Anda di halaman 1dari 37

ESSAR OIL VADINAR REFINERY

Mega Turnaround Sept-Oct 2011


A Bench Mark in the Refining sector looking
at the large Work-scope which was completed
with compressed engineering days and
then fast track start-up of the units

Turnaround Maintenance

Definition :
In petroleum refining , turnaround
means
a
scheduled large-scale maintenance activity wherein
an entire process unit is taken off stream for an
extended period for comprehensive revamp and
renewal. This operation involves a lot of preparations
and requires many precautions, especially at during
startup.

Contents
Turnaround Maintenance

+ Objective / Purpose
+ Process / Procedure
+ Strategy Followed
+ Organogram
+ Key Achievement/Highlights
+ Key Learning
+ What made it happen & final success
+ Major Counts at a glance
+ Sep11 Cost : Budget Vs Actual
+ Duration Schedule Vs Actual

Criteria for T/A Objectives


Aligned with business goals
Clear, unambiguous and prioritized
Measurable, objective and monitored
Based on experience , scope, knowledge and
data
Aggressive but achievable
Deliberated and agreed to key stakeholders

Turnaround Objective / Purpose


+ Make plant safe to operate till next outage.
+ Improve efficiency & throughput of plant by suitable modification.
+ Reduce routine maintenance costs

+ Perform Regulatory Inspection


+ Increase reliability / availability of equipment during operation
+ Re-establish Plant Capacity .
+ Upgrade technology by introducing modern equipment &
Technology

+ Complete corrective /preventive maintenance & project work

Turnaround Objective / Purpose


+ To execute the turnaround with the highest possible
+
+
+
+

safety record.
To achieve the best quality of workman ship.
To complete the turnaround in the shortest possible time.
To complete the turnaround at the lowest possible cost.
Revamp Jobs for Refinery capacity augmentation from 14
MMTPA to 18 MMTPA.
CDU/VDU/SGU Revamp
FCCU Revamp
VBU to CDU Conversion Tie-ins.
SRU Revamp
Train: I integration Tie-ins.

Turnaround Organization - September 2011


Sr.No. Function

Name

1
2
3
4
5
6
7
8
9

Head-Refinery
Chief Turnaround Manager
Overall Operation Co-Ordinator
Tech.Services Co-Ordinator
Construction Co-Ordinator
HSEF
Turnaround manager
Turnaround planning Co-Ordinator
Turnaround-MIS-Co-Ordinator

C Manoharan
Narada Singh
KC Swain
Satheesan V N
G G Mehta (EPIL)
Dr Gopal Jayaraman
P Rambabu
D D Chaudhari / Jayanti Vagdoda
Hembala Dixit

10

Operation Co-Ordinator

ISBL: SKM Rahman/Utility: Chitti Babu/PIT/COT: Ajay Veer

11

Engineering & Inspection

Ramesh Kumar

12

Revamp/Expansion Project Manager Ramakrishna Paramhans (EPMCL)

13
14
15
16
17
18
19
20
21

22
23

Revamp/Expansion Execution
Manager
Overall Tie-ins Co-Ordinator
Instrumentation
Electrical
Civil
EPS
Security
Admin
Reliability/Rotary/ Workshop
Commercial
RSM

Sudhir Porichha (EPIL)


Rakesh Kumar
S. Laxminarayan
Rajeev Kumar
Ashok Srivastava
Dhaval Doshi
Cmdt. Raghuraman
Geojo Paul
Amit Kumar N

J K Jani
RSM

Turnaround Optimisation Program


Strategic Site Turnaround
Review

TR - 0

Turnaround Work Scope


Optimization

TR - 1

Planning, Scheduling, and


Integrated Plan Basis

TR - 2

Integrated Plan Execution


Techniques, T/A Management

TR - 3

Post Turnaround Review

TR - 4

Turnaround Optimisation Program


.

