Anda di halaman 1dari 21

TRANSCANADA

KEYSTONE PIPELINE PROJECT EXECUTION PHASE


HDD EXECUTION PLAN FOR WATER COURSE CROSSINGS

Deadhorse Creek

Rev. 0

Owner: TransCanada
Prime Contractor: Ledcor Pipeline Limited
HDD Contractor: Dwayne Unger Construction Limited

TransCanada
Keystone Pipeline Project Execution Phase
HDD Execution Plan for Water Course Crossings
Deadhorse Creek
TABLE OF CONTENTS
1
INTRODUCTION .......................................................................................................1
1.1
Horizontal Directional Drill Procedure for Water Course Crossings ..................1
2
EXECUTION PLAN...................................................................................................2
2.1
Notifications and Permits ...................................................................................2
2.2
Identification of Buffer Zones .............................................................................2
2.3
Pre-Construction Survey....................................................................................2
2.4
Equipment on Site .............................................................................................3
2.5
Project Entry/Exit Points ....................................................................................3
2.6
Surface and Guide Casing.................................................................................4
2.7
Tracking System ................................................................................................4
2.8
Drill Fluid Pressure Report.................................................................................4
2.9
Pilot Hole ...........................................................................................................5
2.10
Reaming and Hole Opening ..............................................................................6
2.11
Drill Continuance Plan .......................................................................................6
2.12
Drill Fluid Program .............................................................................................7
2.13
Schedule............................................................................................................8
2.14
Buoyancy Control ..............................................................................................8
2.15
Pullback Procedure............................................................................................8
2.16
Cleanup & Restoration.......................................................................................8
2.17
Water Requirements..........................................................................................9
3
ENVIRONMENTAL MANAGEMENT ......................................................................10
3.1
Planning...........................................................................................................10
3.2
Monitoring ........................................................................................................12
3.3
Response.........................................................................................................13
3.4
Directional Drill Mud Release Contingency Plan .............................................13

Deadhorse Creek HDD Execution Plan

1
1.1

INTRODUCTION
Horizontal Directional Drill Procedure for Water Course
Crossings
Deadhorse Creek, Deadhorse Channel, and Road

602m

The trenchless method selected for the crossing(s) is a horizontal directional drill
(HDD) crossing technique. The following is an overview of the steps that will be
involved in the execution of the HDD of the major watercourse crossing. It will
also outline some of the mitigative measures that will be taken to ensure the
effective installation of the proposed water crossing. These measures will be in
conjunction with the measures outlined in the Environmental Protection Plan
(EPP) for this project.

Deadhorse Creek HDD Execution Plan

Page 1

EXECUTION PLAN

2.1

Notifications and Permits


Prior to access or construction activities associated with the crossings, all
watercourse crossing approvals, permits, and/or notifications will be received or
issued respectively. All conditions specified in approvals or permits will be
discussed, understood, and adhered to by company personnel and all
contractors. Any required notifications required in the permits/approvals or
notifications will be provided within the timing specified. Notifications will be
completed as specified, documented, and maintained in the construction field
office.

2.2

Identification of Buffer Zones


All buffer zones or restricted areas will be identified and flagged prior to
mobilization and site preparation. In addition, any restricted areas identified by
permits/approvals will be flagged off. Access to these restricted areas will be
prohibited unless authorized by the appropriate regulatory authority in the case of
permits/approvals or by the authorized Keystone representative.

2.3

Pre-Construction Survey
A pre- construction survey will be completed to confirm the entry and exit points
for the pilot bore as shown on the construction drawings and as staked in the
field. A survey examination of entry and exit points will be done prior to casing
installation or rig-up to verify distances, field stations and elevations along the
proposed centerline. These points will be plotted for the monitoring and
recording of the three dimensional coordinates generated by the magnetic
guidance tracking software. This exercise ensures the pre-alignment and radius
restrictions are maintainable during the execution of the bore. Following receipt
of the survey results a comparison to the engineered designed profile will be
verified and presented to the Clients Representative or concerned parties for
review and approval prior to drilling operations starting.

Deadhorse Creek HDD Execution Plan

Page 2

2.4

Equipment on Site
All equipment used on site shall be cleaned and free of oils, fuel, grease, coolant
and other hydrocarbons or otherwise toxic substances, or any vegetation, soil or
other material prior to mobilization, as per the Environmental Protection Plan
(EPP). Oil changes, refuelling, and lubrication of mobile construction equipment
will only be undertaken at a minimum of 100 m from the water body and only at
approved locations, so as to minimize the potential for water pollution. Fuel
containers will be dual walled tanks or alternatively will be contained within
containment berms constructed to a capacity of 125% of the fuel stored, as per
EPP Appendix E, Specific Measures, #12. Contingency plans will be in place in
the event of fuel or hazardous waste spills.
Equipment Summary
(Note: Equipment changes or substitutions may occur)
Drill:
-American Auger DD1100 Drill rig
-1.1 million lbs of thrust/pull
-105,000 ft lbs of rotary torque.
-Anchor System: Steel I Beam and Deadman system
Cleaning System:
-Triflow 146 equipment including 4 shakers, 2 scalpers, 1 desilter unt, and
1 desander unit
Auxiliary equipment:
-500 Emsco pump
-monel
-jet assembly
-hevi-wate
-60 cube volume tank with 800 gpm cleaning capacity
Drill Size and Type:
-Bit size to be determined.
-5 inch drill stem
Rig layout and site setup may vary as per the provided work space.

