Systeem ID: <TD-nummer systeem> Protocol / Versie: IOC-<xxxx/xxx> / <ver.nr> Versie datum: <datum>
<naam project>
<naam project>
MSD Haarlem
protocol afgeleid van template EMSQEIQ-v1, 11-april-2005
INDEX
2.1
2.2
2.3
2.4
2.5
2.6
2.7
4.1
4.2
5.1
5.2
5.3
5.4
5.5
2.
INTRODUCTION
2.1
INTENT OF THIS DOCUMENT
<General description>
This testing and Commissioning Protocol document, hereinafter referred to as TCP, describes the Testing and
Commissioning protocols to be followed for bringing the newly laid crude oil transfer pipe line into service. The
objective of this TCP is to provide documented proof that the important aspects of mandatory pre-commissioning
tests and commissioning procedures comply with the relevant regulations and approved design intentions and are
carried out in a established sequence. This TCP shall also be used as an audit means to verify the correct
functioning of the equipment and the availability of the supporting documentation.
The TCP must also provide documented proof that:
Compliance with the engineering requirements and product specifications of the equipment;
The equipment has been received according to the mentioned specifications;
The equipment has been correctly installed;
The equipment is fully operational and safe to operate;
The equipment and related regulation system perform as designed and specified;
The relevant tests have been performed, to provide proof that the equipment is ready for use and appropriate
for the intended purpose;
A Pre-commissioning or Commissioning activity shall be considered to be complete only when it has been
witnessed and the procedure and the results of successfully carrying out that procedure have been signed off by
both Contractor and Company. Company may also require Vendors representative to witness and sign that
document.
During all the pre-commissioning & commissioning activities, the Contractor shall involve Companys operating staff
(nominated by the Company) and impart necessary techniques and know-how required for operation and
maintenance of the facilities.
This TCP defines the following state of the Works:
Mechanical Completion
Ready for Pre Commissioning
Ready for Commissioning
Description
2.5
2.6
2.7
3.
DEFINITIONS
Mechanical Completion
Type
Check systems conforming to the requirements of the P & I Ds, drawings and datasheets
Complete any site modifications that may be required
Testing of PSVs .
Leak Testing
Internal Inspection of Vessels
Inspection of strainers / filters, orifice plates and other piping specialties.
Operability test of all utility systems except those, which cannot be operated at the yard
System Flushing and Cleaning
Operability test of all pumps and rotating equipment.
- On line testing and calibration checks of all instruments and loop checking of all such instruments
- Installation and hook-up of gas detector fusible plug, ESD/FSD stations etc.
- ESD/FSD loop testing
- Functional test and associated loop testing incoming and outgoing (to and fro) from well/ fire
shutdown panel
- Functional test and associated loop testing related to Fire and Gas detection system
- Functional test and associated loop testing related to Telemetry Interface Cabinet
- Any other instrument related activity not listed above but mentioned in the relevant functional
specifications elsewhere in the Bid Package
4.
4.1
All tests in this protocol are added in the appendices. The test specific instructions are mentioned at each specific
test.
5.
5.1
Test methodology
This paragraph describes the way a test should be executed, evaluated and how to determine whether or not a test
result is acceptable. The execution of tests and verifications can start after approval of the qualification protocol. All
test- and verification results must be signed for at the provided space.
When all tests and verifications have successfully been completed, it is assumed that all requirements have been
met. When an error is found during the execution of the protocol an error report must be filled out according to
TQS. Each report receives an unique number and is added to the error overview (index) in Appendix F. The error
report is also added in Appendix F.
5.2
Specification checks
These checks must verify if the delivered equipment meets the required specifications. To ensure that the source of
each verification is properly documented, each check must use the verification methods mentioned below. The
verification methods are:
Verification Definition
method
Example
Visual confirmation
Dimensions
Construction material
Allocation
Model no..
Nominal power usage
Specified operating range
Nominal
pressure
temperature
sheets/ certificates.
Equipment
drawings
Miscellaneous
specify)
checked
and
(please --- *
Calibrated range
Pump power / pump rpm
Check lay-out / piping
Check wires / electrical
---
* If possible the specifications must be checked using tests, since that gives complete confidence in the test result.
The above mentioned codes must be noted in the space to register the verification method for each test.
5.3
Documentation standards
The relevant procedures and instructions for documenting the results are stated in the list below:
TQS
TQS\TCP\02-200
TQS\TCP\02-204
Description
Writing and closing of protocols
IC, OC, IOC, IQ, OQ and IOQ protocols
TQS\TCP\02-401
5.4
Mechanical release
Before active tests can take place as part of the TCP, the mechanical release of the installation must be agreed
upon between the Qualification Engineer that executed the protocol and the Project Coordinator that is responsible
for the installation. This is done to verify if the installation is complete as intended and safe to commence with TCP
tests
5.5
It is allowed to commence with the operational tests (Appendix A) if the responsible Qualification Engineer has
verified that the criteria below have been met:
.
Herewith we declare that mechanical release has taken place and that the equipment / installation is safe to
commence with active TCP tests and that no errors have been found
1.
APPENDIX OVERVIEW
Total number of
pages
Error:
Error:
Error:
Error:
ERROR:
Signature
Date