TOPTM
Overview
Strategic Review

Scope

Cost

Schedule Preparedness

Ideal
Timing
Run Cycle (2)

Workscope Review

- 9 months

Execution Review

- 6 months

Preparedness Rev.

Close Out Review

- 3 months

+1 months

Mission for Shutdown


From Chief Turnaround Manager

{S R T C}
SAFETY
RELIABILITY

TIME-BOUND
COST-EFFECTIVE

Turnaround Process / Procedure


+ Collection of all inputs such as previous reports, procurement
lead times, job lists, own and contractor resources availability
etc
+ Gathering information from the previous turnaround by way of
group discussions, reviewing previous plans and turnaround
reports
+ Finalization of job list and freezed after challenging by
experience multi disciplinary Challenging Team
+ Setting of turnaround run lengths and approximate turnaround
duration
+ Preparation of work scope for next turnaround
+ Critical review of work scope
+ Breakdown jobs into specific activities
+ Review implementation option and resource requirement
+ Prepare an achievable plan and well integrated level I, II, III
schedule

Turnaround Process / Procedure


+ Procurement of material
+ Split between the jobs to be carried out by Company
personnel and contractor
+ Contract Planning
+ Resources for running units
+ Check the jobs for pre-requisites such as scaffolding,
insulation removal, blinds, etc
+ Pre-shutdown fabrication
+ Progressive hand over of the execution portion to the field
co-ordinators, planners, field engineers, contractor
supervisors
+ Ensure availability of tools and construction equipment
+ Ensure adequate infrastructure facilities like, labour
colony, canteen / space for eating for workman, medical
facilities, transportation, drinking water, toilet facility etc

Turnaround Process / Procedure


+ Administrative arrangements
+ Security arrangements
+ Implementation plans
+ Monitoring of jobs during execution
+ Contingency plan for Additional resources required
during turnaround
+ Turnaround close-out

Pre Shutdown Preparation


+Keep end blinds /spectacles near line flanges as per positive isolation
plans indicating required date for readiness on tags.
+Keep adequate numbers of Testing Spools, temporary Connections
for connecting pressure gauges & drains/vents for testing of Heat
Exchangers (Both Shell & Tube side)
+Fabrication of Spool Pieces for Heater Pigging Jobs.

+Erection of scaffolding wherever possible e.g. For Heat Exchanger,


inaccessible Blind locations, control Valve s, safety valves, etc.
+Lifting and shifting arrangement for control valves , Safety Valves, etc.

+Provision of Power supply points at planned locations e.g. laying of


additional cable if any for welding, Hydro jetting and Hydro testing M/C.
+ Arrangement of temp. lift and Dehumidification at defined locations.

Preparedness for Safe & Effective Execution


+Detailing of Scope of work for all S/D Jobs
+Preparation of Maintenance Execution Procedure & Work Pack for all
S/D Jobs

+Preparation of TBRA for all Critical S/D activities e.g. Hot jobs,
Modification job, work at height or any other confined space jobs

+Assignment of specific job responsibilities to a group of cross


functional team e.g. team involving Maintenance, Operation, Process,
Safety and Inspection

+Engaging Quality & experienced contractors having good track record


of executing S/D Jobs in other Refineries to the maximum extent.

Preparedness for Safe & Effective Execution


+Inclusion of Contract Safety System in Contractor Scope

+Arrangement for Pre S/D Training to Contract Manpower


+Use of only Certified Tools & Tackles
+Use of Flame Arrestor for all Vehicles,Trailors, Crane & Hydra
+Tool Box Talk by Engineer to Contract Manpower

+Strict Compliance of Safety Work Permit System


+Use of General & Specific PPEs e.g. Life line belt, Fall Arrestor

+Certified Lifting plan for heavy lift


+Certification of Scaffolds & use of Safe to use Tag

Facilities and Services (F & S)


1) Contractor office space / working area

Space for contractors offices have been provided in the S/D yard. Some of the
contractors will have to be located inside the units (from logistic point of view).

