Section complete
Primary
Contractor
SCHLUMBERGER
Cement Engineer
VICTOR CUECA
Arrival date/time
06/05/2013 14:36
Copy To Library
06/05/2013 15:55
N2 used
Ground temp.
Zone isolated
Air temp
CO2
Seabed temp.
F
F
F
Geothermal gradient
1.20 F/100ft
BHCT
80.00 F
WOC time
9.00 hr
BHST
80.00 F
Activity phase
Job Description
CEMENTACION
Casing details
Assembly
Hole size
SURFACE CASING
MD landed
453.0 ft
453.0 ft
12.250 in
06/05/2013
Tubing/Casing size
9.625 in
Rathole length
ft
Depths
Float Shoe TVD
453.0 ft
Packer TVD
ft
Pipe movement
Initial rotating TQ
ft-lbf
Reciprocating drag up
kip
Average rotating TQ
ft-lbf
kip
Max. rotating TQ
ft-lbf
Reciprocating SPM
spm
ft
Pipe Movement
Rotating RPM
rpm
F lu i d s
Section complete
Cementing Fluids
Fluid name
1 TAIL
Fluid type
SLURRY
Class
CLASS G
Density (ppg)
15.60
Description
Fluid Details
Slurry Additives Tests Dial
Slurry
Slurry top TVD
0.0 ft
453.0 ft
bbl
0.0 bbl
CASING SUPPORT
bbl
Type
TAIL
gal/sk94
Class
CLASS G
Mix method
Purpose
Density
15.60 ppg
Yield
bbl
ON THE FLY
ft/sk
Description
bbl
0.0 bbl
Sacks used
Sack size
95.00 lbm
80.00 s/qt
Rheology
RPM
rpm
Funnel viscosity
Fluid name
Fluid density
TAIL
9.50 ppg
Density temp
PV
Fluid type
SLURRY
Rheology temp.
YP
API WL
cc/30min
Gels 10 sec.
Density at press.
ppg
Mud type
Deflection
16.00 cp
14.000 lbf/100ft
5.000 lbf/100ft
Gels 10 min.
8.000 lbf/100ft
Gels 30 min.
10.000 lbf/100ft
St a g e s
Section complete
Cementing Stages
Stage no.
1
Type
PRIMARY 1
Stage Details
Stage Information
MD top
18.5 ft
CT used
Circulate prior
hr
TVD top
18.5 ft
MD CTU
ft
gpm
MD base
453.0 ft
TVD CTU
ft
Circulate press.
psi
TVD base
453.0 ft
psi
Tool contractor
Hole size
12.250 in
psi
Tool description
MD tool top
ft
Returns
ft
Bottom plug
Vol. returns
20.0 bbl
MD plug circ.
ft
Bumped plug
Volume lost
bbl
ft
WOC time
hr
Annular flow
Press. held
psi
Tool desc.
MD stage tool
ft
Pressure remaining
psi
ft
Float held
min
psi
Bump press.
psi
psi
Plug bumped
psi
psi
Float held
Hesitation
psi
Pumping Schedule
Hesitation reason
Fluid pumped
Rate
Volume
Operation
Schedule Details
Foam Details
Placement method
Foam job
Slurry top MD
Slurry base MD
Length
Top of fluid
Density
Quality
Strokes
Bh static temp.
Stroke rate
BH circ. temp.
Bulk cement
Flowline temp.
GL ratio
Mixing rate
Overflush vol.
Preflush vol.
Foam density
Initial ratio
Final ratio
T est s
Section complete
Liner Top Test
Casing Test
Test pressure
Comments
1,200.00 psi
Duration
15 min
Test date
06/05/2013 17:04
Test MD top
ft
ft
Test MD btm.
ft
Packer depth
ft
ft
Fluid density
ppg
Liner overlap
ft
hr
453.0 ft
Cement found
ppg
CET run
CET quality
CBL run
CBL quality
CBL press.
psi
hr
ppg
Shoe Test
Shoetrack top MD
ft
ft
ppg
Tool
ft
hr
Shoetrack drill MD
ft
ft
Interpretation Survey
MD TOC
ft
TOC TVD
ft
Interpreter
Interpretation
TOC sufficient
Remedial cement required
No. squeezes
TOC locate method
Job rating
Detection indicator
In t e r m e d i a t e C i r c u l a t i o n s
Circulation type
Md (ft)
Manufacturer
Equipment type
1 SCHLUMBERGER
Equipment name
PUMP UNIT
MD top (ft)
CEMSTREAK
MD base (ft)
0.0
Objective
4.00
453.0
Caliper (in)
12.250
Successful
Section complete
P u mp E q u i p me n t s
Section complete
Is o l a t e d In t er v a ls
Section complete
Wo r k St r in g s
Section complete
Measured
efficiency (%)
95.00
Evaluation date
06/05/2013 16:44
BHA no.
Assembly name
Summary Components
General
BHA no.
Assembly name
RIH time
MD in
Date/Time in
POOH time
MD out
Date/Time out
Min. ID
Hole size
Left in well
Purpose
Create Obstruction
Predicted Performance
Actual Performance
J o b Ac t i v i t y
Date/Time from
1 06/05/2013 14:44
Date/Time to
06/05/2013 16:44
Duration
Activity class
(hr)
2.01 CEMENTING
Activity code
2500
Activity subcode
2512
Section complete
MD from (ft)
MD to (ft)
453.0
Total hours
R e ma r k s
Operation
0.0
Operation success
Service compa
SCHLUMBERGER
2.01 hr
Section complete
REALIZO CEMENTACION DE CASING DE 9 5/8 ASI: PROBO LINEA CON 2500PSI DURANTE 5MIN,OK. BOMBEO 10BBL DE AGUA FRESCA DE 8.3PPG A 3BPM. MEZCLO Y BOMBEO 79 BBL DE LECHADA PRINCIPAL CONVENCIONAL DE 15PPG A 4 BPM. LAVO LINEAS Y DESLAZO
CON 33.6BBL DE AGUA A 3BPM. ULTIMA PRESION DE CIRCULACION 168PSI. RETORNARON 20 BBL DE LECHADA DE 15PPG, BACK FLOW 0.2BBL. 300 SACOS USADOS