2.5

Project Entry/Exit Points


During site preparations the size, slope grade, berm walls and ingress and
egress will be required for both entry and exit points. The HDD equipment
preferred footprint required on entry is 45m wide x 60m in length, with a level
grade to ensure safe and efficient drilling operation. Rig matting will be placed
on entry to ensure a safe and effective working environment. All mitigative
measures indicated in the EPP will be adhered to in the staging of HDD
equipment (Minimum disturbance).

Deadhorse Creek HDD Execution Plan

Page 3

Sumps or buried tanks will be required on entry and exit points to contain drilling
fluids no larger than 12m in length x 3.5m wide & 1.5m in depth. Support
equipment will be required to assist in all exit side operations.
A staging area will be used to string, weld, coat, and pre-test the pipeline before
pull through. The primary staging area will be located near the exit side of the
water crossing and will be contained within the existing right-of-way limits or
temporary work space.

2.6

Surface and Guide Casing


An experienced contractor will be used to install entry or exit casings in the event
it is required for any watercourse crossings. Casing will be installed according to
the geo-technical information, profile design and/or casing refusal occurs.
Casing will be cleaned by the casing contractor or the HDD rig. Unger personnel
will be on site to ensure the accuracy of the casing installation and a casing
report will be submitted to Clients Representatives for approval. If required 48 x
0.750w casing may be installed on entry no greater than 16-degrees to ensure a
safe and effective work area. A 16 centralizer casing will be inserted through
the 48 conductor casing and a seal test performed on both.

2.7

Tracking System
A magnetic guidance system, Tru-tracker or Paratrack, will be used to track and
to monitor the drill path during the HDD pilot bore (determination of tracking
system will be based on availability at time of drill execution and as specified in
the specifications of the contract document). This system is important to insuring
the proper installation of the HDD design. This system allows the drilling
assembly to control the path the drill takes and calculate the horizontal and
vertical coordinates relative to the initial entry point on surface. A coil grid will be
laid out accordingly on exit/entry points using surveyed stations to ensure the
accuracy of the drill path. This system will be used to generate an as built profile
of the drilled bore.
In the event of a deviation of the drill path the Clients Representatives will be
informed, if required the drilling assembly will be pulled back to an appropriate
location in the bore path and a steering correction initiated. An annular pressure
tool will be run in conjunction with the downhole assembly directly behind the
mudmotor to ensure the proper monitoring of annular and downhole pressures.
An annular pressure graph will be in the control room for reference. For the
shorter bores a Digi-trak walk over system will be used.

2.8

Drill Fluid Pressure Report


TransCanada will calculate the maximum permissible annular pressure, and
create a report that graphically depicts the maximum permissible annular
pressure along the length of the drilled hole. One (1) copy of the report will be

Deadhorse Creek HDD Execution Plan

Page 4

maintained by the Rig Manager and will be used to govern operating procedures,
and one copy will be submitted to the Keystone Representative.
Pressures reaching the upper limit of 25% over expected or falling 25% below
expected will trigger a response to take action to prevent fluid loss. The response
will be as follows:
High annulus pressure
Sudden increase
1. Trip pipe back until pressure drops; a full trip back to entry may be
required.
2. Reduce or stop pumping if pressure does not drop
3. Check mud parameters
4. Check for volume loss
5. With pressure stabilized slowly increase pump speed up to a maximum
flow capacity
Gradual increase over expected
1. Check fluid parameters and modify if required
2. Compare actual drill path to planned
3. If pressure reaches the upper limit, trip back to lower pressures and
condition the hole
Low annulus pressure
Sudden decrease below expected
1. Stop pumping
2. Check returning fluid and volume loss
3. Check for correct tool operation (if point 2 is okay)
4. Prepare a lost circulation mixture and pump down.
5. Monitor for fluid loss
6. Trip back to entry to clean hole and allow plugging agents to work
7. recheck for correct pressure tool operation
8. Trip back while monitoring for fluid loss
Gradual decrease below expected
1. Check drilling fluid parameters
2. Compare drill path to planned
3. Check for reduced flow and fluid loss
4. Mix up lost circulation material and pump down
5. Continue to drill monitoring for reduced flow and volume
6. If losses exist additional plugging agents may be required
7. Monitor for fluid to surface

2.9

Pilot Hole
To initiate the pilot bore, the HDD is set-up in alignment with the inclination &
azimuth according to the engineered design. The steering tool and drill tooling is
then assembled (DHA.). The steering tool is then calibrated and a 4 point roll
check completed. Measurements will be taken of the DHA and from the bit to the
steering probe. The distance from the HDD vices to the entry point will be

Deadhorse Creek HDD Execution Plan

Page 5

recorded and each additional drill pipe measured and recorded in successive
order. A non magnetic collar will be placed behind the downhole assembly in
order to create a non-magnetic buffer between the steering tool and possible
magnetized drill string. The path of the pilot bore will be recorded by taking
periodic readings of the inclination and azimuth using the tracking system to
calculate the vertical and horizontal coordinates relative to the initial entry point.
These reading will be taken in intervals not to exceed 10 meters to ensure
deviation and design parameters are maintained. Drilling fluid will be pumped
through the downhole assembly no greater than 1.9 cubic meters/min. and no
greater than 1200 psi. Drilling fluid returns will accumulate in a contained sump
or tank and be pumped using a 6 Gorman Rupp or Godwin centrifugal pump to
the mud reclaimer for reuse. Solids control will consist of 2 rough cut 146 Tri-flo
shakers. A shale tank will be used to contain drilling cuttings.
A jetting assembly along with an annular pressure tool will be used on this pilot
bore. Real time pressures will be recorded by the drilling instrumentation system,
where an annular pressure system is not available Unger HDD will
mathematically model the drilling fluid in use and calculate the expected
standpipe pressure and a maximum permissible standpipe pressure. This data
will be available to the Client Representative at all times and will be printed every
24 hours.