2) Canteen facilities for contractor


SAB : Own arrangement Space will be provided by EOL.
ECIL : Own arrangement Space will be provided by EOL.
Other contractors: Tea will be served at work place as free of charge to all
the contract labour at 01.00 hr, 4.00 hrs, 7.00 hrs, 10.30
hrs, 15.30 hrs, 16.30 hrs (incl W/s & utility)
Two sheds are being constructed. One at shutdown yard, & another tent in old
parking area (tent by admin along with lighting. Power supply by EOL).
Required tables, chairs, etc will be arranged by Admin.
Lighting arrangement in tin sheds will be provided by elect dept.
3) Canteen facilities for officers:.

Location will be at area in between CCB & LAB.


Tables, chairs, carpet & lighting is being organized by Admin and power supply
by electrical dept.

Facilities and Services (F & S)


4) Drinking Water Facilities :
5) Shutdown office:
6) Urinals & Toilets:

Sufficient no of toilets and urinals have been constructed in shutdown yard.

7) Resting Place :
Separate tents arranged for Dining and Rest room for different contract manpower as well
as for engineer. Near Shutdown yard to avoid manpower movement.
8) First Aid office:
Central first aid tent will be located in front of Lab near E-W road. It will be supplemented by
paramedic officer / doctor on round the clock basis and one ambulance.
9) Accommodation for Labour / Transport.
Accommodation for 10000 Labours have been booked in Labour colony.
For transporting Labours from labour colony to refinery, our trailers will be used and
necessary railing arrangement is being done in our workshop for safety. In addition to this
permission will be given for walking from labour gate to workplace on the fixed route.
10) Office space for foreign expatriates:
11 Timing:

Working time: 08.00 to 20.00 & 20.00 to 8.00 hrs.


Lunch time: 12.30- 13.30 hrs in two batches (30 min break)
Dinner: 22.00 to 23.00 hrs In two batches
Radiography timing: It will be declared on time to time & followed

Detailed Shutdown Planning


+Planning started with setting of Milestones for Planning activities
+Compilation, discussion and finalization of Job list
+Cost Estimation of S/D Jobs, Detail technical study and BOM
preparation for S/D activities, material procurement action

+Preparation of detail scope for awarding the contract


+Preparation

of Work packs by operations


maintenance procedures by maintenance

and

standard

+Finalization of resources, Heavy Equipments, Inspection Plans,


identifying service requirements of technical specialist & expatriate

+Organization of S/D meetings for review, micro detailing and


finalization of overall S/D schedule

Turnaround Organization - September 2011


Sr.
Function
No.

1
2
3
4
5
6
7
8
9

Head-Refinery
Chief Turnaround Manager
Overall Operation Co-Ordinator
Tech.Services Co-Ordinator
Construction Co-Ordinator
HSEF
Turnaround manager
Turnaround planning Co-Ordinator
Turnaround-MIS-Co-Ordinator

Name

11 Engineering & Inspection

C Manoharan
Narada Singh
KC Swain
Satheesan V N
G G Mehta (EPIL)
Dr Gopal Jayaraman
P Rambabu
D D Chaudhari / Jayanti Vagdoda
Hembala Dixit
ISBL: SKM Rahman
Utility: Chitti Babu
PIT/COT: Ajay Veer
Ramesh Kumar

12 Revamp/Expansion Project Manager

Ramakrishna Paramhans (EPMCL)

10 Operation Co-Ordinator

13
14
15
16
17
18
19
20
21
22

Revamp/Expansion Execution
Manager
Overall Tie-ins Co-Ordinator
Instrumentation
Electrical
Civil
EPS
Security
Admin
Commercial
RSM

Sudhir Porichha (EPIL)


