School of Engineering
Department of Electrical Engineering
Spring 2012
IENG300 Engineering Project Management
Assignment 4 Solution
Instructor: Dr. Bassam Hussein
Exercise 10.2:
Codes of ethics are pretty instrumental in providing guidance to the members of particular
professional society. PMI is one of those societies and its members are professional project
managers. Codes of ethics play the following roles in general:
o
o
o
o
o
o
o
o
Adhering to the guidelines provided will constitute a behavior that is most probably ethical
and not doing so would be considered as unethical. Based on those guidelines, appropriate
and inappropriate behavior may be correlated accordingly.
Exercise 10.5
This exercise is designed to illustrate the notion of relationship building through exchange.
Many scenarios are possible here. The key here is to assess your current bank account in that
relationship and what kind of influence currencies would be appropriate for building a
stronger relationship. You may view relationships in terms of transactions. You should be
encouraged to experiment with this concept and see how useful it is.
Page 1
Exercise 11.2
This exercise is designed to choose a decision making method to fit the situation. You
should first privately select what you consider the appropriate decision-making method that
should be used. Different approaches may be used and there may always be a debate
regarding differences in opinion.
Casino Night: Make decision on your own. You have sufficient information and anticipate
no disagreement over the choice.
Trysting Tree Golf Club: Consult with others. While you have sufficient information to
make a decision to insure support for the decision it is wise to share ideas with relevant
stakeholders before making the decision.
New Product Development: Call a meeting a reach a consensus. You do not have
sufficient information to make a decision and it is critical that the team support the decision.
At the end of the exercise, it is useful to review the conditions in which group consensus
should and should not be used.
Exercise 13.3
The project appears to be doing nicely. In both periods 4 and 8 the cost variance is positive
+$300 and +$400, respectively. This suggests a pattern of good cost variance that is
under budget.
The schedule variance is also positive +$300 and +$400 for period 4 and period 8. Since
Task D is already 25% complete, Task B must have been completed at least one period early.
Page 2
End of Period 4
Actual %
Task
Complete
A
Finished
B
50%
C
33%
D
0%
E
0%
Cumulative Totals
EV
$
400
1200
500
0
0
$2100
AC
$
300
1000
500
0
0
$1800
PV
$
400
800
600
0
0
$1800
CV
$
+100
+200
0
0
0
$+300
SV
$
0
+400
-100
0
0
$+300
End of Period 8
Actual %
Task
Complete
A
Finished
B
Finished
C
Finished
D
25%
E
33%
F
0%
Cumulative Totals
EV
$
400
2400
1500
400
300
0
$5000
AC
$
300
2200
1500
300
300
0
$4600
PV
$
400
2400
1500
0
300
0
$4600
CV
$
+100
+200
0
+100
0
0
$+400
SV
$
0
0
0
+400
0
0
$+400
Note: Completion of the answer sheet requires constant reference to the baseline figure.
IENG300 Engineering Project Management
Page 3
Exercise 13.6
After 6 time periods the project is roughly 66% complete and so far work on the project has
taken 1,600 hours less work than planned. There is 400 hours worth of work on Activity 4
which was suppose to have been done that has not done. Since Activity 4 is on the critical
path, the project is behind schedule. If schedule is the number priority, the project manager
may want to consider investing some of the savings on accelerating critical activities.
Page 4
AC
500
500
PV
1000
1000
CV
+500
+500
SV
0
0
AC
1500
1500
PV
2000
2000
CV
+500
+500
SV
0
0
AC
1500
0
200
500
2200
PV
2000
1600
500
1000
5100
CV
+500
0
+100
0
+600
SV
0
-1600
-200
-500
-2300
AC
1500
1000
800
1500
4800
PV
2000
2400
1000
2000
7400
CV
+500
+200
+100
-500
-300
SV
0
-1200
-100
-1000
-2300
AC
1500
2000
800
1500
400
6200
PV
2000
2400
2000
2200
400
9000
CV
+500
+400
+700
0
0
+1600
SV
0
0
-500
-700
0
-1200
AC
1500
2000
2100
1800
PV
2000
2400
2300
2400
CV
+500
+400
+300
+200
SV
0
0
+100
-400
Page 5
5
50%
Cumulative Totals
Indexes
Period
1
2
3
4
5
6
SPI
1.00
1.00
.55
.69
.87
.96
800
9600
CPI
2.00
1.33
1.27
1.06
1.26
1.20
600
8000
PCIB
.07
.14
.19
.35
.54
.66
800
9900
+200
+1600
0
-300
SPI = EV / PV
CPI = EV / AC
PCIB = EV / BAC
Page 6
Page 7