Anda di halaman 1dari 8

Product Manual GIS

Delivery

1.4 Building Requirements


1.4.1 Static and Dynamic Loads

Circuit Breaker

Cable Sealing End

340 340
100
500

650

15KN

250

100

200

250

300

680

15KN
2

1050

350

350

700
620

1525
2145

GIS base frame (2x MSH100x100)

dynamic load points of circuit breaker

Figure 1.4-1: Load points double busbar bay with cable sealing end, VT and LCC
1HDG 918 707 B en

23.01.2009 EXTMEHA

14.09.2009 CHSVOTH

1.4-1

Product Manual GIS


Delivery

Figure 1.4-1 represents a typical double busbar feeder. The loads result from static
and dynamic forces due to bay weight and circuit breaker operation.
For each individual layout the mechanical forces are calculated and a corresponding
drawing is made.

Static Loads
The loads below are calculated per GIS base frame.
S

2 busbars without voltage transformer and local control cubicle

2 x 11 kN

1 busbar without voltage transformer and local control cubicle

2 x 10 kN

additional load for local control cubicle

2 x 1.5 kN

additional load for voltage transformer

2 x 2.5 kN

Dynamic Loads
The dynamic loads are measured in a normal industrial building.
Table 1.4-1: Dynamic Loads due to 40 kA design
Load case

Load per point (kN)

Impulse time (ms)

f (Hz)

On-operation
(tension / pressure)

- 2.8 / 2.8

20 - 50

65

Off-operation
(tension / pressure)

-8/5

10 - 30

45

The dynamic loads are evenly distributed on the load points 2 . The forces upwards
(4 x 8 kN) are reduced by the weight of the bay.

Installation
The bay is delivered with a base frame. The base frame will be welded on a
straightening iron (C-rail), which is integrated in the concrete floor.
If there is no iron structure the GIS supports are to be mounted with chemical anchors
M12 x 160 mm or equivalent.
Max. tensile load per anchor in concrete with minimum stability B25 / DIN 1045 is
10 kN. Dowel depth: 110 mm.

1HDG 918 707 B en

23.01.2009 EXTMEHA

14.09.2009 CHSVOTH

1.4-2

Product Manual GIS


Delivery

1.4.2 Building Requirements and Dimensions


Figure 1.4-1 and Figure 1.4-3 show the recommended dimensions for a GIS in double
busbar layout. Other layouts may require smaller or larger dimensions.
The room tolerances and planeness should be equal or better than DIN 18202 which
means:
Planeness (mm)

12

15

20

on Distance (m)

0.1

10

15

Final overall dimensions are to be defined in cooperation with the client.

Option

2115

2825

3600
500

ca. 1400

2000
(usual case)

1700
(minimum space
for walking)

ca. 600

ca. 3600
5500
Figure 1.4-2: Side view double busbar feeder

1HDG 918 707 B en

23.01.2009 EXTMEHA

14.09.2009 CHSVOTH

1.4-3

Product Manual GIS


Delivery

Factors to be considered for building dimensions:


S

Existing building or other installed equipment

Type of HV connections: Cable, transformer SF6 gas-to-oil bushing or


SF6-air bushing

High voltage cable data, type and outlet direction

Location of GIS local control cabinets

Type of lifting device

The recommended lifting capacity (depending on the weight of heaviest transport unit)
is 30 kN, service crane: 10 kN.
For vertical connection the cable basement normally has a height of 2 m.

WxH=3000x3000
5500

C160
Circuit
Breaker
C160

min.2000

1000

1000

1000

1000

1000

1000

1000

1200

ca. 12000
Figure 1.4-3: Plan View

Figure 1.4-3 shows a 8-bay arrangement. The standard width of a bay is 1 m.


The building dimensions can be easily determined based on the number of bays.
For a convenient and fast HV-cable sealing end assembly, openings for the cables
made 0.5 m x 0.7 m are recommended, see Figure 1.4-1. For special cases contact
ABB.
The large front door (left side in Figure 1.4-3) is the equipment access door
(width x height = 3 m x 3 m). The second door is a standard access door which
is provided for convenience and safety.

1HDG 918 707 B en

23.01.2009 EXTMEHA

14.09.2009 CHSVOTH

1.4-4

Product Manual GIS


Delivery

1.5 Building Requirements


1.5.1 Static and Dynamic Loads

Circuit Breaker

Cable Sealing End

340 340

500

100

1700

18KN

250

680

470
300

250

100

230
700

18KN
2

1050

350 350
700

620

1525
2145

GIS base frame (2 x MSH 100 x 100)

Dynamic load points of circuit breaker

Figure 1.5-1: Load points double busbar bay with cable sealing end, VT and LCC
1HDG 918 708 C en

23.01.2009 EXTMEHA

10.07.2009 CHSVOTH

1.5-1

Product Manual GIS


Delivery

Figure 1.5-1 represents a typical double busbar feeder. The loads result from static
and dynamic forces due to bay weight and circuit breaker operation.
For each individual layout the mechanical forces are calculated and a corresponding
drawing is made.
Static Loads
The loads below are calculated per GIS base frame.
S

2 busbars without voltage transformer and local control cubicle

2 x 14 kN

1 busbar without voltage transformer and local control cubicle

2 x 11 kN

additional load for local control cubicle

2 x 1.5 kN

additional load for voltage transformer

2 x 2.5 kN

Dynamic Loads
The dynamic loads are measured in a normal industrial building.

Table 1.5-1: Dynamic loads due to 40 kA design


Load case

Load per point (kN)

Impulse time (ms)

f (Hz)

On-operation
(tension / pressure)

- 2.8 / 2.8

20 - 50

65

Off-operation
(tension / pressure)

-8/5

10 - 30

45

The dynamic loads are evenly distributed on the load points 2 . The forces upwards
(4 x 8 kN) are reduced by the weight of the bay.

Installation
The bay is delivered with a base frame. The base frame will be welded on a
straightening iron (C-rail), which is integrated in the concrete floor.
If there is no iron structure the GIS supports are to be mounted with chemical anchors
M12 x 160 mm or equivalent.
Max. tensile load per anchor in concrete with minimum stability B25 / DIN 1045 is
10 kN. Dowel depth: 110 mm.

1HDG 918 708 C en

23.01.2009 EXTMEHA

10.07.2009 CHSVOTH

1.5-2

Product Manual GIS


Delivery

1.5.2 Building Requirements and Dimensions


Figure 1.5-1 and Figure 1.5-3 show the recommended dimensions for a GIS in double
busbar layout. Other layouts may require smaller or larger dimensions.
The room tolerances and planeness should be equal or better than DIN 18202 which
means:
Planeness (mm)

12

15

20

on Distance (m)

0.1

10

15

Final overall dimensions are to be defined in cooperation with the client.

Option

2115

2825

3600
500

(usual case)
2000

1700

1650

minimum space
for walking

950

4350
6500

Figure 1.5-2: Side view double busbar feeder

1HDG 918 708 C en

23.01.2009 EXTMEHA

10.07.2009 CHSVOTH

1.5-3

Product Manual GIS


Delivery

Factors to be considered for building dimensions:


S

Existing building or other installed equipment

Type of HV connections: Cable, transformer SF6 gas-to-oil bushing or


SF6-air bushing

High voltage cable data, type and outlet direction

Location of GIS local control cabinets

Type of lifting device

The recommended lifting capacity (depending on the weight of heaviest transport unit)
is 35 kN, service crane: 10 kN.
For vertical connection the cable basement normally has a height of 2 m.

WxH=3000x3000

6500

C160
Circuit
Breaker
C160

min.2000

1200

1200

1200

1200

1200

1500

ca. 11000
Figure 1.5-3: Plan View

Figure 1.5-3 shows a 6-bay arrangement. The standard width of a bay is 1.2 m.
The building dimensions can be easily determined based on the number of bays.
For a convenient and fast HV-cable sealing end assembly, openings for the cables
made 0.5 m x 0.7 m are recommended, see Figure 1.5-1. For special cases pleasecontact ABB.
The large front door (left side in Figure 1.5-3) is the equipment access door
(width x height = 3 m x 3 m).
The second door is a standard door which is provided for convenience and safety.

1HDG 918 708 C en

23.01.2009 EXTMEHA

10.07.2009 CHSVOTH

1.5-4

Anda mungkin juga menyukai