PETROCHINA INTERNATION JABUNG LTD

SHOUT, NORTH, WEST PRODUCTION JABUNG


HAND OVER WELL TESTING AND HOOK UP.
To
: Pak Paison
Subject : Handover note
April, 20, 2010
SOUTH, NORTH, WEST AND WELL HOOK UP JABUNG

Monitoring Activity slick line PT. ENECAL, the program PBU survey at NG*38*
S/S, 39, 39D wells, P.O.P the well, and install gas life valve at NG 31 well
(Completed, Unload unsuccessful).
Monitoring Activity slick line PT. ENECAL, the program SBHP and PBU survey
at MK 05 well.
Monitoring Activity slick line PT.ENECAL, the program PBU survey at NEB 34
well and P.O.P the well.
Monitoring Activity Rig 12 Completion at NG*39*39D (Completed) and move to
WBD-08 well.
Monitoring Activity Rig 11 Completion at Panen Utara 01
Monitoring activity Rig 06 Completion at NEB 71 (Complete) and move to NEB28 well.
Monitoring activity Rig 02 Drilling at SBD-08 and Rig 03 at SBD-02.
Monitoring regular well testing at Geraga, Makmur, Gemah, Ripah, NEB, NB,
SWB, SB, WBD, WB,
Monitoring activity the hook up new gas manifold NEB, 16, 32, 34 at NEB 07
PAD (Completed).
Monitoring well testing by SRP tank at NB, 03, 06, 07, 08 SRP wells.
Monitoring activity HEO brushing from Gemah 08 to Gemah 01 PAD.
Monitoring activity Fab shop hook up install new flow line from GE 08 to GE 01
PAD (waiting material).

Monitoring activity replace temporary separator 1120 to separator V 114 due to


replace inlet SDV corrosion (Complete).
Well testing by gas separator V 114 at MK, 06, 11, 17, 25, 26D, 27, 27D and
NG, 04, 07, 35D wells.
Well testing by separator V 140 at GE 01, 02, 07,25,31,33.
Well testing NB SRP By SRP tank test at, NB 03,06,07,09 wells SRP.

PLAN / OUT STANDING JOB.

Monitoring Activity PT.ENECAL Unit the PBU survey at NEB, 16, 32, 34,
(Continue) and the P.O.P wells.

Monitoring Put on production NEB, 22, 33 wells and testing well by separator
V-114 (coordinate with supv north area).
Regularly of monitoring well testing at Geragai, Makmur, Gemah, Ripah, NEB,
NB, SWB,SB,WBD,WB,
Monitoring activity HEO the brushing area at GE 08 to GE 01( Fab shop waiting
drawing from facilities Jakarta).
Monitoring and follow up Fab shop install spool well head to manifold at GE 28
( prepare material),
Monitoring and follow up install separator, square tank, gas boot, at WBD- 8 ( for
separator from Marmo, square tank, gas boot from KM 06 lay down yard ready
to move).
Monitoring and follow up Separator V 114 to replace temporary MPM separator
V-001 at WB-01 station (Waiting info Pak Chandra / Saiful.)
Monitoring and follow up Civil Construction Additional office well test at lay
down yard ( Waiting Prepare material)
Rig status:
- Rig-2 at SBD-08 drilling
- Rig-3 at SBD-07 drilling.
- Rig-6 at NEB-28 Re Completion.
- Rig-11 at Panen Utara-1 Completion.
- Rig-12 at WBD-08 Completion.

Selamat bekerja
Solihin