Rakesh Kumar
S. Laxminarayan
Rajeev Kumar
Ashok Srivastava
Dhaval Doshi
Cmdt. Raghuraman
Geojo Paul
J K Jani
RSM

Accomplishments of Turnaround which was


completed on schedule in spite of lot of challenges

+ 35 days Turnaround Completed Safely ON SCHEDULE


+ Turnaround Cost within Budget as per plan. Few
variances due to major exigencies during the Turnaround
period.
+ Tie - ins of Train - I new units & facilities with existing
refinery : ISOM, HMU, DHDT, VGO- HT, ARU, SWS, SRU,
DCU, & all OSBL/offsite tankages facilities
+ Revamp of existing units for capacity Augmentation has
been completed : CDU & VDU (18MMTPA) & consistently
will be able to process high TAN crudes , FCCU (3.7MMTPA)
& FCC operation on hydro treated feed, SRU (To Improve the
sulphur recovery from 99 to 99.9 wt%).

Accomplishments of Turnaround which was


completed on schedule in spite of lot of challenges

+ Total Revamp (modification & reinstallation) completed in


28 engineering days;

+ World tallest single crude distillation column revamped (77 trays,


90 meter height)
+ Vacuum distillation column revamped (4 bed, 60 meter height &
new vapour horn installation)
+ Major piping modifications & replacement in existing units i.e. CDU
& FCC (dismantling 75,424 inch meter & erection of 85,098 inch
meter)
+ Revamp completed- 36 Nos. Exchangers - Modifications/New
exchangers, 7 nos. columns & 6 nos. vessels modification, 6 nos.
new ejectors erected in VDU, 29 nos. pumps modification complete
& boxed-up, 4 nos. Filters modification, CDU Heater A & B, VDU
Heater- A & B revamp/ modifications

Turnaround Key Achievement/Highlights


+ FCCU all revamp job completed within schedule without any
incident, this includes Reactor-Riser 2 nos additional Feed
nozzle installation, Tie Ins Job 141 nos , Additional Exchanger
installation 2 nos along with piping, 6 nos Vessels & 4 nos
Pumps modification
+ All Major M & I Job completed within 21 days duration, 36
Column, DHDS reactor catalyst replacement, CCR/NHT Reactor
catalyst replacement, FCCU- 6 nos. bellows replacement, Flue
gas boiler tube banks replacement, MAB Surface condenser
replacement, SRU MCC-1 & 2 major refractory repair, UCT & PCT
10 nos. pumps discharge line replacement, 236 Exchangers, 199
Vessels, All 6 heaters pigging, 16 Heaters maintenance, 102
PCNs (GRM & Reliability related schemes), PCN-Total INCH DIA
:28624,Total INCH MTR: 32500,Steel Structure: 103MT

Turnaround Key Achievement/Highlights


+ 52 Fin fan coolers, Major overhauling of over 50 Compressor/
Turbine/ Pumps. Overhauling of 297 control valves and 551
pressure safety valves,
+ DCS/ESD up gradation in all the units,
+ Capital overhauling of 145 motors, 14 Power Transformers, 45
VACUUM circuit Breakers (33 kV), 201 Vacuum circuit Breakers
(6.6Kv) 198 LT Circuit Breakers. 108 obsolete relays replaced
with High speed Numerical relays,
+ Bus bar differential protection scheme commissioned at Utility,
CCR, FCCU and CDU Electrical Substations, New 33kV
switchboard and 6.6 KV switchboard commissioned in CDU
and Utility Substations.
+ Implementation of Fast Bus Transfer scheme at CDU, CCR,
FCCU, DHDS, and Utility substations and many other important
jobs

Turnaround Key Learning


Temporary Lift was installed at CDU & VDU column,
for movement of light weight materials as well as
workmen from ground to column and Vice Versa
which remarkably reduced required time frame of
execution from 45 days to 35 days and all jobs were
smoothly completed in scheduled timeframe.
Temporary Lift, installed at
CDU / VDU column