2.10 Reaming and Hole Opening


Once the pilot bore is exited according to the specified tolerances, the bore is
then enlarged using hole openers in a series of sizings. The anticipated phases
for the bore are as follow but not limited to;
Casing Installation
12 pilot
18-24 fly cutter
24-36 fly cutter
36-42 fly cutter and packer
While reaming swabbing, cleaning passes will be performed as required to
ensure that the bore is free of obstructions for the next required opening. At least
one reaming pass will be performed after the final opening to ensure a clean bore
for the pull section.

2.11 Drill Continuance Plan


In the event of a frac-out TransCanada, Ledcor Pipelines Limited and the HDD
contractor in association with any appropriate regulatory agencies will determine
an appropriate drill continuance plan. The drill continuance plan may (but is not
limited to) include the following:
1. Fracture Plugging (Bridging) Agents
In certain types of formations or conditions, fracture plugging agents (nontoxic) have been utilized with limited success. Should these agents be
required a selection of the appropriate agent with MSDS sheets will be
submitted to TransCanada for approval. These are pumped down the drill

Deadhorse Creek HDD Execution Plan

Page 6

hole left undisturbed for a predetermined length of time where upon drilling is
restarted. If positive circulation is restored, drilling is continued using the
same principles and contingency plans; if not drilling is halted.
2. Down Hole Cementing
If the fracture zone is determined to be too large for the use of plugging
agents, the drill string maybe inserted to a predetermined depth to allow a
quick setting cement or thermal resin (non-toxic) to be pumped down-hole in
sufficient quantities to seal off the problem zone. If no further fracturing
occurs, drilling is continued using the same principles and contingency plans;
if not, drilling is halted.
While down hole cementing is rarely used, should it be required a plan with
MSDS sheets will be submitted to TransCanada for approval.
3. Contain and Control
If the inadvertent release is on land, determined not to be causing an adverse
effect, and the surface migration of the drilling mud can be adequately
contained and controlled, then drilling can continue with the following
conditions:
o There are no impacts to the environment or other adverse effects (i.e. no
potential to contaminate surface or ground water, third party property
damage or safety risks to the landowner, public or animals.)
o The surface migration of the drilling mud is adequately contained (bermed
with subsoil or a catch pit excavated);
o The contained free drilling mud is adequately controlled (any free drilling
mud migrating to the surface is immediately and continually removed for
the duration of the remaining drilling phase.
o The site is monitored at appropriate periods during the drilling cycle and
the drilling contractor reduces pump/hole pressure accordingly in order to
maintain control of the amount of mud being contained
o The plan is discussed with appropriate regulatory agencies and their
approval is obtained; and
o The affected site is remediated and reclaimed to meet approved criteria.
In the event that none of the above procedures are successful or considered
feasible, the hole will be abandoned, and a re-drill will be considered at a
second location if it can be determined that more favorable geotechnical
conditions exist, using the same principles and contingency plans.

2.12 Drill Fluid Program


The HDD contractor will execute the attached engineered mud program. The
HDD contractor will have full contact with the mud engineer, but the mud
engineer will not be on site unless required. The drilling fluid will be tested for
viscosity, plastic viscosity, sand content, and mud weight and solids control
monitoring during drilling and reaming operations.

Deadhorse Creek HDD Execution Plan

Page 7

2.13 Schedule
Rig-up
Pilot bore
Bore sizing
Swabbing runs
Pullback
Rig-out

3 - 12hr. shifts
9 - 12hr. shifts
27 - 12hr. shifts
3 - 12hr. shifts
1 - 12hr. shift
3 - 12hr. shifts

The Deadhorse Creek crossing should take approximately 46 - 12 shift(s). As


required and subject to TransCanada approval execution of the drill can proceed
as either a 12 hr or 24 hr daily work schedule.

2.14 Buoyancy Control


The minimum rig size requirement without a buoyancy control is 351,000 lbs of
push/pull thrust. As a 1,100,000 lbs rig will be used no buoyancy control plan is
required.

2.15 Pullback Procedure


After the swabbing ream is completed, the pull section is then attached to the
hole opener using a swivel minimizing torsion forces transmitted to the pull
section. Product pipe handling equipment will be required to assist and align the
pull section in such a manner as to reduce axial tensional loads imposed on the
pull section. It is recommended not to exceed a 14 degree exit angle to prevent
excessive tensional forces. Pullback forces will be recorded and available to the
Clients Representative during and after the pullback is complete. If required
buoyancy control maybe used during pullback operations, as the pull section is
advanced to the lowest elevation of the bore, water will be inserted into the
pipeline to achieve neutral buoyancy, reducing the tensional force required to
advance the pull section. Water used for buoyancy control will be disposed of by
the prime contractor/Client.

