports on BBU 0 must be connected to the TX and RX ports on BBU 1, respectively.
l In the BTS3900 (Ver.B), BTS3900 (Ver.C), and BTS3900 (Ver.D) cabinets, the installation positions and
routing of the inter-BBU signal cables are the same. The following figure uses the BTS3900 (Ver.D) DC
cabinet as an example.
Issue 03 (2014-08-30)
147
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Step 5 Lay out the cables according to the instructions in Cabling Requirements. If a fiber optic patch
cord is used as a BBU interconnection signal cable, use binding straps to bind the BBU
interconnection signal cable before using cable ties to secure it. If another type of cable is used
as a BBU interconnection signal cable, directly use cable ties to secure it.
Step 6 Label the installed cables according to the instructions in Attaching an L-Shaped Label.
----End
Procedure
Step 1 Install a BBU alarm cable, as shown in the following figure.
1.
Connect the RJ45 connector at one end of the BBU alarm cable to the EXT-ALM0/EXTALM1 port on the UPEU in the BBU.
2.
Connect the RJ45 connector at the other end of the cable to the external alarm device.
Issue 03 (2014-08-30)
148
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Step 2 Lay out the cable according to the instructions in 12.1 Cabling Requirements and use cable
ties to bind it.
Step 3 Label the installed cable according to the instructions in Attaching an L-Shaped Label.
----End
Context
l
This section describes the procedure for installing RF jumpers in a BTS3900 (Ver.D) DC.
The procedures for installing RF jumpers in BTS3900 (Ver.B), BTS3900 (Ver.C), and
BTS3900 (Ver.D) are the same.
Inter-RFU RF signal cables have been installed in the cabinet before delivery. You need
to check whether they are connected securely.
Procedure
Step 1 Route RF jumpers through the cable holes into the cabinet. Then lay out the jumpers according
to the instructions in Cabling Requirements.
NOTE
Reserve a slack of 300 mm (11.81 in.) for the jumper to facilitate cabling in the upper cabinet if two cabinets
are stacked for capacity expansion.
Step 2 Connect the jumper DIN connector to the ANT port on the RFU panel and use a torque wrench
to tighten the DIN connector with a torque between 25 Nm (221.27 lbfin.) and 35 Nm (309.78
lbfin.), the following figure shows the RF jumper installation when the RFUs are not
interconnected or interconnected, respectively.
Issue 03 (2014-08-30)
149
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Step 3 Use cable ties to bind the RF jumpers, as shown in the following figure.
NOTE
l RF jumpers are routed in the same way regardless of whether or not RFUs are interconnected. As an example,
the following figure shows the RF jumper route when RFUs are not interconnected.
l The RF jumper route for BTS3900 cabinets installed side by side is the same as that for a single BTS3900
cabinet. The following figure shows the RF jumper route for a single BTS3900 cabinet and RF jumper route
for stacked BTS3900 cabinets.
Issue 03 (2014-08-30)
150
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Step 4 Attach color codings to RF jumpers according to the instructions in Color Ring for the Antenna
System and Attaching the Color Ring.
----End
Issue 03 (2014-08-30)
151
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Context
l
If boards and modules have been installed in the cabinets before delivery, CPRI electrical
cables have also been installed in the cabinets before delivery. Installation personnel only
need to install the CPRI electrical cable between cabinets, which is 3 m (9.84 ft.) in length.
This section describes the connections and routing of CPRI electrical cables for a BTS3900
(Ver.D) DC. The connections and routing of CPRI electrical cables for the BTS3900
(Ver.B), BTS3900 (Ver.C), and BTS3900 (Ver.D) are the same.
The connections of CPRI electrical cables depend on the configurations of a base station.
For details, see section "CPRI Cable Connections" in the 3900 Series Base Station
Cables. This section describes the routing of CPRI electrical cables.
Procedure
Step 1 Remove dustproof bags from the connectors at both ends of the CPRI electrical cables.
Step 2 Insert the SFP connectors at one end of the CPRI electrical cables into the CPRI ports on the
corresponding board in the BBU.
NOTE
For details about how to connect and disconnect CPRI cables, see Inserting and Removing CPRI Cables.
Step 3 Connect the other end of the CPRI electrical cables to the corresponding RFUs according to
cabling requirements. The following figure shows the routing.
