April 2003
Volume 4, Number 18
RICS Foundation
April 2003
Electronic Reference PS0420
Published by
RICS Foundation
12 Great George Street
London SW1P 3AD, UK
David Lewis
Harper Adams University College
Editor
Professor Les Ruddock
School of Construction &
Property Management
University of Salford
Salford
Lancs M5 4WT
United Kingdom
Colin Lizieri
University of Reading
Jorge Lopes
Instituto Politecnico de Broganca
John MacFarlane
University of Western Sydney
David Mackmin
Sheffield Hallam University
Nick Millard
Bruton Knowles
Ghassan Aouad
University of Salford
John Moohan
Nottingham Trent University
Paul Bowen
University of Cape Town
Bev Nutt
University College London
Peter Brandon
University of Salford
Jacob Opadeyi
University of the West Indies
Martin Pearson
University of Northumbria at
Newcastle
Jean Carassus
Centre Scientifique et Technique
du Batiment
Steve Pearson
South Bank University
David Chapman
University College London
Paul Chynoweth
University of Salford
Neil Crosby
University of Reading
Mervyn Dobbin
De Montfort University
Srinath Perera
University of Moratuwa
John Perry
University of Birmingham
Martin Sexton
University of Salford
Li Shirong
Chongqing Jianzhu University
Brian Eksteen
University of Port Elizabeth
Martin Skitmore
Queensland University of
Technology
Chris Eves
University of Western Sydney
Martin Smith
University of Nottingham
John Eyre
University of Exeter
Alan Spedding
University of the West of England
Timothy Felton
University of Plymouth
Peter Swallow
De Montfort University
Dominique Fischer
Curtin University of Technology
Julian Swindell
Royal Agricultural College
Richard Grover
Oxford Brookes University
Stephen Hargitay
University of the West of England
Thomas Uher
University of New South Wales
Malcolm Hollis
Malcolm Hollis Consultants
Tony Walker
Hong Kong University
Mike Hoxley
Anglia Polytechnic University
Ian Watson
University of Salford
Contents
Background
Introduction
10
11
Summary
15
15
Introduction
15
Discounting-related data
15
17
19
Summary
19
20
Introduction
20
20
Probability-based techniqiues
21
22
23
Summary
24
25
Introduction
25
Stages of implementation
25
Logic of implementation
27
27
WLC software
32
Summary
34
34
Conclusions
34
35
References
www.rics-foundation.org
RICS Foundation 3
Abstract
This report is a state of the art review of whole life costing in the construction industry. It is the
first of a series reporting on-going research undertaken within the research project Developing an
integrated database for whole life costing applications in construction. This project is funded by
the EPSRC and undertaken by a unique collaboration between two teams of researchers from the
Robert Gordon University and the University of Salford.
The fundamental basics of whole life costing (WLC) are introduced. First, the historical
development of the technique is highlighted. Then, the suitability of various WLC approaches
and techniques are critically reviewed with emphasis on their suitability for application within
the framework of the construction industry. This is followed by a review of WLC mathematical
models in the literature. Data requirements for WLC are then discussed. This includes a review
of various economic, physical, and quality variables necessary for an effective WLC analysis
of construction assets. Data sources within the industry are also highlighted with emphasis on
current data collection and recording systems. In addition, the requirements of a data compilation
procedure for WLC are outlined.
The necessity of including the analysis of uncertainty into WLC studies is discussed. Attempts
to utilise various risk assessment techniques to add to the quality of WLC decision-making are
reviewed with emphasis on their suitability to be implemented in an integrated environment.
Essential requirements for the effective application of WLC in the industry are outlined with
emphasis on the design of the cost breakdown structure and information management throughout
various life cycle phases. Then, directions for further future research are introduced.
Contact
Petrena Morrison
Acknowledgements
E: p.morrison@rgu.ac.uk
1.1
BACKGROUND
1.3
www.rics-foundation.org
RICS Foundation 5
Kishk et al
1.3.2
useful for clients who want to estimate the actual running costs
of the building and also for budgeting purposes. In addition, it
can be a valuable feedback device to assist in the design. This
issue is discussed in more detail in Chapter 5.