2.16 Cleanup & Restoration


Following the completion of the HDD, the pipeline right-of-way and associated
temporary work space will be cleaned up and restored to original conditions. All
measures indicated in the EPP will be followed during clean-up and restoration
activities.
Drilling fluids and cuttings/solids will be disposed of in accordance to Alberta
Energy Resource Conservation Board (formerly Energy Utility Board) Directive
50 Drilling Waste Management. A landspray while drilling, landspread, and/or
mix-bury-cover program will be implemented to dispose of the drilling fluids and
cuttings/solids. Both fluids and solids may be stored on site in sumps, tanks, or
other structures prior to final disposal. Offsite disposal locations, if required, will
be determined in field and approved by a TransCanada representative.

Deadhorse Creek HDD Execution Plan

Page 8

Volumes of both fluids and cuttings/solids for disposal can be highly variable but
are estimated at 790 m3 for fluids and 1160 m3 for cuttings/solids.
A report detailing the drilling mud disposal outcomes (e.i. location, procedures,
quantities, analytical reports, etc.) will be provided to Keystone and to provincial
regulators where required.

2.17 Water Requirements


Estimated water usage for the drill project is 1260 m3 at 1.5m3/min. As per the
EPP the volume of water extracted shall not exceed 10% of the instantaneous
stream flow value and may further be limited to ensure a maintenance flow in the
watercourse, or water body outlet, provides free passage of both ascending and
descending fish during the period of withdrawal.
Should the available water source not meet the above requirements, alternative
arrangements will be made subject to TransCanadas approval.

Deadhorse Creek HDD Execution Plan

Page 9

ENVIRONMENTAL MANAGEMENT

3.1

Planning
The HDD management plan for Deadhorse Creek has been developed to avoid
any harmful alteration, disruption, or destruction of fish and fish habitat due to
drilling fluids and additives entering a water body. The HDD crossing plan meets
the requirements of the EPP and has been developed to ensure that there are no
adverse environmental impacts as a result of the water crossing. In addition to
the EPP, the following mitigation measures will be implemented during the HDD
crossing of Deadhorse Creek.
General
The HDD contractor will comply with the plan prepared for the works, except
where measures must be taken to deal with an emergency.
Deleterious Materials
The Prime Contractor will:
Provide the HDD contractor with a level work pad, and will construct a dirt berm
around the work pad no less than 0.3 metres in height;
Be responsible for managing any dewatering procedures;
Ensure that effective sediment and erosion control measures are in place along
the HDD work-space access route, right-of-way and appurtenances and that
they are functioning properly and are maintained and upgraded as required to
prevent sediment from entering fish habitat.
Limit use of hazardous materials.
MSDS for fuel, lubricants, and mud products will be onsite.
Equipment:
All HDD equipment arriving on location is free from engine oil, hydraulic oil, fuel,
and coolant leaks;
All HDD equipment arriving on location is free from dirt, mud, vegetative debris,
and other substances that may impact the water quality or the fish or fish
habitat values of the water or land productivity;
All equipment is maintained and serviced at least 100 metres from a water
body. If it is not possible to conduct such activities greater than 100 meters
from the watercourse, these activities will occur within a containment area
capable of preventing the accidental release of a deleterious substance from
entering a water body or contamination of soils or vegetation;

Deadhorse Creek HDD Execution Plan

Page 10

Restrict all equipment to cleared Right-of Way and work space;


All portable equipment using fuel, hydrocarbon lubricants, coolants such as
electrical generators and pumps used off of the bermed entry or exit work pad
will be positioned inside of a sandbag berm (or equivalent) lined with leak free
polyethylene or other containment structure that serves to prevent deleterious
substances such as fuel from entering the soil or aquatic environment or
contamination of soils or vegetation;
All fuels, lubricants, coolant, and other substances are contained, controlled,
and handled according to either Alberta or Manitoba Occupational Health
Safety regulations, the Keystone, and the HDD contractors safety policy and
procedures
In the event of a spill or accidental release, the appropriate response will
proceed as per EPP Appendix G, Spill Contingency Plan.
Work Areas
All spoil materials from construction activities will be deposited, whether
temporarily or permanently, above the high water mark of the water body and
in such a manner that does not allow its entry into the riparian zone or the
channel of the water body.
All work areas used by HDD crews have adequate run-off control structures in
place to prevent wash materials or exposed or disturbed sediment from
entering a water body;
Aquatic Resources
Detailed fisheries assessment was completed for the Deadhorse Creek. This
information has been compiled in Appendix C&D of the Section 11 of the
ESA. The contractor is required to follow the recommendations and use the
information provided in these appendices to plan and implement the HDD
program.
All water intakes shall be screened in accordance with the Freshwater Intake
End-of-Pipe Fish Screen Guideline published by the federal Department of
Fisheries and Oceans and screens shall be maintained clear of debris.
Ensure generators and pumps used for water intake have secondary
containment, when stationed, operated or refueled within 100 m of a
watercourse.
Waste Management
The composition of the drilling fluid will be limited to fresh water. If required for
successful drill completion and approved by TransCanada high yield
bentonite, and/or other additives conforming to or exceeding American
Petroleum Institute and Petroleum Services Association of Canada
specifications may be used.

Deadhorse Creek HDD Execution Plan

Page 11

An MSDS sheet is maintained on the work location for all drilling fluid additives.
Any change to the HDD plan requires prior approval from Keystone.

