1) Introduction
1.1) Estimated Area of Scheme
2) Related Theory
2.1) Sewerage System
2.2) Essential Components of Sewerage System
2.3) Sources of waste water
i.
ii.
iii.
Domestic
Industrial
Storm Water
Separate System
Combined System
Partially Combined System
b) Types of Sewers
i.
ii.
iii.
iv.
v.
vi.
vii.
viii.
Sanitary Sewers
Storm Sewer
Combined Sewer
House Sewer
Lateral sewer
Sub-Main Sewer
Vii) Main/ Trunk Sewer
Outfall Sewer
i.
ii.
Sewer system
Sewer Pumping Station
Continuity Equation
Mannings Equation
3.7) Infiltration
3.8) Invert Level
i)
ii)
iii)
iv)
v)
vi)
1) Introduction:
Sewer system must be properly planned, designed and operated in order to protect the
environment and people from serious diseases.
No. of Apartments = 3
No. of Flats = 3
No. of Houses = 281
No. of Schools = 1
No. of Parks = 2
No. of Dispensaries = 1
No. of Graveyards = 1
Description
Persons per plot
28800 m2
34575 m2
2) Related Theory:
5825 m2
Sewer:
It is the pipe or conduit for carrying sewage. It is generally
closed and flow takes place under gravity (Atmospheric
Pressure).
Sewerage:
Sewerage is the system of collection of waste water and conveying it to a point of final disposal
with or without treatment.
i) Domestic:
It is the waste water from houses, offices, other
buildings, hotels and institutions.
ii) Industrial:
It is the liquid waste from the industrial places from
their different industrial processes like dying, paper
matting, tanneries, chemical industries, etc.
i) Separate System
If storm water is carried separately from domestic and industrial wastewater the system is called
as separate system. Separate systems are favored when
There is an immediate need for collection of the sanitary sewage but not for storm water.
When sanitary sewage needs treatment but the storm water does not.
(In Urban area of developing countries, mostly partially combined system is employed as
it is economical)
In Pakistan we use this system.
b) Types of Sewers
i) Sanitary Sewers:
It carries sanitary sewage i.e. waste water from
municipality including Domestic and Industrial
wastewaters.
v) Lateral sewer:
This sewer carries discharge from two or more house
sewers.
i) Manholes:
The purpose of the manhole is cleaning, inspection of the sewage and to have the house
connections.
These are provided at every change of the direction of the pipe and where ever the two pipes of
different diameters are used or where the slope is to be change in the design of the IEER society.
As in the design the diameter of the largest pipe is 610 mm so the spacing of 100m and 120 m is
provided where it was required.
The flush is provided where the velocity of the sewerage is less and waste
materials are settled in the flush tanks which are cleaned periodically.
Find the present population of the project area. Then find the design population from the
given design period. Afterwards find average sewage flow for the design population.
Using this average sewage flow for design population, select peak factor for your project
area from table # 01
Draw the layout of the sewer system keeping in view the layout of the roads and streets
(represent each sewer with a line and manhole with a dot).
Number the manhole and identify each sewer line (Like M1M2, M2M3, etc).
Allocate Plots or Area to each sewer Line. (col 6,7,8)
Measure the length of each sewer line as scale of your map. Also show direction of flow
in sewer line with an arrow.
By adopting per capita sewage flow as 80-85%of water consumption, calculate average
sewage flow (col 11) and infiltration (col, 12.) for each sewer line. For this design
problem take infiltration rate as 5% of average sewage flow.
Calculate peak sewage flow (col, 12) and finally the design flow (col, 1 & IG) for the
sewer lines.
Using the method of back calculation, find approximate diameter (col, 18) and slope (col,
19) for your sewer assuming that the sewer is flowing frill. For back calculation choose a
suitable design table with a suitable self-cleansing velocity (0.7 m/sec). See Table 02.
In the end find the invert level (col,24 & 25) for all the sewers and complete the table of
calculation called Hydraulic Statement.
Where;
Q max
14
=1+(
)
Qavg
4+ P
P is population in thousands
WASA Lahore Design Considers the Following Relationship for Sewer Design
Average Sewage Flow (m3 /day)
2500
2500 5000
5000 10000
10000 25000
25000 50000
50000 100000
100000 250000
250000 500000
> 500000
Peak Factor
4.0
3.4
3.1
2.7
2.5
2.3
2.15
2.08
2.0
225mm to 380mm
460mm to 760mm
3.7) Infiltration:
It is amount of water that enters into the sewers through poor joints, cracked pipes, walls and
covers of manholes. It is nonexistent during dry weather but increases during rainy season.
Water and Sanitation Agency (WASA) Lahore uses the following infiltration rates for the design
of sewer system.
Sewer Diameter
225 mm to 600 mm
> 600 mm
Infiltration
5 % of Avg. Sewage Flow
10 % of Avg. Sewage Flow
We use the concrete pipes with Bell and Spigot Joints in our scheme and different sketches for
these pipes are given below
1:2
Flow
Spigot
Rubber Ring
Jute
Flow
The map is attached with proper highlights of sub-main, main or trunk sewer.
Calculation table prepared on excel is attached with the report.
Longitudinal profiles of sewer are also attached with the report.
For a single sewer line the calculations are shown as;
Diameter:
2
Q= AV = D V
4
D=
4Q
40.007791228
=
1000=119.0745 mm
V
0.7
Slope:
Using Mannings Equation:
1
V = R 3 S 2
n
S=(
Vn
) =0.002504054
2
R3
Invert Level:
Upper Invert Level = Ground Level Earth cover Thickness - Diameter
Upper Invert Level = 100.7 1 0.05 0.310 = 99.34 m
Fall = Slope x Length = 0.002504054 x 105 = 0.262925 m
Lower Invert Levels = Upper Invert Level fall = 99.34 0.262925 = 99.0770 m
Velocity Computation:
2
3
Qfull =AV = 0 .310 0.7=0.0527394 m /sec
4
Qa 0.007791228
=
=0.147730
Q full
0.0527394
d
=0.3( theGraph)
D
Va
=0.6(the Graph)
V full
5) Cost Analysis:
The cost analysis is not the exact one. This cost analysis is performed just to give idea or
concept.
Total Cost = Cost of excavation + Cost of the piping (laying, jointing) + Cost of manholes
Work
Earthwork Cost
Manholes Cost
Pipes Cost
Total Cost
Cost(Rs.)
238551.4238
165000
1067400
1470951.424
Minimum diameter is taken as 310 mm and other diameters are considered according to
WASA standard (locally available).
Minimum clear cover of 1-m is provided above the sewer in order to avoid from impact
of live loading.
We use the concrete pipes with Bell and Spigot Joints in our sewer system.
Minimum self-cleansing velocity was not maintained in most of the pipes so it is
recommended to make a provision of septic tank for every house.
Used Concrete pipes in the sewerage system design which is most economical.
Considering the economy, design is done for the partially combined sewerage system.
Manholes should be cleaned after the passage of time.
Bedding of the sewers should be selected according the criteria by calculating the Load
Factor.
3-edge bearing test should be carried on the sewer pipes to know the strength of the
sewers.
7) References: