Delivery
Circuit Breaker
340 340
100
500
650
15KN
250
100
200
250
300
680
15KN
2
1050
350
350
700
620
1525
2145
Figure 1.4-1: Load points double busbar bay with cable sealing end, VT and LCC
1HDG 918 707 B en
23.01.2009 EXTMEHA
14.09.2009 CHSVOTH
1.4-1
Figure 1.4-1 represents a typical double busbar feeder. The loads result from static
and dynamic forces due to bay weight and circuit breaker operation.
For each individual layout the mechanical forces are calculated and a corresponding
drawing is made.
Static Loads
The loads below are calculated per GIS base frame.
S
2 x 11 kN
2 x 10 kN
2 x 1.5 kN
2 x 2.5 kN
Dynamic Loads
The dynamic loads are measured in a normal industrial building.
Table 1.4-1: Dynamic Loads due to 40 kA design
Load case
f (Hz)
On-operation
(tension / pressure)
- 2.8 / 2.8
20 - 50
65
Off-operation
(tension / pressure)
-8/5
10 - 30
45
The dynamic loads are evenly distributed on the load points 2 . The forces upwards
(4 x 8 kN) are reduced by the weight of the bay.
Installation
The bay is delivered with a base frame. The base frame will be welded on a
straightening iron (C-rail), which is integrated in the concrete floor.
If there is no iron structure the GIS supports are to be mounted with chemical anchors
M12 x 160 mm or equivalent.
Max. tensile load per anchor in concrete with minimum stability B25 / DIN 1045 is
10 kN. Dowel depth: 110 mm.
23.01.2009 EXTMEHA
14.09.2009 CHSVOTH
1.4-2
12
15
20
on Distance (m)
0.1
10
15
Option
2115
2825
3600
500
ca. 1400
2000
(usual case)
1700
(minimum space
for walking)
ca. 600
ca. 3600
5500
Figure 1.4-2: Side view double busbar feeder
23.01.2009 EXTMEHA
14.09.2009 CHSVOTH
1.4-3
The recommended lifting capacity (depending on the weight of heaviest transport unit)
is 30 kN, service crane: 10 kN.
For vertical connection the cable basement normally has a height of 2 m.
WxH=3000x3000
5500
C160
Circuit
Breaker
C160
min.2000
1000
1000
1000
1000
1000
1000
1000
1200
ca. 12000
Figure 1.4-3: Plan View
23.01.2009 EXTMEHA
14.09.2009 CHSVOTH
1.4-4
Circuit Breaker
340 340
500
100
1700
18KN
250
680
470
300
250
100
230
700
18KN
2
1050
350 350
700
620
1525
2145
Figure 1.5-1: Load points double busbar bay with cable sealing end, VT and LCC
1HDG 918 708 C en
23.01.2009 EXTMEHA
10.07.2009 CHSVOTH
1.5-1
Figure 1.5-1 represents a typical double busbar feeder. The loads result from static
and dynamic forces due to bay weight and circuit breaker operation.
For each individual layout the mechanical forces are calculated and a corresponding
drawing is made.
Static Loads
The loads below are calculated per GIS base frame.
S
2 x 14 kN
2 x 11 kN
2 x 1.5 kN
2 x 2.5 kN
Dynamic Loads
The dynamic loads are measured in a normal industrial building.
f (Hz)
On-operation
(tension / pressure)
- 2.8 / 2.8
20 - 50
65
Off-operation
(tension / pressure)
-8/5
10 - 30
45
The dynamic loads are evenly distributed on the load points 2 . The forces upwards
(4 x 8 kN) are reduced by the weight of the bay.
Installation
The bay is delivered with a base frame. The base frame will be welded on a
straightening iron (C-rail), which is integrated in the concrete floor.
If there is no iron structure the GIS supports are to be mounted with chemical anchors
M12 x 160 mm or equivalent.
Max. tensile load per anchor in concrete with minimum stability B25 / DIN 1045 is
10 kN. Dowel depth: 110 mm.
23.01.2009 EXTMEHA
10.07.2009 CHSVOTH
1.5-2
12
15
20
on Distance (m)
0.1
10
15
Option
2115
2825
3600
500
(usual case)
2000
1700
1650
minimum space
for walking
950
4350
6500
23.01.2009 EXTMEHA
10.07.2009 CHSVOTH
1.5-3
The recommended lifting capacity (depending on the weight of heaviest transport unit)
is 35 kN, service crane: 10 kN.
For vertical connection the cable basement normally has a height of 2 m.
WxH=3000x3000
6500
C160
Circuit
Breaker
C160
min.2000
1200
1200
1200
1200
1200
1500
ca. 11000
Figure 1.5-3: Plan View
Figure 1.5-3 shows a 6-bay arrangement. The standard width of a bay is 1.2 m.
The building dimensions can be easily determined based on the number of bays.
For a convenient and fast HV-cable sealing end assembly, openings for the cables
made 0.5 m x 0.7 m are recommended, see Figure 1.5-1. For special cases pleasecontact ABB.
The large front door (left side in Figure 1.5-3) is the equipment access door
(width x height = 3 m x 3 m).
The second door is a standard door which is provided for convenience and safety.
23.01.2009 EXTMEHA
10.07.2009 CHSVOTH
1.5-4