Figure 12-43 Installing CPRI electrical cables
Issue 03 (2014-08-30)
152
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Step 4 Insert the SFP connectors at the other end of the CPRI electrical cables to the CPRI0 ports on
the panels in the RFUs, as shown in Figure 12-43.
Step 5 Route the cables according to the instructions in Cabling Requirements and Cable Holes.
NOTE
l If two cabinets are stacked, when connecting the CPRI port on the RFU in slot 0 in the upper cabinet
and the CPRI0 port on the GTMU in slot 6 in the lower cabinet, choose a shorter cabling path on either
side of the cabinet if the cable length is insufficient. Reserve a certain slack when cabling to prevent
disturbance on removing or inserting boards.
l Route the cables by following the instructions in Figure 12-43. You must route the cables to RFUs
through the cable tray under the RFU subrack.
l Bind the cables during the cable routing. Tie the cables on the binding bracket by leading the cable ties
around the cable in a diagonal way to upper and lower cabling teeth. Ensure that the heads of all the
cable ties are outside the cabling teeth, as shown in the following figure.
Step 6 Place the excess of the installed CPRI electrical cables into the gaps on both sides of the RFU
subrack, as shown in the following figure.
Issue 03 (2014-08-30)
153
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Figure 12-45 Position for placing the excess of the installed CPRI electrical cables
Step 7 Label the installed cables according to the instructions in Attaching an L-Shaped Label.
----End
Context
l
Single-mode optical modules are labeled as SM and multimode optical modules are labeled
as MM.
The puller of a single-mode optical module is blue and the puller of a multimode optical
module is black or gray.
The optical modules to be installed must match the rates of their corresponding ports.
This section describes the connections and routing of CPRI fiber optic cables for a BTS3900
(Ver.D) DC. The connections and routing of CPRI fiber optic cables for the BTS3900
(Ver.B), BTS3900 (Ver.C), and BTS3900 (Ver.D) are the same.
The connections of CPRI fiber optic cables depend on the configurations of a base station.
For details, see section "CPRI Cable Connections" in the 3900 Series Base Station
Cables. This section describes the routing of CPRI fiber optic cables in the GU+UL
scenario.
Issue 03 (2014-08-30)
154
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
NOTICE
The performance of an optical module may deteriorate if it is exposed to the air for more than
20 minutes. Therefore, insert a fiber optic cable into an unpacked optical module within 20
minutes.
NOTE
In the capacity expansion scenario where a new cabinet is stacked on the original cabinet, CPRI fiber optic cables
in the upper cabinet must be installed onsite. The CPRI fiber optic cables in the upper cabinet must be routed
between the installed cables and run upwards.
Procedure
Step 1 Install an optical module, as shown in the following figure.
1.
2.
Insert the optical module into the CPRI port on the GTMU, WBBP, LBBP, UBRI, or UBBP,
and then insert the optical module of the same type into the CPRI_W, CPRI0, or CPRI0/
IR0 port on the RRU.
NOTE
Optical modules with the same labels are of the same type.
3.
Step 2 Install CPRI fiber optic cables, as shown in the following figure.
1.
Remove the dustproof caps from the connectors on the fiber optic cables.
2.
Insert the DLC connectors labeled 2A and 2B at one end of the CPRI fiber optic cable into
the optical modules in the GTMU, WBBP, LBBP, UBRI, or UBBP, and then insert the
DLC connectors labeled 1A and 1B at the other end into the optical module in the RRU.
Issue 03 (2014-08-30)
155
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
NOTICE
l When CPRI fiber optic cables connect the BBU and RRUs, the breakout cables on the
BBU side are 0.34 m (13.39 in.) long and the breakout cables on the RRU side are 0.03
m (1.18 in.) long.
l If an LC-LC fiber optic cable is used, the TX and RX ports on the BBU must be
connected to the TX and RX ports on the RRU, respectively.
Step 3 Route the CPRI fiber optic cable out of the cabinet from the cable hole on the top left or right
according to the instructions in Cabling Requirements, as shown in the following figure.
NOTE
The CPRI fiber optic cable must be routed out of the cabinet from the nearer cable hole. If more than 12
CPRI fiber optic cables need to be routed into or out of the cabinet, route 12 cables from the left cable hole
and the remaining cables from the right cable hole.