1.4
1.4.1
Figure 1.1
The relationship between whole life cost savings and time of implementation
SOURCE: FLANAGAN ET AL 1989
No major
document
revision
required
Document revision required
Major revision required
po
te
nt
ial
Cost
Cost
red
uc
tio
n
C o st
Concept
Design
to
im
t
en
m
e
pl
Development
Construction
Time
6 RICS Foundation
Replacement
1.4.2
1.4.2.2
1991; Bull 1993; Wilkinson 1996; Bhuta and Sarma 1997; Smith
on the parts of the industry practices, the client, and the analyst
Industry barriers
1996).
1.4.2.3
initial cost and then hand over the building to others to maintain.
Analysis difficulties
cost optimisation because the design and cost estimating fees are
Figure 1.2
Client barriers
100%
Ea
se
of
ch
an
ge
LC
itt
ed
Concept
www.rics-foundation.org
Detailed design
Construction
cu
in
st
Co
Kn
ow
le
dg
rr
ed
om
Use
Disposal
RICS Foundation 7
Kishk et al
1.6
The rest of the report consists of three parts. The first part
of databases.
The second part, Chapter 4, is devoted to a critical review of
various techniques proposed to handle risk and uncertainty in
WLC modelling, with special emphasis on the suitability of
Chapter 6.
Lack of confidence
in any results
No real feedback
on performance
Lack of real
evaluation
8 RICS Foundation
PWS = (l + r)-T
Another example is the PWA factor used to calculate the present
2.1
INTRODUCTION
(l + r)T -1
PWA =
r(l + r)T
Figure 2.1a
FA
0
Time
PA = tf FA
where PA is the present amount of money, FA is the future
amount of money, and tf is a factor required to transform
PA = ?
Figure 2.1b
0
Time
for different situations. These factors are easily derived and are
available in most financial and engineering economic texts (e.g.
Fabrycky and Blanchard 1991; Kirk and DellIsola 1995). For
example, the present worth factor, PWS, used to determine the
www.rics-foundation.org
PA = ?
RICS Foundation 9
Kishk et al
2.3
(Flanagan et al 1989).
2.3.2
Equation 2.4
t=1
where
C0i
dOit
dMit
SAVi
RViT
DCiT
t=1
T
t=1
T
10 RICS Foundation
RViT - dDCiT
Equation 2.5
EACi =
NPVi
PWAi
2.3.6
IRRi = r*NPVi = 0
The IRR has an obvious advantage because it is presented as
a percentage with an obvious interpretation (Flanagan et al
NPV = C + R - S + A + M + E
where
C
investment costs
replacement costs
energy costs
www.rics-foundation.org
RICS Foundation 11
Kishk et al
Equation 2.10
1
Rc =
cmf
Rc
cmf
C(csi)
t=0
-t
C(csi)it(1+r)
i=1 t=1
Equation 2.9
NPVi =
where
Ct
(1+r)t
followed.
Equation 2.8
-t
-t
j=1 t=1
where
C0i
Cit
Cjt
the procurement cost at time t=0, including development, design and construction costs, holding charges and
other initial charges associated with initial procurement
the annual cost at time t (0 t T), of function i (0 i n), which can be regarded continuous over time such
as maintenance, cleaning, energy and security
the cost at time t of discontinuous support function j (0 j m), such as repainting, or replacement of
components at specific times
rd
12 RICS Foundation
Equation 2.11
-t
1 n T
NPV = C0 +
C(csi)it (1+r) - d(1+rd)-T
cmf i=1 t=1
Equation 2.12
(1- (1+r)-t)
NPV = C0 + FA(1+r) + A
r
-t
Equation 2.13
nari
where
Equation 2.14
1- (1+r)-nik fik
PWNik =
(1+r) fik -1
Equation 2.15
nik =
int
( )
T
fik
provided that
rem
( )
T
0
fik
T -1 elsewhere
fik
following chapter.
theory (FST). Assuming that all costs and values can be treated
always the case. Secondly, data sets used to develop the models
www.rics-foundation.org
RICS Foundation 13
Kishk et al
(Equation 2.15). This expression accounts for the fact that non-
annual costs recurring at the end of the last year of the analysis
cost.
