TABLE OF CONTENTS
1.0 INTRODUCTION................................................................................................................. 2
2.0 THE PROCUREMENT SYSTEMS........................................................................................... 2
2.1 TRADITIONAL SYSTEM OR DESIGN-BID-BUILD....................................................................4
2.2 INTEGRATED PROCUREMENT SYSTEMS.............................................................................7
(I)Design and Build.............................................................................................................. 7
(ii) variants of design and build.........................................................................................10
2.3 MANAGEMENT ORIENTED PROCUREMENT SYSTEMS.......................................................12
(i) Management Contracting.............................................................................................. 13
(ii) Construction Management............................................................................................16
Concept of Construction Project Management...................................................................19
3.0 TYPES OF CONTRACTS..................................................................................................... 20
3.1 Lump Sum Contracts................................................................................................... 20
3.2 Continual Contracts..................................................................................................... 20
3.3 Measurement Contracts............................................................................................... 21
3.4 Cost Reimbursement Contracts...................................................................................21
4.0 THE BASIS OF CHOICE OF PROCUREMENT STRATEGY......................................................22
5.0 PUBLIC PRIVATE PARTNERSHIPS.......................................................................................24
6.0 PUBLIC PROCUREMENT ACT OF KENYA AND THE EFFECTS OF BUREAUCRACY.................25
6.1 Purpose of the PPDA.................................................................................................... 26
6.2 Procurement Procedures..............................................................................................26
6.3 An Effective Public Procurement System......................................................................27
6.2 Public Entity Procurement Inefficiency.........................................................................29
7.0 CONCLUSION................................................................................................................... 32
8.0 REFERENCES................................................................................................................... 32
1.0 INTRODUCTION
1
categorization
of
the
various
construction
project
of
PROCUREMENT
SYSTEMS
INTEGRATED
SEPARATED
&
COOPERATI
Tradition
al
system
Variant of
Traditiona
l System
Sequenti
al
method
Accelerate
d method
Design
and
Build
Package
deal
Variant of
Design
and Build
Turnkey
method
MANAGEMENT
ORIENTED
Manageme
nt
contracting
Constructio
n
manageme
nt
Develop
and
construct
Contracto
r
Consultant
s
Quantity
surveyor
Engineers:
Electrical,
Architect
Subcontractors
Mechanical,
civil/structu
1.0 Introduction
| Procurement Systems in Building Works
ral.
Suppliers
Project
Brief
Feasibility
Study
Design
concept
Detail
design
Tender &
contract
Construction
Commission
& hand over
Disadvantages
Suitable for:
All clients, including inexperienced clients, complex projects and projects
where functionality is prime objective time predictability, cost certainty.
However, it is not suitable for fast track projects.
Particularly attractive to clients with a strictly limited budget or a limit to
their borrowing powers since construction costs can be determined with
reasonable certainty before commencement of construction.
(I)DESIGN
AND
BUILD
Clients
requirements
prepared
Submission of
proposals
8
Contractor
A
Contractor
B
Contractor
C
Contractors
proposal against
client requirements
Successful
contractor selected
Successful
contractor finalises
design and
produces the
Architect
Engine
er
Contractor
s manager
Contractual relationship
Site
manag
er
Site
engine
er
Organisational relationship
9
Site
survey
or
Suppor
t staff
Project
brief
Feasibility
study
Tender
documentati
on
Concept
design
Tender &
contracti
ng
Construction
Commission &
hand over
Detail design
Contractors
(II)
c.
d.
e.
f.
g.
h.
Construction projects using the system have the potential for early
completion and lower overall costs.
i.
Disadvantages
The building contractors in-house design expertise may be insufficient to
solve the client's needs efficiently
b. Tendering costs are high as contractors must design and produce accurate
proposals as well as estimates
a.
12
d.
e.
f.
Suitable for:
Design
team
Management
Contractor
Contractual relationship
Organisational relationship
Works
contractor
Detail design
and/or shop
drawings
Project
brief
14
Commission &
hand over
Package Contractors
responsibility
Management Contractors
15
The them and us attitude is eradicated as; from the projects onset the
MC becomes part of the project team working together to achieve a
clients objectives of time, cost and quality.