3.2

Monitoring
Keystone will monitor the water body for the introduction of drilling fluid into the
water body. Alternatively, the HDD contractor will monitor the water body for
the introduction of drilling fluid if requested to do so by Keystone.
The HDD contractor will monitor, by visual and electronic means:
o The return flow of drilling fluid from the borehole. A reduction in return
flow shall be taken as indicating a possible seepage of drilling fluid.
o The annular and / or standpipe pressure. An unplanned reduction in
pressure shall be taken as indicating a possible seepage of drilling fluid.
o The tank and pit volumes.
Any unplanned losses or gains will be reported to the Keystone Representative.
The HDD contractor will inspect all HDD equipment once every 12 hour shift to
prevent the deposition of hydrocarbons onto the ground, or into a water body.
Water Quality Monitoring
Qualified personnel will monitor both onshore and channel portions (water
quality) along the drill path and surrounding area (i.e. upstream and
downstream) for a minimum of 200m each direction for signs of drilling mud
release. Larger watercourses may require monitoring beyond 200m each
direction to suit local water conditions and Regulatory guidelines.
At a minimum, water quality monitoring will take place once the pilot hole,
reaming and pipe pullback phases are within 75m of the watercourse banks.
Onshore monitoring beyond 75m, towards the entry and exit points will be
continuous for all drilling phases. Both water quality and onshore monitoring
will continue for a minimum of 12 hours after the pipe pullback is completed.
Site conditions may change (i.e. lack of water, or dry areas between pools,
higher water) throughout the duration of the drilling activities which may
preclude or alter water quality monitoring at pre-determined locations.
Monitoring locations, including alterations from the minimum of 200m each
direction (where required), to suit site specific conditions or water course will be
determined by qualified personnel.
Water quality monitoring personnel will ensure that industry accepted
monitoring equipment and procedures/ methodologies are utilized.

Deadhorse Creek HDD Execution Plan

Page 12

Monitoring personnel will have communications with drilling personnel at all


times during daylight monitoring
Water quality monitoring will take place at a minimum of one sample per site
every 4 hours during daylight hours.
Monitoring measures will be in place during night-time hours to ensure
adequate coverage occurs. This may include walking the drill path only (only
where safe to do so and procedures are in place), water quality measurement
by auto data-loggers installed during daylight hours, and at a minimum will
include increased diligence in monitoring drilling pressures.
Night-time monitoring will not occur where it is deemed unsafe and hazards
cannot be addressed by proper controls.
All appropriate safety precautions and plans will be undertaken to meet
TransCanada and Regulatory requirements.
Monitors will increase the sampling frequency if monitoring of drilling mud
returns indicate that a release may have occurred.

3.3

Response
The Rig Manager is the on-site authority for the HDD contractor. The Rig
Manager has the authority to direct the rig crew, and the materials and
equipment towards the protection of the environment.
In the event a frac-out is observed, drilling will be stopped and contingency
measures implemented.
Contingency measures are consistent with
Department of Fisheries and Oceans Manitoba Operational Statement
regarding High-Pressure Directional Drilling.

3.4

Directional Drill Mud Release Contingency Plan


Objectives
The contingency plan outlined below has been developed and will be employed
to meet the following objectives:
To ensure Contractor has specific measures in place in the event of a
inadvertent mud release and that potential impacts are minimized; and
To ensure corrective action processes are in place to properly manage
inadvertent releases of drilling mud.
The Rig Manager is responsible for implementing and maintaining all mitigation
measures unless otherwise specified.

Deadhorse Creek HDD Execution Plan

Page 13

Specific Measures
Cleanup Plan
1. Develop a cleanup plan, before drilling. The plan will be prepared with the
drill contractor in consultation with Keystone inspection staff. Acquire the
appropriate approvals to access the release area if off right-of-way and for
mud pump-off.
2. Ensure that supervisory personnel are aware of the contingency plan (EPP
Appendix F, Directional Drill Mud Release Contingency Plan) and cleanup
plan before commencement of drilling activity.
Surface Casing
3. Install surface casing at the entry point to a depth that extends beyond the
coarsest material, if warranted.
4. Install surface casing at the exit point, after completion of the pilot hole if
coarse textured near-surface deposits could interfere with drilling mud
circulation.
Mud Composition
5. The composition of drilling fluid will be limited to fresh water. If required for
successful drill completion and approved by TransCanada high yield
bentonite and other additives conforming to or exceeding American
Petroleum Institute and Petroleum Services Association of Canada
specifications may be utilized.
Drilling Sumps
6. Construct subsoil berm(s) or sump(s) down slope from the entry point and
proposed exit point with a capacity adequate to capture anticipated volumes
of drilling mud that could be release during pullback and other drilling
operations.
Contingency Plan Equipment and Supplies
7. Certain equipment will be required onsite in sufficient quantities during drilling
operations to contain any inadvertent drilling mud releases. This equipment
and supplies may include:
sandbags;
filter cloth (e.g., silt fence);
t-bar posts;
straw bales;
shovels;
6 mil polyethylene or equivalent; and
trash pumps c/w sufficient lengths of leak free hose and suction heads.