Chapter 4.
nari
nnoi
nnri
j=1
m=1
k=1
r
AEIi =
1-(1+r) -Ti
Equation 2.18
r (1-(1+r) -nikfik )
AENik =
(1-(1+r) -Ti ) ((1+r) fik -1 )
Equation 2.19
r
AESi =
(1+r) Ti -1
Equation 2.20
r(1+r) -tim
AEOim =
(1+r)-T -1
14 RICS Foundation
2.5
SUMMARY
3.1
INTRODUCTION
includes cost data and the time in the life cycle when associated
for these two cost items. The model developed by Bromilow and
3.2
DISCOUNTING-RELATED DATA
3.2.1
www.rics-foundation.org
RICS Foundation 15
Kishk et al
Equation 3.1
1+r
rf =
-1
1+f
where
f
Role of judgement
3.2.2
The time-scale
Flanagan et al (1989) differentiated between two different timescales: the life of the building, the system, or the component
under consideration and the analysis period.
return that could be earned from the best alternative use of the
3.2.2.1
3.2.1.4
The life
Definition
Examples
Technological
Functional (useful)
Economic
Social
Legal
Deterioration
Physical
Obsolescence
16 RICS Foundation
3.3
Initial costs
These are the costs for the development of the project including
design and other professional fees as well as construction
costs. Compared to future costs, initial costs are relatively
clear and visible at early stages of projects (Kirk and DellIsola
1995). However, even initial cost estimates may not be reliable
as observed by Ashworth (1993) referring to the finding of
Ashworth and Skitmore (1982) that estimates of contractors
tender sums are only accurate to about 13%.
3.3.2
one looks into the future the greater the risk that assumptions
www.rics-foundation.org
RICS Foundation 17
Kishk et al
been made. This highlights once more the need to high quality
labour hours per square foot, equipment hours per square foot,
and material costs per square foot. Kirk and DellIsola (1995)
3.3.4
wear and tear, e.g. refurbishment and alteration costs. These are
an office, the owner must have the space redone to suit the
1995).
2001).
3.3.5
Replacement costs
Operating costs
18 RICS Foundation
users and not floor-area had the greatest correlation with costs-
in-use of hospitals.
3.3.6
Taxes
Howard 2000).
3.5
3.3.7
Denial-to-use costs
SUMMARY
economic variables
cost data
occupancy data
physical data
performance and quality data
3.3.8
Salvage value
The salvage value is the value of the facility at the end of the
analysis period. This could be resultant of the component having
a remaining life, which could be used or sold. It is calculated
as the difference of the resale value of the facility and disposal
discount rate were also discussed. The the net of inflation discount
This is because it takes into consideration the effect of inflation on
costs. The analysis period or the time frame over which costs are
projected is a key issue in any WLC analysis. Many definitions
of the expected life of a building or a component are used. The
costs, if any.
most important lives are the economic life and the useful life. In
3.4
www.rics-foundation.org
RICS Foundation 19
Kishk et al
4.2
4.1
INTRODUCTION
life cost measure (usually the NPV or the EAC) of the least-
parameter on WLC. The flatter the line the more sensitive WLC
approach.
Figure 4.1
20 RICS Foundation
normally distributed; and (2) the high and low 90% estimates
for each cost do in fact correspond to the true 90% points of the
of CI as follows:
PROBABILITY-BASED TECHNIQUES
The low and high 90% estimates are obtained from the
same source as the best estimates; and considered to
represent knowledgeable judgement rather than guesses
Figure 4.2
www.rics-foundation.org
RICS Foundation 21
Kishk et al
and the best alternative is selected such that it has the highest
final choice between alternatives, this will not remove the need
Bowen 1998).
