Section 5
Cable Installation
Introduction
The installation of a power cable can look deceptively simple it isnt!
There are many aspects to be considered, as usual too many to be dealt in
any detail within our time constraints. So in these notes we will look at
some points with regard to installing cables in trenches (the commonest
situation for power cables), leaving the student to extrapolate to other
situations as they arise.
Objectives
At the end of this section you will be able to
Time
You will need about 3 hours for this section.
Resources
PC with Windows Excel or some other spreadsheet package.
137
138
5.2
Legislation
In the case of the Highways, the Secretary of State is the manager of the
highways under the Highway Act 1980. Highway Authority is here the
Street Authority. For non highways, then Street Managers are the
authority body or person responsible to the management and control of
the street example Local Authorities.
5.2.2 Health & Safety at Work etc. Act, 1974
This major piece of health & safety legislation (www.legislation.gov.uk)
affects every aspect of our lives whilst at work, visiting the supermarket,
139
140
141
Maximise bend radius and ensure that the bends are uniform.
impact moling
rockwheel
chain trencher
mole ploughing
micro-tunnelling
jack heading
thrust boring
auger boring
deep tunnelling
142
suitably proportioned
143
144
145
Coefficient of friction =
Pulling tension, T
= W.L. kg
Cable - W kg/m
L metres
Situation
Coeff. of friction
Rough surfaces
0.5 - 1.0
Cement ducts
0.4 - 0.5
Plastic ducts
0.3 - 0.4
0.25
Cable rollers
0.2
0.1
146
L1
L2
R
T3
is the angle of the bend in radians, and R its radius in metres. T1, the
load on the nose of the cable as it approaches the bend, is given by
T1 := W L1
(5.1)
sinh ( )
2 0.5
(5.2)
(5.3)
There is a small error involved when using the simpler expression, about
3% when T1 = 100 kg, but the error decreases to zero at T1 = 750 kg.
Hence:-
T2 := (W L1 ) e
(5.4)
147
By the time the cable has reached position 3 the nose load T3 has
increased to:-
T3 := (W L1 ) e
+ W L2
(5.5)
L1
R2
L2
R1
T3
T5
L3
T4
T3 := (W L1 ) e
T4 :=
+ W L2
(W L1 ) e 1 + W L2 e 2
T5 := (W L3 ) +
(W L1 ) e 1 + W L2 e 2
(5.6)
148
1 = 30 degrees
= 0.25
2 = 90 degrees
L1 = 100 m
R1 = 5 m
L2 = 100 m
R2 = 3 m
L3 = 50 m
Your answer to Exercise 5.1
149
Turn to the end of the book for suggested answers to the exercise
150
Exercise 5.2
Repeat the above exercise, but now let T0 = 100 kg.
Your answer to Exercise 5.2
Turn to the end of the book for suggested answers to the exercise
151
material
conductor area
Copper
50.
Aluminium
35
For 3-core cables, the maximum allowable load is calculated on the basis
of two conductors only. For a 3-core 185 sq.mm. cable, copper
conductors can withstand 1.85 tonnes, whilst an aluminium conductored
cable would be limited to 1.3
tonnes
5.4.2 Bond pulling
Where very heavy cables have to be
installed, even conductor pulling
may
be
insufficient
to
accommodate the tensions needed
for a nose pull, particularly on
difficult routes. The answer is to
adopt the bond pulling technique
that distributes the pulling load
along the cable. And since the
cable goes round the bends without
152
contact with skid plates, there are no bend effects to increase the pulling
tension so effectively the pulling load is simply:
weight/metre x length x coeff. of friction
5.4.3 Side loading limits
But the pulling tension is not the only important parameter. When the
cable travels round a bend it experiences a side load, and the amount of
side loading that a cable can withstand depends upon its construction.
Excessive side loading can flatten metallic sheaths and apply continuous
pressure to the dielectric, insulating papers can be fractured, voids
produced in solid dielectric cables, screen wires indented into XLPE
cores, and strippable screens separated from the XLPE insulation. Not to
be recommended!
The side loadings on the bends (sidewall pressure P n ) are given by the
equation.
P n :=
Tn
Rn
where
(5.7)
P2 :=
1
2
+ W L2 e
(W L1 ) e
R2
(5.8)
The following are maximum side load limits with the cable against skid
plates, and wherever possible pulling should be arranged to provide lower
loads.
153
Cable construction
400
2000
500
Table 5.3 Maximum side loads using skid plates for three cable types
If vertical rollers are used on bends, the small diameter of the rollers
results in the side loading increasing dramatically.
Consequently,
vertical rollers should NEVER be used on bends well-greased skid
plates are essential when heavy and/or arduous pulls are required. But if
you must use vertical rollers, the following side load limits must be
applied. See Table 5.4.
Cable construction
100
200
50
Table 5.4 Maximum side loads using rollers for three cable types
This means that the pulling tension must be greatly reduced, and hence
the length of cable that can be pulled is reduced.
Obviously, the tension plays a major role in determining the sidewall
pressure.
154
Exercise 5.3
Using the same parameters as for the previous exercises, calculate the
sidewall pressure on the cable at the second bend (2, R2) of the above
route, when pulling from left to right, with T0 = 0 kg and T0 = 100 kg.
Your answer to Exercise 5.3
Turn to the end of the book for suggested answers to the exercise
155
Exercise 5.4
Now imagine that the drum is to be positioned at the right hand end of
the above cable route, and the cable pulled from right to left you will
have to re-write the equations accordingly. Using the same parameters
as for the previous exercises, and again ignoring the drum load (i.e. T5 =
0 kg) calculate the tensions on the cable nose at the positions
corresponding to T0T5, and the sidewall pressure on the cable at the
(2, R2) bend.
Your answer to Exercise 5.4
Turn to the end of the book for suggested answers to the exercise
156
Exercise 5.5
Repeat the calculation, but this time set the drum load to 100 kg.
Your answer to Exercise 5.5
Turn to the end of the book for suggested answers to the exercise
157
4. Pay particular attention to the start of the route, as high loads here
have the most significant effect on the pulling load. In particular:
minimise the load needed to pull the cable off the drum.
Powered rollers or caterpillars can also be used, either at the start of the
route or part way along it, to further reduce the loads. As an alternative,
multiple winching positions can be set up along the route the cable
output from one section of the route is then the input to the next section,
but the input tension is reduced to zero, effectively splitting the route in
several smaller pulls.
5.4.5 Other factors affecting maximum pulling lengths
It should be obvious from the foregoing that, so far as nose pulling is
concerned, the route itself can determine the maximum length of cable
that can be pulled in one go when the pulling and side loads are at the
158
maximum values that the cable can withstand, then thats it, you cant go
any further without damaging the cable.
Thats not the case with a full bond pull of course, which distributes the
pulling load along the whole cable length and eliminates side wall
pressure limitations for a bond pull the length that can be installed in
one pull is, in theory, almost unlimited.
However there are other, perhaps less obvious, factors that, individually
or in combination, may impose other limits on the cable length. These
might include:
159
The ability of the ground to support the drum stand and cable
drum
160