Turnaround Key Learning

Dehumidification system provided in CDU & VDU column was


very effective for maintaining comfortable atmosphere inside
column for workmen, by maintaining temperature between 28
to 32 deg C & Relative humidity was less than 65% inside the
columns. This facility has remarkably contributed in reducing
the time mainly for huge quantum of welding / hot work inside
the column. Dehumidification System in CDU & VDU column
Dehumidification System for Reactor-Riser

Turnaround Key Learning

New idea of Exchanger cleaning bay has resulted in huge time


saving by providing central Point for Cleaning of all Tube
Bundles with advance Hydro jetting machines i.e.
Inside/Outside Robotic machines and Inspection (Visual &
Eddy Current Testing) was also carried out at same place which
helped in good housekeeping and keeping ISBL unit free from
Oil, Coking & Sludge and Further reduced House Keeping Job
also.

Exchanger Cleaning Bay

Turnaround Key Learning

Robotic Hydrojetting machine made available at exchanger


cleaning bay for Heat Exchangers Tube bundle cleaning,
Machine operating with multi jet nozzles5 nos working
simultaneously which took 1/5th times of ordinary manually
tube bundle cleaning process, max pressure of 20000 PSI, due
to high pressure & mobility of machines the exchanger tube
bundle cleaning process was very fast and effective, and hard
deposit was removed very easily, thus saving huge time in
cleaning huge number of tube bundles

Robotic Tube bundle


cleaning Machine

What made it happen(from 45 to 35 Days


Decisive Leadership and on spot decisions.
Micro level Turnaround planning started well in advance before 18 months for
man, material , machines, job list and its work pack.
Defined all critical jobs :
1. CDU/VDU column Revamping.
a.

b.
c.

d.
e.

We treat contract manpower as our employee and provide all the facilities
like Accommodations/Food/Transport/Medical/Water/Tea-Snacks at site
only.
Use of new concepts and modernized gadgets e.g. providing lifts as high
as 90 Meters, Dehumidification /AC, Chemical decontamination etc.
Maximizing the pre turnaround activities e.g. 90% scaffolding, issuing of
100% bulk material/ spares and its prefabrication/ machining and placing
in position.
Daily Review and making rolling plan for speedy execution.
Timely supply of equipment and logistics arrangements

What made it happen(from 45 to 35 Days)

2.

CDU/VDU Heater Modification.

a.

Optimise the use of Pigging machines in such a way that critical Heater
handed over with in minimum possible durations.
Use of new concepts and modernized gadgets e.g.SAF RAD
Radiographic machines so that other jobs can be continued.
Heater jobs divided in multiple zones so that welding jobs can be
performed at maximum locations at a time and saved lot of time.
Keep standby manpower for critical activities so that job shuld not suffer
at any cost.

b.
c.
d.

3. FCCU Reactor Refractory repairing:


a. Providing of Dehumidification /AC.
b. Using SAF RAD Radiographic machines,Diamond cutter for refractory,
electrical and instrument testing equipment etc.
c. Using of skilled manpower and guidance from Refractory experts.
d. Ensures Support services like inspection/process availability 24X7 on the
job.

What made it happen(from 45 to 35 Days)


Decisive Leadership and on spot decisions.
Micro level Turnaround planning started well in advance before 18 months for
man, material , machines, job list and its work pack.
Defined all critical jobs :
1. CDU/VDU column Revamping.
a. We treat contract manpower as our employee and provide all the facilities
like Accommodations/Food/Transport/Medical/Water/Tea-Snacks at site
only.
b. Use of new concepts and modernized gadgets e.g. providing lifts as high
as 90 Meters, Dehumidification /AC, Chemical decontamination,
Inside/Outside Robotic Hydro jetting, SAF RAD Radiographic machines,
powered torqueing/tensioning machines, Diamond cutter for refractory,
Ultra-modern rotary laser based condition monitoring, electrical and
instrument testing equipment etc.
c. Maximizing the pre turnaround activities e.g. 90% scaffolding, issuing of
100% bulk material/ spares and its prefabrication/ machining and placing
in position.
d. Timely supply of equipment and logistics arrangements