4.3.3
22 RICS Foundation
Equation 4.1
CI1 =
CI2 =
2A1+ A2 + A3
Equation 4.2
A2
A1+ A2
2A1+ A2 + A3
Buckley (1987), Ward (1985 1989), Chiu and Park (1994), Wang
and Liang (1985), Lai and Ching-Lai (1993), Liang and Song
Figure 4.3
www.rics-foundation.org
RICS Foundation 23
Kishk et al
theory or the fuzzy set theory can be used. This way, the manner
Figure 4.4
4.6
SUMMARY
Data
Intangible
Tangible
Not available
Available
Uncertain
Non-random
INTEGRATION
24 RICS Foundation
Probability &
statistics
Certain
Random
Closed form
solution
5.1
INTRODUCTION
STAGES OF IMPLEMENTATION
www.rics-foundation.org
RICS Foundation 25
Kishk et al
Figure 5.1
Budget forecast
Inception
LEVEL 1
Identify historical data on running costs of homogeneous
building.
Budget estimate
Feasibility
LEVEL 2
Brief cost plan and
price prediction
Outline
proposals
LEVEL 3
Measurement
information and
detailed cost plan
Cost checks
Detail design
Cost checks
Detailed WLCA
after 12 months
occupancy
26 RICS Foundation
Production
information
Bill of quantities
Construction
in the literature.
fits into the RIBA plan of work with the conventional cost
5.3
LOGIC OF IMPLEMENTATION
Figure 5.2
5.4
Compile data
Compare results
www.rics-foundation.org
RICS Foundation 27
Kishk et al
Figure 5.3
SITE DATA
Climatic
Environmental
FACILITY COMPONENTS
Initial cost
Useful life
Maintenance
Operational
PROJECT INFORMATION
Program
Criteria and standards
Operational mode
Quantities
Economics
Miscellaneous data
INPUT
GENERATION OF
ALTERNATIVES
WLC PREDICTIONS
Initial
Operational
Maintenance
Alteration/replacement
Associated tax elements
Salvage value
NON-ECONOMIC
Are the assumptions
about the component
costs balanced with the
functional, technological
and aesthetic factors of the
project?
OUTPUT
5.4.2
Examples of CBSs
28 RICS Foundation
Land
Fees on acquisition
Construction cost
Taxes
Financing cost
Finance for land purchase and construction
Loan charges
B - Operation Cost
Energy
Cleaning
Insurance
Security and health
Manpower
Staff
Management and administration of the building
Land charges (rates)
Equipment associated with occupiers occupation
C - Maintenance Costs
Main structure
External decorations
Internal decorations
Finishes, fixtures and fittings
Plumbing and sanitary services
Heat source
Ventilation and air treatment system
Electrical installations
Gas installations
Lift and conveyor system
External works
D - Occupancy Cost
Client occupancy costs
E - Residual Values
Resale value
Demolition and site clearance
Renovation/refurbishment cost
breakdown structure.
occupancy stages.
5.4.4
www.rics-foundation.org
RICS Foundation 29
Kishk et al
Figure 5.3
popularity.