Deadhorse Creek HDD Execution Plan

Page 14

8. Maintain vacuum trucks onsite during pullback operations as necessary. In


addition vacuum trucks can be mobilized during the pilot and reaming phases
if required.
9. Maintain the appropriate water quality sampling equipment onsite during
drilling operations to ensure that accurate water quality samples are taken.
Onsite equipment to be required by Keystone may include turbidity meters,
sampling poles, chest waders, water sample bottles, and coolers.
10. All of the HDD equipment on site is available to effect an emergency
containment of seepage of drilling fluid, and will be directed by the Rig
Manager
Manpower
11. All of the HDD contractor manpower are available to effect an emergency
containment of seepage of drilling fluid, and will be directed by the Rig
Manager.
Monitoring
12. Supervisory personnel will be onsite at all times during drilling, reaming and
pullback operations to ensure that contingency plan measures will be
implemented immediately and effectively. Keystone will also assign
inspection personnel to the site during all phases of drilling of the waterbody.
13. Monitor and record the amount of fluid return to the mud tank/pit and the
amount of makeup drilling fluid required in the mixing tanks during drilling of
the pilot hole and reaming.
14. Monitor both onshore and below channel portions of the drill path and
surrounding area (i.e., within 200m minimum) for signs of drilling mud
release. The size of the area to be monitored will be determined by
evaluating geo-technical conditions (i.e., amount of fracturing, type and depth
of substrate) and drilling conditions (i.e., depth of drill path, distance between
watercourse and entry and exit points). Monitoring will be on a continual
basis during drilling operations and will continue for at least 12 hours after
shutdown. Ensure that contact is maintained at all times between monitoring
and drilling personnel.
Water Quality Monitoring
15. Ensure the water quality sampling program is in place before drilling and
includes the following information:
Sample locations (both an upstream control site as well as appropriate
downstream sites);
Frequency of sampling; and
Sampling procedures.
16. Increase the sampling frequency if monitoring of drilling mud returns indicate
that a release may have occurred.

Deadhorse Creek HDD Execution Plan

Page 15

Response
17. Where seepage of drilling fluid into a water body or riparian area is detected
as possibly occurring, all drilling operations must stop. Rig Manager will
initiate emergency response plan if seepage of drilling fluid into a water body
or riparian area is confirmed.
18. The observation of a reduction in flow of drilling fluid will constitute a
detection of a possible occurrence of seepage, and thus, if a reduction in the
return flow of drilling fluid should occur, the Rig Manager will;
Stop the advancement of the drilling assembly, pull the drive carriage to
the top of the derrick, and shut off the drilling fluid pumps
Conduct a survey of the ground surface and water body for evidence of
seepage of drilling fluid to surface.
Notify the Keystone Representative.
Assemble measurement data such as annular and/or standpipe pressure,
forward thrust pressure, and observations such as the behavior of the
return flow. Evaluate the measurement data and observations with the
Keystone Representative.
Assist the Keystone Representative in developing a Drill Continuance
Plan that satisfies the requirements of the EPP when so advised,
Wait on orders from the Keystone Representative
Seepage
19. If seepage of drilling fluid to surface does occur, the Rig Manager will:
Stop all drilling operations.
Contain the seepage by erecting a sandbag and polyethylene berm (or
other fit- for-purpose material), or by digging a pit, or a combination of
both.
Notify the Keystone Representative.
Develop and implement a recovery and clean up plan with the Keystone
Representative.
Assemble measurement data such as annular and/or standpipe pressure,
forward thrust pressure, and observations such as the behavior of the
return flow.
Evaluate the measurement data and observations with the Keystone
Representative.
Assist the Keystone Representative in developing a Continuance Plan
that satisfies the purposes of the EPP.
Document the incident according to company procedures.
Geotechnical Information
20. Keystone has completed a geotechnical borehole investigation at each
crossing to assess the subsurface soil conditions. Keystone will design each
crossing to optimize constructability with the subsurface conditions and will
hire a competent contractor to install each crossing.
Pilot Hole Deviation

Deadhorse Creek HDD Execution Plan

Page 16

21. If the pilot bore encounters conditions that interfere with steering accuracy,
then the Rig Manager and Keystone will need to take the appropriate action
to complete the crossing. These actions could include:
Accepting the new drill path; and/or
Adjusting the depth of the borehole path so the drill can avoid the
problematic stratum; or
Pulling out, moving over and drilling a new pilot hole; or
Abandoning the pilot and advising DFO of HDD failure. Requesting
approval of the use of the contingency crossing method.
Loss of Circulation
22. If loss of circulation is encountered during the HDD, then the Rig Manager
and Keystone will need to assess the extent of fluid loss, determine its likely
cause and take the best remedial action. These actions may include:
Determining the fluid loss acceptable and continuing to drill/ream/pull; or
Stopping the operation, re-establishing circulation and restarting the
operation; or
Abandoning the hole, moving over, and boring a new crossing path; or
Abandoning the hole and advising DFO of HDD failure. Requesting
approval of the use of the contingency crossing method.
Given that there are many factors to consider in determining if the HDD fails, a
full evaluation of all relevant data will be made and all reasonable options will be
considered prior to seeking approval to use the contingency plan.
Waste Management
The Contractor and the Rig Manager will put in place the following measures in
place to maintain the cleanliness of the work site.
Store deleterious substances used in the operation and maintenance of
equipment in approved containers, and store containers in a location and
in a manner that protects them from being punctured, crushed and leaked
into the watercourse.
Provide segregated waste disposal containers for all general waste, and
dispose of such waste.
Provide sanitary facilities for crew.
Backfill and stabilize any pits excavated for anchoring or containment.
Dispose of all waste drilling fluid and drilled solids according to and in
conformance with AEUB Directive 50 and other regulatory requirements.
Follow the waste management procedures as outlined in Appendix D, of
the Environmental Protection Plan

