Trigger:

Concept

The Shifts page enables you to assign the shifts available to the resource. The shifts are those
assigned to the workday calendar that are assigned to the organization.
 
In this topic, you will assign shift information for the resource.

Required Field(s) Comments

Output - Result(s) Comments

Additional Information

Last changed on: 1/18/2010 03:34:00 PM Page 1


System Process Document
Assigning Shift Information for the Resource

Procedure

Step Action
1. Begin by navigating to the Departments page.

Click the vertical scrollbar.

Page 2 Last changed on: 1/18/2010 03:34:00 PM


System Process Document
Assigning Shift Information for the Resource

Step Action
2. Click the Manufacturing and Distribution Manager link.

Last changed on: 1/18/2010 03:34:00 PM Page 3


System Process Document
Assigning Shift Information for the Resource

Step Action
3. Click the vertical scrollbar.

Step Action
4. Click the Departments link.

Page 4 Last changed on: 1/18/2010 03:34:00 PM


System Process Document
Assigning Shift Information for the Resource

Step Action
5. Use the Organizations page to select your organization.

Last changed on: 1/18/2010 03:34:00 PM Page 5


System Process Document
Assigning Shift Information for the Resource

Step Action
6. Click the M1 Seattle Manufacturing list item.

Step Action
7. Click the OK button.

or Press [Alt+O].

Page 6 Last changed on: 1/18/2010 03:34:00 PM


System Process Document
Assigning Shift Information for the Resource

Step Action
8. Use the Departments page to select a department.

Last changed on: 1/18/2010 03:34:00 PM Page 7


System Process Document
Assigning Shift Information for the Resource

Step Action
9. Click in the Departments field.

Step Action
10. Press [F11].

Page 8 Last changed on: 1/18/2010 03:34:00 PM


System Process Document
Assigning Shift Information for the Resource

Step Action
11. Enter the desired information into the Department field. Enter "ASSEMBLY".

Last changed on: 1/18/2010 03:34:00 PM Page 9


System Process Document
Assigning Shift Information for the Resource

Step Action
12. Press [Ctrl+F11].

Step Action
13. Click the Resources button.

or Press [Alt+o].

Page 10 Last changed on: 1/18/2010 03:34:00 PM


System Process Document
Assigning Shift Information for the Resource

Step Action
14. Use the Resources page to select a resource to which you want to enter a shift
number.

Last changed on: 1/18/2010 03:34:00 PM Page 11


System Process Document
Assigning Shift Information for the Resource

Step Action
15. Click in the DL-LBR2 Resource field.

Step Action
16. Click the Shifts button.

or Press [Alt+i].

Page 12 Last changed on: 1/18/2010 03:34:00 PM


System Process Document
Assigning Shift Information for the Resource

Step Action
17. Use the Shifts page to assign shifts available to the resource DL-LBR2.

The shifts available are those assigned to the workday calendar assigned to the
organization.

Last changed on: 1/18/2010 03:34:00 PM Page 13


System Process Document
Assigning Shift Information for the Resource

Step Action
18. Click in the Shift Num field.

Step Action
19. Enter the desired information into the Shift Num field. Enter "1".

Page 14 Last changed on: 1/18/2010 03:34:00 PM


System Process Document
Assigning Shift Information for the Resource

Step Action
20. Click in the Description field.

Last changed on: 1/18/2010 03:34:00 PM Page 15


System Process Document
Assigning Shift Information for the Resource

Step Action
21. Click in the Units field.

Step Action
22. Enter the desired information into the Units field. Enter "1".

Page 16 Last changed on: 1/18/2010 03:34:00 PM


System Process Document
Assigning Shift Information for the Resource

Step Action
23. Click in the Shift Num field.

Last changed on: 1/18/2010 03:34:00 PM Page 17


System Process Document
Assigning Shift Information for the Resource

Step Action
24. Enter the desired information into the Shift Num field. Enter "2".

Step Action
25. Click in the Description field.

Page 18 Last changed on: 1/18/2010 03:34:00 PM


System Process Document
Assigning Shift Information for the Resource

Step Action
26. Click in the Units field.

Last changed on: 1/18/2010 03:34:00 PM Page 19


System Process Document
Assigning Shift Information for the Resource

Step Action
27. Enter the desired information into the Units field. Enter "1".

Step Action
28. Click the Save button.

Page 20 Last changed on: 1/18/2010 03:34:00 PM


System Process Document
Assigning Shift Information for the Resource

Step Action
29. You have completed the Assigning Shift Information for the Resource procedure.