5.4.5
5.4.5.1
Standardisation
External painting
Internal painting
Structure
Plumbing (excluding
heating)
Ancillary services
30 RICS Foundation
34: Roofs
0.0
1.0
Decoration
1.1
1.2
External decoration
Internal decoration
2.0
Fabric
2.1
2.2
2.3
2.4
2.5
External walls
Roofs
Other structural items
Fittings and fixtures
Internal finishes
3.0
Services
3.1
3.2
3.3
3.4
3.5
4.0
Cleaning
4.1
4.2
4.3
Windows
External surfaces
Internal
5.0
Utilities
work. The contents of this book (e.g. BMI 1999) are based
5.1
5.2
5.3
5.4
5.5
5.6
Gas
Electricity
Fuel oil
Solid fuel
Water rates
Effluent and drainage costs
6.0
Administrative costs
6.1
6.2
6.3
6.4
6.5
6.6
Services attendants
Laundry
Portage
Security
Rubbish disposal
Property management
7.0
Overheads
7.1
7.2
Property insurance
Rates
8.0
External works
8.1
8.2
8.3
8.4
www.rics-foundation.org
10
11
12
RICS Foundation 31
Kishk et al
5.4.5.2
Elemental interaction
Substructure
Superstructure
5.4.5.4
2A
2B
2C
2D
2E
2F
2G
2H
Frame
Upper floors
Roof
Stairs
External walls
Windows and external doors
Internal walls and partitions
Internal doors
3 10
Internal finishes
3A
3B
3C
Wall finishes
Floor finishes
Ceiling finishes
5 10
Services
5A
5B
5C
5D
5E
5F
5G
5H
5I
5J
5K
5L
5M
5N
5O
Sanitary appliances
Services equipment
Disposal installations
Water installations
Heat source
Space heating and air treatment
Ventilating system
Electrical installations
Gas installations
Lift and conveyor installations
Protective installations
Communication installations
Special installations
Builders work in connection with services
Builders profit and attendance on services
External works
6A
6B
6C
6D
Site works
Drainage
External services
Minor building works
Preliminaries
Contingencies
32 RICS Foundation
WLC SOFTWARE
Vendor
Website
ACEIT 5.x
www.aceit.com
Ampsol
Ampsol Ltd
www.ampsol.com
AssetDesk 1.1
Richmond Systems
www.richmondsys.co.uk
BLCC 5.1
www.eren.doe.gov/femp/resources.html
BridgeLCC 2.0
www.bfrl.nist.gov/bridgelcc
CAMSLCC 2.2
www.camsco.net
CASA
LOGSA
www.logsa.army.mil/alc/casa
EDCAS 3.1
TFD Group
www.tfdg.com
PipeCost
Armtec Ltd
www.big-o.com/contr/softw.htm
RelexLCC 7.3
Relex Software
www.relexsoftware.com/products/lcc.asp
Availability
Models
Risk
Scope of Application
ACEIT 5.x
Commercial
Windows
NPV
MCS
Ampsol
Free
Web based
NPV
None
AssetDesk 1.1
Commercial
Windows
None
None
WLC management
Activity-based CBS
BLCC 5.1
Free
Platform-independent
NPV
NS
SIR
IRR
DPP
SA
WLC decision-making
Generic CBS. Single energy & water cost
items and unlimited items for other
categories
BridgeLCC 2.0
Free
Windows
NPV
SA
MCS
WLC decision-making
Specific CBS suitable only to analyse bridges
CAMSLCC 2.2
Free
Spreedsheet
NPV
None
WLC decision-making
Generic CBS. Single cost item per cost
category
CASA
Free
Windows
NPV
SA
WLC decision-making
Generic CBS
EDCAS 3.1
Commercial
Windows
NPV
None
WLC decision-making
Generic activity-based CBS
PipeCost
Free
Windows
NPV
SA
WLC decision-making
Generic CBS. Single cost item per cost
category
RelexLCC 7.3
Commercial
Windows
NPV
SA
WLC decision-making
User-defined CBS. Unlimited cost items per
category
www.rics-foundation.org
RICS Foundation 33
Kishk et al
5.6
SUMMARY
6.1
CONCLUSIONS
industry has been carried out to identify the strengths and gaps
projects
34 RICS Foundation
6.2
www.rics-foundation.org
RICS Foundation 35
References
Al-Hajj A (1991) Simple cost-significant models for total lifecycle costing in buildings. PhD Thesis, Department of Civil
Engineering, University Of Dundee
Bull J W (1993) The way ahead for life cycle costing in the
construction industry, in Bull J W (ed) Life cycle costing for
construction, Blackie Academic & Professional, Glasgow
36 RICS Foundation
www.rics-foundation.org
RICS Foundation 37
Kishk et al
Kishk M, Al-Hajj A and Pollock R (2001) Inclusion of nonfinancial factors in life-cycle decision-making - a fuzzy
approach, Proceedings of the 17th Annual Conference of the
Association of Researchers in Construction Management, 1:
411-420
38 RICS Foundation
www.rics-foundation.org
RICS Foundation 39