Price is not the only criterion for selection of MC. Rather, in addition, the
ability to make some technical and managerial contribution to the design
and production of a prohect is also considered.
Client obtains keener prices owing to the increased competition for his
construction project.
Disadvantages
16
financial
commitment
before
the
Client has two sets of fees to pay for the professional services of
design and construction management.
Suitable for:
This approach is generally considered to be appropriate for large, complex
fast-track projects particularly where there is a requirement for maximum
flexibility and to overlap design and construction phases.
Client
Design team
Constructio
n manager
Works
contractor
contractual relationship
17
Project
brief &
client
reqms
Feasibility
study
Concept
design
Detail
design
Bidding
&
contracti
ng
Construction
Commission &
hand over
from
several
sponsors/ultimate
users
with
diverse
Fixed price tenders are likely due to timing of Tenders and Works
The client has direct contracts with the trade contractors and pays them
directly ( There is evidence that this results in to lower prices due to
improved cashflow certainty)
More control over each element of the works and hence control of
Quality
Disadvantages
19
The client must provide a good quality brief to the design team as the
design team will not be complete until the client has committed
significant resources to the project
Suitable for:
CONCEPT
OF
Client benefits from having only one person to deal with in all matters
concerning the project
The architect is released from the tasks and problems associated with
managing the project and hence concentrates on design matters the PM
performs an independent and disinterested role and uses this position
well in directing, coordinating and solving construction problems
Disadvantages
21
b.
c.
Client may wish to influence the execution of works hence, assume entire
risk of site operations
24
26
BOOT,
BOT , BOO.
6.1 PURPOSE
OF THE
PPDA
This Act does not directly seek to regulate the private sector, though it does
regulate its interaction with public entities. The PPDA was established in
order to:
Maximise economy and efficiency,
Promote competition and ensure that competitors are treated fairly,
Promote the integrity and fairness of procurement procedures,
Increase transparency and accountability in those procedures,
Increase public confidence in those procedures,
Facilitate the promotion of local industry and economic development.
In order to achieve these objectives, the Act establishes procurement and
disposal procedures. It also sets up the necessary structures to ensure that
the procedures are followed and to provide oversight and compliance
through Public Procurement Oversight Authority (PPOA). Its primary role is to
ensure that procurement procedures established under the Act are adhered
to. In doing this, the PPOA is required to advise, establish standards, and
train procurement
entities and persons, as well as advise government on policy issues.
28
32
b.
Corruption
c.
Inefficiencies
d.
e.
Improves accountability
f.
Fairness is exercised
g.
h.
7.0 CONCLUSION
34
8.0 REFERENCES
1. Akintoye, A and Fitzgerald E (1995) Design and Build: A Survey of Architects Views,
Engineering, Construction and Architectural management
2. Ashworth A (2001) Contractual Procedures in the Construction Industry, UNITEC, New
Zealand
3. Chitkara K K (2005): Project Management - Planning, Scheduling and Controlling Tata
McGraw Hill, New Delhi
4. Kwakye A A (1997) Construction Project Administration In Practice Longman, London
5. Lam, E W M, Albert P C and Chan D W M (2003) Is Design and Build the Preferred Option
to Procure all Projects? Research Fellow, Department of Building and Real estate, The
Hong Kong Polytechnic University
6. Masterman J W E (1996) Building Procurement Systems: An Introduction, E & FN Spon,
London
7. Murdoch J and Hughes W ( 2000) Construction Contract: Law and Management: 3rd Edition
E&FN Spon, London
8. Rowlinson, S (1987) Design and Build Its development and Present Status, Ascot CIOB
9. Songer A D and Molenaar K R (1996) : Selecting Design and Build Public and Private
Sector Owner Attitudess, Journal of Management in Engineering, ASCE.
10. The Aqua Group (2001) Tenders and Contract for Building- 3rd. Edition Blackwell Science,
London
35