Issue 03 (2014-08-30)
156
BTS3900(Ver.D)
Installation Guide
12 Installing Cables
Step 4 Lay out the cables according to the instructions in Cabling Requirements and Cable Holes, and
use cable ties to bind them.
Step 5 Label the installed cables according to the instructions in Attaching an L-Shaped Label.
----End
Issue 03 (2014-08-30)
157
BTS3900(Ver.D)
Installation Guide
13 Installation Checklist
13
Installation Checklist
After the cabinets and devices are installed, you need to check the installation items, installation
environment, and cable-related items.
Item
The installation position of the cabinet strictly complies with the engineering
design.
All the bolts, including those for electrical connections, are tightened. The spring
washers and the flat washers are installed in the correct sequence.
The paint on the surface is intact. The damaged paint is repaired. For details, see
Repainting.
Issue 03 (2014-08-30)
No.
Item
158
BTS3900(Ver.D)
Installation Guide
13 Installation Checklist
No.
Item
No tapes, tails of cable ties, paper, or packing bags are left around the cabinet.
Item
All self-made PGND cables are copper-based with proper core diameters. There
should not be any switch or fuse in the grounding system. No short circuit is allowed.
The PGND cable is securely connected and the AC input power cable and cables
in the cabinet are correctly connected according to the electrical design of the power
system. The screws are tightened. In addition, the inputs or outputs are not shortcircuited.
The redundant part of the power cable or PGND cable is cut off rather than coiled.
The terminals at both ends of the power cable or PGND cable are securely soldered
or crimped.
The bare wires and the terminal handles at the wiring terminals are coated with heat
shrink tubing.
The flat washers and the spring washers are well mounted on all OT terminals.
The exterior of the storage battery is intact without any scratch, dent, or crack.
The shell of the storage battery is clean without any leakage trace.
The wiring terminal on the storage battery stands properly without any damage, and
the post is not covered with any acid substances.
10
The pressure relief valve of the battery is not deformed, and no liquid leaks.
11
The power cables for the storage batteries are correctly connected to the positive
and negative poles.
12
13
Issue 03 (2014-08-30)
The circuit breakers for the storage batteries are set to OFF.
159
BTS3900(Ver.D)
Installation Guide
13 Installation Checklist
Item
All cables, especially the Ethernet cables for communication, are securely
connected. All cable connectors at the bottom of the cabinet are securely installed.
The cables are neatly and tightly bound. The cable ties are evenly spaced and face
the same direction.
Different types of cables, such as the power cable, PGND cable, feeder, fiber optic
cable, E1/T1, and FE/GE signal cable are separately bound.
The layout of all cables facilitates the maintenance and capacity expansion. For
example, the maintenance transfer cable is bound to the outside of the BBU cable
claw, as shown in the following figure.
The extra length of the indoor cable ties is cut off, and the cut surfaces are smooth
without sharp edges. The extra length of 3 mm (0.11 in.) to 5 mm (0.19 in.) of the
outdoor cable ties is reserved when the cable ties are cut.
The connectors of the RF cables are secured to avoid false connection that will cause
an abnormal voltage standing wave ratio (VSWR).
Issue 03 (2014-08-30)
160
BTS3900(Ver.D)
Installation Guide
14
This section describes how to power on a base station and handle a failure in the power supply
to the components in a cabinet.
Prerequisites
l
The power supply to the BTS3900 meets the requirements of the power system, please refer
to Power Supply Requirements of the BTS3900.
The external power supply to the BTS3900 has been shut off.
Circuit breakers on the boards in the BBU have been set to OFF.
Check the version of the base station to confirm that the circuit breakers listed in Table
14-1 have been set to OFF.
Context
DANGER
Exercise caution when performing a power-on check, which involves some high voltage
operations. Direct contact with the input voltage or indirect contact with the input voltage using
a damp object may be fatal.
NOTICE
l Power on a cabinet, BBU3910, or BBU3900 within 7 days after unpacking it. If you power
off a cabinet or BBU for maintenance, restore power to the cabinet or BBU within 48 hours.
l Power on an RRU within 24 hours after unpacking it. If you power off an RRU for
maintenance, restore power to the RRU within 24 hours.
The circuit breakers in BTS3900 base stations are listed as the following table.