Deadhorse Creek HDD Execution Plan

Page 17

Deadhorse River
Trans Canada Pipelines

Industrial Products

UNGER HDD
780-862-0590

CUSTOMER:
PHONE:
FAX:

UNGER002
5/13/2008

PROJECT NUMBER:
DATE:

HORIZONTAL DRILLING FLUIDS PROGRAM


DRILLING PROFILE
ELEVATION (m)

LITHOLOGY

EXIT ANGLE:

16

ENTRY ANGLE

16

LEGEND
Anhydrite / Gypsum
Clay Till
Dolomite
Gravel
Limestone
Sand
Sandstone
Shale/clay
Mudstone

0m

300 m

700 m

35
CASING

Length

Diameter

PROFILE ALONG SURVEYED BOUNDARY OF PIPELINE

EQUIPMENT SPECIFICATIONS

SOLIDS CONTROL EQUIPMENT

RIG SIZE (MT):

500

EQUIPMENT

Liters

RIG MODEL:
ROD LENGTH (M):
ROD OD (mm):
ROD ID (mm)
PUMP OUTPUT (L/MIN):
PILOT BORE DIAM. (mm):
REAM 1 (mm):
REAM 2 (mm):
REAM 3 (mm):
REAM 4 (mm):
PRODUCT PIPE SIZE (in):
HOLE LENGTH (M):
FORMATION TYPE:
* SAFETY FACTOR:

AA 1.1 MILLION

MUD TANK VOL. :


# SHAKERS USED:
SCREEN SIZES (MESH):
# DESANDERS:
DESANDER SIZE(IN):
# DESILTERS:
DESILTER SIZE(IN):
CENTRIFUGE
MUD MOTOR SIZE (IN.)

60

60000

9.6
139.7
101.6
2200
311.0
711.0
914.0
1143.0
30
600
10

MUD FORMULATION
SECTION

Product

Pilot
1500
LPM

SODA ASH
SPIRIT HYB
SPIRIT DRILL LV
DDF PAC R
DDF PAC LV

Quantity (kg/m )

28
2

VOLUME REQUIREMENTS

Total Required (KG)

Bag Count

0
3090
221
0
0
0

0
136
9
0
0
0

Ream 1
1800
LPM

SPIRIT HYB
SPIRIT DRILL LV
DDF PAC R
DDF PAC LV

30
1.5

6474
324
0
0
0

285
13
0
0
0

Ream 2
2000
LPM

SPIRIT HYB
SPIRIT DRILL LV
DDF PAC R
DDF PAC LV

32
1.5

5572
261
0
0
0

249
10
0
0
0

Ream 3
2000
LPM
FLUID
PROPERTIES
PILOT
REAM 1
REAM 2
REAM 3

SPIRIT HYB
SPIRIT DRILL LV
DDF PAC R
DDF PAC LV
pH

7-8
7-8
7-8
7-8

34
1.5

Funnel Vis
sec/L
55-60
60-70
70-80
80-95

none

ADDITIONAL INFORMATION
Use of centrifuge is recommended to maintain lower mud
weight.

clay
%SOLIDS LOAD:

1.2

3
180
n/a
n/a
n/a
n/a

M
42
110

Liters
41977
110372

REAM 1 HOLE VOL.


TOTAL MUD REQ.:

219
216

219397
215800

20

REAM 2 HOLE VOL.


TOTAL MUD REQ.:

367
174

367495
174137

30

REAM 3 HOLE VOL.


TOTAL MUD REQUIRED

575
249

574714
248663

35

575

574714

9-12
10-14
13-15
14-17

15

REAM 4 HOLE VOL.


TOTAL MUD REQUIRED

8455
378
373
15
0
0
0
0
MudWeight
Yield Point Fluid Loss
kg/m3
Pa
cc
1050-1150
1050-1150
1050-1150
1050-1150

Min. ROP
Min/Jnt

INTERVAL
PILOT HOLE VOL.:
MUD REQUIRED:

SWAB PASS

TOTAL ORDER FOR PROJECT

12-15
12-15
12-15
12-15

Product

Quantity

SODA ASH (22.7 kg)


SPIRIT HYB (22.7 kg)
SPIRIT DRILL LV (25 kg)
DDF PAC LV (22.68 kg)
MUD ENGINEER (24 hr)

COMMENTS / RECOMMENDATIONS
Seepage losses should be controlled with the use of Sawdust as needed in the mud pits. A thick
pill can be formulated with Sawdust and/or Magma Fiber for whole losses at 40 kg/m3 in a pill of
high viscosity mud. For increased hole cleaning, increase Spirit HYB concentration in 1 kg/m3
increments.

$/Unit

1048
47

SPIRIT DRILL LV (25 kg)


SPIRITROL (22.7 kg)
SAWDUST (6.8 kg)
MAGMA FIBER (18 kg)

225
120
TOTAL

*Price

$
$
$

$
$
$
$
$
$

All products will be FOB Vermeer Winnipeg warehouse. Pricing as discussed between Unger and
Vermeer.