What made it happen(from 45 to 35 Days)


Engaged best contractor and resources and skilled/ specialized man
power. Optimum deployment & effective utilization of resources

Organization of Turnaround meetings for review, micro detailing and


finalization of overall Turnaround schedule.
Compliance of Systems and Procedures, Strong belief in team work,
motivation and support from Top Management.
Caring of the Employees and Workmen resulted in excellent overall
productivity.

All disciplines viz- Maintenance, Operation, TS/Process, Inspection,


Expansion, HSEF, Security, Project/Engg, HR, CRG, IT, Warehouse,
Commercial, Finance and Administration have demonstrated tireless
effort and cohesive work culture towards achieving Turnaround goal.

The Success : 100% Planned jobs completed


along with last minute surprises
It is worth highlighting that not only 100% planned jobs
have been completed effectively but many important jobs
came at last moment which could be also completed within
this Turnaround period.
Last minute surprises and exigencies were also handled
effectively- CCR Recycle gas compressor major
maintenance due to high vibrations, DHDS Recycle gas
compressor unplanned overhauling due to coking in rotor,
Damage of 4th Bed layers of packing in VDU column,
Shifting of HP steam line from support, Last moment receipt
of CDU/VDU heater tubes & prefabrication, Cracks in CDU
Heater supports and many more., created a huge
pressure.

Turnaround Sep11 : Major counts at a Glance


Total Turnaround duration
Total engineering duration
Total no of blinds provided for plant handover
Turnaround Budget
Turnaround Expenditure
Major Contractor involved
Turnaround Manpower (Officer + Workman+ OEM Experts)
Essar Officers (In 12hrs Shift Rota)
OEM & Expatriate
Cranes (250T,200T,150T ,135T,130T,120T,110T,100T& 60T)
Hydra
Fork Lift
Trailer
Exchanger tube bundle pullers
Hydro-jetting machines
Hydro-testing machines
Insitu Machining sets
Rotomol cleaning machine
Stress relieving machine
Air compressors
Pigging machine
Hydraulic torque tightening m/c
Transformer oil filtration machine
Heating oven for motors
Transformer oil heating and vacuum m/c
Mobile lighting tower
Fire Blankets
Total no. of Revamp Major jobs executed
Total no. of Major M&I jobs executed

35 days
26 days
3924 Nos
74.66 Cr
74.69 Cr
70 Nos
15000 Nos
846 Nos
20 & 5 Nos
57 Nos
39 Nos
10 Nos
33 Nos
05 nos
26 Nos
50
12
2
20
09 Nos
06 Nos
12
3
2 nos
3
2 nos
3500 Nos
1618 Nos
2492 Nos

Turnaround Sep11 Cost : Budget Vs Actual


Rs in Cr.
BudgetMaterial
cost

Sr.
Description
No.
Mechanical/Operations
total)

(Sub

Total
Budget- Budget ( Actual Actual
Total (
Service Material+ Material Service
Actual)
cost
Service)
s Cost
Cost
cost

15.86

40.10

55.96

18.49

35.79

54.63

B Electrical

2.52

2.22

4.74

C Instrument

2.99

0.99

3.98

2.01
1.64

1.90
1.26

3.91
2.90

D Civil

2.99

3.49

1.70

5.58

7.27

1.80

1.80

0.30

0.35

0.65

0.00
0.37

1.53
0.18

1.53
0.55

0.50

E Inspection
F Fire & Safety
G

Admin & Canteen facilities,


Vehicles, OHC & IT

0.00

1.51

1.51

0.09

2.34

2.43

Maintenance
supervisor/Engineers hiring

0.00

2.53

2.53

0.00

1.47

1.47

Total shutdown Budget (in


crores). (Addition of A to H)

22.17

52.48

74.66 24.30 50.04 74.69

74.66

73.96

TOTAL COST (Rs in Cr.)