Issue 03 (2014-08-30)
161
BTS3900(Ver.D)
Installation Guide
Power Device(1)
Circuit Breaker
BTS3900
(Ver.B)
DCDU-01, DCDU-03B,
EPS4890, or
EPS24S48100DC
BTS3900
(Ver.C)
DCDU-11A,
DCDU-11B, or
ETP48150-A3
BTS3900
(Ver.D)
DCDU-12A,
DCDU-12B, or
EPU05A-02
NOTE
(1) In this section, EPU05A-02 is shortened to EPU, EPS4890 and EPS24S48100DC are shortened to EPS,
ETP48150-A3 is shortened to ETP, and a DCDU of any model is shortened to DCDU.
Issue 03 (2014-08-30)
162
BTS3900(Ver.D)
Installation Guide
Issue 03 (2014-08-30)
163
BTS3900(Ver.D)
Installation Guide
Procedure
Step 1 Use a multimeter to measure the resistance between the external power supply and the ground
to ensure that there is no short circuit.
Step 2 Turn on the external power circuit breaker to power on the BTS3900.
Step 3 Optional: Set the circuit breakers on the EPU or ETP or EPS for the corresponding components
to ON, and check the power supply status of each component. Skip this step for the BTS3900
DC scenario.
Table 14-2 Normal status of the components powered by the EPU or ETP or EPS
Cabinet
Componen
t
BTS3900
PMU
PSU
Step 4 Optional: Set the circuit breakers for the corresponding components on each DCDU in a
BTS3900 cabinet to ON. Skip this step if there is no circuit breaker on the DCDU, such as the
DCDU-12A and DCDU-12B.
Step 5 Set the circuit breaker on the UPEU in the BBU to ON.
Step 6 Check the power supply to each component according to the following figure.
Table 14-3 Normal status of components in the cabinet
Component
BBU
RFU
l RUN indicator: on for 0.125s and off for 0.125s or on for 1s and off
for 1s
l ALM indicator: steady off
Fan assembly
l RUN indicator: on for 0.125s and off for 0.125s or on for 1s and off
for 1s
l ALM indicator: steady off
Issue 03 (2014-08-30)
164
BTS3900(Ver.D)
Installation Guide
Component
RRU
l RUN indicator: on for 0.125s and off for 0.125s or on for 1s and off
for 1s
l ALM indicator: steady off
a: If the indicators indicating the status of the CPRI ports are steady red, check whether the
optical module is faulty or the fiber optic cable is broken.
NOTE
The indicators in the preceding table are only examples. For the status of other indicators, see BBU
Hardware Description.
Step 7 Optional: If the power supply to a component fails after the cabinet is powered on, handle the
fault according to the instructions in the following table.
Table 14-4 Troubleshooting
Failure Type
Handling Measure
Check as follows:
1. Remove the board, and check whether any pin of the slot on
the backplane is bent, broken, or missing. Replace the subrack
if necessary.
2. Insert the board into the subrack, and check the status of
indicators on the board.
3. If the indicators indicate an exception, remove the board, insert
it into a vacant slot holding the boards of the same type, and
check the status of the indicators.
l If the board works properly, the original slot is faulty. In
this case, replace the subrack.
l If the fault persists, the board is faulty. In this case, replace
the board.
Issue 03 (2014-08-30)
165
BTS3900(Ver.D)
Installation Guide
Failure Type
Handling Measure
Check as follows:
1. Check whether the indicator on the fuse terminal block that
connects power supply to the component is on. Skip this step
and go to step 2 if this component does not use any fuse
terminal block.
l If the indicator on the fuse terminal block is on, the fuse is
faulty. In this case, replace the fuse according to the
instructions in Replacing a Fuse.
l If the indicator on the fuse terminal block is off, go to step
2.
2. Use a multimeter to measure the input power to the component.
l If the input power is normal, replace the component.
l If the input power is abnormal, check whether the power
cable for the component is connected securely. If the power
cable is not securely connected, turn off the circuit breaker
for the component (if there is no circuit breaker for the
component, remove the connector from the power unit) and
reconnect the power cable. If the power cable is securely
connected, the protector (such as circuit breaker or fuse) on
the component may be damaged. In this case, replace the
damaged protector. If the protector cannot be replaced,
replace the upper-level power distribution component.
----End
Issue 03 (2014-08-30)
166