HDD SUPERVISOR:
CONTACT:

DARREN LITKE
403-690-2703

FLUIDS ENGINEER:
CONTACT:

WAREHOUSE:
CONTACT

Winnipeg, MB

Deadhorse River
Trans Canada Pipelines

Industrial Products

UNGER HDD
780-862-0590

CUSTOMER:
PHONE:
FAX:

UNGER002
5/13/2008

PROJECT NUMBER:
DATE:

HORIZONTAL DRILLING FLUIDS PROGRAM


DRILLING PROFILE
ELEVATION (m) LITHOLOGY

EXIT ANGLE:

16

ENTRY ANGLE

16

LEGEND
Anhydrite / Gypsum
Clay Till
Dolomite
Gravel
Limestone
Sand
Sandstone
Shale/clay
Mudstone

0m

300 m

700 m

35
CASING

Length

Diameter

PROFILE ALONG SURVEYED BOUNDARY OF PIPELINE

EQUIPMENT SPECIFICATIONS
RIG SIZE (MT):
RIG MODEL:
ROD LENGTH (M):
ROD OD (mm):
ROD ID (mm)
PUMP OUTPUT (L/MIN):
PILOT BORE DIAM. (mm):
REAM 1 (mm):
REAM 2 (mm):
REAM 3 (mm):
REAM 4 (mm):
PRODUCT PIPE SIZE (in):
HOLE LENGTH (M):
FORMATION TYPE:
* SAFETY FACTOR:

SOLIDS CONTROL EQUIPMENT


500

EQUIPMENT

AA 1.1 MILLION

MUD TANK VOL. :


# SHAKERS USED:
SCREEN SIZES (MESH):
# DESANDERS:
DESANDER SIZE(IN):
# DESILTERS:
DESILTER SIZE(IN):
CENTRIFUGE
MUD MOTOR SIZE (IN.)

60

9.6
139.7
101.6
2200
311.0
711.0
914.0
1143.0
30
600
1.2

SECTION

Product

Pilot
1500
LPM

SODA ASH
SPIRIT HYB
DDF VIS
DDF PAC R
DDF PAC LV

Ream 1
1800
LPM

Ream 2
2000
LPM

Ream 3
2000
LPM
FLUID
PROPERTIES
PILOT
REAM 1
REAM 2
REAM 3

Quantity (kg/m )

32
0.8
2.5

SPIRIT HYB
DDF VIS
DDF PAC R
DDF PAC LV

34
1

SPIRIT HYB
DDF VIS
DDF PAC R
DDF PAC LV

36
1

SPIRIT HYB
DDF VIS
DDF PAC R
DDF PAC LV
pH

36
1

7-8
7-8
7-8
7-8

2
Funnel Vis
sec/L
65-75
75-85
85-100
90-110

none

ADDITIONAL INFORMATION
Use of centrifuge is recommended to maintain lower mud
weight.

clay with layers of gravel


%SOLIDS LOAD:

10

MUD FORMULATION
3

Liters
60000
3
180
n/a
n/a
n/a
n/a

VOLUME REQUIREMENTS

Total Required (KG)

Bag Count

0
3532
88
0
276
0

0
156
8
0
12
0

7337
216
0
432
0

324
19
0
19
0

6269
174
0
348
0

280
15
0
14
0

13-16
15-18
18-20
18-20

Min. ROP
Min/Jnt

M
42
110

Liters
41977
110372

REAM 1 HOLE VOL.


TOTAL MUD REQ.:

219
216

219397
215800

20

REAM 2 HOLE VOL.


TOTAL MUD REQ.:

367
174

367495
174137

30

REAM 3 HOLE VOL.


TOTAL MUD REQUIRED

575
249

574714
248663

35

575

574714

15

REAM 4 HOLE VOL.


TOTAL MUD REQUIRED

8952
400
249
22
0
0
497
20
MudWeight Yield Point Fluid Loss
kg/m3
Pa
cc
1050-1150
1050-1150
1050-1150
1050-1150

INTERVAL
PILOT HOLE VOL.:
MUD REQUIRED:

SWAB PASS

TOTAL ORDER FOR PROJECT

8-10
8-10
8-10
8-10

COMMENTS / RECOMMENDATIONS
Seepage losses should be controlled with the use of Sawdust as needed in the mud pits. A thick
pill can be formulated with Sawdust and/or Magma Fiber for whole losses at 40 kg/m3 in a pill of
high viscosity mud. For increased hole cleaning, increase Spirit HYB concentration in 1 kg/m3
increments and DDF Vis in 0.1 kg/m3 increments.

Product

Quantity

SODA ASH (22.7 kg)


SPIRIT HYB (22.7 kg)
DDF VIS (11.4 kg)
DDF PAC LV (22.68 kg)
MUD ENGINEER (24 hr)

1159
64
65

SPIRIT DRILL LV (25 kg)


SPIRITROL (22.7 kg)
SAWDUST (6.8 kg)
MAGMA FIBER (18 kg)

$/Unit

225
120
TOTAL

*Price

$
$
$

$
$
$
$
$
$

All products will be FOB Vermeer Winnipeg warehouse. Pricing as discussed between Unger and
Vermeer.

HDD SUPERVISOR:
CONTACT:

DARREN LITKE
403-690-2703

FLUIDS ENGINEER:
CONTACT:

WAREHOUSE:
CONTACT

Winnipeg, MB

Anda mungkin juga menyukai