Justification

Additional Job of Sea water intake


well inside painting, Repairing
and Chemical resisting coating in
pump house basin of Sea water
supply reservoir, CDU /VDU
heater main flue gas duct to stack
cleaning & inspection, Insulation,
Scaffolding

Turnaround Duration Schedule Vs Actual


UNIT
CDU/VDU/S
GU
VBU
TREATERS
FCCU
NHT
CCR
DHDS
ARU
SWS
SRU train-1
SRU train-2
UTILITYUCT
UTILITYPCT
H2S Flare
HC Flare
N2 Plant
Steam

PLANNED
STOPPAGE DATE
& TIME

ACTUAL FEED
CUT OFF
STOPPAGE DATE
& TIME

PLANNED STARTUP DATE & TIME

ACTUAL FEED
CUT IN START UP
DATE & TIME

18/09/11 & 08:00 hrs 18/09/11 & 04:45 hrs

23/10/11 & 08:00 hrs 24/10/11 & 11:08 hrs

19/09/11 & 02:00 hrs 19/09/11 & 00:30 hrs

24/10/11 & 08:00 hrs 24/10/11 & 19:15 hrs

20/09/11 & 08:00 hrs 19/09/11 & 00:30 hrs

23/10/11 & 08:00 hrs 23/10/11 & 18:00 hrs

19/09/11 & 08:00 hrs 19/09/11 & 09:10 hrs

23/10/11 & 08:00 hrs 23/10/11 & 10:25 hrs

18/09/11 & 20:00 hrs 18/09/11 & 21:15 hrs

22/10/11 & 08:00 hrs 23/10/11 & 16:35 hrs

18/09/11 & 20:00 hrs 18/09/11 & 21:35 hrs

21/10/11 & 08:00 hrs 27/10/11 & 05:25 hrs

18/09/11 & 20:00 hrs 18/09/11 & 20:00 hrs

24/10/11 & 08:00 hrs 29/10/11 & 16.00 hrs

21/09/11 & 08:00 hrs 19/09/11 & 09:00 hrs

23/10/11 & 08:00 hrs 23/10/11 & 21:00 hrs

21/09/11 & 12:00 hrs 21/09/11 & 08:15 hrs

23/10/11 & 08:00 hrs 24/10/11 & 04:00 hrs

20/09/11 & 08:00 hrs 19/09/11 & 06:45 hrs

23/10/11 & 08:00 hrs 28/10/11 & 19:10 hrs

20/09/11 & 08:00 hrs 18/09/11 & 09:00 hrs

23/10/11 & 08:00 hrs 31/10/11 & 12:00 hrs

29/09/11 & 08:00 hrs 27/09/11 & 17:00 hrs

11/10/11 & 08:00 hrs 13/10/11 & 16:00 hrs

26/09/11 & 08:00 hrs 25/09/11 & 00:00 hrs

13/10/11 & 08:00 hrs 15/10/11 & 10:00 hrs

26/09/11 & 08:00 hrs 26/09/11 & 11:30 hrs

14/10/11 & 08:00 hrs

30/09/11 & 08:00 hrs 26/09/11 &11:30 hrs

15/10/11 & 08:00 hrs 12/10/11 & 20:30 hrs

01/10/11 & 08:00 hrs 06/10/11 &18:00 hrs

05/10/11 & 08:00 hrs 15/10/11 & 06:00 hrs

01/10/11 & 08:00 hrs 04/10/11 &08:30 hrs

05/10/11 & 08:00 hrs 10/10/11 & 09:00 hrs

15.10.11 & 18.45 Hrs

THANK YOU

Anda mungkin juga menyukai